CN209368811U - A kind of reinforced PTC perforated pipe stake with ribbing - Google Patents

A kind of reinforced PTC perforated pipe stake with ribbing Download PDF

Info

Publication number
CN209368811U
CN209368811U CN201822233728.5U CN201822233728U CN209368811U CN 209368811 U CN209368811 U CN 209368811U CN 201822233728 U CN201822233728 U CN 201822233728U CN 209368811 U CN209368811 U CN 209368811U
Authority
CN
China
Prior art keywords
stake
ptc
perforated pipe
tubular pole
rib
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201822233728.5U
Other languages
Chinese (zh)
Inventor
乐腾胜
雷金波
项炳泉
刘杭杭
童智能
陶俊
洪光炎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Construction Engineering Testing Technology Group Co ltd
Anhui Institute of Architectural Research and Design
Original Assignee
ANHUI SUPERVISION AND INSPECTION STATION NO II OF CONSTRUCTION ENGINEERING QUALITY
Anhui Institute of Architectural Research and Design
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI SUPERVISION AND INSPECTION STATION NO II OF CONSTRUCTION ENGINEERING QUALITY, Anhui Institute of Architectural Research and Design filed Critical ANHUI SUPERVISION AND INSPECTION STATION NO II OF CONSTRUCTION ENGINEERING QUALITY
Priority to CN201822233728.5U priority Critical patent/CN209368811U/en
Application granted granted Critical
Publication of CN209368811U publication Critical patent/CN209368811U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a kind of reinforced PTC perforated pipe stakes with ribbing, the several groups filtration hole that L is opened up successively is spaced including PTC tubular pole and from stake top to stake bottom, the PTC tubular pole is provided with the circular rib that ring is attached on tubular pole appearance wall along stake length direction at stake top L/2 pile cutoff, the circular rib is equipped with several, it is successively laid along stake length direction spacing distance L, is equidistantly laid with several longitudinal ribs along the setting of stake length direction the stake week of the PTC tubular pole.The utility model structure is simple, soil compaction effect effect can be effectively reduced by the filtration hole that pile body is arranged, rib is set on the longitudinal direction and ring section of tubular pole, the stiffness of structural member of PTC perforated pipe stake can be effectively improved, and substantially increase the durability and reliability of PTC perforated pipe stake, its synergistic effect can reduce the differential settlement of pile body after the completion of pile sinking, improve the safety coefficient of pile foundation engineering construction.

Description

A kind of reinforced PTC perforated pipe stake with ribbing
Technical field
The utility model relates to PTC perforated pipe stake technical fields, more particularly to a kind of reinforced PTC perforated pipe stake with ribbing.
Background technique
In recent years, obvious for soft clay area PTC type tubular pole effect of driving pile phenomenon, it successively has developed unidirectionally to wearing Perforated pipe stake, it is two-way to be installed with hole tubular pole, it is starlike to being installed with a variety of PTC perforated pipe stakes such as hole tubular pole, can be effectively by it Reduce the excess pore water pressure of pile sinking generation in pile peripheral earth, improve foundation bearing capacity and obtained certain popularization.
But the excess pore water pressure generated when PTC type tubular pole pile sinking is gradually increased along the increase of depth, and it is above-mentioned PTC perforated pipe stake body bore size is remained unchanged along stake length direction, is caused unknown close to stake bottom reduction soil compaction effect effect It is aobvious, and pile body filtration hole easily blocks, and can not play a role well.
Meanwhile filtration hole is arranged in PTC type tubular pile body, reduces tubular pole bearing capacity to a certain extent.Therefore, how to have While effect ground reduces effect of driving pile influence, guarantee pile sinking quality, improving bearing capacity of pile foundation is art technology research and development people Member makes great efforts to solve the problems, such as always.
In order to effectively reduce the adverse effect of PTC tubular pole effect of driving pile, and guarantee pile sinking quality, improves pile foundation carrying Power and pile foundation construction safety coefficient, this just has to take certain measure.
Utility model content
The purpose of this utility model is to provide a kind of reinforced PTC perforated pipe stakes with ribbing, can improve to a certain extent The shortcoming of existing PTC perforated pipe stake technology further decreases the adverse effect of effect of driving pile, improves the single pile limit and holds Power is carried, the differential settlement after the completion of pile sinking is reduced, guarantees pile sinking quality.
To achieve the goals above, the utility model adopts the technical scheme that a kind of reinforced PTC perforated pipe with ribbing Stake, the several groups filtration hole that L is opened up successively is spaced including PTC tubular pole and from stake top to stake bottom, the PTC tubular pole is rectangular along stake To the circular rib for being provided with ring at stake top L/2 pile cutoff and being attached on tubular pole appearance wall, the circular rib is equipped with several, It is successively laid along stake length direction spacing distance L, is equidistantly laid with several the stake week of the PTC tubular pole and is arranged along stake length direction Longitudinal rib.
It is as above-mentioned technical proposal to further describe:
The filtration hole in same section along 120 ° of stake circumferential direction interval arrangement, and from stake top to stake bottom along stake length direction hole Diameter size is gradually increased by the rate of change of d/10, wherein d is drainage bore dia.
It is as above-mentioned technical proposal to further describe:
The longitudinal rib and filtration hole are arranged alternately for 60 ° in same section along stake circumferential direction interval.
It is as above-mentioned technical proposal to further describe:
The circular rib and longitudinal rib are special-shaped bulge-structure, and the bulge-structure of circular rib and longitudinal rib Partial cross sectional shape is in isosceles trapezoidal structure.
It is as above-mentioned technical proposal to further describe:
The circular rib is identical as the thickness of longitudinal rib.
The utility model has the beneficial effects that:
The utility model structure is simple, can effectively reduce soil compaction effect effect by the filtration hole that pile body is arranged, improve Soil classifiction enhances foundation stability, reduces harm of the pile sinking to adjacent pile foundation Adjacent Buildings, longitudinal direction and ring in tubular pole Rib is set on tee section, the stiffness of structural member of PTC perforated pipe stake can be effectively improved, and substantially increases PTC perforated pipe stake Durability and reliability, synergistic effect can reduce the differential settlement of pile body after the completion of pile sinking, improve pile foundation engineering and apply The safety coefficient of work.
Detailed description of the invention
Fig. 1 be the utility model proposes the reinforced PTC perforated pipe stake with ribbing of one kind structural schematic diagram;
Fig. 2 is the section structure diagram of A-A in Fig. 1;
Fig. 3 is the schematic diagram of the section structure of B-B in Fig. 2;
Fig. 4 is the cross section structure schematic diagram of circular rib and longitudinal rib in the utility model.
Marginal data:
1-PTC tubular pole, 2- filtration hole, 3- longitudinal rib, 4- circular rib.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.
Referring to Fig.1-4, a kind of reinforced PTC perforated pipe stake with ribbing, including PTC tubular pole 1 and from stake top to stake bottom successively The several groups filtration hole 2 that interval L is opened up, PTC tubular pole 1 are provided with ring at stake top L/2 pile cutoff along stake length direction and are attached to tubular pole Circular rib 4 on appearance wall, circular rib 4 are equipped with several, successively lay along stake length direction spacing distance L, purpose exists In the structure by changing tubular pole section increases the contact area of stake soil to a certain extent, improves pile side friction, Neng Goujian Ultimate bearing capacity of single pile is improved singly and effectively, is equidistantly laid with several the stake week of PTC tubular pole 1 along the setting of stake length direction Longitudinal rib 3 mentions it is intended that increasing the contact area of stake soil to a certain extent by the structure for changing tubular pole longitudinal direction High pile side friction, referring to fig. 2, longitudinal rib 3 are arranged alternately for 60 ° in same section along stake circumferential direction interval with filtration hole 2, ginseng See Fig. 1 and Fig. 4, circular rib 4 and longitudinal rib 3 are special-shaped bulge-structure, and the protrusion of circular rib 4 and longitudinal rib 3 The cross sectional shape of structure division is in isosceles trapezoidal structure, and circular rib 4 and longitudinal rib 3 can to the greatest extent can in isosceles trapezoidal structure The contact area of increase PTC tubular pole 1 and the soil body that can be big, and not will cause the damage of rib.
Embodiment 1
Filtration hole 2 in same section along 120 ° of stake circumferential direction interval arrangement, and from stake top to stake bottom along stake length direction aperture Size is gradually increased by the rate of change of d/10, wherein d is drainage bore dia, it is intended that the filtration hole 2 being gradually increased It can preferably inhibit the soil compaction effect of pile peripheral earth depths to act on, improve soil classifiction, enhance foundation stability, reduce Harm of the pile sinking to adjacent pile foundation Adjacent Buildings.
Embodiment 2
The rib thickness and rib top size that circular rib 4 and longitudinal rib 3 is arranged are t, and rib bottom is having a size of 2t, i.e. rib The ratio between thickness, rib top size and rib bottom size are 1:1:2, and the size of 3 convex portion of circular rib 4 and longitudinal rib can also be with Different sizes is selected according to tubular pole size.
Embodiment 3
Circular rib 4 is identical as the thickness of longitudinal rib 3, is conducive to the shearing strength for improving the soil body.
Reinforced PTC perforated pipe stake with ribbing in the utility model only need to use special PTC perforated pipe stake with ribbing in factory Punching block produces as required, and method is compared with perforated pipe stake production technology.In view of pile lining aperture generates stress concentration phenomenon, the structure Part site operation uses static pressure pile-sinking mode, must not use hammer piling and pile vibrosinking mode.In pile driving process, tubular pole pile lining Several holes of upper design allow the interior pore water generated of pile peripheral earth to flow into lumen by side chamber, then extract row with micro pump Out, the moisture content for reducing pile peripheral earth improves the shearing strength of the soil body, enhances foundation bearing capacity, effectively reduces soil compaction during pile driving Influence of the effect to surrounding buildings environment.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this Novel technical solution and its utility model design are subject to equivalent substitution or change, should all cover the protection model in the utility model Within enclosing.

Claims (5)

1. a kind of reinforced PTC perforated pipe stake with ribbing, is successively spaced what L was opened up including PTC tubular pole (1) and from stake top to stake bottom Several groups filtration hole (2), which is characterized in that the PTC tubular pole (1) is provided with ring at stake top L/2 pile cutoff along stake length direction The circular rib (4) being attached on tubular pole appearance wall, the circular rib (4) be equipped with several, along stake length direction spacing distance L according to Secondary laying, the PTC tubular pole (1) are equidistantly laid with several longitudinal ribs (3) along the setting of stake length direction stake week.
2. the reinforced PTC perforated pipe stake with ribbing of one kind according to claim 1, which is characterized in that the filtration hole (2) exists Same section is fast by the variation of d/10 along stake length direction pore size along 120 ° of stake circumferential direction interval arrangement, and from stake top to stake bottom Rate is gradually increased, wherein d is drainage bore dia.
3. the reinforced PTC perforated pipe stake with ribbing of one kind according to claim 1, which is characterized in that the longitudinal rib (3) It is arranged alternately for 60 ° in same section along stake circumferential direction interval with filtration hole (2).
4. the reinforced PTC perforated pipe stake with ribbing of one kind according to claim 1, which is characterized in that the circular rib (4) It is special-shaped bulge-structure with longitudinal rib (3), and the section of the bulge-structure part of circular rib (4) and longitudinal rib (3) Shape is in isosceles trapezoidal structure.
5. the reinforced PTC perforated pipe stake with ribbing of one kind according to claim 1 or 4, which is characterized in that the circular rib (4) identical as the thickness of longitudinal rib (3).
CN201822233728.5U 2018-12-28 2018-12-28 A kind of reinforced PTC perforated pipe stake with ribbing Active CN209368811U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201822233728.5U CN209368811U (en) 2018-12-28 2018-12-28 A kind of reinforced PTC perforated pipe stake with ribbing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201822233728.5U CN209368811U (en) 2018-12-28 2018-12-28 A kind of reinforced PTC perforated pipe stake with ribbing

Publications (1)

Publication Number Publication Date
CN209368811U true CN209368811U (en) 2019-09-10

Family

ID=67828191

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201822233728.5U Active CN209368811U (en) 2018-12-28 2018-12-28 A kind of reinforced PTC perforated pipe stake with ribbing

Country Status (1)

Country Link
CN (1) CN209368811U (en)

Similar Documents

Publication Publication Date Title
CN202689031U (en) Deep foundation pit retaining and protecting retaining wall
CN202039382U (en) Ribbing seabed suction anchor
CN204456186U (en) Being hampered for push pipe jacking, the circle of removing obstacles is inverse makes vertical shaft
CN203167652U (en) Greening and planting system for saline and alkaline land
CN105155548A (en) Cable double-row pile (wall) supporting structure
CN204456076U (en) A kind of reinforced concrete pipe pile
CN205502024U (en) Arch combination envelope that can partially retrieve
CN203284786U (en) Side slope anti-slide and pre-warning system with underground water collection and utilization function
CN109797764A (en) A kind of anti-liquefaction pile foundation suitable for easy liquefaction soil layers
CN209368811U (en) A kind of reinforced PTC perforated pipe stake with ribbing
CN204000840U (en) Concrete floral tube slip casting uplift pile
CN205188976U (en) Drag -line double row pile supporting construction
CN204325837U (en) Basement rock covers the high roadbed reclamation lateral restraint reinforcing construction of soft foundation
CN202023185U (en) Concrete tubular pile
CN205000346U (en) Slope frame for slope reinforcement and water drainage
CN209368810U (en) A kind of novel PTC perforated pipe stake with ribbing
CN206015511U (en) One implant post steel pipe column
CN204898649U (en) A novel PTC type has a heliciform hole tubular pile that is used for deep soft base to handle
CN202359564U (en) Arch steel sheet pile supporting structure
CN202298627U (en) Foundation pit supporting structure
CN206768802U (en) A kind of reinforced PTC perforated pipes stake
CN207047890U (en) It is a kind of to plant raw retaining wall structure from embedded
CN202706046U (en) Anti-floating drainage structure for underground structure
CN205990619U (en) A kind of rich groundwater and geology bad deep pit digging supporting construction
CN102011395A (en) Piling tube

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: No.567, Shanhu Road, Shushan District, Hefei City, Anhui Province 230000

Patentee after: Anhui Construction Engineering Testing Technology Group Co.,Ltd.

Patentee after: ANHUI INSTITUTE OF BUILDING RESEARCH & DESIGN

Address before: No.567, Shanhu Road, Shushan District, Hefei City, Anhui Province 230000

Patentee before: QUALITY OF CONTRUCTION IN ANHUI PROVINCE SUPERVISION AND INSPECTION STATION

Patentee before: ANHUI INSTITUTE OF BUILDING RESEARCH & DESIGN

CP01 Change in the name or title of a patent holder