CN208898457U - Top of building erecting by overhang - Google Patents
Top of building erecting by overhang Download PDFInfo
- Publication number
- CN208898457U CN208898457U CN201821730897.3U CN201821730897U CN208898457U CN 208898457 U CN208898457 U CN 208898457U CN 201821730897 U CN201821730897 U CN 201821730897U CN 208898457 U CN208898457 U CN 208898457U
- Authority
- CN
- China
- Prior art keywords
- plate
- building
- pipe fitting
- sliding part
- guide rail
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a kind of top of building erectings by overhang, I-shaped guide rail is installed on the parapet top surface of top of building, guide rail includes the vertical plate of top plate and bottom plate and connection top and bottom plate, the sliding part being slidably matched is set on top plate, an inner circle pipe fitting is fixedly mounted on sliding part, an outer circle pipe fitting is arranged on the periphery of interior round tube part, right angle rack is fixedly installed on outer round tube part, hanging point is arranged in the end of right angle rack, for installing lifting rope and platform sling.The utility model is slid on I-shaped guide rail by sliding part, and positioning bolt is recycled to be locked, and can according to need the position of adjustment hanging point, and each position of outside vertical surface of building is covered convenient for cleaning operation range, improves working efficiency, and practicability is good.Sliding part is coupled using left component and right component, is mounted on the top plate of I-shaped guide rail, and sound construction is reliable, and installation and removal are convenient.
Description
Technical field
The utility model relates to build aerial lift device field, especially a kind of top of building erecting by overhang.
Background technique
As the speed of urban modernization is constantly accelerated, the skyscraper in city is continuously emerged.In order to increase aesthetics
With the better daylighting effect of acquisition, many facades use glass curtain wall or composite curtain wall, after a period of time can not
What is avoided brings cleaning and maintenance issues.For the periodical safety cleaning of external wall and repair and maintenance, increasingly by people
Attention.The cleaning measure of facade at present mainly uses two methods of window cleaning equipment and big rope platform sling, and window cleaning equipment is due to making
Valence is higher, and other than super high-rise building, the acceptance of acquisition is not high.Big rope platform sling needs building to have the extension that can be knotted
Point, for the building of not set dedicated big rope platform sling hanging point, hanging point be it is artificial randomly selected, safety and reliability is not
Foot, for being provided with the building of dedicated big rope platform sling hanging point, hanging point can not usually be moved, and practicability is not high.
Utility model content
The applicant is for immovable platform sling hanging point position, practicability present in above-mentioned existing structure cleaning measure
The disadvantages of not high with reliability, provides a kind of structurally reasonable top of building erecting by overhang, can adjust extension as needed
The position of point and hanging point are at a distance from metope, and work efficiency is high, and solid and reliable, practicability is good.
Technical solution used by the utility model is as follows:
A kind of top of building erecting by overhang installs I-shaped guide rail, guide rail on the parapet top surface of top of building
Vertical plate including top plate and bottom plate and connection top and bottom plate, is arranged the sliding part being slidably matched on top plate, solid on sliding part
Dingan County fills an inner circle pipe fitting, and an outer circle pipe fitting is arranged on the periphery of interior round tube part, is fixedly installed on outer round tube part straight
Hanging point is arranged in the end of angle support, right angle rack, for installing lifting rope and platform sling.
As a further improvement of the above technical scheme:
Sliding part is coupled by left component and right component, and left component and right component are centered around the periphery of top plate jointly.
Left component includes turning over the right baffle-plate to be formed under the bearing plate and bearing plate above top plate, and right baffle-plate is located at vertical plate
Side, right component includes that the right shell body and right shell body positioned at the vertical plate other side turn over the liner plate to be formed, and bearing plate and liner plate are logical
It crosses and is bolted.
It is mounted on the idler wheel of horizontal direction in left baffle and right baffle lower surface, the idler wheel of the left and right sides is along vertical plate
Two sides roll, and limit to sliding part.
Extend positioning tab on the side of bearing plate and right baffle-plate, open up location hole on positioning tab, on the top of guide rail
Compartment offers one group of several connecting hole on plate, and positioning bolt passes through the location hole of bearing plate, connecting hole and right baffle-plate
It is connect after location hole with nut.
In the lower surface of bearing plate, rubber pad, rubber pad and top plate contact are set.
It is provided with through-hole of a pair of of line by die on outer circle pipe fitting, several pairs of lines are provided on inner circle pipe fitting and pass through die
Adjustment hole, adjust bolt-through through-hole and one pair of them adjustment hole and be fixedly connected with nut.
A plate is fixed in outer round tube part upper end, is fixedly welded right angle rack on plate.
Right angle rack is connected on the periphery of outer circle pipe fitting by a hang plate.
It is embedded into U-shaped part in advance in parapet wall, U-shaped part secures a base plate to the top surface of parapet by fastener
On.
The beneficial effects of the utility model are as follows:
The utility model is slid on I-shaped guide rail by sliding part, recycles positioning bolt to be locked, Ke Yigen
According to the position for needing to adjust hanging point, each position of outside vertical surface of building is covered convenient for cleaning operation range, improves work effect
Rate, practicability are good.Sliding part is coupled using left component and right component, is mounted on the top plate of I-shaped guide rail, structure
Solid and reliable, installation and removal are convenient.It is limited by two idler wheels, plays guiding role, convenient for sliding part I-shaped
It is steadily slid on guide rail.By being rotatably assorted between inner circle pipe fitting and outer circle pipe fitting, during installation, the bracket on outer circle pipe fitting
The inside above building, when in use, bracket is gone on the outside of building, and a variety of usage modes are packed up and stretched in realization.By
Removable connection structure is used in sliding part and I-shaped guide rail, when not using this equipment, can be removed on I-shaped guide rail
Component, do not influence the overall beautiful of top of building parapet.
Detailed description of the invention
Fig. 1 is the schematic diagram of the utility model.
Fig. 2 is the broken away view of the utility model.
Fig. 3 is the Local map of the utility model.
Fig. 4 is the sectional view of sliding part.
In figure: 1, guide rail;2, sliding part;3, left component;3a, bearing plate;3b, right baffle-plate;4, right component;4a, right shell body;
4b, liner plate;5, idler wheel;6, lug;7, positioning bolt;8, inner circle pipe fitting;9, outer circle pipe fitting;10, bolt is adjusted;11, plate;
12, bracket;13, hanging point;14, parapet;15, U-shaped part.
Specific embodiment
With reference to the accompanying drawing, illustrate specific embodiment of the present utility model.
As shown in Figures 1 to 4, parapet of the top of building erecting by overhang described in the utility model in top of building
By installation of embedded parts one I-shaped guide rail 1 on 14, guide rail 1 includes the vertical plate of top plate and bottom plate and connection top and bottom plate, in advance
Embedded part is the merging intracorporal U-shaped part 15 of wall, and the bottom plate of guide rail 1 is fixed on the top surface of parapet 14 by fastener.It is pushing up
The sliding part 2 being slidably matched is set on plate, and sliding part 2 is coupled by left component 3 and right component 4, left component 3 and right component 4
It is centered around the periphery of top plate jointly.Left component 3 includes turning over the left side to be formed under the bearing plate 3a and bearing plate 3a above top plate
Baffle 3b, right baffle-plate 3b are located at the side of vertical plate, and right component 4 includes on the right shell body 4a and right shell body 4a of the vertical plate other side
The liner plate 4b to be formed is turned over, bearing plate 3a and liner plate 4b is bolted by multiple, and bolt runs through connection liner plate 4b and right gear up and down
Plate 4a.It is mounted on the idler wheel 5 of horizontal direction in right baffle-plate 3b and the lower surface right shell body 4a, the idler wheel 5 of the left and right sides is along vertical
Two sides of plate roll, and limit to sliding part 2.In the lower surface of bearing plate 3a, rubber pad, rubber pad and top plate are set
Contact slides the abrasion being subject to for reducing sliding part 2.Extend positioning tab 6 on the side of bearing plate 3a and right baffle-plate 3b,
Location hole is opened up on positioning tab 6, the location interval formula that location hole is corresponded on the top plate of guide rail 1 offers one group of several company
Hole is connect, positioning bolt 7 connect with nut after the location hole by the location hole of bearing plate 3a, connecting hole and right baffle-plate 3b, realizes
The selectivity of sliding part 2 positions.
Referring to Figures 1 and 2, an inner circle pipe fitting 8 is fixedly mounted on the upper face of bearing plate 3a, in interior round tube part 8
It is arranged an outer circle pipe fitting 9 on periphery, through-hole of a pair of of line by die is provided on outer circle pipe fitting 9, is provided on inner circle pipe fitting 8
Several pairs of lines adjust bolt 10 through through-hole and one pair of them adjustment hole and fix company with nut by the adjustment hole of die
It connects.It takes out when adjusting bolt 10, the angle of adjustment outer circle pipe fitting 9 can be rotated, when installation and adjustment bolt 10, outer circle pipe can be made
The position of part 9 is fixed, and is limited it and is rotated and loosen.A plate 11 is fixed in outer 9 upper end of round tube part, is fixed on plate 11
Right angle rack 12 is welded, right angle rack 12 is connected on the periphery of outer circle pipe fitting 9 by a hang plate.The end of right angle rack 12
Hanging point 13 is arranged in portion, for installing lifting rope and platform sling.
The utility model passes through the I-shaped guide rail 1 of installation of embedded parts when implementing on the parapet 14 of top of building,
Left component 3 and right component 4 are installed on guide rail 1, a combination thereof is made to be connected into sliding part 2.Outside the inner circle pipe fitting 8 on bearing plate 3a
It is arranged outer circle pipe fitting 9 week, bracket 12 is provided on outer circle pipe fitting 9.During installation, outer circle pipe fitting 9 is located on the inside of building, in reality
Border in use, adjustable outer circle pipe fitting 9 and bracket 12 deflection angle, and by adjust bolt 10 lock.Then adjustment is slided
Position of the moving part 2 on guide rail 1, mobile sliding part 2 arrive suitable position, are locked by positioning bolt 7.Hanging point on bracket 12
Lifting rope and platform sling are installed in 13 positions, and worker takes platform sling and cleans to building wall.When needing to adjust cleaning positions, remove
Positioning bolt 7, mobile sliding part 2 arrives the next position, then is locked.
Above description is the explanation to the utility model, is not the restriction to utility model, without prejudice to the utility model
In the case where spirit, the utility model can make any type of modification.
Claims (10)
1. a kind of top of building erecting by overhang, it is characterised in that: the erector on parapet (14) top surface of top of building
Font guide rail (1), guide rail (1) include the vertical plate of top plate and bottom plate and connection top and bottom plate, and setting is slidably matched on top plate
An inner circle pipe fitting (8) is fixedly mounted on sliding part (2), is arranged one on the periphery of interior round tube part (8) for sliding part (2)
Right angle rack (12) are fixedly installed on outer round tube part (9) in outer circle pipe fitting (9), and hanging point is arranged in the end of right angle rack (12)
(13), for installing lifting rope and platform sling.
2. top of building erecting by overhang described in accordance with the claim 1, it is characterised in that: sliding part (2) by left component (3) and
Right component (4) couples, and left component (3) and right component (4) are centered around the periphery of top plate jointly.
3. top of building erecting by overhang according to claim 2, it is characterised in that: left component (3) includes being located at top plate
It is turned over the right baffle-plate to be formed (3b) under the bearing plate (3a) and bearing plate (3a) of top, right baffle-plate (3b) is located at the side of vertical plate, right
Component (4) includes that the right shell body (4a) and right shell body (4a) positioned at the vertical plate other side turn over the liner plate to be formed (4b), bearing plate
(3a) is bolted with liner plate (4b).
4. top of building erecting by overhang described in accordance with the claim 3, it is characterised in that: in right baffle-plate (3b) and right shell body
The lower surface (4a) is mounted on the idler wheel (5) of horizontal direction, and the idler wheel (5) of the left and right sides is rolled along two sides of vertical plate,
Sliding part (2) is limited.
5. top of building erecting by overhang described in accordance with the claim 3, it is characterised in that: in bearing plate (3a) and right baffle-plate
Extend on the side of (3b) positioning tab (6), positioning tab opens up location hole on (6), and compartment is opened on the top plate of guide rail (1)
Equipped with one group of several connecting hole, positioning bolt (7) is determined by the location hole of bearing plate (3a), connecting hole and right baffle-plate (3b)
Position Kong Houyu nut connection.
6. top of building erecting by overhang described in accordance with the claim 3, it is characterised in that: set in the lower surface of bearing plate (3a)
Set rubber pad, rubber pad and top plate contact.
7. top of building erecting by overhang described in accordance with the claim 1, it is characterised in that: outer circle pipe fitting is provided with a pair on (9)
Line is provided with adjustment hole of several pairs of lines by die on inner circle pipe fitting (8), is adjusted bolt (10) and passed through by the through-hole of die
Reach through hole and one pair of them adjustment hole are simultaneously fixedly connected with nut.
8. top of building erecting by overhang described in accordance with the claim 1, it is characterised in that: fixed in outer round tube part (9) upper end
One plate (11) is fixedly welded right angle rack (12) on plate (11).
9. top of building erecting by overhang described in accordance with the claim 1, it is characterised in that: right angle rack (12) is inclined by one
Inclined plate is connected on the periphery of outer circle pipe fitting (9).
10. top of building erecting by overhang described in accordance with the claim 1, it is characterised in that: pre- in parapet (14) wall
It is embedded into U-shaped part (15), U-shaped part (15) is secured a base plate to by fastener on the top surface of parapet (14).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821730897.3U CN208898457U (en) | 2018-10-25 | 2018-10-25 | Top of building erecting by overhang |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821730897.3U CN208898457U (en) | 2018-10-25 | 2018-10-25 | Top of building erecting by overhang |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208898457U true CN208898457U (en) | 2019-05-24 |
Family
ID=66576786
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821730897.3U Active CN208898457U (en) | 2018-10-25 | 2018-10-25 | Top of building erecting by overhang |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208898457U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109231088A (en) * | 2018-10-25 | 2019-01-18 | 无锡恒尚装饰工程有限公司 | Top of building erecting by overhang |
-
2018
- 2018-10-25 CN CN201821730897.3U patent/CN208898457U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109231088A (en) * | 2018-10-25 | 2019-01-18 | 无锡恒尚装饰工程有限公司 | Top of building erecting by overhang |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108545628B (en) | A kind of mobile hanging device of Super High and its hanging method | |
CN202144438U (en) | Telescopic hanging basket | |
CN208642145U (en) | A kind of efficient watering dust collecting device of architectural engineering | |
CN204001893U (en) | Traction steel rope of cable lift-sliding parking storehouse under simple and easy back boom | |
CN202324576U (en) | Rail-mounted platform system used for installing cornice and ceiling aluminium sheet curtain wall | |
CN105003082A (en) | Glass curtain wall mounting equipment and glass curtain mounting method | |
CN208898457U (en) | Top of building erecting by overhang | |
CN107165401A (en) | Cantilever Beams bottom wall construction method | |
CN106044651A (en) | Aerial operation basket | |
CN205493732U (en) | High altitude curtain cleaning robot | |
CN202731262U (en) | Installation and maintenance safe platform for air conditioner external unit | |
CN109231088A (en) | Top of building erecting by overhang | |
CN113235906A (en) | Integrally-lifted peripheral protection hanging frame and lifting method | |
CN204602519U (en) | Paint roller more changing device under horizontal galvanizing unit | |
CN218406396U (en) | Movable hanging basket for construction of building structure outer vertical face | |
CN201730624U (en) | Construction work vehicle for subway region tunnel | |
CN201952195U (en) | Telescopic wall supporting wheel | |
CN212771963U (en) | Movable suspension operation platform | |
CN213391263U (en) | Device for conveying glass plates | |
CN204872473U (en) | Carton lift transmission device | |
CN205529054U (en) | Zinc -plated automatic acid dip pickle is managed in side | |
CN205894632U (en) | Spiral arm over -and -under type mobile scaffold | |
CN110820649A (en) | Highway tunnel cleaning system | |
CN213508061U (en) | Construction equipment for bridge engineering | |
CN217708658U (en) | Curtain wall installation can climb roofing system of hanging |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CP01 | Change in the name or title of a patent holder |
Address after: 214117 No.8, Tonghu Road, Ehu Town, Xishan District, Wuxi City, Jiangsu Province Patentee after: Jiangsu Hengshang Energy Saving Technology Co.,Ltd. Address before: 214117 No.8, Tonghu Road, Ehu Town, Xishan District, Wuxi City, Jiangsu Province Patentee before: WUXI HENGSHANG DECORATION ENGINEERING Co.,Ltd. |
|
CP01 | Change in the name or title of a patent holder |