CN209578468U - A kind of cooling device for welding equipment - Google Patents

A kind of cooling device for welding equipment Download PDF

Info

Publication number
CN209578468U
CN209578468U CN201920186270.4U CN201920186270U CN209578468U CN 209578468 U CN209578468 U CN 209578468U CN 201920186270 U CN201920186270 U CN 201920186270U CN 209578468 U CN209578468 U CN 209578468U
Authority
CN
China
Prior art keywords
blower
welding
storage box
welding bench
cooling device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201920186270.4U
Other languages
Chinese (zh)
Inventor
司英建
笪祖朋
殷宗香
吕明刚
李慧
万国强
施国滨
肖定军
杨钦权
陈晓辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201920186270.4U priority Critical patent/CN209578468U/en
Application granted granted Critical
Publication of CN209578468U publication Critical patent/CN209578468U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Farming Of Fish And Shellfish (AREA)

Abstract

The utility model discloses a kind of cooling devices for welding equipment, welding bench, the top side of the welding bench is respectively arranged with ice storage box and the second blower, and the air intake of second blower is connected with the side of ice storage box, the outlet air end of second blower is connected with discharge pipe, the top side of the ice storage box is connected with sealing cover by movable axis, the top other side of the welding bench is respectively arranged with the first blower and disposal box, baffle is provided in the cored slab of lid arrangement, baffle can reduce the flow velocity of liquid, the time for being detained liquid in cored slab is longer, it is more preferable to carry out cooling effect to welding object, when ice cube slowly melts, since ice cube volume is reduced, spring is slowly compound, so that ice cube slowly rises, the air intake of the first blower can be located at by enabling to ice cube so always, so as to So that the wind of the second blower blowout is cold wind always, accelerates cooling time, improve work efficiency.

Description

A kind of cooling device for welding equipment
Technical field
The utility model relates to weld cooling technology field, specially a kind of cooling device for welding equipment.
Background technique
Welding equipment refer to realize welding procedure required for equipment, welding equipment include welding machine, welding procedure equipment and Weld auxiliary implement.
Process that is cooling, instigating the temperature of hot object to reduce without phase change.
Most of existing cooling device is all that natural wind is cooled down, and causes cooling time longer in this way, to influence Welding efficiency.
Summary of the invention
The purpose of this utility model is to provide a kind of cooling devices for welding equipment, to solve above-mentioned background technique The cooling time of middle proposition is longer, influences the problem of welding efficiency.
To achieve the above object, the utility model provides the following technical solutions: a kind of cooling device for welding equipment, Including welding bench, the top side of the welding bench is respectively arranged with ice storage box and the second blower, and second blower into Wind end is connected with the side of ice storage box, and the outlet air end of second blower is connected with discharge pipe, the top one of the ice storage box Side is connected with sealing cover by movable axis, and the top other side of the welding bench is respectively arranged with the first blower and disposal box, and The outlet air end of first blower is connected with the side of disposal box, and cored slab, the sky are provided at the top of the welding bench The inside of core is fixed with baffle, and the lower inside of the ice storage box is fixed with placement plate, the top of the placement plate by spring Portion is provided with ice cube, and the lower inside of the welding bench is respectively arranged with liquid reserve tank and water pump, and the liquid feeding end of the water pump is logical It crosses liquid suction pipe to be connected with the side of liquid reserve tank, the outlet end of the water pump is connected with perfusion tube, and one end of the perfusion tube Through welding bench inner upper and be connected with the side of cored slab, the top of the liquid reserve tank through there is outlet tube, and One end of the outlet tube through welding bench inner upper and be connected with the other side of cored slab, the liquid reserve tank it is another Side through there is a drainpipe, and one end of the drainpipe through welding bench inner upper and be connected with the bottom of ice storage box It is logical.
Preferably, the side of the welding bench is provided with operation panel, and the operation panel and the first blower, the second wind Machine and water pump are electrically connected.
Preferably, the outer surface of the ice storage box is provided with observation window.
Preferably, handle is welded at the top of the sealing cover.
Preferably, the production material protection of the cored slab has copper and aluminium.
Preferably, the bottom of the welding bench is provided with rubber pad.
Preferably, the air intake of first blower is connected with dust gathering arrester.
Preferably, the baffle plate setting has multiple groups.
Compared with prior art, the utility model has the beneficial effects that cooling device of this kind for welding equipment is arranged There are ice storage box, ice cube, the second blower, a baffle, water pump, spring, placement plate, drainpipe and liquid reserve tank, when being cooled down, work Make in the placement plate that ice cube is placed in ice storage box by personnel, placement plate is made spring be squeezed contraction by gravity, then Staff starts the second blower, then the air intake of the second blower carries out being evacuated into ice storage box to be sprayed by discharge pipe, by In under the action of ice cube, so that the air themperature in ice storage box is lower, the wind of at this moment the second blower extraction is also cold wind, is accelerated Cooling efficiency, and ice melting water is entered in liquid reserve tank by drainpipe, then be pumped into cored slab by water pump, by In being provided with baffle in cored slab, baffle can reduce the flow velocity of liquid, so that the time that liquid is detained in cored slab Longer, thus more preferable to welding object progress cooling effect, when ice cube slowly melts, since ice cube volume is reduced, spring is slowly Compound, so that ice cube slowly rises, the air intake of the first blower can be located at by enabling to ice cube so always, so that The wind of second blower blowout is cold wind always, accelerates cooling time, improves work efficiency.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 bows for the utility model cored slab and cuts open structural schematic diagram;
Fig. 3 is the utility model cored slab structural schematic diagram;
Fig. 4 is the utility model ice storage box structural schematic diagram.
In figure: 1, welding bench;2, cored slab;3, disposal box;4, the first blower;5, dust gathering arrester;6, the second blower;7, ice storage Case;8, movable axis;9, sealing cover;10, ice cube;11, placement plate;12, spring;13, operation panel;14, drainpipe;15, liquid storage Case;16, water pump;17, liquid suction pipe;18, perfusion tube;19, discharge pipe;20, outlet tube;21, baffle;22, observation window;23, handle.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
In the utility model: the model LCY2251F of water pump.
Fig. 1-4 is please referred to, the utility model provides a kind of technical solution: a kind of cooling device for welding equipment, packet Include welding bench 1, the top side of welding bench 1 is respectively arranged with ice storage box 7 and the second blower 6, and the air intake of the second blower 6 with The side of ice storage box 7 is connected, and the outlet air end of the second blower 6 is connected with discharge pipe 19, and the top side of ice storage box 7 passes through activity Axis 8 is connected with sealing cover 9, and the top other side of welding bench 1 is respectively arranged with the first blower 4 and disposal box 3, and the first blower 4 Outlet air end be connected with the side of disposal box 3, the top of welding bench 1 is provided with cored slab 2, and the inside of cored slab 2 is fixed with The lower inside of baffle 21, ice storage box 7 is fixed with placement plate 11 by spring 12, and the top of placement plate 11 is provided with ice cube 10, The lower inside of welding bench 1 is respectively arranged with liquid reserve tank 15 and water pump 16, and the liquid feeding end of water pump 16 passes through liquid suction pipe 17 and storage The side of liquid case 15 is connected, and the outlet end of water pump 16 is connected with perfusion tube 18, and one end of perfusion tube 18 is through welding bench 1 Inner upper and be connected with the side of cored slab 2, the top of liquid reserve tank 15 is through having outlet tube 20, and the one of outlet tube 20 It holds the inner upper through welding bench 1 and is connected with the other side of cored slab 2, the other side of liquid reserve tank 15, which is run through, draining Pipe 14, and one end of drainpipe 14 through welding bench 1 inner upper and be connected with the bottom of ice storage box 7.
Fig. 1 and 4 are please referred to, the side of welding bench 1 is provided with operation panel 13, and operation panel 13 and the first blower 4, Two blowers 6 and water pump 16 are electrically connected, and start or close the first blower 4, the second wind by operation panel 13 convenient for staff Machine 6 and water pump 16, the outer surface of ice storage box 7 are provided with observation window 22, observe ice cube by observation window 22 convenient for staff 10 situations melted, so that ice cube 10 is added at any time, the top of sealing cover 9 is welded with handle 23, passes through handle convenient for staff Hand 23 opens sealing cover 9, so that staff's addition ice cube 10 is more convenient.
Fig. 1-3 is please referred to, the production material protection of cored slab 2 has copper and aluminium, so that the conductivity of heat of cored slab 2 is more It is good, so that coolant liquid and welding object are able to carry out heat exchange, accelerate cooling efficiency, the bottom of welding bench 1 is provided with rubber pad, this Sample makes welding bench more stable, is not easy to shake.
Fig. 1-3 is please referred to, the air intake of the first blower 4 is connected with dust gathering arrester 5, so that dust can quickly be inhaled Enter into disposal box, reduce the number of staff's cleaning, baffle 21 is provided with multiple groups, reduces the flow velocity of coolant liquid, make It obtains coolant liquid and welding object has the sufficient time to carry out heat exchange.
Working principle: firstly, staff first checks whether the device is intact, if any damage on-call maintenance, then should Device installs, and then staff will need the article welded to be placed on cored slab 2, then welds to it, then work Make personnel and open sealing cover 9, then ice cube 10 is placed in placement plate 11, at this moment since placement plate 11 is made bullet by gravity Spring 12 is shunk, and then staff closes top cover labyrinth 9, then starts the first blower 4, the second blower by operation panel 13 again 6 and water pump 16, then the air intake of the second blower 6 carries out being evacuated into ice storage box 7 to be sprayed by discharge pipe 19, due in ice cube Under the action of 10, so that the air themperature in ice storage box 7 is lower, the wind of at this moment the second blower 6 extraction is also cold wind to welding object It is cooled down, the starting of the first blower 4 is evacuated welding object, on the one hand can siphon away the dust welded on object, another party The heat on welding object has also been taken away in face, and the dust being sucked away stores in disposal box 3, and water circulating pump 16 will be in liquid reserve tank 15 Liquid is pumped into inside cored slab 2, under the action of baffle 21, reduces the flow velocity of liquid, and at this moment coolant liquid passes through cored slab 2 Heat exchange is carried out with welding object, to reduce the bulk temperature of welding object, at the same time, ice cube 10 slowly melts with the time Change, thawing is entered in liquid reserve tank 15 by drainpipe 14 in case further carrying out heat exchange to welding object, and ice cube 10 melts Afterwards, volume slowly becomes smaller, and the gravity that at this moment spring 12 is subject to becomes smaller, and spring 12 is slowly compound, so that ice cube 10 is slowly lifted, from And make ice cube 10 always situated in the air intake of the second blower 6, guarantee that the second blower 6 blowout wind is cold wind always, as work people After member observes that ice cube 10 slowly melts by observation window 22, staff opens sealing cover 9 and adds new ice cube 10.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (8)

1. a kind of cooling device for welding equipment, including welding bench (1), it is characterised in that: the top of the welding bench (1) Side is respectively arranged with ice storage box (7) and the second blower (6), and the one of the air intake of second blower (6) and ice storage box (7) Side is connected, and the outlet air end of second blower (6) is connected with discharge pipe (19), and the top side of the ice storage box (7) passes through Movable axis (8) is connected with sealing cover (9), and the top other side of the welding bench (1) is respectively arranged with the first blower (4) and dust Case (3), and the outlet air end of first blower (4) is connected with the side of disposal box (3), sets at the top of the welding bench (1) It is equipped with cored slab (2), the inside of the cored slab (2) is fixed with baffle (21), and the lower inside of the ice storage box (7) passes through bullet Spring (12) is fixed with placement plate (11), is provided with ice cube (10) at the top of the placement plate (11), the inside of the welding bench (1) It is respectively arranged below liquid reserve tank (15) and water pump (16), and the liquid feeding end of the water pump (16) passes through liquid suction pipe (17) and liquid storage The side of case (15) is connected, and the outlet end of the water pump (16) is connected with perfusion tube (18), and the one of the perfusion tube (18) It holds the inner upper through welding bench (1) and is connected with the side of cored slab (2), the top of the liquid reserve tank (15) is run through Have outlet tube (20), and one end of the outlet tube (20) is through the inner upper of welding bench (1) and another with cored slab (2) Side is connected, and the other side of the liquid reserve tank (15), which is run through, to be had drainpipe (14), and one end of the drainpipe (14) is run through In welding bench (1) inner upper and be connected with the bottom of ice storage box (7).
2. a kind of cooling device for welding equipment according to claim 1, it is characterised in that: the welding bench (1) Side be provided with operation panel (13), and the operation panel (13) and the first blower (4), the second blower (6) and water pump (16) it is electrically connected.
3. a kind of cooling device for welding equipment according to claim 1, it is characterised in that: the ice storage box (7) Outer surface be provided with observation window (22).
4. a kind of cooling device for welding equipment according to claim 1, it is characterised in that: the sealing cover (9) Top be welded with handle (23).
5. a kind of cooling device for welding equipment according to claim 1, it is characterised in that: the cored slab (2) Production material protection have copper and aluminium.
6. a kind of cooling device for welding equipment according to claim 1, it is characterised in that: the welding bench (1) Bottom be provided with rubber pad.
7. a kind of cooling device for welding equipment according to claim 1, it is characterised in that: first blower (4) air intake is connected with dust gathering arrester (5).
8. a kind of cooling device for welding equipment according to claim 1, it is characterised in that: the baffle (21) sets It is equipped with multiple groups.
CN201920186270.4U 2019-02-02 2019-02-02 A kind of cooling device for welding equipment Expired - Fee Related CN209578468U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920186270.4U CN209578468U (en) 2019-02-02 2019-02-02 A kind of cooling device for welding equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920186270.4U CN209578468U (en) 2019-02-02 2019-02-02 A kind of cooling device for welding equipment

Publications (1)

Publication Number Publication Date
CN209578468U true CN209578468U (en) 2019-11-05

Family

ID=68354289

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920186270.4U Expired - Fee Related CN209578468U (en) 2019-02-02 2019-02-02 A kind of cooling device for welding equipment

Country Status (1)

Country Link
CN (1) CN209578468U (en)

Similar Documents

Publication Publication Date Title
CN108811453B (en) Communication box with dust removal heat dissipation function
CN109346790B (en) Safe and automatic disassembling method for waste hard-shell lithium ion power battery through controllable discharge
CN206412686U (en) A kind of circulating dedusting cooling top cover of box-type substation
CN213701214U (en) Crushing device is disassembled to waste lead-acid batteries high efficiency
CN206997720U (en) A kind of tin slab is molded cooling device
CN209578468U (en) A kind of cooling device for welding equipment
CN108550947A (en) Waste lithium cell electrolyte lithium hexafluoro phosphate recycle device and application method
CN207154756U (en) Lead accumulator cast welding machine cooling device
CN208727697U (en) A kind of useless pipe processing unit
CN218218981U (en) High-efficient integrative machine of unfreezing clearance that unfreezes
CN209189998U (en) A kind of plasma cutting machine cooling collection device of slag
CN211063181U (en) High-efficient heat dissipation power equipment
CN213790896U (en) A refining furnace flue gas processing apparatus for production of tin copper alloy line
CN211527151U (en) Glass fiber reinforced plastic cooling tower with water-saving function
CN206772062U (en) A kind of continuous waste gas from smelting furnace of up-drawing method collects dissolver
CN210097150U (en) Cleaning device for dust remover
CN208419593U (en) A kind of anti-oxidation melting appartus of metal
CN210135717U (en) Freezer frost and melt water collection device
CN208485966U (en) Inhale aluminum pipe cleaning plant
CN209521459U (en) A kind of calligraphy automatic grinding inkstone device
CN208536622U (en) Metal Melting circulating water equipment
CN208406147U (en) One kind putting rosin vapour-recovery unit during perfume (or spice)
CN213660547U (en) Lithium battery with heat dissipation mechanism
CN110076453A (en) A kind of material gasification treatment device for optical-fiber laser cutting machine
CN210857767U (en) Roof intelligence snow removing protection machine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20191105

Termination date: 20210202