CN204457784U - Large-diameter shield in a kind of tunneling air channel receives and starting well - Google Patents

Large-diameter shield in a kind of tunneling air channel receives and starting well Download PDF

Info

Publication number
CN204457784U
CN204457784U CN201520080067.0U CN201520080067U CN204457784U CN 204457784 U CN204457784 U CN 204457784U CN 201520080067 U CN201520080067 U CN 201520080067U CN 204457784 U CN204457784 U CN 204457784U
Authority
CN
China
Prior art keywords
air channel
ring beam
shield
supporting
starting well
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201520080067.0U
Other languages
Chinese (zh)
Inventor
汪波
宫本福
李宏安
薛彦
李建军
杨冬梅
黄齐武
张丽丽
孙文龙
李会
李志强
赵新生
张全利
白郁明
芦荣海
杜海巍
兴丘慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Municipal Construction Co Ltd
Beijing MTR Construction Administration Corp
Original Assignee
Beijing Municipal Construction Co Ltd
Beijing MTR Construction Administration Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Municipal Construction Co Ltd, Beijing MTR Construction Administration Corp filed Critical Beijing Municipal Construction Co Ltd
Priority to CN201520080067.0U priority Critical patent/CN204457784U/en
Application granted granted Critical
Publication of CN204457784U publication Critical patent/CN204457784U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The large-diameter shield that the utility model relates in a kind of tunneling air channel receives and starting well, and it comprises top, air channel ring beam, supporting and protection structure, base plate, sidewall structure, side wall ring beam and bottom, air channel ring beam; Wherein, top, described air channel ring beam is arranged on the top of supporting and protection structure; In described supporting and protection structure, form large shield structure receive and starting well; Bottom, described air channel ring beam is arranged on the bottom of supporting and protection structure; Described side wall ring beam is arranged on the both sides of supporting and protection structure; Described sidewall structure is positioned at the outside of side wall ring beam; Described base plate is positioned at the bottom of bottom, air channel ring beam.The object that large-diameter shield reception in tunneling air channel of the present utility model and starting well can realize " when the air channel structure of termination, station is when can not complete construction before large-diameter shield arrives on schedule; the soil excavation and the strengthened ring beam structure that first complete position, shield crossing air channel are built; form shield structure and receive and starting well; allow shield structure pass through in advance ", does not need reduction shield driving speed or shutdown to wait for.

Description

Large-diameter shield in a kind of tunneling air channel receives and starting well
[technical field]
The utility model relates to a kind of shield structure and receives and starting well, and the large-diameter shield be specifically related in a kind of tunneling air channel receives and starting well, belongs to railway traffic engineering technical field.
[background technology]
Subway sectional tunnel and station all adopt large-diameter shield to tunnel, and once form one-tunnel two-tracks tunnel, station digs on shield tunnel basis, and this construction method and planned management of project better can solve subway engineering conventional at present and prepare run into difficulty.But adopt this planned management of project mode generally all to require to complete the air channel structure construction at two ends, station before arrival station, possess the condition receiving shield structure or shield crossing is provided.
Because air channel is tunneling big cross section high side wall structure, need the long period just can complete construction, if removed by ground, pipeline changes the factor such as to move and restricts, ventilating shaft and air channel structure may can not complete structure construction before arrival, shield structure can only slow down driving speed or wait, affect the realization of shield-tunneling construction efficiency and " hole leads to target ", and the Enlargement excavation duration of station agent structure also can be subject to corresponding impact.
Therefore, for solving the problems of the technologies described above, necessaryly provide large-diameter shield in a kind of tunneling air channel of innovation to receive and starting well, to overcome described defect of the prior art.
[utility model content]
For solving the problem, the purpose of this utility model is to provide the large-diameter shield in a kind of tunneling air channel to receive and starting well, and it receives and the condition started for providing large-diameter shield in the air channel not yet completing air channel entire infrastructure construction.
For achieving the above object, the technical scheme that the utility model is taked is: the large-diameter shield in a kind of tunneling air channel receives and starting well, and it comprises top, air channel ring beam, supporting and protection structure, base plate, sidewall structure, side wall ring beam and bottom, air channel ring beam; Wherein, top, described air channel ring beam is arranged on the top of supporting and protection structure; Form large shield structure in described supporting and protection structure to receive and starting well; Bottom, described air channel ring beam is arranged on the bottom of supporting and protection structure; Described side wall ring beam is arranged on the both sides of supporting and protection structure; Described sidewall structure is positioned at the outside of side wall ring beam; Described base plate is positioned at the bottom of bottom, air channel ring beam.
Large-diameter shield in tunneling air channel of the present utility model receives and starting well is further: described supporting and protection structure adopts grid concrete spraying support structure, and grid Pin distance is 50cm ~ 75cm.
Compared with prior art; the utility model has following beneficial effect: the object that the large-diameter shield reception in tunneling air channel of the present utility model and starting well can realize " when the air channel structure of termination, station is when can not complete construction before large-diameter shield arrives on schedule; the soil excavation and the strengthened ring beam structure that first complete position, shield crossing air channel are built; form shield structure and receive and starting well; allow shield structure pass through in advance ", does not need reduction shield driving speed or shutdown to wait for.Guarantee shield driving not by the restriction of air channel, station construction; Whole planned management of project is served as theme with running tunnel, can realize the target of " hole leads to " as early as possible.
[accompanying drawing explanation]
Fig. 1 be construction step 1 of the present utility model) working drawing.
Fig. 2-1 be construction step 2 of the present utility model) working drawing.
Fig. 2-2 is Fig. 2 sectional drawings along A-A.
Fig. 3-1 be construction step 3 of the present utility model) working drawing.
Fig. 3-2 is Fig. 2 sectional drawings along B-B.
Fig. 4 be construction step 4 of the present utility model) working drawing.
Fig. 5 is that large-diameter shield in tunneling air channel of the present utility model receives and the structural representation of starting well.
[detailed description of the invention]
Refer to shown in Figure of description 5, the utility model is that the large-diameter shield in a kind of tunneling air channel receives and starting well, and it is made up of a few parts such as top, air channel ring beam 10, supporting and protection structure 11, base plate 13, sidewall structure 14, side wall ring beam 15 and bottom, air channel ring beams 16.
Wherein, top, described air channel ring beam 10 is arranged on the top of supporting and protection structure 11.
Form large shield structure in described supporting and protection structure 10 to receive and starting well 12, this supporting and protection structure 10 adopts grid concrete spraying support structure, and grid Pin distance is 50cm ~ 75cm
Bottom, described air channel ring beam 16 is arranged on the bottom of supporting and protection structure 11.Described side wall ring beam 15 is arranged on the both sides of supporting and protection structure 10.
Described sidewall structure 14 is positioned at the outside of side wall ring beam 15.Described base plate 13 is positioned at the bottom of bottom, air channel ring beam 16.
Large-diameter shield in tunneling air channel of the present utility model receive and the Specific construction step of starting well as follows:
1), as shown in Figure 1, before arrival, grouting and reinforcing 2 is carried out to the soil body of shield structure turnover both sides, air channel 1, improve the self-stable ability of the soil body, can adopt the method that in surface grout injection and little pilot tunnel, slip casting combines, the soil strength index after the scope of grouting and reinforcing and slip casting should be determined by calculating under the loading condition considering shield crossing operating mode.
2), as shown in Figure 2, using vertical shaft 3 as construction passage, ingate is opened at shaft wall after grouting and reinforcing is carried out to the soil body at ingate position, the three Pin grid solid matters at ingate position.By the little pilot tunnel 4 of both sides, shaft excavation air channel, the distance being not less than 5m should be kept between two little pilot tunnels, little pilot tunnel adopts short benching tunnelling method to excavate, stay Core Soil, the step pitch of each excavation is 0.75m, and often before circulation excavation, the reply arch soil body adopts advanced tubule to carry out grouting and reinforcing, and grouting serous fluid adopts cement paste, if stratum is moisture, answer cementing water glass dual slurry.
3), as shown in Figure 3, castinplace pile 5 in the little pilot tunnel 4 in both sides, pilot tunnel through rear construction air channel and stake apical cap beam 6, castinplace pile 5 can adopt the mode of mechanical hole building or manually digging hole, the castinplace pile diameter of mechanical hole building is generally 800mm, and the castinplace pile diameter of manually digging hole is generally 1000mm or 1200mm.Then excavate air channel middle drift 9 cubic metres of earth and perform arch preliminary bracing 7 and arch inner lining structure 8, middle drift adopts short benching tunnelling method to excavate, and stay Core Soil, according to vault and Ground Subsidence Monitoring result, interim vertical supporting and Temporary invert are set in middle drift if desired.Before middle drift 9 excavates, the reply middle drift arch soil body adopts advanced deep hole grouting or per-fore pouring liquid with small pipe to reinforce.
4) the air channel top loop girder construction 10 at large-diameter shield export & import position, as shown in Figure 4, is applied.
5), as shown in Figure 5, in air channel, excavation large-diameter shield passes through the earthwork at position, air channel downwards, the large shield structure of reverse construction is adopted to receive and starting well 11, receive and to utilize at shield structure export & import position in hole castinplace pile as supporting and protection structure 12 with starting well, all the other both sides adopt grid concrete spraying support pattern, and grid Pin is apart from being 50cm ~ 75cm, after soil excavation to shaft bottom design elevation, apply base plate 13, sidewall structure 14 and side wall ring beam 15 and bottom ring beam 16.Around large-diameter shield export & import, ring beam sets up bracing members, bracing members is bearing on the castinplace pile at export & import position by ring beam.
Above detailed description of the invention is only the preferred embodiment of this creation, and not in order to limit this creation, any amendment made within all spirit in this creation and principle, equivalent replacement, improvement etc., within the protection domain that all should be included in this creation.

Claims (2)

1. the large-diameter shield in tunneling air channel receives and a starting well, it is characterized in that: comprise top, air channel ring beam, supporting and protection structure, base plate, sidewall structure, side wall ring beam and bottom, air channel ring beam; Wherein, top, described air channel ring beam is arranged on the top of supporting and protection structure; In described supporting and protection structure, form large shield structure receive and starting well; Bottom, described air channel ring beam is arranged on the bottom of supporting and protection structure; Described side wall ring beam is arranged on the both sides of supporting and protection structure; Described sidewall structure is positioned at the outside of side wall ring beam; Described base plate is positioned at the bottom of bottom, air channel ring beam.
2. the large-diameter shield in tunneling air channel as claimed in claim 1 receives and starting well, it is characterized in that: described supporting and protection structure adopts grid concrete spraying support structure, and grid Pin distance is 50cm ~ 75cm.
CN201520080067.0U 2015-02-04 2015-02-04 Large-diameter shield in a kind of tunneling air channel receives and starting well Expired - Fee Related CN204457784U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201520080067.0U CN204457784U (en) 2015-02-04 2015-02-04 Large-diameter shield in a kind of tunneling air channel receives and starting well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201520080067.0U CN204457784U (en) 2015-02-04 2015-02-04 Large-diameter shield in a kind of tunneling air channel receives and starting well

Publications (1)

Publication Number Publication Date
CN204457784U true CN204457784U (en) 2015-07-08

Family

ID=53664686

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201520080067.0U Expired - Fee Related CN204457784U (en) 2015-02-04 2015-02-04 Large-diameter shield in a kind of tunneling air channel receives and starting well

Country Status (1)

Country Link
CN (1) CN204457784U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105298501A (en) * 2015-11-11 2016-02-03 上海市城市建设设计研究总院 Construction method for auxiliary air duct structure of underground excavation station
CN106089220A (en) * 2016-07-15 2016-11-09 中铁第四勘察设计院集团有限公司 In a kind of water, shield machine arrives and receives structure and method of reseptance

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105298501A (en) * 2015-11-11 2016-02-03 上海市城市建设设计研究总院 Construction method for auxiliary air duct structure of underground excavation station
CN106089220A (en) * 2016-07-15 2016-11-09 中铁第四勘察设计院集团有限公司 In a kind of water, shield machine arrives and receives structure and method of reseptance
CN106089220B (en) * 2016-07-15 2019-01-29 中铁第四勘察设计院集团有限公司 Shield machine, which reaches, in a kind of water receives structure and method of reseptance

Similar Documents

Publication Publication Date Title
CN104653188B (en) A kind of large-diameter shield that arranges in tunneling air channel receives and the method for starting well
CN102758632B (en) Rock stratum double initial support layering method for establishing large-scale underground structure
CN102562075B (en) Large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method
CN106703828B (en) The construction method of subway station is built using prefabricated assembled lining cutting combination PBA
CN102644466B (en) Joist arching method for constructing ultra-shallow buried large-span underground excavated subway station in rocky stratum
CN106567717B (en) It is a kind of to double as construction access ramp structure and construction method using subway entrance
CN101864963B (en) Large-section loess tunnel construction method
CN100554646C (en) Shield method combines the job practices of building the subway station with shallow burial hidden digging
CN104612698A (en) Method for constructing upper step middle partition wall of shallow-buried excavation tunnel
CN102155232B (en) Construction method of large-span asymmetrical double-arch railway tunnel under terrain bias pressure condition
CN105041349A (en) Underground excavation construction method for expanded excavation of station on basis of metro regional shield tunnel
CN102373930A (en) Rapid construction method of weak surrounding rock large-section multi-arc tunnel
CN102071947A (en) Construction method for soft surrounding rock section of large-span tunnel portal
CN106761778A (en) A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground
CN103089270B (en) Excavating method suitable for large section loess tunnels
CN105201516A (en) Subway station body structure and four-joint-arch PBA underground excavation construction method thereof
CN109139021A (en) A kind of more pilot tunnel Construction Organization Methods of multi-step
CN107401161A (en) High ferro shield tunnel construction method is worn under pipe-roof method and MJS method joint reinforcements
CN103993885A (en) Construction method for underground excavation tunnel side-direction hole opening supporting system
CN106049538A (en) Reverse-building-method underground engineering building envelope crown beam anti-floating node
CN205100989U (en) Utilize oblique access structure of subway access & exit double as construction
CN104712343B (en) A kind of big shield is built the shield of air channel structure again and is missed the stop method after first missing the stop
CN104295301A (en) Shallow-buried excavation construction method for cataclastic rock subway tunnel intersection
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure
CN204851266U (en) Secretly dig shaft structure directly over station

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150708

Termination date: 20160204

CF01 Termination of patent right due to non-payment of annual fee