CN209780193U - Suspension type scaffold - Google Patents
Suspension type scaffold Download PDFInfo
- Publication number
- CN209780193U CN209780193U CN201920067984.3U CN201920067984U CN209780193U CN 209780193 U CN209780193 U CN 209780193U CN 201920067984 U CN201920067984 U CN 201920067984U CN 209780193 U CN209780193 U CN 209780193U
- Authority
- CN
- China
- Prior art keywords
- connecting piece
- main
- supporting beam
- pull rod
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Movable Scaffolding (AREA)
Abstract
本实用新型公开了一种悬吊式脚手架。该悬吊式脚手架,包括与混凝土主体立面垂直设置的多根主支撑梁,每根主支撑梁通过拉杆与悬挑构件相连,拉杆的上端通过拉杆上连接件悬挂于悬挑构件上,拉杆的下端均通过拉杆下连接件与主支撑梁相连,相邻的两根主支撑梁均通过横支撑梁连接。本实用新型悬吊式脚手架,悬挑长度大,施工范围大,增大了施工的准确性和安全性;融合了吊篮和脚手架的特点,具有拼装式安拆快速、悬挑长度大、作业面宽敞、对其他作业工序的影响小、定型加工、可周转使用等特点。
The utility model discloses a suspension scaffold. The suspended scaffolding includes a plurality of main support beams vertically arranged on the concrete main body facade, each main support beam is connected with the cantilever member through a tie rod, and the upper end of the tie rod is suspended on the cantilever member through the upper connection piece of the tie rod, and the tie rod The lower ends of each are connected to the main support beam through the lower connecting piece of the tie rod, and the two adjacent main support beams are connected through the cross support beam. The utility model of the suspension scaffold has a large cantilever length and a large construction range, which increases the accuracy and safety of the construction; it combines the characteristics of the hanging basket and the scaffold, and has the advantages of fast assembly and disassembly, large cantilever length, and easy operation. It has the characteristics of spacious surface, little impact on other operating procedures, stereotyped processing, and reusable use.
Description
技术领域technical field
本实用新型涉及一种悬吊式脚手架。The utility model relates to a suspension scaffold.
背景技术Background technique
建筑物为了突显建筑气场、彰显建筑地位,通常会在屋顶设计“屋帽”这一悬挑造型。“屋帽”施工时,在完成主要支撑受力结构施工后,需在“屋帽”底部进行装饰面的施工,但该处施工操作平台搭设较为困难。传统方式主要是采用钢管落地式脚手架、悬挑式脚手架或吊篮,在实际施工过程中发现这几种方式都存在一些缺陷,例如:(1)当悬挑构件悬挑较长且标高较高时,普通钢管脚手架和吊篮则存在较大局限性;(2)吊篮安装固定麻烦,水平作业面受限,操作平台稳定性差,安全隐患比较多,而且悬挑长度受限,还影响混凝土主体立面及屋面相关工序的施工;(3)悬挑式脚手架悬挑长度有限,搭设工程量大,工序拆装麻烦,立杆间距小影响施工,还会影响悬挑层范围内其它工序的施工。In order to highlight the architectural aura and highlight the status of the building, the roof is usually designed with a cantilever shape of "roof hat". During the construction of the "roof cap", after the construction of the main supporting force-bearing structure is completed, the construction of the decorative surface needs to be carried out at the bottom of the "roof cap", but it is difficult to set up the construction operation platform at this place. The traditional method mainly uses steel pipe floor scaffolding, cantilevered scaffolding or hanging baskets. In the actual construction process, it is found that these methods have some defects, for example: (1) When the cantilevered components are long and the elevation is high However, ordinary steel pipe scaffolding and hanging baskets have relatively large limitations; (2) the installation and fixing of hanging baskets is troublesome, the horizontal working surface is limited, the stability of the operating platform is poor, there are many safety hazards, and the length of the cantilever is limited, which also affects the concrete. The construction of the main facade and roof related processes; (3) the length of the cantilevered scaffolding is limited, the amount of erection is large, the disassembly and assembly of the process is troublesome, and the small distance between the poles affects the construction and other processes within the range of the cantilevered layer. construction.
因此,现亟需一种新型的作业结构来解决上述问题。Therefore, need a kind of novel operating structure badly now to solve the above problems.
实用新型内容Utility model content
本实用新型提供了一种拼装式安拆快速、悬挑长度大、作业面宽敞、定型加工、可周转使用的悬吊式脚手架,解决了现有技术中存在的问题。The utility model provides a suspended scaffold which can be assembled and disassembled quickly, has a large overhang length, a spacious working surface, is shaped and processed, and can be used repeatedly, and solves the problems existing in the prior art.
本实用新型为解决上述技术问题所采用的技术方案是:The technical scheme that the utility model adopts for solving the problems of the technologies described above is:
一种悬吊式脚手架,包括一端与混凝土主体立面连接的多根主支撑梁,所述主支撑梁位于同一水平面上,主支撑梁靠近混凝土主体立面的一端均通过一主支撑梁连接件与混凝土主体立面相连,每根主支撑梁均通过一组拉杆与悬挑构件相连,相邻的两根主支撑梁均通过若干根垂直于主支撑梁的横支撑梁连接,每根横支撑梁的两端分别通过一横支撑梁连接件与主支撑梁相连,所述主支撑梁与横支撑梁交叉布置形成一网格平台。A suspended scaffolding, comprising a plurality of main support beams connected at one end to the facade of the concrete main body, the main support beams are located on the same horizontal plane, and the ends of the main support beams close to the facade of the concrete main body pass through a main support beam connector Connected with the main concrete facade, each main support beam is connected to the cantilever member through a set of tie rods, and the adjacent two main support beams are connected by several transverse support beams perpendicular to the main support beam, and each transverse support The two ends of the beam are respectively connected to the main support beam through a cross support beam connector, and the main support beam and the cross support beam are arranged crosswise to form a grid platform.
所述拉杆的上端均通过一拉杆上连接件悬挂于悬挑构件上,所述拉杆的下端均通过一拉杆下连接件与主支撑梁相连。The upper ends of the pull rods are hung on the cantilever member through a pull rod upper connection piece, and the lower ends of the pull rods are connected with the main support beam through a pull rod lower connection piece.
在网格平台的顶部设有台阶架,所述台阶架由台阶立杆、台阶横杆和台阶纵杆拼装形成,台阶立杆、台阶横杆和台阶纵杆的交叉部通过扣件连接,台阶立杆的下端通过台阶立杆连接件与网格平台相连,在台阶架的台阶面上铺设有踏板。A step frame is provided on the top of the grid platform, and the step frame is formed by assembling step vertical bars, step horizontal bars and step vertical bars. The intersections of the step vertical bars, step horizontal bars and step vertical bars are connected by fasteners, and the steps The lower end of the pole is connected with the grid platform through the step pole connecting piece, and a pedal is laid on the step surface of the step frame.
所述主支撑梁连接件包括通过化学锚栓固定于混凝土主体立面上的T型连接件,所述主支撑梁的端部通过螺栓与T型连接件相连;所述拉杆上连接件为可套接在悬挑构件上的拼接方框,所述拼接方框由三根短杆通过螺栓依次连接后再与拉杆连接形成,所述拉杆下连接件为焊接在主支撑梁上的连接耳板,拉杆下端通过螺栓与连接耳板相连;所述横支撑梁连接件为焊接在主支撑梁上的连接耳板,横支撑梁两端通过螺栓与连接耳板相连。The main support beam connector includes a T-shaped connector fixed on the facade of the concrete main body through chemical anchor bolts, and the end of the main support beam is connected to the T-shaped connector through bolts; The splicing frame socketed on the cantilevered member, the splicing frame is formed by connecting three short rods sequentially through bolts and then connecting with the tie rods, the lower connecting part of the pull rods is the connecting ear plate welded on the main support beam, The lower end of the tie rod is connected to the connecting ear plate through bolts; the connecting part of the cross support beam is the connecting ear plate welded on the main support beam, and the two ends of the cross support beam are connected to the connecting ear plate through bolts.
所述台阶立杆连接件包括焊接于网格平台顶部的套管,所述台阶立杆的下端插接于套管内,并通过头部穿入套管内的螺栓顶紧在套管内。The connecting part of the step vertical rod includes a casing welded on the top of the grid platform, the lower end of the step vertical rod is plugged into the casing, and is tightened in the casing by the bolt whose head penetrates into the casing.
相邻的两根横支撑梁之间通过若干根副支撑梁连接。Two adjacent transverse support beams are connected by several auxiliary support beams.
在靠近安装悬挑构件的混凝土主体上设有加固结构,所述加固结构包括呈折线排列在混凝土主体顶部的多根加固梁,每根加固梁的端部均通过一加固梁连接件与混凝土主体的顶部相连。A reinforcement structure is provided on the concrete body close to the installation of the cantilever component, the reinforcement structure includes a plurality of reinforcement beams arranged in broken lines on the top of the concrete body, and the end of each reinforcement beam is connected to the concrete body through a reinforcement beam connector connected at the top.
所述加固梁连接件包括通过通过化学锚栓固定在混凝土主体上的加固梁垫板,在加固梁垫板上焊接有加固梁连接板,加固梁的两端均通过螺栓与加固梁连接板相连。The reinforced beam connector includes a reinforced beam backing plate fixed on the concrete body through chemical anchor bolts, a reinforced beam connecting plate is welded on the reinforced beam backing plate, and both ends of the reinforced beam are connected to the reinforced beam connecting plate by bolts .
本实用新型采用上述结构,具有以下优点:The utility model adopts the above structure and has the following advantages:
本实用新型悬吊式脚手架,通过拉杆与悬挑构件进行悬挂连接,通过主支撑梁和混凝土主体立面连接,融合了吊篮和脚手架的特点,保证平台的稳定性和安全性,具有施工范围大、悬挑长度大、拼装式安拆快速、悬挑长度大、作业面宽敞、对其他作业工序的影响小、定型加工、可周转使用等特点,增大了施工的准确性和安全性;支撑梁可以抵消一部分脚手架整体载荷施加在混凝土主体上的扭矩,从而降低悬挑构件受到的负载,可以一定程度上减少混凝土主体需要的加固;拉杆和主支撑梁可以先在地面进行模块化预组装,可以减少高空作业量。The suspended scaffolding of the utility model is suspended and connected with the cantilevered components through the tie rods, connected with the main support beam and the facade of the concrete main body, combines the characteristics of the hanging basket and the scaffolding, ensures the stability and safety of the platform, and has a wide range of construction Large, large overhang length, fast assembled installation and disassembly, large overhang length, spacious working surface, little impact on other operating procedures, finalized processing, and turnaround use, etc., which increase the accuracy and safety of construction; The support beam can offset the torque applied to the concrete body by part of the overall load of the scaffold, thereby reducing the load on the cantilevered components and reducing the reinforcement required for the concrete body to a certain extent; the tie rods and main support beams can be pre-assembled modularly on the ground , can reduce the amount of high-altitude operations.
附图说明Description of drawings
图1为本实用新型的结构示意图;Fig. 1 is the structural representation of the utility model;
图2为在网格平台顶部搭建台阶架后的结构示意图;Fig. 2 is the schematic diagram of the structure after the step frame is built on the top of the grid platform;
图3为图1中A部的放大结构示意图;Fig. 3 is the schematic diagram of the enlarged structure of part A in Fig. 1;
图4为图2中B部的放大结构示意图;Fig. 4 is the schematic diagram of the enlarged structure of part B in Fig. 2;
图5为T型连接件的放大结构示意图;Figure 5 is a schematic diagram of an enlarged structure of a T-shaped connector;
图6为拉杆上连接件的放大结构示意图;Fig. 6 is a schematic diagram of an enlarged structure of the connecting piece on the pull rod;
图7为拉杆下连接件的放大结构示意图;Fig. 7 is a schematic diagram of an enlarged structure of the lower connecting piece of the pull rod;
图8为台阶立杆连接件的放大结构示意图;Fig. 8 is a schematic diagram of an enlarged structure of a step pole connector;
图9为加固梁连接件的放大结构示意图。Fig. 9 is an enlarged structural schematic diagram of a reinforced beam connector.
图中,1、主支撑梁,2、主支撑梁连接件,21、T型连接件,3、拉杆,4、拉杆上连接件,41、短杆,5、拉杆下连接件,51、连接耳板,6、横支撑梁,7、横支撑梁连接件,8、台阶立杆,9、台阶横杆,10、台阶纵杆,12、台阶立杆连接件,121、套管,13、踏板,14、副支撑梁,15、加固梁,16、加固梁连接件,161、加固梁垫板,162、加固梁连接板。In the figure, 1. Main supporting beam, 2. Connecting piece of main supporting beam, 21. T-shaped connecting piece, 3. Pull rod, 4. Upper connecting piece of pulling rod, 41. Short rod, 5. Lower connecting piece of pulling rod, 51. Connection Ear plate, 6, cross support beam, 7, cross support beam connector, 8, step vertical rod, 9, step cross bar, 10, step vertical rod, 12, step vertical rod connector, 121, casing, 13, Pedal, 14, auxiliary supporting beam, 15, reinforcing beam, 16, reinforcing beam connector, 161, reinforcing beam backing plate, 162, reinforcing beam connecting plate.
具体实施方式:Detailed ways:
为能清楚说明本方案的技术特点,下面通过具体实施方式,并结合其附图,对本实用新型进行详细阐述。In order to clearly illustrate the technical features of this solution, the utility model will be described in detail below through specific implementation methods and in conjunction with the accompanying drawings.
实施例1:Example 1:
如图1中所示,本实施例悬吊式脚手架,包括一端与混凝土主体立面连接的多根主支撑梁1,所述主支撑梁1位于同一水平面上,主支撑梁1靠近混凝土主体立面的一端均通过一主支撑梁连接件2与混凝土主体立面相连,每根主支撑梁1均通过一组拉杆3与悬挑构件相连,相邻的两根主支撑梁1均通过若干根垂直于主支撑梁1的横支撑梁6连接,每根横支撑梁6的两端分别通过一横支撑梁连接件7与主支撑梁1相连,所述主支撑梁1与横支撑梁6交叉布置形成一网格平台。As shown in Figure 1, the suspended scaffolding of this embodiment includes a plurality of main support beams 1 connected at one end to the facade of the concrete main body. One end of the surface is connected to the concrete main body facade through a main support beam connector 2, each main support beam 1 is connected to the cantilever member through a set of tie rods 3, and two adjacent main support beams 1 are connected through several The cross support beams 6 perpendicular to the main support beam 1 are connected, and the two ends of each cross support beam 6 are respectively connected to the main support beam 1 through a cross support beam connector 7, and the main support beam 1 intersects with the cross support beam 6 The arrangement forms a grid platform.
所述拉杆3的上端均通过一拉杆上连接件4悬挂于悬挑构件上,所述拉杆3的下端均通过一拉杆下连接件5与主支撑梁1相连。The upper ends of the tie rods 3 are hung on the suspension member through a tie rod upper connecting piece 4 , and the lower ends of the tie rods 3 are connected with the main support beam 1 through a tie rod lower connecting piece 5 .
具体施工时,横支撑梁连接件7与混凝土主体立面的连接位置向左侧或右侧偏离悬挑构件与混凝土主体立面的连接位置10cm,防止混凝土主体立面受力过于集中。另外,主支撑梁与混凝土主体立面的位置关系优选垂直连接。During specific construction, the connection position of the cross-support beam connector 7 and the concrete main facade deviates 10 cm from the connection position of the cantilever member and the concrete main facade to the left or right, so as to prevent the concrete main facade from being too concentrated. In addition, the positional relationship between the main support beam and the facade of the concrete main body is preferably connected vertically.
本实施例悬吊式脚手架,通过拉杆与悬挑构件进行悬挂连接,通过主支撑梁1和混凝土主体立面连接,支撑梁可以抵消一部分脚手架整体载荷施加在混凝土主体上的扭矩,从而降低悬挑构件受到的负载,可以一定程度上减少混凝土主体需要的加固。而传统的悬挑式脚手架是通过支撑梁的一端固定在混凝土主体的顶部而实现悬挑,这种悬挑方式为下部承托式支撑,将由下部的支撑梁承担全部的载荷,混凝土主体与支撑梁连接位置处受到的扭矩较大。In this embodiment, the suspended scaffolding is suspended and connected with the cantilevered components through the tie rods, and the main support beam 1 is connected to the facade of the concrete main body. The supporting beam can offset a part of the torque exerted by the overall load of the scaffold on the concrete main body, thereby reducing the overhang The load on the member can reduce to some extent the reinforcement required for the concrete body. In the traditional cantilevered scaffolding, one end of the supporting beam is fixed on the top of the concrete main body to achieve cantilevering. This kind of cantilevering method is the lower support type support, and the lower supporting beam will bear all the load. The concrete main body and the support The torsional moment experienced at the beam connection location is relatively high.
实施例2:Example 2:
本实施例中,每组拉杆3的数量为两根,分别与主支撑梁1的中部和远离混凝土主体立面的一端相连,保证主支撑梁的受力均衡。In this embodiment, there are two tie rods 3 in each group, which are respectively connected to the middle of the main support beam 1 and the end far away from the concrete main body facade, so as to ensure the force balance of the main support beam.
实施例3:Example 3:
本实施例与实施例2的不同之处在于:The difference between this embodiment and embodiment 2 is:
如图1-图9中所示,在网格平台的顶部设有台阶架,方便工人进行不同高度的施工操作。As shown in Figures 1-9, a step frame is provided on the top of the grid platform, which is convenient for workers to carry out construction operations at different heights.
所述台阶架由台阶立杆8、台阶横杆9和台阶纵杆10拼装形成,台阶立杆8、台阶横杆9和台阶纵杆10的交叉部通过扣件连接,台阶立杆8的下端通过台阶立杆连接件12与网格平台相连,在台阶架的台阶面上铺设有踏板13。所述扣件为现有技术中搭建脚手架所使用的普通扣件,在台阶架的侧面设有护栏,防止坠落事故的发生,保证工人的施工安全。The step frame is formed by assembling the step vertical bar 8, the step cross bar 9 and the step vertical bar 10, the intersection of the step vertical bar 8, the step cross bar 9 and the step vertical bar 10 is connected by a fastener, and the lower end of the step vertical bar 8 The grid platform is connected to the grid platform through the step pole connecting piece 12, and a pedal 13 is laid on the step surface of the step frame. The fasteners are common fasteners used to build scaffolds in the prior art, and guardrails are provided on the side of the step frame to prevent falling accidents and ensure the construction safety of workers.
所述台阶立杆连接件12包括焊接于网格平台顶部的套管121,所述台阶立杆8的下端插接于套管121内,并通过头部穿入套管121内的螺栓顶紧在套管121内,采用上述安装结构实现了台阶架的便捷安装、拆卸,以及周转使用。The step vertical rod connector 12 includes a sleeve 121 welded on the top of the grid platform, the lower end of the step vertical rod 8 is inserted into the sleeve 121, and is tightened by the bolt whose head penetrates into the sleeve 121. In the casing 121, the above installation structure is adopted to realize the convenient installation, disassembly, and turnover use of the step frame.
实施例4:Example 4:
如图1-图9中所示,本实施例中主支撑梁连接件2、所述拉杆上连接件4、拉杆下连接件5、横支撑梁连接件7采用的具体形式为:As shown in Figures 1-9, in this embodiment, the main supporting beam connector 2, the upper connecting member 4 of the tie rod, the lower connecting member 5 of the pulling rod, and the connecting member 7 of the horizontal supporting beam adopt the following specific forms:
所述主支撑梁连接件2包括通过化学锚栓固定于混凝土主体立面上的T型连接件21,所述主支撑梁1的端部通过螺栓与T型连接件21相连;所述拉杆上连接件4为可套接在悬挑构件上的拼接方框,所述拼接方框由三根短杆41通过螺栓依次连接后再与拉杆3连接形成,所述拉杆下连接件5为焊接在主支撑梁1上的连接耳板51,拉杆3下端通过螺栓与连接耳板51相连;所述横支撑梁连接件7为焊接在主支撑梁1上的连接耳板51,横支撑梁6两端通过螺栓与连接耳板51相连。The main support beam connector 2 includes a T-shaped connector 21 fixed on the facade of the concrete main body by chemical anchor bolts, and the end of the main support beam 1 is connected with the T-shaped connector 21 by bolts; The connecting piece 4 is a splicing box that can be sleeved on the cantilevered member. The splicing box is formed by connecting three short rods 41 sequentially through bolts and then connecting with the tie rod 3. The lower connecting piece 5 of the tie rod is welded on the main The connecting ear plate 51 on the support beam 1, the lower end of the pull rod 3 is connected to the connecting ear plate 51 through bolts; Connect to the connecting ear plate 51 by bolts.
拉杆3的上端均通过拼接方框悬挂于悬挑构件上,方便安装和后期拆除,对悬挑构件没有损伤。The upper ends of the pull rods 3 are hung on the cantilevered components through spliced square frames, which is convenient for installation and later dismantling, and does not damage the cantilevered components.
实施例5:Example 5:
如图1-图9中所示,相邻的两根横支撑梁6之间通过若干根副支撑梁14连接,所述主支撑梁、横支撑梁及副支撑梁相互交叉形成网格平台。为了提高施工安全性,实际操作时,在网格平台的上表面铺设有安全网。As shown in FIGS. 1-9 , two adjacent horizontal support beams 6 are connected by several auxiliary support beams 14 , and the main support beams, horizontal support beams and auxiliary support beams cross each other to form a grid platform. In order to improve construction safety, a safety net is laid on the upper surface of the grid platform during actual operation.
实施例6:Embodiment 6:
如图1-图9中所示,当原混凝土主体不能满足安装悬吊式脚手架的荷载要求时,需要先对混凝土主体进行加固,因此本实施例在靠近安装悬挑构件的混凝土主体上设有加固结构,所述加固结构包括呈折线排列在混凝土主体顶部的多根加固梁15,每根加固梁15的端部均通过一加固梁连接件16与混凝土主体的顶部相连。As shown in Figures 1-9, when the original concrete body cannot meet the load requirements for installing a suspended scaffold, the concrete body needs to be reinforced first, so this embodiment is provided on the concrete body close to the installation of the cantilever component The reinforcement structure includes a plurality of reinforcement beams 15 arranged on the top of the concrete body in broken lines, and the end of each reinforcement beam 15 is connected to the top of the concrete body through a reinforcement beam connector 16 .
所述加固梁连接件16包括通过通过化学锚栓固定在混凝土主体上的加固梁垫板161,在加固梁垫板161上焊接有加固梁连接板162,加固梁16的两端均通过螺栓与加固梁连接板162相连。The reinforcing beam connector 16 includes a reinforcing beam backing plate 161 fixed on the concrete main body by chemical anchor bolts, a reinforcing beam connecting plate 162 is welded on the reinforcing beam backing plate 161, and both ends of the reinforcing beam 16 are connected with The reinforcing beam connecting plates 162 are connected.
上述各实施方式中,所述主支撑梁、横支撑梁和副支撑梁为工字钢,所述拉杆、加固梁为槽钢。In each of the above embodiments, the main supporting beam, the horizontal supporting beam and the auxiliary supporting beam are I-beams, and the tie rods and reinforcement beams are channel steels.
实施例1中所述悬吊式脚手架的施工方法,包括如下步骤:The construction method of suspended scaffold described in embodiment 1 may further comprise the steps:
(1)将拉杆3通过拉杆下连接件5与主支撑梁1进行连接,并将连接好的每组拉杆3和主支撑梁1吊装至安装高度;具体方法为:在地面将各连接耳板焊接在主支撑梁上,并把拉杆3使用螺栓固定在主支撑梁的连接耳板上,采用固定在悬挑构件上的卷扬机吊装将每组拉杆3和主支撑梁1吊装到位后,采用螺栓将主支撑梁1固定在预埋在混凝土主体上的主支撑梁连接件2,调节主支撑梁1水平,把拉杆3预固定在悬挑构件上,调节拉杆3的垂直度,固定拉杆3上端;(1) Connect the tie rod 3 to the main support beam 1 through the lower connection piece 5 of the tie rod, and hoist each set of connected tie rods 3 and the main support beam 1 to the installation height; It is welded on the main support beam, and the tie rod 3 is fixed on the connecting ear plate of the main support beam with bolts. After hoisting each set of tie rods 3 and the main support beam 1 with the hoist fixed on the cantilevered member, the bolts are used to Fix the main support beam 1 to the main support beam connector 2 pre-buried on the concrete body, adjust the level of the main support beam 1, pre-fix the tie rod 3 on the cantilever member, adjust the verticality of the tie rod 3, and fix the upper end of the tie rod 3 ;
将拉杆3和主支撑梁1先在地面进行模块化预组装,可以减少高空作业量;Modular pre-assembly of tie rod 3 and main support beam 1 on the ground can reduce the amount of high-altitude work;
(2)通过拉杆上连接件4将拉杆与悬挑构件相连,通过主支撑梁连接件2将主支撑梁1与混凝土主体立面相连;具体方法为:将拉杆3通过拼接成方框的短杆41与悬挑构件连接,下部通过连接耳板与主支撑梁1连接;(2) Connect the tie rod with the cantilever member through the tie rod upper connector 4, and connect the main support beam 1 with the concrete main body facade through the main support beam connector 2; the specific method is: the tie rod 3 is spliced into a short frame The rod 41 is connected with the suspension member, and the lower part is connected with the main support beam 1 through the connecting ear plate;
(3)将横支撑梁6通过横支撑梁连接件7与主支撑梁1相连;(3) The cross support beam 6 is connected with the main support beam 1 by the cross support beam connector 7;
(4)在相邻的两根横支撑梁6之间安装副支撑梁14;(4) Auxiliary support beams 14 are installed between two adjacent transverse support beams 6;
(5)在主支撑梁、横支撑梁及副支撑梁相互交叉形成的网格平台上铺设安全网;(5) Lay a safety net on the grid platform formed by the intersecting main support beams, transverse support beams and auxiliary support beams;
(6)在网格平台顶部搭建台阶架,具体方法为:(6) Build a step frame on the top of the grid platform, the specific method is:
具体施工时,将台阶立杆8、台阶横杆9和台阶纵杆10的交叉部通过90°钢管扣件连接,台阶立杆8的下端插接在套管121内,并通过旋紧套筒上的螺栓固定台阶立杆8,套管121底部焊接在网格平台上,套筒长150mm直径60mm,间距1400mm。During specific construction, the intersection of the step vertical bar 8, the step cross bar 9 and the step longitudinal bar 10 is connected by a 90° steel pipe fastener, the lower end of the step vertical bar 8 is inserted into the sleeve 121, and the sleeve is tightened The bolts on the top fix the step pole 8, and the bottom of the casing 121 is welded on the grid platform. The length of the sleeve is 150mm, the diameter is 60mm, and the spacing is 1400mm.
通过台阶立杆连接件12与网格平台相连,得到具有四个台阶的台阶架,每个台阶高差600mm,宽度1200mm,Connect with the grid platform through the step pole connecting piece 12 to obtain a step frame with four steps, each step has a height difference of 600mm and a width of 1200mm.
在台阶架的台阶面上铺设250x3000mm穿孔钢踏板13,踏板采用3mm铁丝捆绑,每块踏板不少于四个绑扎点,台阶架的立面铺设12mm竹胶板,竹胶板与搭建台阶架的钢管之间采用铁丝绑扎。Lay 250x3000mm perforated steel pedals 13 on the step surface of the step frame. The pedals are bound with 3mm iron wires. The steel pipes are bound with iron wires.
(7)在台阶架的外侧安装护栏,护栏的横向栏杆通过90°钢管扣件与竖向栏杆连接,间距1200mm,并与台阶架连接,护栏顶部使用钢管与悬挑构件连接,间距1400mm。(7) Install guardrails on the outside of the step frame. The horizontal railings of the guardrail are connected to the vertical railings through 90° steel pipe fasteners with a spacing of 1200mm, and are connected to the step frame.
当原混凝土主体不能满足安装悬吊式脚手架的荷载要求时,需要先对混凝土主体进行加固。根据设计图纸进行加固,加固时严格按图施工,保证所用材料符合设计要求,安装正确,受力方向正确。加固方案如图在施工前进行混凝土主体的加固,具体方法为:在安装悬挑构件的混凝土主体立面上以及混凝土主体的顶部安装多个加固梁连接件,各加固梁连接件通过加固梁连接,且加固梁连接件呈折线结构排列。When the original concrete body cannot meet the load requirements for installing the suspended scaffold, the concrete body needs to be reinforced first. Reinforcement is carried out according to the design drawings, and the construction is strictly carried out according to the drawings during reinforcement to ensure that the materials used meet the design requirements, the installation is correct, and the force direction is correct. The reinforcement scheme is as shown in the figure. Reinforce the concrete body before construction. The specific method is: install multiple reinforcement beam connectors on the facade of the concrete body where the cantilever components are installed and on the top of the concrete body, and each reinforcement beam connector is connected by a reinforcement beam. , and the reinforced beam connectors are arranged in a broken line structure.
施工完成后,拆除本实用新型悬吊式脚手架时,因为是高层建筑工程,拆除时采用间隔一跨拆除,先拆除转角部位的网格平台,然后间隔一跨,拆除一跨,使用卷扬机运输踏板、钢管和槽钢,剩余的网格平台整体一跨用4台卷扬机下落到地面,扣件及小型配件从施工电梯往下运输。After the construction is completed, when dismantling the suspended scaffolding of the utility model, because it is a high-rise construction project, it is removed at intervals. First remove the grid platform at the corner, and then remove the span at intervals, and use the hoist to transport the pedals , steel pipe and channel steel, and the remaining grid platform is lowered to the ground with 4 winches in one span, and the fasteners and small accessories are transported down from the construction elevator.
本实用新型悬吊式脚手架,利用悬挑构件以及主支撑梁作为受力结构,在悬挑构件每根支撑杆的下方做一根支撑梁,支撑梁一端固定在混凝土主体上,并且通过拉杆悬挂固定在悬挑构件上,支撑梁之间采用横支撑梁连接,并配合副支撑梁形成一网格平台,网格平台上可以铺设安全网,保证平台的稳定性和安全性,融合了吊篮和脚手架的特点,具有拼装式安拆快速、悬挑长度大、作业面宽敞、定型加工、可周转使用等特点。The utility model suspended scaffold uses the cantilevered member and the main support beam as the force-bearing structure, and a support beam is made under each support rod of the cantilever member, and one end of the support beam is fixed on the concrete main body, and is suspended by a tie rod. Fixed on the cantilevered components, the support beams are connected by cross support beams, and form a grid platform with the auxiliary support beams. Safety nets can be laid on the grid platform to ensure the stability and safety of the platform. With the characteristics of scaffolding, it has the characteristics of fast assembly and disassembly, large cantilever length, spacious working surface, stereotyped processing, and turnover use.
上述具体实施方式不能作为对本实用新型保护范围的限制,对于本技术领域的技术人员来说,对本实用新型实施方式所做出的任何替代改进或变换均落在本实用新型的保护范围内。The above-mentioned specific implementation manners cannot be regarded as limitations on the protection scope of the present utility model. For those skilled in the art, any alternative improvements or transformations made to the embodiments of the present utility model fall within the protection scope of the present utility model.
本实用新型未详述之处,均为本技术领域技术人员的公知技术。The parts of the utility model that are not described in detail are the known techniques of those skilled in the art.
Claims (8)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201920067984.3U CN209780193U (en) | 2019-01-16 | 2019-01-16 | Suspension type scaffold |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201920067984.3U CN209780193U (en) | 2019-01-16 | 2019-01-16 | Suspension type scaffold |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN209780193U true CN209780193U (en) | 2019-12-13 |
Family
ID=68792883
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201920067984.3U Expired - Fee Related CN209780193U (en) | 2019-01-16 | 2019-01-16 | Suspension type scaffold |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN209780193U (en) |
Cited By (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109577632A (en) * | 2019-01-16 | 2019-04-05 | 中建八局第建设有限公司 | A kind of swinging scaffold and its construction method |
| CN111456400A (en) * | 2020-03-24 | 2020-07-28 | 中国五冶集团有限公司 | A high-altitude temporary operating platform structure |
| CN112663928A (en) * | 2020-12-30 | 2021-04-16 | 大连九洲建设集团有限公司 | Decoration engineering operation platform for high-altitude large cantilever structure and mounting and dismounting method |
| CN115959262A (en) * | 2023-01-03 | 2023-04-14 | 江南造船(集团)有限责任公司 | Temporary construction platform for liquid dome area of cargo tank of transport ship and installation method thereof |
| CN120739307A (en) * | 2025-07-29 | 2025-10-03 | 广东雄桥建设集团有限公司 | Movable building hand and foot frame easy to disassemble and assemble |
-
2019
- 2019-01-16 CN CN201920067984.3U patent/CN209780193U/en not_active Expired - Fee Related
Cited By (6)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN109577632A (en) * | 2019-01-16 | 2019-04-05 | 中建八局第建设有限公司 | A kind of swinging scaffold and its construction method |
| CN109577632B (en) * | 2019-01-16 | 2023-10-27 | 中建八局第一建设有限公司 | Suspended scaffolding and construction method thereof |
| CN111456400A (en) * | 2020-03-24 | 2020-07-28 | 中国五冶集团有限公司 | A high-altitude temporary operating platform structure |
| CN112663928A (en) * | 2020-12-30 | 2021-04-16 | 大连九洲建设集团有限公司 | Decoration engineering operation platform for high-altitude large cantilever structure and mounting and dismounting method |
| CN115959262A (en) * | 2023-01-03 | 2023-04-14 | 江南造船(集团)有限责任公司 | Temporary construction platform for liquid dome area of cargo tank of transport ship and installation method thereof |
| CN120739307A (en) * | 2025-07-29 | 2025-10-03 | 广东雄桥建设集团有限公司 | Movable building hand and foot frame easy to disassemble and assemble |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN209780193U (en) | Suspension type scaffold | |
| CN104196222B (en) | The suspension scaffold of tools type section steel builder's jack | |
| CN201158933Y (en) | High-rise maintaining scaffold device with extruding structure | |
| CN103452311B (en) | A kind of erection method of shaped steel suspended structural support frame | |
| CN212534174U (en) | Raft foundation steel bar supporting tool | |
| CN109898848B (en) | A climbing integral steel platform formwork system and its construction method | |
| CN104389419A (en) | Cantilevered formwork platform installation structure and construction method | |
| CN112854702A (en) | Large-span silo roof construction platform and erection method | |
| CN115787996A (en) | Overhung construction method and overhung frame for super-high building | |
| CN211689948U (en) | A suspension operation platform device for the construction of a cable-stayed bridge tower | |
| CN222991120U (en) | A cantilever concrete structure formwork scaffolding structure | |
| CN111764623B (en) | Hanging construction platform module and construction method of high altitude large cantilever steel roof frame | |
| CN212866793U (en) | Assembled construction elevator stops layer platform | |
| CN202090577U (en) | Template supporting construction platform for lift wells in high-rise buildings | |
| CN212406038U (en) | Lower hanging construction platform module of high-altitude large-cantilever steel roof truss | |
| CN210025768U (en) | A operation platform system for caisson template installation | |
| CN207177310U (en) | A kind of crane beam on rock wall for underground power house reinforcing bar is from steady structure | |
| CN215594920U (en) | Back-jacking type overhanging structure formwork supporting system | |
| CN216475804U (en) | A steel truss floor deck | |
| CN215669490U (en) | A cantilever type pipe pile lifting positioning bracket | |
| CN115897975A (en) | A high-altitude suspended platform formwork system and its construction method | |
| CN209874434U (en) | Simple and easy scaffold frame of encorbelmenting of building high latitude | |
| CN109577632B (en) | Suspended scaffolding and construction method thereof | |
| CN218264949U (en) | Concrete cantilever member support system | |
| CN201137297Y (en) | Board-free frame structure formwork support rack |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20191213 |