A kind of auxiliary device of tunnel bracing members installation Download PDFInfo
- Publication number
- CN209539374U CN209539374U CN201821702066.5U CN201821702066U CN209539374U CN 209539374 U CN209539374 U CN 209539374U CN 201821702066 U CN201821702066 U CN 201821702066U CN 209539374 U CN209539374 U CN 209539374U
- Authority
- CN
- China
- Prior art keywords
- bracing members
- auxiliary device
- tunnel
- steel pipe
- jacking
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
The utility model relates to a kind of tunnel bracing members installation auxiliary device, it include: bearing support, bearing support middle part be equipped with jack, be connected with a steel pipe above jack, a jacking connected on steel pipe, jacking connects vault bracing members.The construction personnel that the utility model efficiently solves tunnel support work surface is more, reduce the time of personnel's operation under unstable surrounding rock, provide the tunnel bracing members installation auxiliary device that a kind of safety coefficient is high, speed of application is fast, the number of turnover is more, structure is simple, is easily installed, it ensures production safety, produces great social and economic benefit.
Description
Technical field
The utility model belongs to the technical field of construction such as water conservancy and hydropower, highway, railway, municipal administration, and in particular to a kind of tunnel
Bracing members installation auxiliary device.
Background technique
In the engineering constructions such as water conservancy and hydropower, highway, railway, municipal administration, to ensure Wall Rock of Tunnel stabilization and construction safety,
During tunnel support, preliminary bracing generally uses bracing members to carry out supporting construction after excavating for IV, V class surrounding rock.By right
It excavates region and carries out bracing members reinforcing, can carry immediately, to ensure the stabilization of tunnel excavation country rock.In previous underground chamber work
In the construction of journey excavation supporting, when especially constructing to the bracing members of preliminary bracing, mostly based on manually installed, work surface installation
Personnel are more.For the location of country rock difference, tend to produce because surrounding rock stability is poor, safety accident caused by supporting not in time etc.
Raw biggish economic loss is unfavorable for the engineering constructions such as current water conservancy and hydropower, highway, railway, municipal administration construction and to safety, economy
The demand of benefit.
Utility model content
The purpose of this utility model is the construction personnel in order to control supporting work surface, reduces personnel under unstable surrounding rock
The time of operation provides the tunnel that a kind of safety coefficient is high, speed of application is fast, the number of turnover is more, structure is simple, is easily installed
Bracing members installation auxiliary device, it is ensured that production safety.
A kind of the technical solution of the utility model are as follows: tunnel bracing members installation auxiliary device, comprising: bearing support, bearing support
Middle part be equipped with jack, the steel pipe of a different-diameter is connected with above jack, a jacking is connected on steel pipe, jacking connects vault
Bracing members.
The bearing support be it is tower-shaped, be made of fashioned iron, lacing wire and steel plate up and down two ladder-shaped frames.
The vault bracing members are arc.
The jacking is T shape, and here is joint steel pipe, and the above is connection vault bracing members rectangle frame slot.
The good effect of the utility model:
1, it realizes and realizes temporary support protection in the arch of non-supporting, reduce the dead time of personnel, effectively improve
The safety coefficient of bracing members arch installation personnel, it is ensured that construction production safety.
2, using the device, the speed that construction personnel installs arch is accelerated, the construction time is shortened.
3, lightweight construction, assembly and disassembly are flexible and convenient, and the number of turnover is more, produce greatly society and economic effect
Benefit.
Detailed description of the invention
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment
Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, for ordinary skill people
For member, without creative efforts, it is also possible to obtain other drawings based on these drawings.
Fig. 1 is the tunnel bracing members installation auxiliary device cross-sectional configuration schematic diagram of the utility model.
Fig. 2 is the portion the A enlarged drawing in Fig. 1.
Fig. 3 is the side view of Fig. 2
Fig. 4 is the portion the B enlarged drawing in Fig. 1.
Fig. 5 is the top view of Fig. 4.
In figure: 1- bearing support, 2- lacing wire, 3- jack, 4- steel plate, the steel pipe of 5- different-diameter, 6- vault bracing members, 7-
Jacking.
Specific embodiment
In order to make the purpose of the utility model, technical solutions and advantages more clearly understood, with reference to embodiments, to this
Utility model is further elaborated.It should be appreciated that specific embodiment described herein is only used to explain that this is practical
It is novel, it is not used to limit the utility model.
As shown in Figure 1, the tunnel bracing members installation auxiliary device of the utility model is by bearing support, bearing support be it is tower-shaped, by
Fashioned iron 1, lacing wire 2 and steel plate 4 constitute two ladder-shaped frames up and down.The middle part steel plate 4 of bearing support is equipped with jack 3, such as Fig. 4, Fig. 5
It is shown.It is connected with the steel pipe 5 of a different-diameter above jack, a jacking 7 is connected on steel pipe, the jacking 7 is T shape, under
Face is joint steel pipe, and the above is connection vault bracing members rectangle frame slot, as shown in Figure 2 and Figure 3.Jacking connects vault bracing members 6,
For fixing arch bracing members, the vault bracing members are arc.
Specific production method: fashioned iron, lacing wire, steel plate, different model steel pipe, vault bracing members and top are carried out according to design drawing
Jack is purchased in the blanking and assembling of support.After processing is completed, progress is assembled for tunnel bracing members auxiliary device main structure, then with
Jack combination debugging.After the completion of tunnel excavation is got rid of the danger, the hole slag charge within the scope of device is cleaned out first, then carries out device peace
Arch steel arch-shelf top is carried out the installation of arch reinforced mesh, reinforced mesh at scar 5cm height using jack by dress
By arch steel arch-shelf top to scar after being installed, spray concrete is then carried out.After the completion of the preliminary bracing of arch, it is connected with top
Fashioned iron is allowed to form entirety, then hangs reinforced mesh in time and is welded to connect muscle, so that front and back steel arch-shelf is formed entirety, finally tear open
Except auxiliary device, it is transferred to the use of subsequent cycle steel shotcrete support.
Claims (2)
1. a kind of auxiliary device of tunnel bracing members installation, it is characterised in that: include: the middle part of bearing support, bearing support equipped with thousand
Jin pushes up, and the steel pipe of a different-diameter is connected with above jack, and a jacking is connected on steel pipe, and jacking connects vault bracing members;It is described
Bearing support be it is tower-shaped, be made of fashioned iron, lacing wire and steel plate up and down two ladder-shaped frames;The jacking is T shape, and here is to connect
Steel pipe is connect, the above is connection vault bracing members rectangle frame slot.
2. the auxiliary device of tunnel bracing members installation according to claim 1, it is characterised in that: the vault bracing members
For arc.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821702066.5U CN209539374U (en) | 2018-10-19 | 2018-10-19 | A kind of auxiliary device of tunnel bracing members installation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821702066.5U CN209539374U (en) | 2018-10-19 | 2018-10-19 | A kind of auxiliary device of tunnel bracing members installation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209539374U true CN209539374U (en) | 2019-10-25 |
Family
ID=68247172
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821702066.5U Active CN209539374U (en) | 2018-10-19 | 2018-10-19 | A kind of auxiliary device of tunnel bracing members installation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209539374U (en) |
-
2018
- 2018-10-19 CN CN201821702066.5U patent/CN209539374U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101864963B (en) | Large-section loess tunnel construction method | |
CN206942764U (en) | The supplementary structure of assembly and disassembly shield machine or TBM development machines in a kind of hole | |
CN203239357U (en) | Adjacent tunnel supporting structure suitable for collapsible loess | |
CN101539021B (en) | Road tunnel excavation method | |
CN102305077A (en) | Rapid construction method of large-section multi-arc tunnel | |
CN105003272A (en) | Reversed construction method for expanding and excavating stations on sectional shield tunnel foundations of subways | |
CN102373930A (en) | Rapid construction method of weak surrounding rock large-section multi-arc tunnel | |
CN110306592A (en) | It is a kind of elder generation shield after well underground pipe gallery construction method | |
CN104775832A (en) | Primary support structure of corrugated steel tunnel | |
CN203583493U (en) | Combined lattice steel frame spray anchoring foundation pit supporting structure | |
CN209539374U (en) | A kind of auxiliary device of tunnel bracing members installation | |
CN110159323A (en) | The construction method fixed with steel arch-shelf is excavated suitable for extra-large cross-section underground chamber | |
CN108979663A (en) | A kind of main structure of subway station construction method using interim middle spacer post support | |
CN208734343U (en) | A kind of station tunnel excavation structure with interim middle spacer post support | |
CN105156130B (en) | A kind of constructing tunnel exempts from supporting safe construction method | |
CN103775094B (en) | Gravel soil stratum medium-sized section water-conveyance tunnel two step three step excavation construction method | |
CN207647521U (en) | Supporting structure system is faced in a kind of rock matter large section tunnel inclined shaft hole of becoming a full member forever | |
CN204646267U (en) | A kind of corrugated steel Tunnel structure | |
CN205936634U (en) | Big section joint rock mass subway tunnel supporting construction of little clean distance | |
CN113944479A (en) | Unfavorable geological tunnel three-fork construction method | |
CN212003200U (en) | A expand and dig structure for shield tunnel foundation is last | |
CN111305856B (en) | Shield construction starting method for subway in narrow section | |
CN204457784U (en) | Large-diameter shield in a kind of tunneling air channel receives and starting well | |
CN210396760U (en) | Assembled supporting system for diversion tunnel construction | |
CN104500114B (en) | Metro built by mining method transverse passage-way temporary support system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||