CN208933955U - Organizational pile foundation structure suitable for coral reef geology - Google Patents

Organizational pile foundation structure suitable for coral reef geology Download PDF

Info

Publication number
CN208933955U
CN208933955U CN201820989865.9U CN201820989865U CN208933955U CN 208933955 U CN208933955 U CN 208933955U CN 201820989865 U CN201820989865 U CN 201820989865U CN 208933955 U CN208933955 U CN 208933955U
Authority
CN
China
Prior art keywords
pile
prestressed pipe
steel pipe
organizational
coral reef
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820989865.9U
Other languages
Chinese (zh)
Inventor
张鸿
张永涛
王敏
郑和晖
代浩
巫兴发
田飞
游新鹏
彭成明
杜松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Second Harbor Engineering Co
CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd
Original Assignee
CCCC Second Harbor Engineering Co
CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Second Harbor Engineering Co, CCCC Highway Long Bridge Construction National Engineering Research Center Co Ltd filed Critical CCCC Second Harbor Engineering Co
Priority to CN201820989865.9U priority Critical patent/CN208933955U/en
Application granted granted Critical
Publication of CN208933955U publication Critical patent/CN208933955U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Artificial Fish Reefs (AREA)

Abstract

The utility model discloses a kind of organizational pile foundation structures suitable for coral reef geology, comprising: pile for prestressed pipe, end portion is inserted into ground, and sets bored concrete pile in its lower section;Steel pipe post is located above the pile for prestressed pipe, and is set in the pile for prestressed pipe outside and the hollow grouting space separated by a distance for forming an annular, and partly overlap be arranged therebetween, and grouting material is filled in the hollow grouting space of lap;Ground is exposed on the steel pipe post top, for connecting with external structure.The organizational pile foundation of the utility model can make full use of the high intensity of perfusion Skin friction and pile for prestressed pipe, and pile foundation self weight can be greatly reduced, reduce pile body design length;Especially suitable for the foundation construction under coral reef geological conditions, be not only able to satisfy rough seas, but can assembling, rapid construction, environment-friendly high-efficiency is with good economic efficiency.

Description

Organizational pile foundation structure suitable for coral reef geology
Technical field
The utility model relates to organizational pile foundation construction applications.More specifically, the utility model relates to one kind to be suitable for coral The organizational pile foundation structure of reef geology.
Background technique
Pile foundation with its construction is simple, cost is low, settlement Control effect is good etc., and advantages are widely used in China basis In engineering construction.Under the conditions of conventional geology, basically formed based on driven pile, cast-in-situ bored pile and steel pipe composite pile at present Pile Foundations Design is theoretical and design method, and for the foundation structure research under coral reef special geologic condition, still locate both at home and abroad In theoretical research stage.
It was verified that traditional cast-in-situ bored pile work efficiency is low under coral reef geological conditions, from great, and steel pipe is squeezed into Stake is then highly vulnerable to breakage the big Coral Reef Rock of uneven, more gaps, brittleness, to reduce pile bearing capacity;No matter any apply Work mode cannot all be suitable for coral reef geology, secondly, traditional bored concrete pile or steel-pipe pile are all under off-lying sea adverse circumstances well There are goods and materials transport difficult, working procedure is complicated, durability is poor, perishable the disadvantages of.
Currently, assembling rapid construction is one of the important development direction in bridge construction field.Meanwhile country is to off-lying sea island The Development control area dynamics of reef is increasing, and foundation structure construction is the key that islands and reefs construction, the Large scale construction that faces the future (code Head, airfield runway, tourist facilities etc.), it would be highly desirable to the durable organizational pile foundation structure suitable for coral reef geology of exploiting economy.
Utility model content
The utility model provides a kind of organizational pile foundation structure suitable for coral reef geology, which can make full use of The high intensity of Skin friction and pile for prestressed pipe is perfused, pile foundation self weight can be greatly reduced, reduce pile body design length.
In order to achieve the goal above, the utility model provides a kind of organizational pile foundation structure suitable for coral reef geology, comprising:
Pile for prestressed pipe, end portion is inserted into ground, and sets bored concrete pile in its lower section.
Preferably, the organizational pile foundation structure suitable for coral reef geology, further includes:
Steel pipe post is located above the pile for prestressed pipe, and is set in outside the pile for prestressed pipe and is separated by one Set a distance forms the hollow grouting space of an annular, and partly overlaps be arranged therebetween, the hollow grouting space of lap Interior filling grouting material;Ground is exposed on the steel pipe post top, for connecting with external structure.
Preferably, the organizational pile foundation structure suitable for coral reef geology, further includes:
Temporary support bracket is vertically connected at the pile for prestressed pipe, and circumferential around pile for prestressed pipe setting Described, temporary support bracket is tightly attached to the steel pipe post lower end, to play support fixed function to the steel pipe post.
Preferably, the organizational pile foundation structure suitable for coral reef geology, the steel pipe post connect a grout pipe, It is connected to the hollow grouting space between the pile for prestressed pipe and steel pipe post, to inculcate grouting material into the hollow structure.
Preferably, the organizational pile foundation structure suitable for coral reef geology, open up on the steel pipe post side wall to A few spillage mouth, after being poured and filled for hollow grouting space, extra grouting material is flowed out from spillage mouth.
Preferably, the organizational pile foundation structure suitable for coral reef geology, the pile for prestressed pipe inner wall and institute It is uneven to state steel pipe post inner wall, forms concave-convex shearing resistance key teeth.
Preferably, the organizational pile foundation structure suitable for coral reef geology, further includes robust structure, specific to wrap It includes:
Cyclic structure, it is circumferentially distributed to be integrated in the pile for prestressed pipe lower end and being connected thereto, in the cyclic structure Portion is hollow, and interior bottom surface raises upward, and forms multiple arc-shaped protrusions;
Cyclic annular fixture block, circumferentially distributed to be integrated in the pile for prestressed pipe lower end and being connected thereto, the ring-type fixture block card In the hollow structure of the cyclic structure, and the cyclic annular fixture block lower surface is recessed inwardly to form multiple arc-shaped grooves, The arc-shaped groove and the arc-shaped protrusion correspond, and mate with each other, the outer wall of the ring-type fixture block with it is described The inner wall of cyclic structure is separated by a distance, and is connected each other by multiple springs;
Cyclic annular strip, circumferential direction is attached at the pile for prestressed pipe outer wall, and the cyclic annular strip lower end passes through the ring-type Structural top, and it is fixed on the cyclic annular fixture block top.
The utility model is include at least the following beneficial effects: the organizational pile foundation of the utility model can make full use of bored concrete pile Pile foundation self weight can be greatly reduced in the high intensity of all side frictions and UHPC tubular pole, reduce pile body design length, meanwhile, it breaks Broken coral cay sandstone block can also be repaired well under cement slurry extruding.
The further advantage, target and feature of the utility model will be partially reflected by the following instructions, and part will also pass through Research and practice to the utility model and be understood by the person skilled in the art.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of organizational pile foundation structure in the utility model embodiment 1;
Fig. 2 is the structural schematic diagram of organizational pile foundation structure in embodiment 2;
Fig. 3 is the structural schematic diagram of the utility model robust structure.
Specific embodiment
The following describes the utility model in further detail with reference to the accompanying drawings, to enable those skilled in the art referring to explanation Book text can be implemented accordingly.
It should be noted that experimental method described in following embodiments is unless otherwise specified conventional method, institute Reagent and material are stated, unless otherwise specified, is commercially obtained;In the description of the present invention, term " transverse direction ", The instruction such as " longitudinal direction ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outside" Orientation or positional relationship be to be based on the orientation or positional relationship shown in the drawings, be merely for convenience of description the utility model and letter Change description, be not the device of indication or suggestion meaning or element must have a particular orientation, constructed with specific orientation and Operation, therefore should not be understood as limiting the present invention.
Embodiment 1
As shown in Figure 1, the utility model provides a kind of organizational pile foundation structure suitable for coral reef geology, comprising:
Pile for prestressed pipe 1, end portion is inserted into coral reef ground, and bored concrete pile 2 is set in its lower section;The prestressing force Tubular pole is UHPC tubular pole.Pile for prestressed pipe 1 is squeezed into certain depth, is able to maintain that Equilibrium, by 1 conduct of pile for prestressed pipe Casing carries out conventional helical drilling operation directly in hole.Pile for prestressed pipe 1 can prevent collapse hole, while can also with balancing water pressure Surface water, protection aperture ground, spud pile base location and drill bit guiding role etc. is enough isolated;And using bored concrete pile carry out into One step is fixed, and is compared to full utilization pile for prestressed pipe 1 and is fixed, and not only firm effect is more preferable in this way, identical strong It is smaller to the destruction of coral cay sandstone under degree, it does not need all to squeeze into pile for prestressed pipe 1 in ground, and broken corals Cay sandstone block can also be repaired well under cement slurry extruding.And 1 inner wall of pile for prestressed pipe is uneven, shape At concave-convex shearing resistance key teeth, so that connection effect is more preferably between the pile for prestressed pipe 1 and bored concrete pile 2.
Embodiment 2
In another embodiment, as shown in Fig. 2, the organizational pile foundation structure suitable for coral reef geology, further includes:
Steel pipe post 3 is located at 1 top of pile for prestressed pipe, and is set in 1 outside of pile for prestressed pipe and is separated by Certain distance forms the hollow grouting space 4 of an annular, and partly overlaps be arranged therebetween, and the hollow grouting of lap is empty Interior filling grouting material;Ground is exposed on the steel pipe post top, for connecting with external structure;The steel pipe post inner wall is recessed Convex injustice forms concave-convex shearing resistance key teeth.Temporary support bracket 5, is vertically connected at the pile for prestressed pipe 1, and it is circumferential around The pile for prestressed pipe setting, the temporary support bracket 5 is tightly attached to 3 lower end of steel pipe post, to the steel pipe post 3 Play support fixed function.The steel pipe post 3 connects a grout pipe 6, be connected to the pile for prestressed pipe 1 and steel pipe post 3 it Between hollow grouting space, to inculcate grouting material into the hollow structure.At least one leakage is opened up on 3 side wall of steel pipe post Mouth 7 is starched, after being poured and filled for hollow grouting space, extra grouting material is flowed out from spillage mouth.Steps are as follows for its Specific construction: Step 1), UHPC tubular pole are reached the last, and temporary support bracket is welded in designed elevation;Inserting piling prestressed pipe is equipped using piling Stake, during piling, drilling rod is inserted into pile for prestressed pipe, and drilling driving sinks when boring;Step 2) promotes drilling rod, transfers reinforcing bar Cage and conduit, the casting concrete into conduit;Prefabricated steel pipe post is set in outside the pile for prestressed pipe by step 3) Portion, and temporary support carries out spot welding reinforcing, fills in hollow grouting space finally by grout pipe on bracket after being adjusted in place Slurry, by dew slurry mouth outflow after filling, it is ensured that grouting gap is completely full, and grouting in place, that is, stops.Entire superstructure is also It is that steel pipe post 3 is whole across in erection process, scene only needs to carry out sleeve grouting connection, greatly accelerates speed of application.
In another embodiment, the organizational pile foundation structure suitable for coral reef geology, further includes: robust structure, Comprising:
Cyclic structure 8, circumferentially distributed to be integrated in 1 lower end of pile for prestressed pipe and being connected thereto, the cyclic structure 8 Inner hollow, interior bottom surface raise upward, and form multiple arc-shaped protrusions 9;Cyclic annular fixture block 10, it is circumferentially distributed in described pre- 1 lower end of stress tubular pole and being connected thereto is integrated, and the ring-type fixture block 10 is arranged in the hollow structure of the cyclic structure 5, And 10 lower surface of the cyclic annular fixture block is recessed inwardly to form multiple arc-shaped grooves 11, the arc-shaped groove 11 and the circle Arcuation protrusion 9 corresponds, and mates with each other, and the outer wall of the ring-type fixture block 10 and the inner wall of the cyclic structure 5 are homogeneous At a certain distance, and each other it is connected by multiple springs 12;Cyclic annular strip 13, circumferential direction are attached at the pile for prestressed pipe 1 Outer wall, and cyclic annular 13 lower end of strip passes through 8 top of cyclic structure, and is fixed on 10 top of the cyclic annular fixture block.This Sample can play good buffer function when there is significant shock generation, such as when earthquake generation, can first absorb counteracting one Divide energy, reduces the influence to pile for prestressed pipe 1 to the greatest extent.
It is not only in the description and the implementation although the embodiments of the present invention have been disclosed as above Listed utilization, it can be applied to various fields suitable for the present invention completely, for those skilled in the art, Other modifications may be easily implemented, therefore without departing from the general concept defined in the claims and the equivalent scope, this reality It is not limited to specific details and legend shown and described herein with novel.

Claims (6)

1. a kind of organizational pile foundation structure suitable for coral reef geology characterized by comprising
Pile for prestressed pipe, end portion is inserted into ground, and sets bored concrete pile in its lower section;
Further include:
Steel pipe post is located above the pile for prestressed pipe, and is set in outside the pile for prestressed pipe and is separated by a spacing From the hollow grouting space for forming an annular, and between the two partly overlap is arranged, and fills out in the hollow grouting space of lap Charge slurry;Ground is exposed on the steel pipe post top, for connecting with external structure.
2. being suitable for the organizational pile foundation structure of coral reef geology as described in claim 1, which is characterized in that further include:
Temporary support bracket, is vertically connected at the pile for prestressed pipe, and circumferential around described in pile for prestressed pipe setting, Temporary support bracket is tightly attached to the steel pipe post lower end, to play support fixed function to the steel pipe post.
3. being suitable for the organizational pile foundation structure of coral reef geology as described in claim 1, which is characterized in that the steel pipe post connects A grout pipe is connect, the hollow grouting space between the pile for prestressed pipe and steel pipe post is connected to, to be filled into the hollow structure Defeated grouting material.
4. being suitable for the organizational pile foundation structure of coral reef geology as described in claim 1, which is characterized in that the steel pipe post side At least one spillage mouth is opened up on wall, after being poured and filled for hollow grouting space, extra grouting material is flowed out from spillage mouth.
5. being suitable for the organizational pile foundation structure of coral reef geology as described in claim 1, which is characterized in that the pile for prestressed pipe Inner wall and the steel pipe post inner wall are uneven, form concave-convex shearing resistance key teeth.
6. being suitable for the organizational pile foundation structure of coral reef geology as described in claim 1, which is characterized in that further include firm knot Structure specifically includes:
Cyclic structure, it is circumferentially distributed to be integrated in the pile for prestressed pipe lower end and being connected thereto, in the cyclic structure inside Sky, interior bottom surface raise upward, and form multiple arc-shaped protrusions;
Cyclic annular fixture block, circumferentially distributed to be integrated in the pile for prestressed pipe lower end and being connected thereto, the ring-type fixture block is arranged in In the hollow structure of the cyclic structure, and the cyclic annular fixture block lower surface is recessed inwardly to form multiple arc-shaped grooves, described Arc-shaped groove and the arc-shaped protrusion correspond, and mate with each other, the outer wall of the ring-type fixture block and the ring-type The inner wall of structure is separated by a distance, and is connected each other by multiple springs;
Cyclic annular strip, circumferential direction is attached at the pile for prestressed pipe outer wall, and the cyclic annular strip lower end passes through the cyclic structure Top, and it is fixed on the cyclic annular fixture block top.
CN201820989865.9U 2018-06-26 2018-06-26 Organizational pile foundation structure suitable for coral reef geology Active CN208933955U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820989865.9U CN208933955U (en) 2018-06-26 2018-06-26 Organizational pile foundation structure suitable for coral reef geology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820989865.9U CN208933955U (en) 2018-06-26 2018-06-26 Organizational pile foundation structure suitable for coral reef geology

Publications (1)

Publication Number Publication Date
CN208933955U true CN208933955U (en) 2019-06-04

Family

ID=66715413

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820989865.9U Active CN208933955U (en) 2018-06-26 2018-06-26 Organizational pile foundation structure suitable for coral reef geology

Country Status (1)

Country Link
CN (1) CN208933955U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867634A (en) * 2018-06-26 2018-11-23 中交第二航务工程局有限公司 Organizational pile foundation structure and its construction method suitable for coral reef geology
CN113250189A (en) * 2021-06-21 2021-08-13 郑州辉昂装饰设计工程有限公司 Construction method of combined pile foundation for reinforcing prestressed pipe pile
CN113417282A (en) * 2021-07-22 2021-09-21 中国电建集团华东勘测设计研究院有限公司 Novel single-pile transition section and installation method thereof

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108867634A (en) * 2018-06-26 2018-11-23 中交第二航务工程局有限公司 Organizational pile foundation structure and its construction method suitable for coral reef geology
CN108867634B (en) * 2018-06-26 2023-05-05 中交第二航务工程局有限公司 Combined pile foundation structure suitable for coral reef geology and construction method thereof
CN113250189A (en) * 2021-06-21 2021-08-13 郑州辉昂装饰设计工程有限公司 Construction method of combined pile foundation for reinforcing prestressed pipe pile
CN113250189B (en) * 2021-06-21 2023-08-04 郑州辉昂装饰设计工程有限公司 Construction method of combined pile foundation for reinforcing prestressed pipe pile
CN113417282A (en) * 2021-07-22 2021-09-21 中国电建集团华东勘测设计研究院有限公司 Novel single-pile transition section and installation method thereof

Similar Documents

Publication Publication Date Title
CN108867634A (en) Organizational pile foundation structure and its construction method suitable for coral reef geology
CN208933955U (en) Organizational pile foundation structure suitable for coral reef geology
CN205857201U (en) A kind of anchor pole mini pile multistage support structure
CN202543906U (en) Precast pile with reserved grouting pipes
CN102605767A (en) Precast pile reserved with grouting pipe and piling process of precast pile
CN105350531A (en) Pipe pile-anchor rod composite foundation capable of bearing pulling and pressing bidirectional loads and construction technology
CN103485347A (en) Batter pile used for building foundation pit support and construction method thereof
CN205776157U (en) Assembled underground continuous wall
CN105926589B (en) It is adapted to the steel-pipe pile and its grouting method of coral reef geology
CN103321234A (en) Load-bearing structure built on high slope or geological complex area and constructing method thereof
CN102808407A (en) Construction method of soft-foundation reinforced concrete cast-in-place pile
CN102220764B (en) Construction method of deep foundation pit bracing system
CN104074197A (en) Large-diameter thin-walled tubular pile composite anchor rod type foundation pit support structure and construction method thereof
CN203613568U (en) Anti-floating cement soil pile and anti-floating anchor rod combined anti-floating system
CN103410529B (en) A kind of support of tunnel arch springing ruggedized construction for weak surrounding rock and construction method
CN201406687Y (en) Deep foundation pit supporting structure
CN2509232Y (en) Long-corn cement soil combined piles
CN109989346A (en) Bridge major diameter precast concrete tubular column basis and its construction method
CN209584855U (en) Bridge major diameter precast concrete tubular column basis
CN109881662A (en) Major diameter high-performance UHPC- steel pipe composite pile base and its construction method
CN213173700U (en) Precast pile for soft foundation treatment
CN209923935U (en) Co-location combined pile wall supporting structure in upper-soft and lower-hard stratum
CN202266065U (en) Heliostat pillar
CN110889235A (en) Underground pile foundation construction engineering design method
CN206956724U (en) A kind of anti-float roof bolt stump