CN209412983U - A kind of assembled interlayer arrangement concrete truss overhanging construction - Google Patents

A kind of assembled interlayer arrangement concrete truss overhanging construction Download PDF

Info

Publication number
CN209412983U
CN209412983U CN201821342625.6U CN201821342625U CN209412983U CN 209412983 U CN209412983 U CN 209412983U CN 201821342625 U CN201821342625 U CN 201821342625U CN 209412983 U CN209412983 U CN 209412983U
Authority
CN
China
Prior art keywords
concrete truss
truss
precast
overhanging
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821342625.6U
Other languages
Chinese (zh)
Inventor
尹犟
俞大有
李昌州
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Minsheng Zhuyou Co Ltd
Original Assignee
China Minsheng Zhuyou Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Minsheng Zhuyou Co Ltd filed Critical China Minsheng Zhuyou Co Ltd
Priority to CN201821342625.6U priority Critical patent/CN209412983U/en
Application granted granted Critical
Publication of CN209412983U publication Critical patent/CN209412983U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a kind of assembled interlayers to arrange concrete truss overhanging construction, including multiple vertically arranged overhanging units, the upward lateral inclination setting of overhanging unit, the inclined direction for the overhanging unit being disposed adjacent is opposite, the assembled interlayer arrangement concrete truss overhanging construction is in polyline shaped, shear wall is disposed in the vertical load-bearing main body, the shear wall is integrally continuously arranged from bottom to top along assembled interlayer arrangement concrete truss overhanging construction and is surrounded by least one Core Walls Structure, the overhanging unit two-way is in length and breadth equipped with multiple rows of precast concrete truss at interval of one layer, the Core Walls Structure is fixedly connected in the two-way precast concrete truss intersected with it in length and breadth, it is connected between the multiple rows of precast concrete truss of same layer by precast beam, precast floor slab and the precast concrete truss and/or shear wall are solid Fixed connection.This building cantilever part formed one on have day, under have ground balcony space, reach the function of villa.

Description

A kind of assembled interlayer arrangement concrete truss overhanging construction
Technical field
The utility model belongs to building engineering field more particularly to a kind of assembled interlayer arrangement concrete truss overhanging type Building.
Background technique
In the major premise that land resource that China can be used in urban construction is limited, population constantly increases, urbanization accelerates Under, the soil that downtown area can be sent out is fewer and fewer, and the rare degree in the especially superior location in big city is particularly evident, on the contrary , city is but rising steadily to housing demand, therefore low-density residential buildings form has been not suitable for surviving in China city, and high Layer agglomerated residence has obtained broad development with the advantage of its higher plot ratio.It is low at home in most of more developed city The villa house of density often build Outskirts of City or outer suburbs location in, and people gradually have found Suburban Life mode during house Facing the Space Quality of inhabitation and travel to and fro between residence time cost and lack improve life it is mating between contradiction.Cause This, in order to solve the contradiction of comfort and convenience, the agglomerated residence of villadom has been increasingly becoming as real estate market high-end product New lover.This kind of house is located at downtown prime location mostly, and the function distribution of villa house is imitated on Size Dwelling Design, and has " hanging garden ", occupant, which stays indoors, can get close to nature;Plane figure design can also be optimized, possessed as villa a The inhabitation atmosphere of property secret;Along with the full landscape balcony etc. towards Urban Parks or waters, therefore praised by real estate developers For " the aerial villa " in city.To a certain extent, it is equivalent to villa house ensemble, extends to aerial, " guide look crowd Mountain is small " imposing manner to be sometimes villa incomparable.
Villa embodies a kind of natural life style as a kind of high-quality house, more representative of inhabitation culture and Spirit becomes the best inhabitation selection of people's good life needs, and price is high, remote, mating uneven congruence of living all is general The logical people are difficult to the major reason received to it.And the soil and construction cost of aerial villa and common high residential building are suitable, enjoy By villa quality and occupy downtown prime location, be the house of new generation that people go after like a flock of ducks, demand crowd will not It is only limitted to the elite crowd of booming income again, but ruck and middle class, the scale of construction of the market demand is than present high level House is bigger, not only contains the demand crowd of existing high residential building, will also include a part of existing villa demand crowd.Therefore As the high-end house in down town, demand is very wide in central U.S. villa.
Utility model content
The purpose of the utility model is to provide a kind of structure novel, assembly efficiency height, villa house ensemble is simultaneously extended to One of sky assembled interlayer arranges concrete truss overhanging construction.
Above-mentioned purpose is to be achieved through the following technical solutions: a kind of assembled interlayer arrangement concrete truss overhanging type is built It builds, including multiple vertically arranged overhanging units, the overhanging unit includes multilayered structure, and the overhanging unit laterally inclines upwards Tiltedly setting, the inclined direction for the overhanging unit being disposed adjacent is on the contrary, assembled interlayer arrangement concrete truss overhanging type is built It builds in polyline shaped, the assembled interlayer arrangement concrete truss overhanging construction includes vertical load-bearing main body and overhanging in institute The cantilever part outside vertical load-bearing main body is stated, shear wall is disposed in the vertical load-bearing main body, the shear wall is along assembly At least one Core Walls Structure is continuously arranged from bottom to top and be surrounded by formula interlayer arrangement concrete truss overhanging construction integrally, described Overhanging unit at interval of one layer it is two-way in length and breadth be equipped with multiple rows of precast concrete truss, the Core Walls Structure is two-way with its phase in length and breadth The precast concrete truss of friendship is fixedly connected, and is connected between the multiple rows of precast concrete truss of same layer by precast beam, prefabricated building Plate is fixedly connected with the precast concrete truss and/or shear wall.
Cantilever part described herein refers to the part overhang outside vertical load-bearing main body, and vertical load-bearing main body is specifically Refer to and bears building structure self weight and vertical additional load, mobile load and the structure position that it is successively transferred to basis;It is two-way in length and breadth Refer to overhanging direction and the vertical direction of overhanging unit.
Adjacent two overhanging units constitute a firm cellular construction in this building structure, and consolidating cellular construction is triangle Shape rock-steady structure, this building structure can be made of multiple firm cellular constructions, and whole building is in broken line type, and concrete truss is every Overhanging unit increments overhanging, the number of plies of each overhanging unit can be set according to specific actual conditions, if every layer overhangs 2.1 meters, that 4 layers overhang 8.4m altogether, and cantilever part, which is formed on one, day, under have the balcony space on ground, reach the function of villa, above may be used Trees etc. are planted, the function distribution of villa house is imitated on Size Dwelling Design, by villa house ensemble, extend to aerial, inhabitation Person stays indoors to get close to naturally, can also optimize plane figure and design, and the inhabitation atmosphere of individual character secret is possessed as villa It encloses, forms aerial villa;Experiment proves that this cantilevered structure can satisfy structure safety and requirement.
Specifically, this building is in the floor direction taken in upwards, every layer of upper space be it is open, have day in formation, to The upper direction for being incremented by overhanging, every layer of lower space be it is unobstructed, be down ground, one side house type of every floor has a direction There is day on being, can be planted, garden is formed, and the aerial villa of the general top grade is 2 layer of one family, then the trees of first layer Plant can be more than that layer is high, reach the second layer, make 2 layers of function of enjoying garden villa.Concrete truss is as building The main load-carrying member of main structure can replace prefabricated post and wallboard to use, the pure solid concrete of truss weight ratio of use Gently, advantageous to the economy and antidetonation of structure entirety, and a large amount of concrete and bar material can be saved, truss can be conducive to room Between between connection, in forming chamber can be changed large space, reach the large space function of villa.
This structure is main vertical load-bearing and horizontal anti-seismic component by assembled Core Walls Structure, every first floor from Core Walls Structure Overhang one layer of assembling truss structure out, the assembling truss structure of this layer overhanging not only undertakes the load of this floor, also undertakes The load of next level plate, so that upper one layer of flooring forms a large space without vertical supporting, to form real nothing The changeable space of any obstruction.
Further technical solution is that bilevel floor is connected with the concrete truss of same layer, and upper layer floor is taken It connects and is fixed on the top boom of the concrete truss, the lower boom side of the concrete truss is equipped with dowel, described The splice ends of precast floor slab, which are equipped with, stretches out muscle, and the dowel mutually splices with the stretching muscle, the concrete truss and institute State precast floor slab connected by post-cast strip it is integral, the dowel and stretch out muscle be anchored in the post-cast strip.
Main load-carrying member of the concrete truss of the utility model as constructure body structure, can replace prefabricated post and Wallboard uses, this connecting node makes full use of the design feature of concrete truss, throws away company by the side in concrete truss Muscle is connect, the splice ends of precast floor slab, which are equipped with, stretches out muscle, and dowel is overlapped with stretching muscle and cast-in-place formation post-cast strip will mix here Solidifying soil truss connect integral with precast floor slab, and precast floor slab delivers load to concrete truss.
Further technical solution is that connection sleeve is embedded in the concrete truss, the opening of the connection sleeve It is connected outside end and the concrete truss, the dowel is fixedly connected with the connection sleeve.In this way, assembly efficiency is high, Connection is reliable, does not influence the transport of concrete truss.
Further technical solution is that the dowel is beard muscle, and the beard muscle is embedded in the upper layer truss Bottom.
Further technical solution is that bracket is equipped with described in the concrete truss, and the precast floor slab is overlapped on described It is fixedly connected on bracket and with bracket.
Further technical solution is that the precast floor slab is overlapped on one end on the bracket and is equipped with insertion hole, described Bracket is equipped with anchoring piece, and described anchoring piece one end is anchored in the bracket, inserts in the hole described in other end insertion.The insertion Grouting material is perfused in hole.In this way, by grouting material anchoring piece can connect with precast beam it is integral, and then increase bracket in advance The globality of floor processed, connection is more reliable, and the grouting material is preferably mortar.
Further technical solution is that the Core Walls Structure is perpendicular as the shear wall-concrete truss overhanging construction To traffic core, the shear wall-concrete truss overhanging construction stair or elevator setting are in the Core Walls Structure.Due to cutting Stability after power wall formation Core Walls Structure is stronger, and the stress of Core Walls Structure is better than the perpend wall being separately provided, and Core Walls Structure is as vertical The escape route of traffic nuclear protection building, makes building when an earthquake occurs, guarantees the safety of staircase.
Further technical solution is notch to be equipped at the top of the concrete truss, the both ends of the precast beam are taken respectively It connects in the notch at the top of the two rows of concrete truss being disposed adjacent, the concrete truss is equipped with connector, described pre- Beam processed is equipped with jack hole, and the top of the precast beam is equipped with recess, and the jack hole is connected to the recess, and the connector is worn It crosses the jack hole to protrude into the recess, fastener is equipped in the recess, the fastener is connected with the connector.
Further technical solution is that the connector is screw rod, and the fastener is nut, one end anchor of the screw rod Gu the other end, which is worn, connects the nut in the concrete truss.
Further technical solution is to be perfused with grouting material in the jack hole and recess.The utility model passes through insertion Concrete truss is formed effective dry type with precast beam and connect by connector and fastener in the jack hole of precast beam, is being filled With in the process, after concrete truss is vertical good, it is only necessary to the lapping ends of precast beam be arranged in the hoisting process of precast beam In the notch of concrete truss, while connector is inserted into the jack hole in the precast beam and recess, so It is fastened afterwards by fastener, above structure is conducive to the conduction of power between concrete truss and precast beam, while greatly improving existing The efficiency of field installation, improves construction speed.
Further technical solution is that the shear wall and precast concrete truss splice, and the shear wall is mixed with prefabricated The splicing side of solidifying soil truss is equipped with built-in fitting, is fixedly connected with shear wall with precast concrete truss by welding built-in fitting.
Further technical solution is that the concrete truss includes the precast concrete truss list of multiple horizontal splicings Member, the precast concrete truss element connection are integral.In this way, precast concrete truss element component is smaller relatively light, it is convenient for It transports and lifts, by being assembled into monolithic concrete truss in assembling process, globality is relatively preferable, and installation effectiveness is high.
Further technical solution is that the precast concrete truss element is triangular structure, two precast concretes The bevel edge of truss element is spliced to form truss module, multiple horizontally-spliced composition concrete truss of truss module.In this way, the triangle Shape component can form standard module, can largely produce without make-to-order, and directly assembly when having demand has weldering It connecing, is bolted two ways and forms entirety, this concrete truss cellular manufacture mould standard, modularization are high-efficient,
Further technical solution is that the precast concrete truss element being disposed adjacent is bolted, described prefabricated Concrete truss unit is equipped with jack hole, and the bolt is worn the jack hole for connecing adjacent precast concrete truss splicing side and passed through Nut fastening.
Further technical solution, which is that precast concrete truss element splicing side is equipped with, stretches out stirrup, mutually splices The stretching reinforcing bar of precast concrete truss element mutually overlap, the precast concrete truss element mutually spliced passes through the area Hou Jiao Connect integral, the stretching anchorage of stirrups is in the area Hou Jiao.
Further technical solution is that precast concrete truss element splicing side is equipped with notch and vertical jack hole, The precast concrete truss element splicing side mutually spliced forms accommodation groove, is equipped with link block, the connection in the accommodation groove Block also is provided with vertical jack hole, the vertical jack hole of the vertical jack hole of the link block and the precast concrete truss element Be connected, wear connect muscle wear connect the vertical jack hole link block is connected with precast concrete truss element it is integral.
Further technical solution is that transverse structure muscle, the transverse direction are embedded in the precast concrete truss element One end of structure muscle is connected with grout sleeve, and the other end is extend out to outside precast concrete truss element, the precast concrete of side The stretching muscle of truss element stretches in the grout sleeve of precast concrete truss element adjacent thereto and anchoring of being in the milk.
Further technical solution is that the vacancy position in the concrete truss is filled with foamed concrete or sound insulation Plate.In this way, then forming internal partition wall by filling-foam concrete or sound insulation plate girder, foamed concrete can in specific assembling process After prefabricated by the way of installation, the mode poured can also be used and fill, self threading pin or nailing then can be used in triangle sound insulationg board It is connect with concrete truss unit.
Further technical solution is that the top boom and lower boom of the concrete truss are equipped with the first built-in fitting, institute It states and is equipped with concrete support in concrete truss, the concrete support includes diagonal brace, and the both ends of the diagonal brace are equipped with second Built-in fitting, first built-in fitting and the second built-in fitting are detachably connected.In this way, then may be used in the place that building does not need setting To remove, mode changes relatively flexibly, and if desired later period house type is changed, want to get through in certain several room, meeting structure stress Under the premise of, it can be supported with dismantling concrete, directly formation large space.
Further technical solution is that first built-in fitting and the second built-in fitting include at least connecting plate, the company Fishplate bar is equipped with threaded connection hole, and first built-in fitting and the second built-in fitting are bolted.In this way, assembly and disassembly is simple Just, and connection is reliable.
Detailed description of the invention
The attached drawing for constituting a part of the utility model is used to provide a further understanding of the present invention, this is practical new The illustrative embodiments and their description of type are not constituteed improper limits to the present invention for explaining the utility model.
Fig. 1 is that assembled interlayer involved in a kind of embodiment of the utility model arranges concrete truss overhanging construction Structural schematic diagram;
Fig. 2 is that assembled interlayer involved in a kind of embodiment of the utility model arranges concrete truss overhanging construction First layer shear wall Core Walls Structure and second layer precast floor slab arragement construction schematic diagram;
Fig. 3 is that assembled interlayer involved in a kind of embodiment of the utility model arranges concrete truss overhanging construction Second layer shear wall Core Walls Structure and second layer concrete truss arragement construction schematic diagram;
Fig. 4 is that assembled interlayer involved in a kind of embodiment of the utility model arranges concrete truss overhanging construction The arragement construction schematic diagram of concrete truss and precast beam;
Fig. 5 is the structural representation after the assembly is completed of an overhanging unit involved in a kind of embodiment of the utility model Figure;
Fig. 6 is the structural representation of a firm unit after the assembly is completed involved in a kind of embodiment of the utility model Figure;
It is intended to;
Fig. 7~11 are that assembled interlayer involved in the utility model another embodiment arranges concrete truss overhanging Formula builds assembling process schematic diagram;
Figure 12 is the connecting node of concrete truss involved in a kind of embodiment of the utility model and precast floor slab Schematic diagram;
Figure 13 is that schematic diagram is arranged in dowel involved in a kind of embodiment of the utility model;
Figure 14 is the connecting node of concrete truss and precast floor slab involved in the utility model another embodiment Schematic diagram;
Figure 15 is the cross-sectional view in Figure 14 along the face A-A;
Figure 16 is the connection structure signal of concrete truss involved in a kind of embodiment of the utility model and shear wall Figure;
Figure 17~23 are the structural schematic diagram of concrete truss involved in a kind of embodiment of the utility model;
Figure 24 and Figure 25 is respectively the Finite element analysis results figure under a kind of embodiment.
In figure:
1 concrete truss, 2 precast beam, 3 precast floor slab, 4 concrete truss unit
5 built-in connection, 6 Core Walls Structure 7 overhangs 8 shear wall of unit
9 top boom, 10 lower boom, 12 first built-in fitting
Vertical 15 concrete support of web member, 16 dowel of 13 second built-in fitting 14
17 connection 18 transverse structure muscle of sleeve, 19 grout sleeve, 20 foamed concretes
The 21 bolts 22 stretching stretching stirrup 24 of muscle 23, which is worn, connects muscle
25 basic 28 brackets of vertical 26 cantilever part of load-bearing main body 27
29 built-in fitting, 30 link block, 33 post-cast strip, 34 anchoring piece
35 areas Hou Jiao
Specific embodiment
The utility model is described in detail with reference to the accompanying drawing, the description of this part be only it is exemplary and explanatory, There should not be any restriction effect to the protection scope of the utility model.In addition, those skilled in the art's retouching according to this document It states, the corresponding combination can be carried out to the feature in embodiment in this document and in different embodiments.
The utility model embodiment is as follows, and referring to Fig.1~6 and Fig. 7~11, a kind of assembled interlayer arranges concrete purlin Frame overhanging construction, including multiple vertically arranged overhanging units 7, the overhanging unit 7 includes multilayered structure, and the overhanging is single The upward lateral inclination setting of member 7, the inclined direction for the overhanging unit 7 being disposed adjacent is on the contrary, the assembled interlayer arranges coagulation Native truss overhanging construction is in polyline shaped, and the assembled interlayer arrangement concrete truss overhanging construction includes vertical load-bearing master Body 25 and overhang cantilever part 26 outside the vertical load-bearing main body 25, is disposed with and cuts in the vertical load-bearing main body 25 Power wall 8, the shear wall 8 are integrally continuously arranged and are enclosed from bottom to top along assembled interlayer arrangement concrete truss overhanging construction Be coiled at least one Core Walls Structure 6, the overhanging unit 7 at interval of one layer it is two-way in length and breadth be equipped with multiple rows of precast concrete truss 1, The Core Walls Structure 6 is fixedly connected in the two-way precast concrete truss 1 intersected with it in length and breadth, the multiple rows of precast concrete purlin of same layer It is connected between frame 1 by precast beam 2, the precast floor slab 3 is fixedly connected with precast concrete truss 1 and/or shear wall 8.
Cantilever part 26 described herein, which refers to, overhangs part outside vertical load-bearing main body 25, and vertical load-bearing main body 25 It specifically refers to bear building structure self weight and vertical additional load, mobile load and the structure position that it is successively transferred to basis 27; The two-way overhanging direction for referring to overhanging unit 7 and vertical direction in length and breadth.
Adjacent two overhanging units 7 constitute a firm cellular construction in this building structure, and consolidating cellular construction is three Angular rock-steady structure, this building structure can be made of multiple firm cellular constructions, and whole building is in broken line type, concrete truss 1 every overhanging unit 7 is incremented by overhanging, and the number of plies of each overhanging unit 7 can be set according to specific actual conditions, if every layer of overhanging 2.1 Rice, then 4 layers overhang 8.4m altogether, cantilever part 26, which is formed on one, day, under have the balcony space on ground, reach the function of villa Can, trees etc. can be planted above, and the function distribution that villa house is imitated on Size Dwelling Design extends to villa house ensemble In the air, occupant stays indoors to get close to naturally, can also optimize plane figure and design, and individual character secret is possessed as villa Inhabitation atmosphere, form aerial villa;Experiment proves that this cantilevered structure can satisfy structure safety and requirement.
Specifically, this building is in the floor direction taken in upwards, every layer of upper space be it is open, have day in formation, to The upper direction for being incremented by overhanging, every layer of lower space be it is unobstructed, be down ground, one side house type of every floor has a direction There is day on being, can be planted, garden is formed, and the aerial villa of the general top grade is 2 layer of one family, then the trees of first layer Plant can be more than that layer is high, reach the second layer, make 2 layers of function of enjoying garden villa.Concrete truss 1 is as building The main load-carrying member of object main structure can replace prefabricated post and wallboard to use, the pure solid concrete of truss weight ratio of use It is light, advantageous to the economy and antidetonation of structure entirety, and can save a large amount of concrete and bar material, truss can be conducive to Connection between room reaches the large space function of villa can be changed large space in forming chamber.
This structure is main vertical load-bearing and horizontal anti-seismic component, every alternating floor from Core Walls Structure 6 by assembled Core Walls Structure 6 Building overhangs a floor assembling truss structure out, and the assembling truss structure of this layer overhanging not only undertakes the load of this floor, also holds The load of next level plate is carried on a shoulder pole, so that upper one layer of flooring forms a large space without vertical supporting, to be formed real Changeable space without any obstruction.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 12, bilevel floor with it is same The concrete truss 1 of layer is connected, and upper layer floor is overlapped and is fixed on the top boom 9 of the concrete truss 1, the concrete 10 side of lower boom of truss 1 is equipped with dowel 16, and the splice ends of the precast floor slab 3, which are equipped with, stretches out muscle 22, the dowel 16 are connected into the precast floor slab 3 by post-cast strip 33 whole with the mutually splicing of stretching muscle 22, the concrete truss 1 Body, the dowel 16 and stretching muscle 22 are anchored in the post-cast strip 33.
Main load-carrying member of the concrete truss 1 of the utility model as constructure body structure can replace prefabricated post It is used with wallboard, this connecting node makes full use of the design feature of concrete truss 1, by getting rid of in the side of concrete truss 1 Dowel 16 out, the splice ends of precast floor slab 3, which are equipped with, stretches out muscle 22, dowel 16 and stretches out the overlap joint of muscle 22 and cast-in-place here It forms post-cast strip 33 and connect concrete truss 1 with precast floor slab 3 integral, precast floor slab 3 delivers load to concrete purlin Frame 1.
It is pre- in the concrete truss 1 such as Figure 13 in another embodiment of the utility model on the basis of above-described embodiment Be embedded with connection sleeve 17, be connected outside the open end of the connection sleeve 17 and the concrete truss 1, the dowel 16 and The connection sleeve 17 is fixedly connected.In this way, assembly efficiency is high, connection is reliable, does not influence the transport of concrete truss 1.
On the basis of above-described embodiment, in another embodiment of the utility model, the dowel 16 is beard muscle, the Hu Sub- muscle is embedded in the bottom of the upper layer truss.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 14 and Figure 15, the concrete truss 1 is described equipped with bracket 28, and the precast floor slab 3 is overlapped on the bracket 28 and is fixedly connected with bracket 28.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 15, the precast floor slab 3 is overlapped on One end on the bracket 28 is equipped with insertion hole, and the bracket 28 is equipped with anchoring piece 34, and described 34 one end of anchoring piece is anchored at institute It states in bracket 28, inserts in the hole described in other end insertion.Described insert in the hole is perfused with grouting material.In this way, can by grouting material Anchoring piece 34 is connect to globality that is integral, and then increasing bracket 28 and precast floor slab 3 with precast beam 2, connection is more reliable, The grouting material is preferably mortar.
On the basis of above-described embodiment, in another embodiment of the utility model, the Core Walls Structure 6 is used as the shear wall 8- The vertical traffic core of 1 overhanging construction of concrete truss, the stair of 1 overhanging construction of shear wall 8- concrete truss or Elevator setting is in the Core Walls Structure 6.Stability after forming Core Walls Structure 6 due to shear wall 8 is stronger, and the stress of Core Walls Structure 6 is excellent In the escape route that the perpend wall being separately provided, Core Walls Structure 6 are built as vertical traffic nuclear protection, make building when an earthquake occurs, Guarantee the safety of staircase.
On the basis of above-described embodiment, in another embodiment of the utility model, it is equipped with and lacks at the top of the concrete truss 1 Mouthful, the both ends of the precast beam 2 are overlapped on respectively in the notch at 1 top of two rows of concrete truss being disposed adjacent, described Concrete truss 1 is equipped with connector, and the precast beam 2 is equipped with jack hole, and the top of the precast beam 2 is equipped with recess, described to wear It connects hole to be connected to the recess, the connector passes through the jack hole and protrudes into the recess, and fastening is equipped in the recess Part, the fastener are connected with the connector.
On the basis of above-described embodiment, in another embodiment of the utility model, the connector is screw rod, the fastener For nut, one end of the screw rod is anchored in the concrete truss 1, and the other end, which is worn, connects the nut.
On the basis of above-described embodiment, in another embodiment of the utility model, it is perfused in the jack hole and recess Slurry.The utility model by insertion precast beam 2 jack hole in connector and fastener by concrete truss 1 with it is prefabricated Beam 2 forms effective dry type connection, in assembling process, after concrete truss 1 is vertical good, it is only necessary in the lifting of precast beam 2 In journey by the lapping ends of precast beam 2 in the notch that concrete truss 1 is set, while making connector insertion described prefabricated It in jack hole and recess in beam 2, is then fastened by fastener, above structure is conducive to concrete truss 1 and pre- The conduction of power between beam 2 processed, while field erected efficiency is greatly improved, improve construction speed.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 16, the shear wall 8 is mixed with prefabricated Solidifying soil truss 1 splices, and the splicing side of the shear wall 8 and precast concrete truss 1 is equipped with built-in fitting 29, pre-buried by welding Shear wall 8 is fixedly connected by part 29 with precast concrete truss 1.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 17~23, the concrete truss 1 Precast concrete truss element 4 including multiple horizontal splicings, the precast concrete truss element 4 connects integral.In this way, 4 component of precast concrete truss element is smaller relatively light, is readily transported and lifts, integral mixed by being assembled in assembling process Solidifying soil truss 1, globality is relatively preferable, and installation effectiveness is high.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 17, the precast concrete truss list Member 4 is triangular structure, and the bevel edge of two precast concrete truss elements 4 is spliced to form truss module, and multiple truss modules are horizontal To being spliced to form concrete truss 1.In this way, the triangular member can form standard module, it can be largely raw without make-to-order It produces, directly assembly when having demand has welding, bolt 21 to connect two ways and forms entirety, this concrete truss list First 4 production moulds standardization, modularization, it is high-efficient,
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 17, precast concrete truss element 4 Equipped with built-in connection 5, the splicing side of the built-in connection 5 precast concrete truss element 4 is mutually spliced Built-in connection 5 weld it is integral.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 18, the precast concrete being disposed adjacent Truss element 4 is connected by bolt 21, and the precast concrete truss element 4 is equipped with jack hole, the bolt 21 wear connect it is adjacent Precast concrete truss 1 splice side jack hole and by nut fastening.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 19, the precast concrete truss list Member 4 splices side and is equipped with stretching stirrup 23, and the stretching reinforcing bar of the precast concrete truss element 4 mutually spliced mutually overlaps, mutually The precast concrete truss element 4 of splicing by the area Hou Jiao 35 connect it is integral, the stretching stirrup 23 be anchored at it is described after pour In area 35.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 20, the precast concrete truss list Member 4 splices side and is equipped with notch and vertical jack hole, and the precast concrete truss element 4 mutually spliced splices side and forms accommodation groove, Link block 30 is equipped in the accommodation groove, the link block 30 also is provided with vertical jack hole, and vertically wearing for the link block 30 connects Hole is connected with the vertical jack hole of the precast concrete truss element 4, wears to connect muscle 24 and wear and connects the vertical jack hole for institute State link block 30 and precast concrete truss element 4 connect it is integral.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 21, the precast concrete truss list It is embedded with transverse structure muscle 18 in member 4, one end of the transverse structure muscle 18 is connected with grout sleeve 19, and the other end is extend out to Outside precast concrete truss element 4, the stretching muscle 22 of the precast concrete truss element 4 of side stretches to adjacent thereto pre- In the grout sleeve 19 of concrete truss unit 4 processed and anchoring of being in the milk.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 22, in the concrete truss 1 Vacancy position is filled with foamed concrete 20 or sound insulationg board.In this way, passing through filling-foam concrete 20 or the plate girder then shape that insulates against sound At internal partition wall, the prefabricated rear mode installed is can be used in foamed concrete 20 in specific assembling process, and the mode poured can also be used Filling, triangle sound insulationg board then can be used self threading pin or nailing and connect with concrete truss unit 4.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 23, the concrete truss 1 it is upper Chord member 9 and lower boom 10 are equipped with the first built-in fitting 12, are equipped with concrete support 15, the coagulation in the concrete truss 1 Soil support 15 includes diagonal brace, and the both ends of the diagonal brace are equipped with the second built-in fitting 13, and first built-in fitting 12 and second is pre-buried Part 13 is detachably connected.In this way, can then remove in the place that building does not need setting, mode changes relatively flexibly, and the later period If desired house type is changed, want to get through in certain several room, under the premise of meeting structure stress, can be supported with dismantling concrete 15, directly formation large space.
Concrete truss includes vertical web member 14, and the vertical web member 14 connects top boom 9 and lower boom 10.
On the basis of above-described embodiment, in another embodiment of the utility model, such as Figure 23, first built-in fitting 12 and Two built-in fittings 13 include at least connecting plate, and the connecting plate is equipped with threaded connection hole, first built-in fitting 12 and second Built-in fitting 13 is connected by bolt 21.In this way, assembly and disassembly is easy, and connect reliable.
A kind of calculating verification result under embodiment is as follows, as follows through finite element analysis computation verification result, such as Figure 24 institute Show, as seen from the figure, depth of building is 16 layers (total 48m high), and (seismic force is smaller) adds up horizontal position under 6 degree of area's geological processes Moving is 18.8mm, and every layer of horizontal displacement is about 1.175mm (18.8/16=1.175), and story drift is 1/2553 (1.175/ 3000, wherein 3000mm is that layer is high), less than the limit value of 1/1200 angle of displacement most stringent of in assembled high-level structure, meet anti- Shake requires.
As shown in figure 25, vertical displacement of the overhanging part under vertical load and earthquake load is up to 49.5mm, overhangs Total distance is 24m, and the deflection limit value of cantilever member is 2*24000/400=120mm, and vertical maximum displacement is less than deflection limit value, Therefore the cantilevered structure can satisfy structure safety and requirement.
The above is only the preferred embodiment of the utility model, it is noted that for the common skill of the art For art personnel, without departing from the principle of this utility model, several improvements and modifications can also be made, these improve and Retouching also should be regarded as the protection scope of the utility model.

Claims (10)

1. a kind of assembled interlayer arranges concrete truss overhanging construction, which is characterized in that hanged including multiple vertically arranged Unit is chosen, the overhanging unit includes multilayered structure, the upward lateral inclination setting of overhanging unit, the overhanging list being disposed adjacent Member inclined direction on the contrary, the assembled interlayer arrangement concrete truss overhanging construction be in polyline shaped, the assembled every Layer arrangement concrete truss overhanging construction includes vertical load-bearing main body and overhangs outstanding outside the vertical load-bearing main body Position is chosen, shear wall is disposed in the vertical load-bearing main body, the shear wall is outstanding along assembled interlayer arrangement concrete truss Choose that formula building is whole continuously to arrange from bottom to top and be surrounded by least one Core Walls Structure, the overhanging unit at interval of one layer in length and breadth Two-way to be equipped with multiple rows of precast concrete truss, the Core Walls Structure is fixed in the two-way precast concrete truss intersected with it in length and breadth It connects, is connected between the multiple rows of precast concrete truss of same layer by precast beam, precast floor slab and the precast concrete truss And/or shear wall is fixedly connected.
2. assembled interlayer according to claim 1 arranges concrete truss overhanging construction, which is characterized in that upper and lower two The floor of layer is connected with the concrete truss of same layer, and upper layer floor overlaps and is fixed on the top boom of the concrete truss On, the lower boom side of the concrete truss is equipped with dowel, and the splice ends of the precast floor slab, which are equipped with, stretches out muscle, the company It connects muscle mutually to splice with the stretching muscle, the concrete truss connect integral, institute with the precast floor slab by post-cast strip It states dowel and stretches out muscle and be anchored in the post-cast strip.
3. assembled interlayer according to claim 2 arranges concrete truss overhanging construction, which is characterized in that described mixed It is embedded with connection sleeve in solidifying soil truss, is connected outside the open end of the connection sleeve and the concrete truss, the company Muscle is connect to be fixedly connected with the connection sleeve.
4. assembled interlayer according to any one of claims 1 to 3 arranges concrete truss overhanging construction, feature It is, for the Core Walls Structure as the shear wall-concrete truss overhanging construction vertical traffic core, the shear wall-is mixed The stair or elevator setting of solidifying soil truss overhanging construction are in the Core Walls Structure.
5. assembled interlayer according to claim 4 arranges concrete truss overhanging construction, which is characterized in that described mixed Notch is equipped at the top of solidifying soil truss, the both ends of the precast beam are overlapped on the two rows of concrete truss tops being disposed adjacent respectively In the notch in portion, connector is equipped at the top of the concrete truss, the precast beam is equipped with jack hole, the top of the precast beam Equipped with recess, the jack hole is connected to the recess, and the connector passes through the jack hole and protrudes into the recess, described Fastener is equipped in recess, the fastener is connected with the connector.
6. assembled interlayer according to claim 4 arranges concrete truss overhanging construction, which is characterized in that described to cut Power wall and precast concrete truss splice, and the splicing side of the shear wall and precast concrete truss is equipped with built-in fitting, pass through Shear wall is fixedly connected by welding built-in fitting with precast concrete truss.
7. assembled interlayer according to claim 4 arranges concrete truss overhanging construction, which is characterized in that described mixed Solidifying soil truss includes the precast concrete truss element of multiple horizontal splicings, and the precast concrete truss element connects into whole Body.
8. assembled interlayer according to claim 7 arranges concrete truss overhanging construction, which is characterized in that described pre- Concrete truss unit spliced processed side is equipped with notch and vertical jack hole, the precast concrete truss element splicing side mutually spliced Form accommodation groove, be equipped with link block in the accommodation groove, the link block also is provided with vertical jack hole, the link block it is vertical Jack hole is connected with the vertical jack hole of the precast concrete truss element, wears to connect muscle and wear and connects the vertical jack hole for institute State link block connected with precast concrete truss element it is integral.
9. assembled interlayer according to claim 7 arranges concrete truss overhanging construction, which is characterized in that described mixed Vacancy position in solidifying soil truss is filled with foamed concrete or sound insulationg board.
10. assembled interlayer according to claim 9 arranges concrete truss overhanging construction, which is characterized in that described The top boom and lower boom of concrete truss are equipped with the first built-in fitting, are equipped with concrete support, institute in the concrete truss Stating concrete support includes diagonal brace, and the both ends of the diagonal brace are equipped with the second built-in fitting, first built-in fitting and second pre-buried Part is detachably connected.
CN201821342625.6U 2018-08-20 2018-08-20 A kind of assembled interlayer arrangement concrete truss overhanging construction Expired - Fee Related CN209412983U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821342625.6U CN209412983U (en) 2018-08-20 2018-08-20 A kind of assembled interlayer arrangement concrete truss overhanging construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821342625.6U CN209412983U (en) 2018-08-20 2018-08-20 A kind of assembled interlayer arrangement concrete truss overhanging construction

Publications (1)

Publication Number Publication Date
CN209412983U true CN209412983U (en) 2019-09-20

Family

ID=67930149

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821342625.6U Expired - Fee Related CN209412983U (en) 2018-08-20 2018-08-20 A kind of assembled interlayer arrangement concrete truss overhanging construction

Country Status (1)

Country Link
CN (1) CN209412983U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109281405A (en) * 2018-08-20 2019-01-29 中民筑友有限公司 A kind of assembled interlayer arrangement concrete truss overhanging construction

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109281405A (en) * 2018-08-20 2019-01-29 中民筑友有限公司 A kind of assembled interlayer arrangement concrete truss overhanging construction
CN109281405B (en) * 2018-08-20 2023-10-20 筑友智造智能科技有限公司 Assembled interlayer arrangement concrete truss overhanging type building

Similar Documents

Publication Publication Date Title
CN101215819B (en) Separated double-layer bridge-floor cable stayed bridge
CN205875394U (en) Antidetonation concrete beam column that dry process is connected
CN209412984U (en) A kind of building
CN209412983U (en) A kind of assembled interlayer arrangement concrete truss overhanging construction
CN109281390A (en) A kind of assembly concrete truss shear wall building structure
CN209412976U (en) A kind of shear wall-concrete truss overhanging construction
CN106088328A (en) A kind of group frame
CN209412968U (en) A kind of assembly concrete truss shear wall building structure
CN209412967U (en) A kind of assembly concrete truss building structure
CN209412982U (en) A kind of interlayer cantilevered concrete truss formula building
CN102392417B (en) Dual-cantilever bearing support structure for large steel pipe and installation method
CN109281478A (en) A kind of assembly method of shear wall-concrete truss overhanging construction
CN109372123A (en) A kind of interlayer cantilevered concrete truss formula building
CN109281405A (en) A kind of assembled interlayer arrangement concrete truss overhanging construction
CN109372101A (en) A kind of assembly method of assembled interlayer arrangement concrete truss overhanging construction
CN106013097B (en) Mountain area abrupt slope great diameter and long pile cages construction sizing mould bases in situ and construction method
CN109281394A (en) A kind of shear wall-concrete truss overhanging construction
CN209412977U (en) A kind of precast concrete truss element and precast concrete truss
CN109372097A (en) A kind of assembly concrete truss building structure
CN109281395A (en) A kind of assembly method of assembly concrete truss building
CN109281404A (en) A kind of building
CN209353367U (en) On across active service highway door opening bracket upright post basis
CN109372266A (en) A kind of assembly method of interlayer cantilevered concrete truss formula building
CN206408743U (en) A kind of assembly concrete node
CN109372100A (en) A kind of assembly method of assembly concrete truss shear wall building

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190920

CF01 Termination of patent right due to non-payment of annual fee