CN210066507U - Combined high pier capping beam construction support - Google Patents

Combined high pier capping beam construction support Download PDF

Info

Publication number
CN210066507U
CN210066507U CN201920509055.3U CN201920509055U CN210066507U CN 210066507 U CN210066507 U CN 210066507U CN 201920509055 U CN201920509055 U CN 201920509055U CN 210066507 U CN210066507 U CN 210066507U
Authority
CN
China
Prior art keywords
pier
bracket
platform
bridge
rods
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201920509055.3U
Other languages
Chinese (zh)
Inventor
陈松洲
王晋
李玲玉
黄灿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Middle Cross-Channel Bridge South Engineering Co Ltd
Road and Bridge International Co Ltd
Original Assignee
Middle Cross-Channel Bridge South Engineering Co Ltd
Road and Bridge International Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Middle Cross-Channel Bridge South Engineering Co Ltd, Road and Bridge International Co Ltd filed Critical Middle Cross-Channel Bridge South Engineering Co Ltd
Priority to CN201920509055.3U priority Critical patent/CN210066507U/en
Application granted granted Critical
Publication of CN210066507U publication Critical patent/CN210066507U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The utility model provides a combined high pier capping beam construction bracket, wherein two brackets are respectively arranged at two sides of each pier along the bridge direction, and a bearing beam, a distribution beam and a capping beam construction template are sequentially arranged on the brackets; connect an L type gallows in every bracket bottom, L type gallows includes a montant and a horizontal pole, the pier shaft is hugged closely to the montant, the upper end passes through the round pin hub connection with bracket bottom sprag board, the one end of lower extreme fixed connection horizontal pole, the other end of horizontal pole is followed and is extended to the level along the bridge, has set up many spinal branchs vaulting pole between the horizontal pole of all L type gallows that lie in pier with one side, lay the panel on the bracing piece and form platform down, the pier bottom is equipped with the lower cat ladder that leads to platform down along the pier shaft. The utility model discloses a lower platform carries out the installation of support and dismantles, has solved the problem that high mound support did not have the installation to dismantle construction platform in the past.

Description

Combined high pier capping beam construction support
Technical Field
The utility model relates to a bridge bent cap construction formwork support, concretely relates to modular bent cap construction formwork support system.
Background
Under the condition that the ground support cannot be adopted due to terrain and geological reasons at the bridge position, the construction of the bridge high pier capping beam in mountain and valley areas can adopt a pin rod type, hoop type or bracket type support structure. A hole that runs through the pier stud needs to be reserved to the round pin stick method, and the later stage adopts the concrete to fill, and it is difficult to guarantee to pack the concrete quality, and round cross-section bending resistance effect of round pin stick is not good moreover, and the bearing capacity is not high. By adopting the hoop method, the value of the friction coefficient between the hoop and the pier stud is difficult to master, and the slippage accident of the hoop is easy to occur during construction, so that the bearable load is limited. The bracket method is characterized in that brackets are installed on a pier by means of connecting pieces embedded in a pier body, and although certain influence is caused on the appearance of the pier body, the bracket method is high in bearing capacity, so that the bracket method is frequently adopted in large-volume bent cap construction. No matter above be round pin stick formula, staple bolt formula or cow-leg formula support, because the support is installed at high mound top, no lower part basis supports, does not have construction platform during installation is dismantled, consequently all has the problem of support mounting and dismantlement difficulty.
Disclosure of Invention
The utility model aims to solve the not enough of current bent cap support construction existence, provide one set of be convenient for installation and the combination formula bridge bent cap construction support of dismantling.
The technical scheme of the utility model as follows:
the utility model provides a modular high mound bent cap construction support, installs two brackets through pier shaft built-in fitting respectively in every pier in the same direction as the bridge both sides, and the transverse bridge has set up the spandrel girder to putting up on the bracket of pier with one side, has set up the distribution roof beam on the spandrel girder, installs bent cap construction template, its characterized in that on the distribution roof beam: the bottom of each bracket is connected with an L-shaped hanging bracket, each L-shaped hanging bracket comprises a vertical rod and a cross rod, the vertical rods are tightly attached to the pier body, the upper ends of the vertical rods are connected with the bracket bottom supporting plate through pin shafts, the lower ends of the vertical rods are fixedly connected with one end of the cross rod, and the other end of the cross rod horizontally extends along the direction along the bridge; the vertical rods of the two L-shaped hanging frames on each side of each pier are connected through a cross brace, a plurality of supporting rods are arranged among the cross rods of all the L-shaped hanging frames on the same side of the pier in an overlapping mode, a panel is laid on the supporting rods to form a lower platform, and lower platform guardrails are arranged on the periphery of the lower platform; and a lower crawling ladder leading to the lower platform is arranged at the bottom of the pier along the pier body.
The utility model discloses a modular bent cap construction support, support girder place on supporting the bracket, bear the upper portion load by supporting bracket and built-in fitting jointly, and the bracket below has set up lower platform through L shape gallows, makes things convenient for the workman to install, demolish the bent cap support. The problem of traditional support mounting dismantlement do not have operation platform is solved to can guarantee the work progress safety.
Drawings
Fig. 1 is a schematic view showing a vertical structure of a transverse bridge of the present invention;
fig. 2 is a schematic view of the vertical structure along the direction of the bridge.
Detailed Description
As shown in fig. 1 and 2, in the combined high pier capping beam construction support provided by the present invention, two corbels 2 are respectively installed on two sides of each pier 1 along the bridge direction through pier body embedded parts, a bearing beam 3 is erected on the corbel of the same side of the pier 1 along the transverse bridge direction, a distribution beam 4 is erected on the bearing beam 3, and a capping beam construction template 5 is installed on the distribution beam 4; an L-shaped hanging bracket is connected to the bottom of each bracket 2, and comprises a vertical rod 6 and a cross rod 7. Bracket 2 includes curb plate and roof, and the curb plate is connected with pier shaft built-in fitting, and the roof level sets up, two vertical backup pads of roof bottom welding. The vertical rod 6 is tightly attached to the pier body, the upper end of the vertical rod is positioned between the two support plates of the bracket, a pin shaft is transversely arranged between the two support plates of the bracket and the upper end of the vertical rod, and the vertical rod is connected with the support plate at the bottom of the bracket through the pin shaft; the lower end of the vertical rod 6 is fixedly connected with one end of a cross rod 7, and the other end of the cross rod 7 horizontally extends along the bridge direction. The vertical rods 6 of the two L-shaped hanging frames on each side of each pier are connected through a cross brace 8, a plurality of support rods 9 are erected among the cross rods 7 of all the L-shaped hanging frames on the same side of the pier, a panel is laid on the support rods 9 to form a lower platform, and lower platform guardrails 10 are arranged on the periphery of the lower platform; and a lower ladder 11 leading to the lower platform is arranged at the bottom of the pier along the pier body.
The utility model discloses when the installation, earlier through pier shaft built-in fitting installation bracket 2, after 2 installations of bracket are accomplished, connect L type gallows, set up down the platform bottom the bracket, lower platform sets up the completion back, can carry out support superstructure's installation construction with the help of lower platform.
Support dismantlement after accomplishing for the construction of being convenient for, the utility model discloses install between two corbels tops of every pier every side and fill up roof beam 12, fill up and install wedge on the roof beam 12 and unload frame 13, spandrel girder 3 sets up on the wedge unloads the frame.
In order to ensure the stable integral structure of the support, after the bearing beams 3 are installed, the bearing beams on the two sides of the bridge pier are connected through a plurality of tension rods 14.
The utility model discloses 4 upper berths of distribution beam are equipped with the panel and form the upper mounting plate, and upper mounting plate guardrail 15 is installed to the upper mounting plate periphery. When the bent cap is poured, constructors mainly operate on the upper platform, and can perform auxiliary operations on the lower platform. In order to facilitate the constructors to get on and off the platform, an upper ladder stand 16 is erected between the lower platform and the upper platform.

Claims (4)

1. The utility model provides a modular high mound bent cap construction support, installs two brackets through pier shaft built-in fitting respectively in every pier in the same direction as the bridge both sides, and the transverse bridge has set up the spandrel girder to putting up on the bracket of pier with one side, has set up the distribution roof beam on the spandrel girder, installs bent cap construction template, its characterized in that on the distribution roof beam: the bottom of each bracket is connected with an L-shaped hanging bracket, each L-shaped hanging bracket comprises a vertical rod and a cross rod, the vertical rods are tightly attached to the pier body, the upper ends of the vertical rods are connected with the bracket bottom supporting plate through pin shafts, the lower ends of the vertical rods are fixedly connected with one end of the cross rod, and the other end of the cross rod horizontally extends along the direction along the bridge; the vertical rods of the two L-shaped hanging frames on each side of each pier are connected through a cross brace, a plurality of supporting rods are arranged among the cross rods of all the L-shaped hanging frames on the same side of the pier in an overlapping mode, a panel is laid on the supporting rods to form a lower platform, and lower platform guardrails are arranged on the periphery of the lower platform; and a lower crawling ladder leading to the lower platform is arranged at the bottom of the pier along the pier body.
2. The modular high pier capping beam construction bracket of claim 1, wherein: the bridge pier is characterized in that a pad beam is arranged between the tops of two corbels on each side of each bridge pier, a wedge-shaped unloading frame is arranged on the pad beam, and the bearing beams are erected on the wedge-shaped unloading frame.
3. The modular high pier capping beam construction bracket of claim 1, wherein: the bearing beams on two sides of the pier are connected through a plurality of tension rods.
4. The modular high pier capping beam construction bracket of claim 1, wherein: a panel is laid on the distribution beam to form an upper platform, and upper platform guardrails are installed on the periphery of the upper platform; an upper ladder stand is erected between the lower platform and the upper platform.
CN201920509055.3U 2019-04-15 2019-04-15 Combined high pier capping beam construction support Active CN210066507U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201920509055.3U CN210066507U (en) 2019-04-15 2019-04-15 Combined high pier capping beam construction support

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201920509055.3U CN210066507U (en) 2019-04-15 2019-04-15 Combined high pier capping beam construction support

Publications (1)

Publication Number Publication Date
CN210066507U true CN210066507U (en) 2020-02-14

Family

ID=69436848

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201920509055.3U Active CN210066507U (en) 2019-04-15 2019-04-15 Combined high pier capping beam construction support

Country Status (1)

Country Link
CN (1) CN210066507U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111395183A (en) * 2020-03-31 2020-07-10 云南工程建设总承包股份有限公司 System and method for electric bridge type scaffold platform for double-column pier construction
CN111749135A (en) * 2020-05-30 2020-10-09 中交路桥建设有限公司 Integral dismantling method for 0# block bracket of continuous rigid frame bridge
CN111877187A (en) * 2020-08-03 2020-11-03 青岛理工大学 Wedge block protection mechanism and assembled bridge cantilever construction bracket
CN114922084A (en) * 2022-06-06 2022-08-19 中铁大桥局第七工程有限公司 Bracket system for rectangular high-pier capping beam construction

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111395183A (en) * 2020-03-31 2020-07-10 云南工程建设总承包股份有限公司 System and method for electric bridge type scaffold platform for double-column pier construction
CN111749135A (en) * 2020-05-30 2020-10-09 中交路桥建设有限公司 Integral dismantling method for 0# block bracket of continuous rigid frame bridge
CN111877187A (en) * 2020-08-03 2020-11-03 青岛理工大学 Wedge block protection mechanism and assembled bridge cantilever construction bracket
CN111877187B (en) * 2020-08-03 2021-07-16 青岛理工大学 Wedge block protection mechanism and assembled bridge cantilever construction bracket
CN114922084A (en) * 2022-06-06 2022-08-19 中铁大桥局第七工程有限公司 Bracket system for rectangular high-pier capping beam construction

Similar Documents

Publication Publication Date Title
CN210066507U (en) Combined high pier capping beam construction support
JP5047680B2 (en) Construction method of continuous viaduct
CN206768611U (en) Bridge pier hanging basket mounting operation platform
CN107313360A (en) Overhead cable formula is without support bearing replacement operating platform
CN107604827A (en) A kind of porous large-span freely-supported steel truss girder bridge erection method
CN105178163A (en) Novel continuous beam type rail
CN207267966U (en) Overhead cable formula is without stent bearing replacement operating platform
CN111827116A (en) Combined high pier capping beam construction support
CN110700119A (en) Upper traveling system of assembled Bailey beam hanging basket and design method thereof
CN202718127U (en) Scaffold tube support for underground foundation pit
CN202000265U (en) Concrete construction formwork for high pier of bridge
CN103835238B (en) A kind of high pier cable stayed bridge No. 0 block non-stand construction method and the structure in constructing
CN203866711U (en) Large span cable-stayed bridge tower beam three-way temporary consolidation structure
CN218322325U (en) Pier column-beam-bent cap integrated public rail double-layer viaduct
CN108797380B (en) Suspension construction device and construction method for suspension irrigation continuous beam bracket
CN104452598B (en) The construction method of pier prestressed cap beam with extra length Construction Supporting System in water
CN211815605U (en) Construction device for pile column type pier tie beam and capping beam
CN210395127U (en) Assembled Bailey beam hanging basket upper walking system
CN104404885B (en) The device of pre-jacking force is applied for pier prestressed cap beam with extra length in water
CN209079700U (en) One kind is firmly across mounting structure
CN209194354U (en) High-altitude long-span binder base-supporting shellfish thunder support construction
CN202831591U (en) Special-shaped truss operation platform capable of hoisting to super high space
CN112854702A (en) Large-span silo roof construction platform and erection method
CN207092508U (en) A kind of spigot-and-socket builder's jack
CN219080110U (en) Steel-pipe column support construction safety platform device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant