CN209211915U - A kind of high-altitude wire frame installation system - Google Patents
A kind of high-altitude wire frame installation system Download PDFInfo
- Publication number
- CN209211915U CN209211915U CN201822116013.1U CN201822116013U CN209211915U CN 209211915 U CN209211915 U CN 209211915U CN 201822116013 U CN201822116013 U CN 201822116013U CN 209211915 U CN209211915 U CN 209211915U
- Authority
- CN
- China
- Prior art keywords
- wire frame
- altitude wire
- unloading
- sliding rail
- altitude
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
High-altitude wire frame installation system disclosed by the utility model includes the synchronization discharge mechanism for high-altitude wire frame to be installed to be sent to the slide device in unloading site to and is offloaded to high-altitude wire frame from unloading site installation site, slide device includes sliding rail, electric block and ice boots, sliding rail is arranged on company's wall column on the inside of structure outer, ice boots are arranged in sliding rail and can slide along sliding rail, and electric block connect with high-altitude wire frame by wirerope and draws high-altitude wire frame and slides in sliding rail.Synchronous discharge mechanism includes long bolt, support frame and rotating device, and long bolt is welded to connect on high-altitude wire frame, and support frame is erected on structure outer, and rotating device setting is threadedly coupled on the support frame and with long bolt.The system structure is simple, and process is easy to operate, and installation effectiveness is high, and good economy performance is not limited by construction site, is particularly suitable for the whole unloading of middle-size and small-size rack.
Description
Technical field
The utility model relates to high-altitude wire frame mounting technique field, specially a kind of high-altitude wire frame installation system.
Background technique
High-altitude wire frame is by plurality of rods part by node, the Spacial Frame Structures formed according to certain rule.High-altitude wire frame
In installation process, strict control installation quality, prevents accident.
Currently, high-altitude wire frame installation, which is typically employed in below construction area, sets up full hall scaffold, formed by scaffold
One workbench, construction personnel complete installation exercise on workbench.But it sets up full hall scaffold and needs consuming longer
Duration, and tube material is more, and construction cost is higher.Another kind be it is on the ground that high-altitude wire frame assembly is good, then adopt
With hanging device by high-altitude wire frame integral level or vertical lifting to installation site.Difficulty of construction is big for this mode, and
The weight of construction site and network frame hoisting unit is restricted.In addition, since high-altitude wire frame is among underground garage structure, it can not
It is installed using big machinery.
Utility model content
The purpose of this utility model is to provide a kind of high-altitude wire frame installation systems, are expended with solving to set up full hall scaffold
Duration is longer, needs more tube material, and construction cost is higher;By high-altitude wire frame integral hoisting in the presence of difficulty of construction is big, construction
The weight of place and network frame hoisting unit is restricted;High-altitude wire frame is not available big machinery among underground garage structure
The technical issues of being installed.
In order to solve the above-mentioned technical problem, the utility model provides a kind of high-altitude wire frame installation system, including for will be to
The high-altitude wire frame of installation send to the slide device in unloading site and high-altitude wire frame is offloaded to installation site from unloading site
Synchronous discharge mechanism;
The slide device includes sliding rail, electric block and ice boots, and company's wall on the inside of structure outer is arranged in the sliding rail
On column, the ice boots are arranged in sliding rail and can slide along sliding rail, and the electric block is connected by wirerope and high-altitude wire frame
It connects and draws high-altitude wire frame and slided in sliding rail;
The synchronous discharge mechanism includes long bolt, support frame and rotating device, and the long bolt is welded to connect in high-altitude
On rack, support frame as described above is erected on structure outer, rotating device setting on the support frame and with long bolt screw thread
Connection.
Preferably, the rotating device includes:
Nut is unloaded, is threaded in outside long bolt;
Backing plate is unloaded, offers connecting hole thereon, the unloading nut is stuck in connecting hole and fixes with unloading backing plate
Connection;
Swing handle is connected on unloading backing plate, when the swing handle rotates, on the opposite unloading nut of the long bolt
Lower movement, and then high-altitude wire frame is driven to move up and down.
Preferably, additional backing plate is additionally provided between unloading backing plate and the support frame.
Preferably, additional bolts are threaded on the long bolt above the unloading nut.
Preferably, the ice boots include:
Ice boots ontology, including two pieces of parallel baffles;
Idler wheel, quantity at least two, the idler wheel are equipped with idler wheel axis along central axes, and the idler wheel passes through in idler wheel
Axis is horizontally installed between two block baffles, and the bottom of idler wheel exceeds the bottom of baffle;
Locating fastener is arranged in the upper surface of two block baffles, forms card slot between the locating fastener and baffle.
Preferably, the locating fastener includes one piece of riser and one block of level board, between the level board, riser and baffle
Form card slot.
Preferably, positioning plate is equipped between the bottom of the baffle.
Preferably, attached stiffener is equipped between the baffle both ends.
Compared with prior art, it the characteristics of the utility model and has the beneficial effect that
(1) high-altitude wire frame to be assembled is stuck in ice boots in the utility model, high-altitude wire frame is drawn by electric block
To unloading site, discharge mechanism is then made, by rotary motion device simultaneously, makes multiple unloading sites of rack while mentioning
It rises, then lands, finally realize the installation of high-altitude wire frame.Entire work progress is easy to operate, and installation effectiveness is high, and less personnel are
The installation of achievable common high-altitude wire frame unit.And it does not need not needing using scaffold is set up using large crane.
(2) structure of the ice boots of the utility model is simple, is easy to make, can Reusability, can be moved using only a small amount of boots
Dynamic large size high-altitude wire frame, narrow place especially highlights its dominance on construction ground.Ice boots are lightweight and convenient, are moved easily.
(3) the synchronization discharge mechanism of the utility model discharging quantity each by control long bolt, realizes multiple unloading positions
High-altitude wire frame, is slowly smoothly promoted or is dropped to designated position by the synchronous unloading of point.Synchronous discharge mechanism structure is simple, adopts
It can make, can recycle of live leftover pieces, it is cheaper by 50% using computer control synchronous hydra-ulic jacks than large area
More than.And synchronous discharge mechanism is not limited by construction site.
Detailed description of the invention
Fig. 1 is the Construction State schematic diagram of slide device.
Fig. 2 is the schematic view of the front view of ice boots.
Fig. 3 is the overlooking structure diagram of ice boots.
Fig. 4 is the side structure schematic view of ice boots.
Fig. 5 is the Construction State schematic diagram of synchronous discharge mechanism.
Fig. 6 is the schematic view of facade structure of synchronous discharge mechanism.
Fig. 7 is the planar structure schematic diagram of synchronous discharge mechanism.
Fig. 8 is the arrangement schematic diagram of slide device.
Fig. 9 is the arrangement schematic diagram of synchronous discharge mechanism.
Appended drawing reference: 1- slide device, 11- sliding rail, 12- electric block, 13- ice boots, 131- ice boots ontology, 1311- gear
Plate, 1312- positioning plate, the attached stiffener of 1313-, 132- idler wheel, 133- locating fastener, 1331- riser, 1332- level board, 134-
The synchronous discharge mechanism of idler wheel axis, 135- card slot, 14- wirerope, 2-, 21- long bolt, 22- support frame, 23- rotating device,
231- unloads nut, 232- unloading backing plate, 233- swing handle, 24- and adds backing plate, 25- additional bolts, 3- high-altitude wire frame, 31-
Net rack support, 32- bolt sphere, 4- structure outer, 5- unloading site, 6- connect wall column.
Specific embodiment
To make technological means of the utility model, character of innovation, reaching purpose and effect is easy to understand, below
The present invention will be further described.
The embodiment recorded herein is the specific specific embodiment of the utility model, for illustrating the utility model
Design, be it is explanatory and illustrative, should not be construed as the limit to the utility model embodiment and the scope of the utility model
System.In addition to the embodiment recorded herein, those skilled in the art can also be public based on the claim of this application book and specification institute
For the content opened using obvious other technical solutions, these technical solutions include using doing to the embodiment recorded herein
The technical solution of any obvious substitutions and modifications out.
As shown in figure 1-9, a kind of high-altitude wire frame installation system, including for sending high-altitude wire frame (3) to be installed to unloading
It carries the slide device (1) of site (5) and high-altitude wire frame (3) is offloaded to the synchronous of installation site from unloading site (5) and unload
Device (2).
Slide device (1) includes sliding rail (11), electric block (12) and ice boots (13), and sliding rail (11) is arranged in structure outer
(4) on company's wall column (6) on the inside of, ice boots (13) are arranged in sliding rail (11) and can slide along sliding rail (11), electric block
(12) it is connect by wirerope (14) with high-altitude wire frame (3) and draws high-altitude wire frame (3) sliding in sliding rail (11).
Ice boots (13) include ice boots ontology (131), idler wheel (132) and locating fastener (133), and ice boots ontology (131) includes
Two pieces of parallel baffles (1311) are arranged between the bottom of two block baffles (1311) equipped with positioning plate (1312) and are arranged
Attached stiffener (1313) between two block baffles (1311) both ends.Idler wheel (132) at least two, idler wheel (132) is along axis
Line is equipped with idler wheel axis (134), and idler wheel (132) is horizontally installed between two block baffles (1311) by idler wheel axis (134), rolls
The both ends of wheel axis (134) are fixed with bolt.The bottom of idler wheel (132) exceeds the bottom of baffle (1311).Locating fastener (133)
For adjusting glide direction, prevent high-altitude wire frame (3) from skidding off sliding rail (11).Locating fastener (133) includes one piece of riser (1331)
With one piece of level board (1332), card slot (135) are formed between level board (1332), riser (1331) and baffle (1311).Ice boots
Ontology (131) using Q235B steel plate make, steel plate with a thickness of 20mm.Idler wheel (132) be rotating pin, material 40Cr,
Specification is 100mm.Idler wheel axis (134) is steel-casting.
Synchronous discharge mechanism (2) include long bolt (21), support frame (22), rotating device (23), additional backing plate (24) and
Additional bolts (25), long bolt (21) are welded to connect on high-altitude wire frame (3), and support frame (22) is erected on structure outer (4),
Rotating device (23) is arranged on support frame (22) and is threadedly coupled with long bolt (21).Unload backing plate (232) and support frame
(22) additional backing plate (24) are additionally provided between, for reinforcing fixed unloading backing plate (232).Unload the long spiral shell above nut (231)
Additional bolts (25) are threaded on bar (21), for reinforcing fixed unloading nut (231).Long bolt (21) is high-strength long spiral shell
Bolt, material are No. 45 steel, specification 35mm.Support frame (22) can be selected according to engineering characteristic, generally use H profile steel, material
Q235B。
Rotating device (23) includes unloading nut (231), unloading backing plate (232) and swing handle (233), unloads nut
(231) it is threaded in long bolt (21) outside.Connecting hole is offered in unloading backing plate (232), unloading nut (231) is stuck in connection
It is fixedly connected in hole and with unloading backing plate (232).Swing handle (233) is connected in unloading backing plate (232), swing handle
(233) when rotating, opposite unloading nut (231) of long bolt (21) moves up and down, and then high-altitude wire frame (3) is driven to move up and down.
Swing handle (233) is galvanized steel bar pipe, material Q345B, specification 35mm.Unload backing plate (232) and additional backing plate (24)
For steel plate, material Q235B.
The construction method of above-mentioned high-altitude wire frame installation system the following steps are included:
Step 1: production ice boots (13), the placement location of Deepen Design ice boots (13) and unloading site (5).Ice boots
(13) production method are as follows: first according to design drawing production ice boots ontology (131) and locating fastener (133), idler wheel (132) are blocked
Between two block baffles (1311), idler wheel axis (134) passes through the hole opened up on baffle (1311) and idler wheel (132), then uses
Bolt is fixed.
Step 2: being applied on sliding rail (11) company's of being placed on wall column (6) or in individual steel column support in sliding rail (11)
Several ice boots (13) are spaced apart in sliding rail (11), by the net rack support of high-altitude wire frame (3) by the lubricants such as brush butter
(31) it is stuck in the card slot (135) of ice boots (13), so that high-altitude wire frame (3) is fixed in ice boots (13).
Step 3: even by the net rack support (31) of the end of wirerope (14) on electric block (12) and high-altitude wire frame (3)
It connects, electric block (12) traction high-altitude wire frame (3) slides into unloading site (5) in sliding rail (11).
Step 4: support frame (22) is erected on the structure outer (4) at unloading site (5).
Step 5: the bottom end of long bolt (21) is welded in the bolt sphere (32) of high-altitude wire frame (3).
Step 6: selecting the unloading nut (231) with long bolt (21) cooperation, connection will be opened up in unloading backing plate (232)
Unloading nut (231) is stuck in connecting hole and is welded and fixed, then welds swing handle in unloading backing plate (232) by hole
(233), the production of rotating device (23) is completed.Then rotating device (23) is placed on support frame (22) and and long bolt
(21) it is threadedly coupled.
Step 7: rotating in the forward direction the rotating device (23) at each unloading site (5) simultaneously, long bolt (21) is transported upwards
Dynamic, entire high-altitude wire frame (3) is gradually promoted.Controlling long bolt (21) each discharging quantity is 1~2 screw thread height, i.e., 1~
3mm, it is ensured that synchronous unloading.
Step 8: packing up ice boots (13) and sliding rail (11), while reversely rotating the rotating device at each unloading site (5)
(23), long bolt (21) moves downward, and entire high-altitude wire frame (3) is gradually reduced, by the high-altitude wire frame (3) and existing high-altitude wire frame
(3) the embedded part at net rack support (31) is bolted together to form entirety.Controlling long bolt (21) each discharging quantity is 1~2
A screw thread height, i.e. 1~3mm, it is ensured that synchronous unloading.
Above-mentioned high-altitude wire frame installation system can be incorporated in long 67.2m, the installation of the roofing spherical net brace of wide 42m.One group
High-altitude wire frame (3) has 26 unloading sites (5), can accurately control the balance between multiple devices, and control long bolt (21) is single
Secondary discharging quantity realizes the synchronous unloading in multiple unloading sites.
Above embodiment is only that preferred embodiments of the present invention are described, not to the utility model
Range be defined, under the premise of not departing from the spirit of the design of the utility model, those of ordinary skill in the art are to this is practical
The various changes and improvements that novel technical solution is made should all fall into the protection scope that the utility model claims book determines
It is interior.
Claims (8)
1. a kind of high-altitude wire frame installation system, which is characterized in that including for sending high-altitude wire frame (3) to be installed to unloading position
The slide device (1) of point (5) and the synchronization discharge mechanism that high-altitude wire frame (3) is offloaded to installation site from unloading site (5)
(2);
The slide device (1) includes sliding rail (11), electric block (12) and ice boots (13), and the sliding rail (11) is arranged in structure
On company's wall column (6) on the inside of exterior wall (4), the ice boots (13) are arranged in sliding rail (11) and can slide along sliding rail (11), institute
Electric block (12) are stated to connect with high-altitude wire frame (3) by wirerope (14) and draw high-altitude wire frame (3) in sliding rail (11)
Middle sliding;
The synchronous discharge mechanism (2) includes long bolt (21), support frame (22) and rotating device (23), the long bolt (21)
It is welded to connect on high-altitude wire frame (3), support frame as described above (22) is erected on structure outer (4), and the rotating device (23) sets
It sets on support frame (22) and is threadedly coupled with long bolt (21).
2. a kind of high-altitude wire frame installation system according to claim 1, it is characterised in that the rotating device (23) includes:
It unloads nut (231), is threaded in long bolt (21) outside;
It unloads backing plate (232), offers connecting hole thereon, the unloading nut (231) is stuck in connecting hole and pads with unloading
Plate (232) is fixedly connected;
Swing handle (233) is connected in unloading backing plate (232), when the swing handle (233) rotates, the long bolt
(21) opposite unloading nut (231) moves up and down, and then high-altitude wire frame (3) is driven to move up and down.
3. a kind of high-altitude wire frame installation system according to claim 2, it is characterised in that: the unloading backing plate (232) and
Additional backing plate (24) are additionally provided between support frame (22).
4. a kind of high-altitude wire frame installation system according to claim 2, it is characterised in that: on the unloading nut (231)
Additional bolts (25) are threaded on the long bolt (21) of side.
5. a kind of high-altitude wire frame installation system according to claim 1, it is characterised in that the ice boots (13) include:
Ice boots ontology (131), including two pieces of parallel baffles (1311);
Idler wheel (132), quantity at least two, the idler wheel (132) are equipped with idler wheel axis (134) along central axes, the rolling
Wheel (132) is horizontally installed between two block baffles (1311) by idler wheel axis (134), and the bottom of idler wheel (132) exceeds baffle
(1311) bottom;
Locating fastener (133) is arranged in the upper surface of two block baffles (1311), the locating fastener (133) and baffle (1311)
Between formed card slot (135).
6. a kind of high-altitude wire frame installation system according to claim 5, it is characterised in that: locating fastener (133) packet
Include one piece of riser (1331) and one piece of level board (1332), the level board (1332), riser (1331) and baffle (1311) it
Between formed card slot (135).
7. a kind of high-altitude wire frame installation system according to claim 6, it is characterised in that: the bottom of the baffle (1311)
Between be equipped with positioning plate (1312).
8. a kind of high-altitude wire frame installation system according to claim 7, it is characterised in that: baffle (1311) both ends it
Between be equipped with attached stiffener (1313).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822116013.1U CN209211915U (en) | 2018-12-17 | 2018-12-17 | A kind of high-altitude wire frame installation system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201822116013.1U CN209211915U (en) | 2018-12-17 | 2018-12-17 | A kind of high-altitude wire frame installation system |
Publications (1)
Publication Number | Publication Date |
---|---|
CN209211915U true CN209211915U (en) | 2019-08-06 |
Family
ID=67464948
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201822116013.1U Active CN209211915U (en) | 2018-12-17 | 2018-12-17 | A kind of high-altitude wire frame installation system |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN209211915U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109372274A (en) * | 2018-12-17 | 2019-02-22 | 北京城建集团有限责任公司 | A kind of high-altitude wire frame installation system and its construction method |
-
2018
- 2018-12-17 CN CN201822116013.1U patent/CN209211915U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109372274A (en) * | 2018-12-17 | 2019-02-22 | 北京城建集团有限责任公司 | A kind of high-altitude wire frame installation system and its construction method |
CN109372274B (en) * | 2018-12-17 | 2023-12-01 | 北京城建集团有限责任公司 | High-altitude net rack installation system and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108222482B (en) | Gate-type self-adapting stretching hydraulic climbing plateform system and its method of climbing | |
CN208650862U (en) | A kind of anti-collapse suspension device of constructing tunnel | |
CN104358415B (en) | Concrete prefabricated element can be recombinated portable production system and production method thereof | |
CN204716124U (en) | Portable removable level-sensing device inspection platform | |
CN104631810A (en) | High-altitude movable hanging basket system and construction method thereof | |
CN109372274A (en) | A kind of high-altitude wire frame installation system and its construction method | |
CN209211915U (en) | A kind of high-altitude wire frame installation system | |
CN205242885U (en) | Lightweight concrete prefabricated staircase connection structure | |
CN207194416U (en) | A kind of scaffold for building for being easy to assembling | |
CN201786031U (en) | Slip-formed concrete distributing bin device | |
CN103276722B (en) | A kind of low clearance pile frame and using method thereof | |
CN105416939B (en) | Refuse transfer station lowering or hoisting gear and its operational method | |
CN201486198U (en) | Lifting tower and mobile base station | |
CN111058609A (en) | Construction and protection integrated portable operation platform and method | |
CN206957175U (en) | A kind of planar dimension and adjustable for height operating platform | |
CN107938677A (en) | Municipal road construction places machine automatically with digging hole filling pile concrete-pouring template | |
CN209567730U (en) | A kind of small-sized lattice dead man steel construction | |
CN204754150U (en) | Dish -type node formula scaffold | |
CN203701552U (en) | Attached scaffold for lifted through worm, gear and screw rod | |
CN202829444U (en) | Mounting device of large-scaled storage tank | |
CN201923647U (en) | Pipe kicking device of oil-field derrick pipe conveying machine | |
CN207812455U (en) | Municipal road construction places machine automatically with digging hole filling pile concrete-pouring template | |
CN206156063U (en) | Civil engineering pipe fitting placing rack | |
CN105401598A (en) | Automatic formwork lowering system hoisting device and method for top-down construction | |
CN206318671U (en) | Intelligent support robot |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |