CN209428961U - A kind of steel box-girder installation bracket equipped with safe operation platform - Google Patents
A kind of steel box-girder installation bracket equipped with safe operation platform Download PDFInfo
- Publication number
- CN209428961U CN209428961U CN201822039715.4U CN201822039715U CN209428961U CN 209428961 U CN209428961 U CN 209428961U CN 201822039715 U CN201822039715 U CN 201822039715U CN 209428961 U CN209428961 U CN 209428961U
- Authority
- CN
- China
- Prior art keywords
- platform
- steel
- welded
- operating platform
- steel box
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model provides a kind of steel box-girder installation bracket equipped with safe operation platform, the operating platform that connection one extends horizontally outward in the end of two I-shaped goosenecks of cradle top, platform side and two I-steel beam-ends are welded, the construction personnel passway of rectangle is equipped among platform, ladder is equipped between the lateral bar and operating platform bottom of the top between outermost two steel columns of bracket direction across bridge, it is welded among the lower end of ladder and lateral bar, the construction personnel passway on upper end and operating platform is welded far from the side of steel column.The utility model problem narrow for operating space at the top of existing steel box-girder installation falsework, sets up operating platform at bracket both ends, under the premise of not influencing steel box-girder installation, provides the operating space of safety spaciousness for construction personnel.
Description
Technical field
The utility model relates to steel box girder bridge technical field of construction, and in particular to a kind of facing for steel box-girder installation
When bracket.
Background technique
Steel box girder bridge has many advantages, such as that big span, short construction period and working procedure are simple, is widely used in across existing
The science of bridge building of road.When steel box-girder installation, need to set up multiple falseworks, each falsework below steel box-girder
Including direction across bridge two rows of steel columns disposed in parallel, every steel column lower end is supported in ground base, every row's steel column it is upper
End is connected by I-shaped gooseneck, is connected by diagonal brace with lateral between adjacent steel column.
When steel box-girder installation, sand cylinder or jack to be installed in cradle top, be used for temporary support steel box-girder, and right
Steel box-girder absolute altitude is adjusted and controls;After steel box-girder is adjusted in place, sand cylinder or very heavy heights of roofs are reduced, steel box-girder is fallen on into bridge
On pier support.It needs to be operated at the top of falsework by construction personnel in work progress.But falsework headspace is narrow
It is narrow, operating space and walking passageway of the plank as construction personnel can only be set up between the horizontal-associate bar between two rows of steel columns, no
Only construction is inconvenient, and since most of constructing operations are positioned at the progress of bracket both ends, face do-nothing operation and be highly detrimental to ensure
The safety of construction personnel.
Summary of the invention
The purpose of this utility model is that can not ensure construction personnel's safety operation for existing steel box-girder mounting bracket
Problem provides a kind of steel box-girder installation bracket equipped with safe operation platform, facilitates construction, and ensure the peace of construction personnel
Entirely.
The technical solution of the utility model is as follows:
A kind of steel box-girder installation bracket equipped with safe operation platform, the bracket includes that direction across bridge is disposed in parallel
The lower end of two rows of steel columns, every steel column is supported in ground base, is connected between adjacent steel column by diagonal brace and lateral
It connects, the upper end of every row's steel column is connected by I-shaped gooseneck, it is characterised in that: the connection one in the end of two I-shaped goosenecks
The operating platform extended horizontally outward along I-shaped gooseneck, the side of the operating platform and I-steel beam-end are welded, behaviour
Make the construction personnel passway that rectangle is equipped among platform, the lateral of the top between outermost two steel columns of direction across bridge
Be equipped with ladder between bar and operating platform bottom, welded among the lower end of the ladder and the lateral bar, the upper end of ladder and
It is welded far from the side of steel column construction personnel passway on operating platform.
The utility model attended operation platform on existing steel box-girder installation falsework, and operating platform is in bracket
Both ends extend outwardly, and under the premise of not influencing to install steel box-girder on bracket, have expanded cradle top space significantly, can be to construction
Personnel provide the spacious operating environment of safety, facilitate construction personnel in steel column and I-steel cross rail top setting sand cylinder or
Jack, and the adjustment control steel box-girder absolute altitude in steel box-girder installation, are able to satisfy construction requirement, and can sufficiently ensure constructor
Member's safety.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model direction across bridge;
Fig. 2 be the utility model along bridge to structural schematic diagram;
Fig. 3 is the planar structure schematic diagram of operating platform frame.
Specific embodiment
As shown in Figure 1 and Figure 2, the utility model bracket includes direction across bridge two rows of steel columns 1 disposed in parallel.Every row's steel is vertical
Column has more, two for being located at bracket one end in row's steel column is merely illustrated in Fig. 1, the structure of the bracket other end is identical.Often
The lower end of root steel column 1 is supported in ground base 2, face between two adjacent steel columns 1 and between two rows in every row
It between two steel columns, is all connected by diagonal brace 3 and lateral 4, the upper end of every row's steel column is connected by I-shaped gooseneck 5, two
The operating platform 6 that the end connection one of root I-shaped gooseneck 5 extends horizontally outward along I-shaped gooseneck 5, the operating platform 6
Side and 5 end of I-shaped gooseneck are welded;The construction personnel passway of rectangle is equipped among the operating platform 6, in direction across bridge
Ladder 7 is equipped between outermost two steel columns 1 between the lateral 4 and operating platform bottom of the top, under the ladder 7
It holds and is welded among the lateral 4, side of the construction personnel passway far from steel column on the upper end and operating platform of ladder 7
Welding.
In above structure, on the other hand channel of 7 one side of ladder as construction personnel's down operation platform 1 is made
For the support of platform, stabilization is played to platform, and platform and bracket is made to connect into a firm entirety.Construction personnel Ke Tong
It crosses round-trip on the channel that ladder is set up between platform and bracket lateral and carries out corresponding constructing operation.
As shown in figure 3, the operating platform 6 include it is horizontally disposed by more horizontally disposed cross bars 61 and Duo Gen and with cross
The rectangular platform frame that the vertical vertical pole 62 of bar is welded into is laid with flat surface plate on the platform framework.After being laid with platform panel,
The top surface of platform panel will be flushed with the top surface of I-shaped gooseneck 5.
When the cross bar 61 of platform framework is connect with vertical pole 62, construction personnel passway 63 is reserved among platform framework,
When being laid with platform panel, corresponding passway is also set with the corresponding position in construction personnel passway on platform framework.
Further, the utility model in the specific implementation, can be in side of the operating platform 6 far from steel column and and I-steel
The parallel two sides of crossbeam 5, are respectively set platform guardrail 8, form a semi open model operating platform, can both construction personnel be protected to pacify
Entirely, and facilitate construction personnel in steel column and I-steel cross rail top setting sand cylinder or jack, and adjustment control steel box-girder
The operation such as absolute altitude.
Claims (3)
1. a kind of steel box-girder installation bracket equipped with safe operation platform, including direction across bridge two rows of steel disposed in parallel are vertical
The lower end of column, every steel column is supported in ground base, is connected by diagonal brace with lateral between adjacent steel column, every row's steel
The upper end of column is connected by I-shaped gooseneck, it is characterised in that: in the end of two I-shaped goosenecks, connection one is along I-steel
The operating platform that crossbeam extends horizontally outward, the side of the operating platform and two I-steel beam-ends are welded, operating platform
Centre is equipped with the construction personnel passway of rectangle, the lateral bar of the top and behaviour between outermost two steel columns of direction across bridge
Make to be equipped with ladder between mesa base, be welded among the lower end of the ladder and the lateral bar, the upper end of ladder and operation are flat
It is welded far from the side of steel column construction personnel passway on platform.
2. the steel box-girder installation bracket according to claim 1 equipped with safe operation platform, it is characterised in that: described
Operating platform includes the rectangle being welded by horizontally disposed and vertical with the cross bar vertical pole of more horizontally disposed cross bars and Duo Gen
Platform framework is equipped with flat surface plate on the platform framework, and the top surface of the platform panel and the top surface of I-shaped gooseneck are neat
It is flat.
3. the steel box-girder installation bracket according to claim 1 equipped with safe operation platform, it is characterised in that: described
Side and with I-shaped gooseneck parallel two sides of the operating platform far from steel column, are respectively arranged with platform guardrail.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822039715.4U CN209428961U (en) | 2018-12-05 | 2018-12-05 | A kind of steel box-girder installation bracket equipped with safe operation platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822039715.4U CN209428961U (en) | 2018-12-05 | 2018-12-05 | A kind of steel box-girder installation bracket equipped with safe operation platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209428961U true CN209428961U (en) | 2019-09-24 |
Family
ID=67970936
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822039715.4U Active CN209428961U (en) | 2018-12-05 | 2018-12-05 | A kind of steel box-girder installation bracket equipped with safe operation platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209428961U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113309008A (en) * | 2021-07-05 | 2021-08-27 | 中建八局第四建设有限公司 | Steel case roof beam temporary support construction safety work platform |
-
2018
- 2018-12-05 CN CN201822039715.4U patent/CN209428961U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113309008A (en) * | 2021-07-05 | 2021-08-27 | 中建八局第四建设有限公司 | Steel case roof beam temporary support construction safety work platform |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106939707B (en) | A kind of restricted clearance large-scale steel structure supporting platform from method for improving | |
CN106760529A (en) | Roof system steel truss slipping and assembling operation platform and installation method | |
KR101026012B1 (en) | Bridge deck dismantling method by means of united pulling jack and pier | |
CN210066507U (en) | Combined high pier capping beam construction support | |
CN206902556U (en) | It is a kind of to combine protector across both wired bridge constructions | |
WO2022252829A1 (en) | Liftable scaffold, lifting and installation methods thereof, and construction method for prefabricated building | |
CN110512517B (en) | Bridge engineering construction platform | |
CN209428961U (en) | A kind of steel box-girder installation bracket equipped with safe operation platform | |
CN107740352A (en) | The isolating and protecting platform and construction method of bridge maintaining transformation are shared applied to rail-road | |
CN206707237U (en) | Cable-stayed type top layer construction platform for elevator installation | |
CN219280494U (en) | Tower beam temporary consolidation supporting structure for bridge tower stability control | |
CN202990427U (en) | Climbing discharging platform | |
CN209780193U (en) | Suspension type scaffold | |
CN204475182U (en) | The mounting tool of a kind of Railway Bridges And Piers pier top hanging basket | |
CN208167484U (en) | The steel construction overline bridge being easily installed | |
CN114319159B (en) | Ascending ramp dismantling system and construction method | |
CN209194354U (en) | High-altitude long-span binder base-supporting shellfish thunder support construction | |
CN211313347U (en) | Assembled walkway plate device | |
CN209227390U (en) | A kind of assembled Multifunction side is across cast-in-place support | |
CN210589859U (en) | Movable precast beam concrete cloth construction platform | |
CN210002824U (en) | Large-span arch curved surface grid roof construction platform | |
CN203755178U (en) | Novel ultra-wide large-span specially-shaped steel arch bridge construction device | |
CN112726416A (en) | Support structure meeting field construction security and construction method | |
CN102587649A (en) | Template profiled bar supporting system of high and large cantilever structure | |
CN202831591U (en) | Special-shaped truss operation platform capable of hoisting to super high space |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |