CN102605767A - Precast pile reserved with grouting pipe and piling process of precast pile - Google Patents

Precast pile reserved with grouting pipe and piling process of precast pile Download PDF

Info

Publication number
CN102605767A
CN102605767A CN2012100832649A CN201210083264A CN102605767A CN 102605767 A CN102605767 A CN 102605767A CN 2012100832649 A CN2012100832649 A CN 2012100832649A CN 201210083264 A CN201210083264 A CN 201210083264A CN 102605767 A CN102605767 A CN 102605767A
Authority
CN
China
Prior art keywords
pile
grouting
grouting pipe
pipe
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012100832649A
Other languages
Chinese (zh)
Inventor
丁智
魏新江
张涛
葛国宝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou City University
Original Assignee
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang University City College ZUCC filed Critical Zhejiang University City College ZUCC
Priority to CN2012100832649A priority Critical patent/CN102605767A/en
Publication of CN102605767A publication Critical patent/CN102605767A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

一种预留注浆管预制桩,包括桩身,所述桩身底部与桩头固定连接,所述桩身内设桩侧注浆管和桩端注浆管;所述桩端注浆管位于桩身的中心位置,所述桩侧注浆管隔段预设桩侧单向出浆口,桩端注浆管的下端与所述桩身下端出口连通;所述桩侧注浆管的上端安装桩侧连接管,所述桩端注浆管的上端安装桩端连接管,所述桩侧连接管和桩端连接管均与桩身的上端面连接。以及一种成桩工艺。本发明提供一种有效提高桩侧摩擦力和桩端承载力、降低成本的预留注浆管预制桩及其成桩工艺。

Figure 201210083264

A prefabricated pile with a reserved grouting pipe, comprising a pile body, the bottom of the pile body is fixedly connected with the pile head, and a pile side grouting pipe and a pile end grouting pipe are arranged inside the pile body; the pile end grouting pipe is located at The center position of the pile body, the pile side grouting pipe interval preset pile side one-way grouting outlet, the lower end of the pile end grouting pipe is connected with the outlet at the lower end of the pile body; the upper end of the pile side grouting pipe The pile side connecting pipe is installed, the pile end connecting pipe is installed on the upper end of the pile end grouting pipe, and the pile side connecting pipe and the pile end connecting pipe are all connected with the upper surface of the pile body. And a pile-forming process. The invention provides a prefabricated pile with a reserved grouting pipe and a pile forming process which can effectively improve pile side friction force and pile end bearing capacity and reduce cost.

Figure 201210083264

Description

一种预留注浆管预制桩及其成桩工艺A prefabricated pile with reserved grouting pipe and its pile forming process

技术领域 technical field

本发明涉及一种预制桩及其成桩工艺。The invention relates to a prefabricated pile and a pile forming process thereof.

背景技术 Background technique

随着我国建筑事业的大力发展桩基础成为各种建筑物尤其是高层建筑、重型厂房、地铁车站等广泛采用的一种深基础形式。根据不同的分类标准桩基可划分为不同的类型,按成桩方法可分为:预制桩(木桩、钢桩、混凝土桩)、灌注桩(沉管灌注桩、钻孔灌注桩、挖空灌注桩)、就地搅拌桩等。从经济、环保、安全等角度出发,混凝土预制桩以及灌注桩的使用相当普遍。对于在覆盖层松软的土层、地下水比较多的土层以及工期紧急地情况下采用预制桩施工具有明显的优势,但是由于吊桩设备的限制导致单节桩长长度不足,接桩位置又会成为薄弱面,沉桩后桩身裂缝会降低桩身强度、桩端承载力不高、桩侧摩阻力小。对于钻孔灌注桩,虽然适用于复杂的土层但是桩身质量不易控制,容易出现断桩、露筋、夹泥等问题,导致单桩承载力不高。近年来后注浆工艺有所发展并得到了广泛的使用,但是在钻孔灌注桩中采用后注浆工艺时注浆孔的通畅不易保证;对于PHC管桩,由于管壁太薄,水平承载力低,由此引入的后注浆工艺可以对管桩的水平承载力有所提高,但是在桩底桩侧同时注浆时又面临桩侧注浆难以控制,桩底注浆需控制钻孔深度等问题。根据上述问题若能开发出一种兼具预制桩和后注浆相结合的新工艺将会为桩基的施工解决很多问题,预留注浆管预制桩便是这一思路的实施。With the vigorous development of my country's construction industry, pile foundation has become a deep foundation form widely used in various buildings, especially high-rise buildings, heavy factory buildings, and subway stations. According to different classification standards, pile foundations can be divided into different types. According to the method of pile formation, they can be divided into: prefabricated piles (wooden piles, steel piles, concrete piles), cast-in-place piles (sinking tube cast-in-place piles, bored cast-in-place piles, hollowed-out piles) Cast-in-situ piles), in-situ mixing piles, etc. From the perspectives of economy, environmental protection, and safety, the use of concrete prefabricated piles and cast-in-situ piles is quite common. It has obvious advantages in the construction of prefabricated piles in the soft soil layer of the covering layer, the soil layer with a lot of groundwater, and the emergency construction period. If it becomes a weak surface, the cracks in the pile body will reduce the strength of the pile body after sinking the pile, the bearing capacity of the pile tip is not high, and the frictional resistance of the pile side is small. For bored cast-in-situ piles, although they are suitable for complex soil layers, the quality of the pile body is not easy to control, and problems such as broken piles, exposed tendons, and mud inclusions are prone to occur, resulting in low bearing capacity of single piles. In recent years, the post-grouting process has been developed and widely used, but it is not easy to ensure the smoothness of the grouting hole when the post-grouting process is used in bored piles; for PHC pipe piles, because the pipe wall is too thin, the horizontal bearing The post-grouting process introduced from this can improve the horizontal bearing capacity of the pipe pile, but it is difficult to control the pile side grouting when grouting at the pile bottom at the same time, and the pile bottom grouting needs to control the drilling issues of depth. According to the above problems, if a new technology combining prefabricated piles and post-grouting can be developed, many problems will be solved for the construction of pile foundations. Prefabricated piles with reserved grouting pipes are the implementation of this idea.

发明内容Contents of the invention

为了克服已有预制桩及其成桩工艺的桩侧摩擦力较小、桩端承载力较小、成本较高的不足,本发明提供一种有效提高桩侧摩擦力和桩端承载力、降低成本的预留注浆管预制桩及其成桩工艺。In order to overcome the deficiencies of the existing prefabricated piles and their pile forming process, which have relatively small pile side friction, small pile end bearing capacity, and high cost, the present invention provides a method that effectively improves pile side friction and pile end bearing capacity, reduces Cost reserved grouting pipe prefabricated pile and its pile forming process.

本发明解决其技术问题所采用的技术方案是:The technical solution adopted by the present invention to solve its technical problems is:

一种预留注浆管预制桩,包括桩身,所述桩身底部与桩头固定连接,所述桩身内设桩侧注浆管和桩端注浆管;所述桩端注浆管位于桩身的中心位置,所述桩侧注浆管隔段预设桩侧单向出浆口,桩端注浆管的下端与所述桩身下端出口连通;所述桩侧注浆管的上端安装桩侧连接管,所述桩端注浆管的上端安装桩端连接管,所述桩侧连接管和桩端连接管均与桩身的上端面连接。A prefabricated pile with a reserved grouting pipe, comprising a pile body, the bottom of the pile body is fixedly connected with the pile head, and a pile side grouting pipe and a pile end grouting pipe are arranged inside the pile body; the pile end grouting pipe is located at The center position of the pile body, the pile side grouting pipe interval preset pile side one-way grouting outlet, the lower end of the pile end grouting pipe is connected with the outlet at the lower end of the pile body; the upper end of the pile side grouting pipe The pile side connecting pipe is installed, the pile end connecting pipe is installed on the upper end of the pile end grouting pipe, and the pile side connecting pipe and the pile end connecting pipe are all connected with the upper surface of the pile body.

进一步,所述桩头包括圆锥头部和圆柱身部,所述圆柱身部呈笼状或网状。Further, the pile head includes a conical head and a cylindrical body, and the cylindrical body is in the shape of a cage or a net.

更进一步,桩端注浆管的下端安装四通管。Furthermore, a four-way pipe is installed at the lower end of the pile end grouting pipe.

再进一步,所述桩头内填充碎石。Still further, gravel is filled in the pile head.

所述桩身有至少两段,靠上的桩身的下端出口与相邻靠下的桩身的上端面连接,且上下相邻的桩身内的两根侧注浆管连通,两根桩端注浆管连通。The pile body has at least two sections, the outlet at the lower end of the upper pile body is connected to the upper surface of the adjacent lower pile body, and the two side grouting pipes in the upper and lower adjacent pile bodies are connected, and the two pile ends The grouting pipe is connected.

所述桩侧注浆管和桩端注浆管为波纹管。The pile side grouting pipe and the pile end grouting pipe are corrugated pipes.

一种预留注浆管预制桩的成桩工艺,所述成桩工艺包括以下步骤:A pile-forming process for prefabricated piles with reserved grouting pipes, the pile-forming process comprises the following steps:

(1)、布置模板和钢筋,将桩端注浆管设在桩身中心位置,桩侧注浆管布置在桩身的桩侧,(1), arrange formwork and steel bars, set the pile end grouting pipe at the center of the pile body, and arrange the pile side grouting pipe at the pile side of the pile body,

(2)用先张法加工预应力桩的桩身;(2) Process the pile body of the prestressed pile with the pretensioning method;

(3)打桩并将桩送至设计标高后开始注浆;(3) Start grouting after piling and sending the pile to the design elevation;

(4)采用连接管将注浆管接头分别与桩侧注浆管和桩端注浆管连通;(4) Connecting pipes are used to connect the grouting pipe joints with the pile side grouting pipe and the pile end grouting pipe respectively;

(5)用高压水疏通桩侧注浆管和桩端注浆管,打开出浆口;(5) Dredge the pile side grouting pipe and the pile end grouting pipe with high pressure water, and open the grout outlet;

(6)先进行桩侧注浆,再进行桩端注浆,形成预制桩。(6) The pile side grouting is carried out first, and then the pile end grouting is carried out to form a prefabricated pile.

进一步,所述步骤(1)中,桩侧注浆管和桩端注浆管的主体均采用塑料波纹管,端头连接管为带有内螺纹的钢管。Further, in the step (1), the main bodies of the pile side grouting pipe and the pile end grouting pipe are made of plastic corrugated pipes, and the connecting pipes at the ends are steel pipes with internal threads.

再进一步,所述步骤(1)中,桩身的两端增设预埋件;所述步骤(2)中,将上下相邻的两段桩身的预埋件对焊。Still further, in the step (1), the two ends of the pile body are provided with embedded parts; in the step (2), the embedded parts of the two sections of the pile body adjacent up and down are butt-welded.

所述步骤(1)中,将模板在开有与桩侧单向出浆口配合的孔。In the step (1), the formwork is provided with a hole matching the one-way slurry outlet on the side of the pile.

本发明的技术构思为:使用的塑料波纹管一方面有很好的弯曲性能,另一方面在预应力施加完毕截断预应力钢筋时即能协调桩身的变形又能与桩身紧密地咬合,其次塑料波纹管价格低廉可以节约工程造价,综合各方面的因素该设计有很大的优势。The technical idea of the present invention is: on the one hand, the plastic corrugated pipe used has good bending performance; on the other hand, when the prestressing force is applied and the prestressed steel bar is cut off, it can coordinate the deformation of the pile body and tightly bite with the pile body. Secondly, the low price of the plastic corrugated pipe can save the engineering cost, and the design has great advantages in all aspects.

当桩侧浆液注入时,首先对桩侧泥皮进行破坏、消除,对桩周土起到渗透和挤密作用,充填桩与桩侧周围土体的间隙,随着注浆量和注浆压力的增加,现场的护壁泥皮在高压浆液的顶压、充填、挤压作用下被破坏并挤出地表,逐渐扩大桩侧压密区范围,使桩侧土的应力路径和固结状态改变。当桩侧为粘性土或粉质土等渗透性差的土时形成劈裂注浆,如果桩侧为砂砾性等渗透性能较好的土层时,形成桩侧压密注浆状态。桩侧后压浆使水泥浆与桩侧泥皮、土层之间发生挤密、渗入、充填、劈裂等过程,提高了桩侧土体的强度以及桩侧混凝土与土体之间的粘结力,且增大了桩径,提高了桩侧摩阻力,从而提高了单桩承载力。When the pile side grout is injected, the mud skin on the pile side is firstly destroyed and eliminated, which can infiltrate and compact the soil around the pile, and fill the gap between the pile and the soil around the pile side. With the increase of the number of soil retaining walls, the site wall mud skin is destroyed and squeezed out of the ground surface under the action of top pressure, filling, and extrusion of high-pressure grout, gradually expanding the range of pile side compaction area, and changing the stress path and consolidation state of pile side soil. When the pile side is soil with poor permeability such as cohesive soil or silty soil, split grouting will be formed. If the pile side is a soil layer with better permeability such as gravel, the pile side compaction grouting state will be formed. Post grouting on the pile side causes the process of compaction, infiltration, filling, splitting and other processes between the cement slurry and the pile side mud skin and soil layer, which improves the strength of the pile side soil and the adhesion between the pile side concrete and soil. In addition, the diameter of the pile is increased, and the frictional resistance of the pile side is increased, thereby increasing the bearing capacity of the single pile.

桩端注浆时,由于预制桩头内碎石的存在,一方面可以防止桩端出浆口被堵塞形成良好的出浆通道,另一方面注浆结束后浆液与碎石、桩端伸出的钢筋结合形成抗压能力比较大的混凝土。而且随着注浆量的增加,桩底逐渐形成“梨形头”压密区域也逐渐扩大,最终桩底可产生扩底桩的效果,也会大大地提高单桩承载力。During pile tip grouting, due to the existence of gravel in the prefabricated pile head, on the one hand, it can prevent the grout outlet at the pile tip from being blocked to form a good grout channel. The combination of steel bars forms concrete with relatively high compressive capacity. Moreover, as the amount of grouting increases, the pile bottom gradually forms a "pear-shaped head" and the compaction area gradually expands. Finally, the bottom of the pile can produce the effect of an expanded bottom pile, and the bearing capacity of a single pile will also be greatly improved.

本发明适合于上覆土层为松软土层、地下水流大、工期比较紧迫等传统预制桩适用的情况。此外,本发明结合了传统预制桩、预应力管桩、钻孔灌注桩后注浆工艺的优势,比传统预制桩有更高的承压能力以及抗拔性能。The invention is suitable for the situation where the traditional prefabricated piles are suitable for the overlying soil layer is soft soil layer, the groundwater flow is large, and the construction period is relatively tight. In addition, the invention combines the advantages of the post-grouting process of traditional prefabricated piles, prestressed pipe piles and bored piles, and has higher pressure bearing capacity and pullout resistance than traditional prefabricated piles.

本发明的有益效果主要表现在:(1)桩身钢筋所施加的低预应力可以有效地减轻吊桩、打桩过程出现的裂缝,可以保证桩身质量。(2)注浆管布置更合理,不易被堵塞,提高施工效率。(3)通过注浆工艺可以弥补接桩缺陷,并且在桩身出现裂缝的情况下,后压浆可以填充于裂缝,达到修补桩身的效果。(4)使桩侧摩擦力以及桩端承载力大大提高,进而可以减少打桩数量,节约造价。(5)在设计时就考虑到后注浆,比将后注浆作为补救措施节省人力以及财力,也达到了经济高效的目的。(5)工艺简单,并且可以在保证桩身承载力的前提下大大地缩短工期。(6)桩头填料可用矿渣、建筑废料,可将废品重新利用,节能环保。The beneficial effects of the present invention are mainly manifested in: (1) The low prestress applied by the steel bars of the pile body can effectively reduce the cracks in the process of hanging and driving piles, and can ensure the quality of the pile body. (2) The layout of the grouting pipes is more reasonable, not easy to be blocked, and the construction efficiency is improved. (3) The defects of the pile connection can be compensated by the grouting process, and in the case of cracks in the pile body, post-pressing grouting can fill the cracks to achieve the effect of repairing the pile body. (4) The side friction force of the pile and the bearing capacity of the pile end are greatly improved, thereby reducing the number of pilings and saving the cost. (5) The post-grouting is considered in the design, which saves manpower and financial resources compared with post-grouting as a remedial measure, and also achieves the purpose of cost-effectiveness. (5) The process is simple, and the construction period can be greatly shortened under the premise of ensuring the bearing capacity of the pile body. (6) Slag and construction waste can be used as pile head filler, and waste products can be reused to save energy and protect the environment.

本发明同时具有上述特点,从而大幅提高了桩的承载能力同时减少工程成本,可有效地为桩基工程服务。The present invention has the above-mentioned characteristics at the same time, thereby greatly improving the bearing capacity of the pile while reducing the engineering cost, and can effectively serve the pile foundation engineering.

附图说明 Description of drawings

图1是预留注浆管预制桩桩身结构示意图。Fig. 1 is a schematic diagram of the prefabricated pile body structure with reserved grouting pipes.

图2是预留注浆管预制桩A-A剖面结构示意图。Fig. 2 is a schematic diagram of the A-A section structure of the prefabricated pile with reserved grouting pipes.

图3是预留注浆管预制桩连接段桩身A-A结构示意图。Fig. 3 is a schematic diagram of the pile body A-A of the connecting section of the prefabricated pile with reserved grouting pipes.

图4是预留注浆管预制桩B-B截面结构示意图。Fig. 4 is a schematic diagram of the B-B cross-sectional structure of the prefabricated pile with reserved grouting pipes.

图5是桩头结构示意图。Figure 5 is a schematic diagram of the pile head structure.

图6是接桩卡具的示意图。Fig. 6 is a schematic diagram of the pile-connecting jig.

具体实施方式 Detailed ways

下面结合附图对本发明作进一步描述。The present invention will be further described below in conjunction with the accompanying drawings.

实施例1Example 1

参照图1~图4,一种预留注浆管预制桩,采用预制桩与后注浆工艺相结合,桩身采用低预应力混凝土,内设桩侧注浆管5,桩端注浆管7;桩头10为预制,桩头内填充碎石9,并将桩头与桩端焊接成整体。桩侧注浆管隔段预设桩侧单向出浆口6,桩端设置与桩端注浆管连接的四通管8作为桩底出浆口,尽量保证三个出浆口均匀分布(在水平面的投影为120°)Referring to Figures 1 to 4, a prefabricated pile with reserved grouting pipes is combined with prefabricated piles and post-grouting technology. 7; The pile head 10 is prefabricated, the pile head is filled with gravel 9, and the pile head and the pile end are welded into a whole. The one-way grouting outlet 6 on the pile side is preset in the pile side grouting pipe section, and the four-way pipe 8 connected to the pile end grouting pipe is set at the pile end as the pile bottom grouting outlet, so as to ensure that the three grouting outlets are evenly distributed ( The projection on the horizontal plane is 120°)

上述预制桩头10为类似“蒙古包”状的整体,其中圆柱部分(与桩端连接区域以下)为笼状或网状。The above-mentioned prefabricated pile head 10 is a whole similar to a "yurt", and the cylindrical part (below the connection area with the pile end) is in the shape of a cage or a net.

上述碎石9也可由砂砾、钢渣、建筑碎块代替。Above-mentioned crushed stone 9 also can be replaced by gravel, steel slag, building debris.

实施例2Example 2

参照图1~图6,一种预留注浆管预制桩的成桩工艺,包括如下步骤:Referring to Figures 1 to 6, a pile-forming process for prefabricated piles with reserved grouting pipes includes the following steps:

(1)布置模板、钢筋及桩侧注浆管5、桩端注浆管7和下桩端预埋件11和上桩端预埋件13,桩底注浆管7设在中心位置,桩侧注浆管5布置在桩侧;注浆管的主体采用塑料波纹管(桩侧注浆管可用4分管,桩端注浆管可用6分管),端头连接管为带有内螺纹的钢管4。(1) Arrange templates, steel bars and pile side grouting pipes 5, pile end grouting pipes 7, lower pile end embedded parts 11 and upper pile end embedded parts 13. The pile bottom grouting pipe 7 is arranged at the center, and the pile end The side grouting pipe 5 is arranged on the side of the pile; the main body of the grouting pipe is a plastic corrugated pipe (4 pipes can be used for the pile side grouting pipe, and 6 pipes can be used for the pile end grouting pipe), and the end connecting pipe is a steel pipe with internal thread 4.

(2)用先张法加工预应力桩的桩身,施加的预应力不要太大(4-6MPa即可),以避免打桩时桩身混凝土被压碎。(2) Use the pretensioning method to process the pile body of the prestressed pile, and the applied prestress should not be too large (4-6MPa is enough), so as to avoid the concrete of the pile body being crushed during pile driving.

(3)当混凝土达到强度要求后截断两端多余钢筋,对于桩端部分的钢筋要留出略小于桩头10圆柱部分的长度。(3) When the concrete reaches the strength requirement, cut off the excess steel bars at both ends, and reserve a length slightly smaller than the length of the pile head 10 cylinders for the steel bars at the pile end.

(4)连接桩端出浆口——四通管8(亦可预埋置)。(4) Connect the slurry outlet at the pile end—the four-way pipe 8 (also can be pre-embedded).

(5)将预制桩头10内填充碎石料9,碎石料不要填充过满以防损坏桩端出浆口。(5) Fill the crushed stone material 9 in the prefabricated pile head 10, and the crushed stone material should not be overfilled to prevent damage to the pile end slurry outlet.

(6)将桩头10按图与下桩端预埋件11焊接成桩。(6) Weld the pile head 10 with the lower pile end embedded part 11 according to the figure to form a pile.

(7)打桩时最好采用特制桩帽,以防损坏注浆口,将桩送至设计标高后开始注浆。(7) It is best to use special pile caps when driving piles to prevent damage to the grouting port, and start grouting after sending the piles to the design elevation.

(8)采用连接管3将桩侧注浆管外接头1、桩端注浆管外接头2分别与相应的内螺纹钢管连接,形成注浆通道。(8) Using the connecting pipe 3 to connect the external joint 1 of the pile side grouting pipe and the external joint 2 of the pile end grouting pipe to corresponding internal threaded steel pipes respectively to form a grouting channel.

(9)用高压水疏通注桩侧注浆管5、桩端注浆管7,打开出浆口。(9) Use high-pressure water to dredge the side grouting pipe 5 and the pile end grouting pipe 7, and open the grouting outlet.

(10)注浆采取注浆压力与注浆量双控制的措施,先进行桩侧注浆,再进行桩端注浆(一般在桩侧注浆结束6小时左右)。(10) Grouting adopts measures of dual control of grouting pressure and grouting volume, firstly carry out pile side grouting, and then pile end grouting (generally about 6 hours after the end of pile side grouting).

在需要接桩的情况下,每节桩的两端增设预埋件,将两段桩的预埋件对焊(空隙内可填充碎石料)。In the case of pile connection, add embedded parts at both ends of each section of pile, and butt weld the embedded parts of the two sections of piles (the gap can be filled with gravel).

为了保证成桩后桩侧单向出浆口6的完好,可以考虑在步骤1中,将模板在相应的位置留出略大于桩侧注浆管5的孔。In order to ensure the integrity of the one-way grouting outlet 6 on the pile side after the pile is completed, it may be considered that in step 1, a hole slightly larger than the grouting pipe 5 on the pile side is reserved in the corresponding position of the formwork.

如图2、3顺序布置模板、钢筋及桩侧注浆管5、桩端注浆管7、下桩端预埋件11和上桩端预埋件13,尽量保证桩端注浆管7设在中心位置,桩侧注浆管5布置在桩侧;注浆管的主体采用塑料波纹管(桩侧注浆管用四分管,桩端注浆管用六分管),并在端头处替换为带有内螺纹的钢管4;将预制桩头10内填充碎石料9用以改善注浆效果,碎石料不要填充过满以防损坏桩端出浆口;将桩头10按图与桩端预埋件11焊接成桩;注浆采取注浆压力与注浆量双控制的措施,先进行桩侧注浆,再进行桩端注浆(一般在桩侧注浆结束6小时)。As shown in Figures 2 and 3, formwork, steel bars and pile side grouting pipe 5, pile end grouting pipe 7, lower pile end embedded part 11 and upper pile end embedded part 13 are arranged in order to ensure that the pile end grouting pipe 7 is set as far as possible. At the center position, the pile side grouting pipe 5 is arranged on the pile side; the main body of the grouting pipe adopts a plastic corrugated pipe (a quarter pipe for the pile side grouting pipe, and a sextant pipe for the pile end grouting pipe), and replaces it with a belt at the end. There is a steel pipe 4 with internal thread; the prefabricated pile head 10 is filled with crushed stone material 9 to improve the grouting effect, and the crushed stone material should not be filled too much to prevent damage to the pile end grout outlet; Embedded parts 11 are welded into piles; grouting adopts the measures of double control of grouting pressure and grouting volume, firstly carry out pile side grouting, and then carry out pile end grouting (generally 6 hours after pile side grouting).

Claims (10)

1.一种预留注浆管预制桩,包括桩身,所述桩身底部与桩头固定连接,其特征在于:所述桩身内设桩侧注浆管和桩端注浆管;所述桩端注浆管位于桩身的中心位置,所述桩侧注浆管隔段预设桩侧单向出浆口,桩端注浆管的下端与所述桩身下端出口连通;所述桩侧注浆管的上端安装桩侧连接管,所述桩端注浆管的上端安装桩端连接管,所述桩侧连接管和桩端连接管均与桩身的上端面连接。1. A prefabricated pile with a reserved grouting pipe, comprising a pile body, the bottom of the pile body is fixedly connected with the pile head, and it is characterized in that: a pile side grouting pipe and a pile end grouting pipe are arranged in the pile body; The pile end grouting pipe is located at the center of the pile body, the pile side grouting pipe section is preset with a one-way grouting outlet on the pile side, and the lower end of the pile end grouting pipe communicates with the outlet at the lower end of the pile body; the pile A pile side connecting pipe is installed on the upper end of the side grouting pipe, and a pile end connecting pipe is installed on the upper end of the pile end grouting pipe, and both the pile side connecting pipe and the pile end connecting pipe are connected with the upper surface of the pile body. 2.如权利要求1所述的预留注浆管预制桩,其特征在于:所述桩头包括圆锥头部和圆柱身部,所述圆柱身部呈笼状或网状。2. The prefabricated pile with reserved grouting pipe according to claim 1, characterized in that: the pile head includes a conical head and a cylindrical body, and the cylindrical body is in the shape of a cage or a net. 3.如权利要求1或2所述的预留注浆管预制桩,其特征在于:桩端注浆管的下端安装四通管。3. The prefabricated pile with reserved grouting pipe according to claim 1 or 2, characterized in that: a four-way pipe is installed at the lower end of the grouting pipe at the pile end. 4.如权利要求1或2所述的预留注浆管预制桩,其特征在于:所述桩头内填充碎石。4. The prefabricated pile with reserved grouting pipe according to claim 1 or 2, characterized in that: the pile head is filled with gravel. 5.如权利要求1或2所述的预留注浆管预制桩,其特征在于:所述桩身有至少两段,靠上的桩身的下端出口与相邻靠下的桩身的上端面连接,且上下相邻的桩身内的两根侧注浆管连通,两根桩端注浆管连通。5. The reserved grouting pipe prefabricated pile according to claim 1 or 2, characterized in that: the pile body has at least two sections, the lower end outlet of the upper pile body and the upper end of the adjacent lower pile body The end faces are connected, and the two side grouting pipes in the upper and lower adjacent pile bodies are connected, and the two pile end grouting pipes are connected. 6.如权利要求1或2所述的预留注浆管预制桩,其特征在于:所述桩侧注浆管和桩端注浆管为波纹管。6. The prefabricated pile with reserved grouting pipe according to claim 1 or 2, characterized in that: the pile side grouting pipe and the pile end grouting pipe are corrugated pipes. 7.一种如权利要求1所述的预留注浆管预制桩的成桩工艺,其特征在于:所述成桩工艺包括以下步骤:7. A pile-forming process of the reserved grouting pipe prefabricated pile as claimed in claim 1, characterized in that: the pile-forming process comprises the following steps: (1)、布置模板和钢筋,将桩端注浆管设在桩身中心位置,桩侧注浆管布置在桩身的桩侧,(1), arrange formwork and steel bars, set the pile end grouting pipe at the center of the pile body, and arrange the pile side grouting pipe at the pile side of the pile body, (2)用先张法加工预应力桩的桩身;(2) Process the pile body of the prestressed pile with the pretensioning method; (3)打桩并将桩送至设计标高后开始注浆;(3) Start grouting after piling and sending the pile to the design elevation; (4)采用连接管将注浆管接头分别与桩侧注浆管和桩端注浆管连通;(4) Connecting pipes are used to connect the grouting pipe joints with the pile side grouting pipe and the pile end grouting pipe respectively; (5)用高压水疏通桩侧注浆管和桩端注浆管,打开出浆口;(5) Dredge the pile side grouting pipe and the pile end grouting pipe with high pressure water, and open the grout outlet; (6)先进行桩侧注浆,再进行桩端注浆,形成预制桩。(6) The pile side grouting is carried out first, and then the pile end grouting is carried out to form a prefabricated pile. 8.如权利要求7所述的预留注浆管预制桩的成桩工艺,其特征在于:所述步骤(1)中,桩侧注浆管和桩端注浆管的主体均采用塑料波纹管,端头连接管为带有内螺纹的钢管。8. The pile-forming process of prefabricated piles with reserved grouting pipes as claimed in claim 7, characterized in that: in the step (1), the main bodies of the pile side grouting pipes and the pile end grouting pipes are all made of plastic corrugated Pipe, the end connecting pipe is a steel pipe with internal thread. 9.如权利要求7或8所述的预留注浆管预制桩的成桩工艺,其特征在于:所述步骤(1)中,桩身的两端增设预埋件;所述步骤(2)中,将上下相邻的两段桩身的预埋件对焊。9. The pile forming process of reserved grouting pipe prefabricated piles as claimed in claim 7 or 8, is characterized in that: in the described step (1), the two ends of the pile body are provided with embedded parts; the described step (2) ), butt-weld the pre-embedded parts of the upper and lower adjacent piles. 10.如权利要求7或8所述的预留注浆管预制桩的成桩工艺,其特征在于:所述步骤(1)中,将模板在开有与桩侧单向出浆口配合的孔。10. The pile-forming process of prefabricated piles with reserved grouting pipes as claimed in claim 7 or 8, characterized in that: in the step (1), the formwork is provided with a unidirectional grout outlet on the side of the pile. hole.
CN2012100832649A 2012-03-27 2012-03-27 Precast pile reserved with grouting pipe and piling process of precast pile Pending CN102605767A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100832649A CN102605767A (en) 2012-03-27 2012-03-27 Precast pile reserved with grouting pipe and piling process of precast pile

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100832649A CN102605767A (en) 2012-03-27 2012-03-27 Precast pile reserved with grouting pipe and piling process of precast pile

Publications (1)

Publication Number Publication Date
CN102605767A true CN102605767A (en) 2012-07-25

Family

ID=46523500

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100832649A Pending CN102605767A (en) 2012-03-27 2012-03-27 Precast pile reserved with grouting pipe and piling process of precast pile

Country Status (1)

Country Link
CN (1) CN102605767A (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106906822A (en) * 2017-03-08 2017-06-30 威海齐德新型建材有限公司 A kind of prefabricated foundation stake and construction method
CN107447750A (en) * 2017-09-22 2017-12-08 金陵科技学院 A kind of high intensity and it is easy to the building stake poured
CN108468336A (en) * 2018-04-16 2018-08-31 浙江大学 Slip casting machine and construction method for Ruins protection
CN108643169A (en) * 2018-06-11 2018-10-12 北京市地质工程公司 One kind can slip casting prefabricated pile and its piling construction and grouting method
CN109868813A (en) * 2017-12-04 2019-06-11 中国二十冶集团有限公司 The bottom sealing method of pile for prestressed pipe
CN111021359A (en) * 2019-12-25 2020-04-17 中铁上海工程局集团有限公司 Pressure-controllable intelligent post-grouting device and method for pile end and pile side of cast-in-situ bored pile
CN111778980A (en) * 2020-07-31 2020-10-16 中建四局第一建筑工程有限公司 A large diameter pile grouting device
CN112227353A (en) * 2020-11-06 2021-01-15 河南聚誉帆工程技术咨询有限公司 An assembled integral static pressure pile
CN112832235A (en) * 2021-01-08 2021-05-25 翟宇思 Construction method and construction device for precast pile post-grouting
CN114411727A (en) * 2022-02-25 2022-04-29 南京东土建设科技有限公司 Built-in post-grouting device for realizing multi-depth grouting of tubular pile
CN114457833A (en) * 2022-02-21 2022-05-10 三峡大学 Pile foundation structure capable of being strengthened on coral sand and method
CN114908737A (en) * 2021-02-09 2022-08-16 上海斐晟企业管理有限公司 Precast pile with preset grouting pipe
CN116397687A (en) * 2023-05-26 2023-07-07 上海勘测设计研究院有限公司 Composite pile foundation

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5129762A (en) * 1990-02-06 1992-07-14 Entreprises Morillon Corvol Courbot S.A. Metallic turbular pile equipped with a device able to inject grout close to the wall of the pile
EP0346941B1 (en) * 1984-03-23 1994-10-26 Stump Bohr GmbH Method for producing construction elements in the soil, such as piles, anchors or the like, and apparatus for applying this method
CN1335434A (en) * 2001-09-01 2002-02-13 叶长生 High-pressure mortar spraying deposition process of prefabricated steel bar reinforced concrete pile
CN101182716A (en) * 2007-12-05 2008-05-21 中北大学 Pile sinking method of synchronous grouting static pressure prefabricated pile
CN201665871U (en) * 2010-03-25 2010-12-08 北京中岩大地工程技术有限公司 Long screw drilling bored pile post-grouting technology device
CN202543906U (en) * 2012-03-27 2012-11-21 浙江大学城市学院 Precast pile with reserved grouting pipes

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0346941B1 (en) * 1984-03-23 1994-10-26 Stump Bohr GmbH Method for producing construction elements in the soil, such as piles, anchors or the like, and apparatus for applying this method
US5129762A (en) * 1990-02-06 1992-07-14 Entreprises Morillon Corvol Courbot S.A. Metallic turbular pile equipped with a device able to inject grout close to the wall of the pile
CN1335434A (en) * 2001-09-01 2002-02-13 叶长生 High-pressure mortar spraying deposition process of prefabricated steel bar reinforced concrete pile
CN101182716A (en) * 2007-12-05 2008-05-21 中北大学 Pile sinking method of synchronous grouting static pressure prefabricated pile
CN201665871U (en) * 2010-03-25 2010-12-08 北京中岩大地工程技术有限公司 Long screw drilling bored pile post-grouting technology device
CN202543906U (en) * 2012-03-27 2012-11-21 浙江大学城市学院 Precast pile with reserved grouting pipes

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106906822A (en) * 2017-03-08 2017-06-30 威海齐德新型建材有限公司 A kind of prefabricated foundation stake and construction method
CN107447750A (en) * 2017-09-22 2017-12-08 金陵科技学院 A kind of high intensity and it is easy to the building stake poured
CN109868813A (en) * 2017-12-04 2019-06-11 中国二十冶集团有限公司 The bottom sealing method of pile for prestressed pipe
CN108468336B (en) * 2018-04-16 2023-09-01 浙江大学 Grouting machine and construction method for site protection
CN108468336A (en) * 2018-04-16 2018-08-31 浙江大学 Slip casting machine and construction method for Ruins protection
CN108643169A (en) * 2018-06-11 2018-10-12 北京市地质工程公司 One kind can slip casting prefabricated pile and its piling construction and grouting method
CN111021359A (en) * 2019-12-25 2020-04-17 中铁上海工程局集团有限公司 Pressure-controllable intelligent post-grouting device and method for pile end and pile side of cast-in-situ bored pile
CN111778980A (en) * 2020-07-31 2020-10-16 中建四局第一建筑工程有限公司 A large diameter pile grouting device
CN112227353A (en) * 2020-11-06 2021-01-15 河南聚誉帆工程技术咨询有限公司 An assembled integral static pressure pile
CN112832235A (en) * 2021-01-08 2021-05-25 翟宇思 Construction method and construction device for precast pile post-grouting
CN114908737A (en) * 2021-02-09 2022-08-16 上海斐晟企业管理有限公司 Precast pile with preset grouting pipe
CN114457833A (en) * 2022-02-21 2022-05-10 三峡大学 Pile foundation structure capable of being strengthened on coral sand and method
CN114457833B (en) * 2022-02-21 2024-03-12 三峡大学 Pile foundation structure capable of being reinforced on coral sand and method
CN114411727A (en) * 2022-02-25 2022-04-29 南京东土建设科技有限公司 Built-in post-grouting device for realizing multi-depth grouting of tubular pile
CN114411727B (en) * 2022-02-25 2024-02-20 南京东土建设科技有限公司 Built-in post grouting device for realizing multi-depth grouting of tubular piles
CN116397687A (en) * 2023-05-26 2023-07-07 上海勘测设计研究院有限公司 Composite pile foundation

Similar Documents

Publication Publication Date Title
CN102605767A (en) Precast pile reserved with grouting pipe and piling process of precast pile
CN102587361B (en) A construction method of high polymer material grouting wedge-shaped prefabricated pile
CN202543906U (en) Precast pile with reserved grouting pipes
CN105201514B (en) A kind of water-bearing stratum shaft wall structure and construction method
CN205369231U (en) Steel -pipe pile is filled in drilling
CN104018518A (en) Prefabricated underground diaphragm wall and method for constructing outer basement wall and floor slabs
CN111519618A (en) Post-grouting device for prestressed pipe pile and construction method thereof
CN202945622U (en) Composite repaired structure of reinforced concrete base plate cracks in basement
CN101575859B (en) Anti-seepage Joint of Underground Diaphragm Wall and Its Construction Method
CN108978635A (en) Synchronous grouting steel sheet pile and using method
CN102864777A (en) Fast prestress anchor stock structure and construction method
CN204356768U (en) A kind of special-shaped precast concrete pile
CN107700521B (en) A building foundation reinforcement underpinning pier and its construction method
CN204000925U (en) Prefabricated diaphragm wall
CN111455973A (en) Composite foundation structure of prefabricated solid CFG pile and construction method thereof
CN108360505A (en) A kind of filling pile structure and its construction method passing through solution cavity
CN105113513B (en) Anti-seepage foundation pit supporting structure and construction method
CN207659986U (en) A kind of building or structures foundation stabilization underpin pier
CN101545255B (en) Method for manufacturing a PHC tubular pile in soft soil region through chambering and grouting
CN107254872B (en) Prestressed pipe pile bottom floating and fixing sealing device and control method thereof
CN107401163A (en) A kind of construction method for being used to cut down pile tube negative friction
CN108643215B (en) Construction method of anchor pier type foundation after rotary spraying and pressing into variable cross section
CN217870437U (en) Mechanical drilling and grouting pile for prestressed precast tubular pile
CN207047839U (en) A kind of pile for prestressed pipe stake bottom floating sealing device
CN114575354B (en) Unloading assembled pile anchor multistage supporting structure and construction method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120725