CN208858134U - The security platform of high-altitude installation exercise - Google Patents
The security platform of high-altitude installation exercise Download PDFInfo
- Publication number
- CN208858134U CN208858134U CN201821372689.0U CN201821372689U CN208858134U CN 208858134 U CN208858134 U CN 208858134U CN 201821372689 U CN201821372689 U CN 201821372689U CN 208858134 U CN208858134 U CN 208858134U
- Authority
- CN
- China
- Prior art keywords
- sidebar
- security platform
- vertical bar
- link
- installation exercise
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
A kind of security platform of high-altitude installation exercise, its be characterized by it by: hanging plate, sidebar, link, bottom plate, railing form, sidebar is located at left and right two sides, railing is located at front and back two sides, bottom plate is in lower section, top is formed to open wide, there is the security platform of guardrail in five faces, sidebar is the rectangle frame of two vertical bars and two cross bar compositions perpendicular to vertical bar, it wherein is formed with the hook matched with hanging plate on a vertical bar, link is fixed on vertical bar, the both ends of railing bend downward 90 degree, it is inserted in link, bottom plate is fixed on the lower section of sidebar.The utility model has the characteristics that simple, fast assembling-disassembling, can not only reduce the dependence to large-tonnage lifting equipment, can also reduce and increase artificial, material investment, the advantage for having installation speed fast, at low cost to setting up scaffold.And property easy for installation, in terms of be all substantially better than traditional method.
Description
Technical field
The utility model relates to a kind of security platforms of high-altitude installation exercise.
Background technique
In Large Infrastructure Projects project construction, large-tonnage cementing tank (referring to 6 meters of diameter or more or 500 tons or more) is pacified vertically
There is the features such as hoisting component is big, tonnage weight, sling height height, and warehouse junction seals, fastening bolt is more when dress.It is affected by this,
People often lie down cementing tank on the ground when construction and installation, hang standing installation with big ton crane again after carrying out warehouse docking, or
It is installed by the way of scaffolding, these methods are at high cost, and the material utilization amount for setting up scaffold is big, back work consumes
Installation period is longer.
Summary of the invention
The purpose of the utility model is to overcome current cementing tank installation high altitude operation difficulty it is big, large tonnage crane rent
The deficiencies of difficult, machine-team expense height or the material for setting up scaffold consumption are more, it is flat to provide a kind of activity safety that can be used for high altitude operation
Platform successively uses repeatedly as tank body increases, and to reduce the dependence to large tonnage crane or reduce the material consumption of scaffold, adds
The security platform of the high-altitude installation exercise of fast installation progress.
Technical solution used by the utility model is a kind of security platform of high-altitude installation exercise, is characterized by it
By: hanging plate, sidebar, link, bottom plate, railing form, and sidebar is located at left and right two sides, and railing is located at front and back two sides, bottom plate in lower section,
It forms top to open wide, there is the security platform of guardrail in five faces, and sidebar is two vertical bars and two cross bar compositions perpendicular to vertical bar
Rectangle frame is fixed with link wherein being formed with the hook matched with hanging plate on a vertical bar on vertical bar, the both ends of railing are turned under
90 degree of folding, is inserted in link, bottom plate is fixed on the lower section of sidebar.
The muti-piece hanging plate of the utility model is fixed on the mounted cementing tank of preceding layer, then hangs over the hook of sidebar
On hanging plate, realizing that the security platform of high-altitude installation exercise is fixed with cementing tank, worker can stand and operate on platform, thus
It avoids renting large tonnage crane, or reduces the artificial of the material and investment for setting up scaffold consumption, the fast, cost with installation speed
Low advantage.
The bottom plate is made of two horizontal stripes and several strips, and the both ends of strip are respectively and vertically fixed on horizontal stripe, horizontal stripe two
End length is respectively greater than 50 mm or more of sidebar cross section.For preventing sidebar from moving left and right.
Strip is that interval is fixed on horizontal stripe, and the width of two root long item of outermost is less than the width between two vertical bar of sidebar.Bottom
Plate is mounted in sidebar.
Spacing on the inside of two root long item of outermost and sidebar is 15-25mm.
The height of sidebar outside vertical is 1200-1300 mm, is fixed with 1-3 root cross bar in the middle.The selection one of height
As above the waist of people, below shoulder, safety facilitates operation again.Middle part cross bar quantity is more, and safety is good, but influences overall weight.
There is 3-5 link interval to be fixed on vertical bar.The quantity of link is identical as railing quantity, generally with the quantity of cross bar
It is identical.
The shape of hanging plate is " Ω ", and middle part is semi-cylindrical or super semi-cylindrical, can pass through the hook of sidebar, both sides are length
Rectangular component.Muti-piece hanging plate is fixed on cementing tank, for fixing security platform.
The utility model has the characteristics that simple, fast assembling-disassembling, can not only reduce the dependence to large-tonnage lifting equipment,
It can also reduce and increase artificial, material investment to setting up scaffold, with fast, the at low cost advantage of installation speed.And
Property easy for installation, practicability etc. are all substantially better than traditional method.
Detailed description of the invention
Fig. 1 is cementing tank lifting schematic diagram
Fig. 2 is the utility model arrangement schematic diagram
Fig. 3 is the mounting structure schematic diagram of the utility model
Fig. 4 is the structural schematic diagram of the utility model each component in addition to hanging plate
Fig. 5 is the structural schematic diagram of hanging plate
Fig. 6 is the structural schematic diagram of sidebar and link
Fig. 7 is the structural schematic diagram of bottom plate
Wherein: 1 hanging plate, 2 sidebar, 21 vertical bar, 22 cross bar 23 links up with 3 link, 4 bottom plate, 5 railing, 10 high-altitude peace
Pretend 20 cementing tank of security platform of industry.
Specific embodiment
The utility model is described in detail with reference to the accompanying drawing, the following examples can make the technology of this profession
Personnel more understand the utility model, but do not limit the utility model in any form.
As shown in figs. 1-7, the major diameter cementing tank of the utility model meaning refers to 6 meters of diameter or more or 500 tons or more, no
Only scantling is big, tonnage is heavy, sling height is high and the connection bolt of interlayer is thousands of a.
A kind of security platform of high-altitude installation exercise, it by: hanging plate 1, sidebar 2, link 3, bottom plate 4, railing 5 form,
Wherein hanging plate 1 selects the production of 8mm steel plate, and the shape of hanging plate is " Ω ", and middle part is semi-cylindrical or super semi-cylindrical, can pass through side
The hook on column, both sides are rectangular component, and for being weldingly fixed on cementing tank, the radius of circle is that 13-15mm(hook is φ
The reinforcing bar of 25mm).Muti-piece hanging plate is welded in 2000 mm spacing away from 150-200mm below articulamentum.
Sidebar is located at the left and right two sides of security platform, and railing is located at front and back two sides, and bottom plate forms top and open wide in lower section,
There is the security platform of guardrail in five faces, and sidebar 2 is as shown in fig. 6, sidebar is two vertical bars 21 and two cross bars 22 perpendicular to vertical bar
The rectangle frame of composition is fixed with link 3 wherein be formed with the hook 23 matched with hanging plate on a vertical bar on vertical bar, outside sidebar
The height of side vertical bar is 1200-1300 mm, is fixed with 1-3 root cross bar in the middle.Sidebar uses the reinforcement fabrication of φ 25mm,
Sidebar width 500mm-600 mm, height 1200-1300 mm.The vertical bar upper end of the inside of sidebar directly curves hook, or with system
Good hook is fixed on the vertical bar on the inside of sidebar, links up with length 200-250 mm.
Link 3 is located on the vertical bar of the two sides of sidebar for non-floating rail, has 3-5 link interval to be fixed on vertical bar.
The quantity of link is identical as 5 quantity of railing, generally identical as the quantity of cross bar.Link internal diameter φ 30mm, outer diameter φ 33mm, length
100 mm are connect in the method for welding with vertical bar;Railing 5 makes of φ 25mm, the long distance for taking two links, generally in 1500-
2000 mm, both ends bend downward 90 degree, are fabricated to vertical crotch, and the long 150-200mm of crotch is inserted in link.
Bottom plate 4 is made of two horizontal stripes and several strips, and the both ends of strip, which are respectively perpendicular, to be weldingly fixed on horizontal stripe, horizontal stripe two
End length is respectively greater than 50 mm or more of sidebar cross section.The reinforcement fabrication of the utility model φ 25mm, horizontal stripe length 700-800
The both sides mm are respectively greater than 100 mm of sidebar cross section, for preventing sidebar from moving left and right, the long 1550-2050 mm of strip, with spacing
100mm is welded on horizontal stripe, and overall width is less than the spacing 15- on the inside of two root long item of sidebar inner width 30-50mm(outermost and sidebar
25mm).Bottom plate is installed on the cross bar below sidebar, installation Shi Keli be laid flat again into frame.
The hanging plate of the utility model is fixed on the mounted cementing tank of preceding layer, and the hook of sidebar is then hung over hanging plate
On, realize that the security platform of high-altitude installation exercise is fixed with cementing tank, worker can stand and operate on platform, to avoid
Large tonnage crane is rented, or reduces the artificial of the material and investment for setting up scaffold consumption, has installation speed fast, at low cost
Advantage.
The utility model can be used alone, and multiple can also combine use, and sidebar 2, bottom plate 4, railing 5 can split into list
Part, and it is independent using simple to reach production, piece weight is light, easy for installation, high-altitude dismantling holds to have the function of each single-piece
Easy purpose.Simultaneously because each platform is independently installed, tank body radian is can be ignored to railing with radian molding arrangement in single platform
It is required that reaching Fast Installation, safe purpose is ensured.
Claims (7)
1. a kind of security platform of high-altitude installation exercise, it is characterised in that it is by hanging plate (1), sidebar (2), link (3), bottom
Plate (4), railing (5) composition, sidebar are located at left and right two sides, and railing is located at front and back two sides, and bottom plate forms top and open wide in lower section,
There is the security platform of guardrail in five faces, and sidebar is rectangle of two vertical bar (21) He Lianggen perpendicular to cross bar (22) composition of vertical bar
Frame is fixed with link on vertical bar, the both ends of railing are turned under wherein being formed with the hook (23) matched with hanging plate on a vertical bar
90 degree of folding, is inserted in link, bottom plate is fixed on the lower section of sidebar.
2. a kind of security platform of high-altitude installation exercise according to claim 1, it is characterised in that the bottom plate is by two
Horizontal stripe and several strips are constituted, and the both ends of strip are respectively and vertically fixed on horizontal stripe, and it is cross-section that horizontal stripe both ends length is respectively greater than sidebar
50 mm or more of face.
3. a kind of security platform of high-altitude installation exercise according to claim 2, it is characterised in that strip is that interval is solid
It is scheduled on horizontal stripe, the width of two root long item of outermost is less than the width between two vertical bar of sidebar.
4. a kind of security platform of high-altitude installation exercise according to claim 2, it is characterised in that two root long of outermost
Spacing 15-25mm on the inside of item and sidebar.
5. a kind of security platform of high-altitude installation exercise according to claim 1, it is characterised in that sidebar outside vertical
Height be 1200-1300 mm, be fixed with 1-3 root cross bar in the middle.
6. a kind of security platform of high-altitude installation exercise according to claim 5, it is characterised in that have between 3-5 link
Every being fixed on vertical bar.
7. a kind of security platform of high-altitude installation exercise according to claim 1, it is characterised in that the shape of hanging plate is
" Ω ", middle part are semi-cylindrical or super semi-cylindrical, can pass through the hook of sidebar, both sides are rectangular component.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821372689.0U CN208858134U (en) | 2018-08-24 | 2018-08-24 | The security platform of high-altitude installation exercise |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821372689.0U CN208858134U (en) | 2018-08-24 | 2018-08-24 | The security platform of high-altitude installation exercise |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208858134U true CN208858134U (en) | 2019-05-14 |
Family
ID=66415586
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821372689.0U Active CN208858134U (en) | 2018-08-24 | 2018-08-24 | The security platform of high-altitude installation exercise |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208858134U (en) |
-
2018
- 2018-08-24 CN CN201821372689.0U patent/CN208858134U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201598820U (en) | Single-point suspension external hanging rack | |
CN207499385U (en) | Plug-in tower crane supporting beam, which has bad luck installation and climbs, uses operating platform | |
CN204626921U (en) | A kind of fixed working platform without scaffold construction elevator | |
CN109653484B (en) | Roofing superelevation faces external hanging flower basket mounting structure of empty curtain engineering | |
CN104153586B (en) | A kind of suspension cable hangs the construction method of mounting purlines | |
CN209011528U (en) | A kind of all steel attachment type raise scaffold | |
CN208858134U (en) | The security platform of high-altitude installation exercise | |
CN208363666U (en) | It is a kind of for build face side construction safety protection frame | |
CN101440660A (en) | Guiding-rail attached lifting scaffold | |
CN205894636U (en) | Cage device for high-altitude welding operation of steel structure | |
CN202731270U (en) | Movable platform for aerial installation operation of space steel structure | |
CN205574235U (en) | Bulk freighter wing tank section construction stores pylon | |
CN201141203Y (en) | Guiding-rail attached lifting scaffold | |
CN209723570U (en) | Steel column docking installation operation platform | |
CN208899840U (en) | For volumed space building inner top constructing device | |
CN204212388U (en) | Monolithic combined scaffold | |
CN204038917U (en) | Detachable external hanging type operating platform | |
CN203514813U (en) | Novel overhanging discharging platform | |
CN206693590U (en) | A kind of Quick-mounting aluminium alloy scaffold | |
CN207377096U (en) | Overlength large girder scaffold building structure | |
CN207419689U (en) | A kind of prefabricated balcony slab | |
CN104631811A (en) | Back-hooking suspension mechanism | |
CN203923917U (en) | Job platform at the bottom of a kind of packaged type bridge | |
CN210420883U (en) | Bridge construction crossbeam construction operation platform | |
CN215829977U (en) | A suspended door formula support for high altitude tower building vestibule fitment |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |