Prior art keywords
slope
intercepting ditch
ditch
water blocking
intercepting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821595637.XU
Other languages
Chinese (zh)
Inventor
贾帅杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Highway Engineering Construction (Group) Co Ltd
Original Assignee
Shandong Highway Engineering Construction (Group) Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Highway Engineering Construction (Group) Co Ltd filed Critical Shandong Highway Engineering Construction (Group) Co Ltd
Priority to CN201821595637.XU priority Critical patent/CN208884304U/en
Application granted granted Critical
Publication of CN208884304U publication Critical patent/CN208884304U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A30/00Adapting or protecting infrastructure or their operation
    • Y02A30/60Planning or developing urban green infrastructure

Abstract

The utility model provides a kind of intercepting ditch structure for excavation cutting top of the slope, includes top of the slope, intercepting ditch, the water blocking ridge;The top of the slope is the Slope roof construction of excavation cutting, which is provided with slope diagonally downward to line of slope is met, and top of the slope has intercepting ditch toward back line of slope a distance build at edge;The intercepting ditch is mortar flag stone concave structure, which is horizontal plane, and top surface is overlapped with top of the slope top surface;The intercepting ditch bottom surface is equipped with sand-gravel cushion;The top of the slope has the water blocking ridge to meeting line of slope build by intercepting ditch, which is concrete trapezium structure, and it is step shape and to be connect with top of the slope by pre-buried bar planting that water blocking ridge bottom surface, which is built,;The structure can intercept rainwash, prevent water flow from can wash away and corroding execavated rockmass or embankment slope foot, and destroy to top of the slope small.

Description

A kind of intercepting ditch structure for excavation cutting top of the slope
Technical field
The utility model relates to road drainage field more particularly to a kind of intercepting ditch structures for excavation cutting top of the slope.
Background technique
The main reason for express highway roadbed pavement destruction is Moisture Damage.Therefore, successfully express highway roadbed road surface is arranged Water design is particularly important.At present, domestic often to pay attention to deficiency to Water Drainage of Expressway design, design is extensive, mechanical, for Property is not strong.And pumping equipment is in the form of a single, and bricklaying dosage is big, and cost is high, and landscape is poor.Especially, in cutting or side slope of embankment When the flow path surface on top inflow road circle is larger, execavated rockmass or embankment slope foot can be washed away and be corroded to water flow, lead to blocking very To Que Di.
Utility model content
The purpose of this utility model is that it is in view of the drawbacks of the prior art and insufficient, it provides a kind of for excavation cutting top of the slope Intercepting ditch structure, which can intercept rainwash, prevent water flow from can wash away and corroding execavated rockmass or embankment slope foot, and Top of the slope is destroyed small.
A kind of in order to achieve the above purposes, the technical solution adopted by the utility model is: intercepting water for excavation cutting top of the slope Ditch structure includes top of the slope, intercepting ditch, the water blocking ridge;The top of the slope be excavation cutting Slope roof construction, the top of the slope top surface to It meets line of slope and is provided with slope diagonally downward, and top of the slope has intercepting ditch toward back line of slope a distance build at edge; The intercepting ditch is mortar flag stone concave structure, which is horizontal plane, and top surface is overlapped with top of the slope top surface;It is described to intercept water Ditch bottom surface is equipped with sand-gravel cushion;The top of the slope by intercepting ditch to meet line of slope build have the water blocking ridge, which is mixed Solidifying soil trapezium structure, water blocking ridge bottom surface, which is built, to be step shape and is connect with top of the slope by pre-buried bar planting.
Preferably, the top of the slope is to the slope met line of slope and be provided with diagonally downward 2%.
Preferably, the intercepting ditch is with a thickness of 200-300mm, and intercepting ditch height is 500-800mm.
Preferably, the intercepting ditch inner wall is not less than 5000mm apart from slope edges.
The beneficial effects of the utility model are: the structure can intercept rainwash, prevent water flow from can wash away and corroding excavation Side slope or embankment slope foot, and top of the slope is destroyed small.
Detailed description of the invention
Attached drawing described herein is to be used to provide a further understanding of the present invention, and constitutes one of the application Point, but do not constitute the restriction to the utility model.
Fig. 1 is intercepting ditch structural schematic diagram.
Wherein: 1 is top of the slope, and 2 be intercepting ditch, and 2-1 is sand-gravel cushion, and 3 be the water blocking ridge.
Specific embodiment
In conjunction with attached drawing, the utility model is described in further detail.
As shown, a kind of intercepting ditch structure for excavation cutting top of the slope, includes top of the slope 1, intercepting ditch 2, the water blocking ridge 3;The top of the slope 1 is the Slope roof construction of excavation cutting, which is provided with diagonally downward oblique to line of slope is met Rate, and top of the slope 1 has intercepting ditch 2 toward back line of slope a distance build at edge;The intercepting ditch 2 is mortar flag stone spill knot Structure, 2 bottom surface of intercepting ditch are horizontal plane, and top surface is overlapped with 1 top surface of top of the slope;2 bottom surface of intercepting ditch is equipped with sand-gravel cushion 2- 1;The top of the slope 1 by intercepting ditch 2 to meet line of slope build have the water blocking ridge 3, the water blocking ridge 3 be concrete trapezium structure, gear 3 bottom surface of the water ridge, which is built, to be step shape and is connect with top of the slope 1 by pre-buried bar planting.
When it is implemented, the top of the slope 1 is to the slope met line of slope and be provided with diagonally downward 2%.
When it is implemented, the intercepting ditch 2 is with a thickness of 200-300mm, and 2 height of intercepting ditch is 500-800mm.
When it is implemented, 2 inner wall of intercepting ditch is not less than 5000mm apart from 1 edge of top of the slope.

Claims (4)

1. a kind of intercepting ditch structure for excavation cutting top of the slope, it is characterised in that: include top of the slope, intercepting ditch, the water blocking ridge;Institute The Slope roof construction that top of the slope is excavation cutting is stated, which is provided with slope diagonally downward to line of slope is met, and Top of the slope has intercepting ditch toward back line of slope a distance build at edge;The intercepting ditch is mortar flag stone concave structure, this section Ditch bottom surface is horizontal plane, and top surface is overlapped with top of the slope top surface;The intercepting ditch bottom surface is equipped with sand-gravel cushion;The top of the slope is being cut By ditch to meet line of slope build have the water blocking ridge, the water blocking ridge be concrete trapezium structure, water blocking ridge bottom surface build be step Shape is simultaneously connect with top of the slope by pre-buried bar planting.
2. a kind of intercepting ditch structure for excavation cutting top of the slope according to claim 1, it is characterised in that: the top of the slope To the slope met line of slope and be provided with diagonally downward 2%.
3. a kind of intercepting ditch structure for excavation cutting top of the slope according to claim 1, it is characterised in that: described to intercept water Ditch is with a thickness of 200-300mm, and intercepting ditch height is 500-800mm.
4. a kind of intercepting ditch structure for excavation cutting top of the slope according to claim 1, it is characterised in that: described to intercept water Ditch inner wall is not less than 5000mm apart from slope edges.
CN201821595637.XU 2018-09-28 2018-09-28 A kind of intercepting ditch structure for excavation cutting top of the slope Active CN208884304U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821595637.XU CN208884304U (en) 2018-09-28 2018-09-28 A kind of intercepting ditch structure for excavation cutting top of the slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821595637.XU CN208884304U (en) 2018-09-28 2018-09-28 A kind of intercepting ditch structure for excavation cutting top of the slope

Publications (1)

Publication Number Publication Date
CN208884304U true CN208884304U (en) 2019-05-21

Family

ID=66514509

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821595637.XU Active CN208884304U (en) 2018-09-28 2018-09-28 A kind of intercepting ditch structure for excavation cutting top of the slope

Country Status (1)

Country Link
CN (1) CN208884304U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112281909A (en) * 2020-10-09 2021-01-29 杭州华耕土地规划设计咨询有限公司 Ecological retaining wall of last ditch lower base retaining block suitable for massif slope

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112281909A (en) * 2020-10-09 2021-01-29 杭州华耕土地规划设计咨询有限公司 Ecological retaining wall of last ditch lower base retaining block suitable for massif slope

Similar Documents

Publication Publication Date Title
CN103122641A (en) Slope reinforced structure and reinforcing method thereof
CN109098064A (en) The sponge urban road structure for avoiding rainwater on road surface from depositing
CN206352331U (en) The concave herbaceous field structure of sponge the idea of the city
CN208685545U (en) A kind of bank protection structure improving land and water domain ecological environment
CN110387861A (en) It is a kind of for the earth rock cofferdam remodeling method for leading over-level flood off of meeting an urgent need
CN109083096A (en) A kind of step-like ecological slope protection structure of reservoir area fluctuating zone and its implementation method
CN209669895U (en) Intercept water side slope of embankment ecological protection
CN208884304U (en) A kind of intercepting ditch structure for excavation cutting top of the slope
CN110145007A (en) The drainage system of Dumping Sites
CN210797803U (en) Anti-blocking drain pipe
JP2018204391A (en) Gabion and slope reinforcing structure using the same
CN209538128U (en) A kind of dam structure promoted for reservoir landscape
CN104695379A (en) Ecological river channel revetment structure
KR101173505B1 (en) Debris barrier
CN106012951B (en) Avoid the reservoir structure that solution cavity is built the method for reservoir and its built in In Limestone Area
CN205171454U (en) Ecological bank protection
CN209568531U (en) A kind of water storage system of discarded Rare-earth Mine
CN103999592A (en) Method for avoiding vegetation degradation of acid mine waste rock yard
CN103981838B (en) A kind of bank protection construction method
CN207553116U (en) A kind of greening friction pile of stake top rescinded angle
CN208167660U (en) A kind of protection against erosion intercepting ditch
CN209010891U (en) A kind of multi-functional lobby drainage facility
CN212104428U (en) Water seepage drain pipe
CN206941613U (en) A kind of environment-friendly type grass planting Concrete Highway protective slope structure
CN208717870U (en) A kind of prefabricated component check dam

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant