CN208816046U - A kind of novel hydropower hole penetrating device - Google Patents
A kind of novel hydropower hole penetrating device Download PDFInfo
- Publication number
- CN208816046U CN208816046U CN201821431246.4U CN201821431246U CN208816046U CN 208816046 U CN208816046 U CN 208816046U CN 201821431246 U CN201821431246 U CN 201821431246U CN 208816046 U CN208816046 U CN 208816046U
- Authority
- CN
- China
- Prior art keywords
- hole penetrating
- plastic
- retractable support
- pipe
- penetrating device
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Perforating, Stamping-Out Or Severing By Means Other Than Cutting (AREA)
Abstract
The utility model discloses a kind of novel hydropower hole penetrating device, including damping base and formed punch, it is provided with high pressure water-injection pump at the end position of the damping base upper left, using the utility model waterpower hole penetrating device labor intensity is reduced, sealing of hole worker's repercussion is good;Open-work efficiency is doubled.1~2 hole is rushed by original per tour and is increased to 3~4 holes of per tour punching;Accelerate coal roadway tunneling speed, lane is because of the big problem influence digging footage of gas emission on 21031 before open-work, 1~1.5m of per tour digging footage, 1.5~2m of lane per tour digging footage on 21031 after open-work, it is single into providing effective and safe guarantee to improve, after the utility model waterpower hole penetrating device, Li Goukuang, which is realized, quickly eliminates coal and gas prominent danger, prevent human casualty accident, simultaneously again because being equipped with damping base, would not high pressure water-injection pump be damaged at work, not only increase production efficiency in this way, and also a save resource.
Description
Technical field
The utility model belongs to waterpower hole penetrating device correlative technology field, and in particular to a kind of novel hydropower hole penetrating device.
Background technique
When coal mine underground construction layer-through drilling takes out coal-bed gas in advance, waterpower is usually carried out afterwards in place in drilling construction at present
Punching is gone out the coal near drilling by water pressure, and loose coal seam expands pressure release circle, enhances gas permeability, improves extraction effect
Fruit, hydraulic flushing in hole are usually to stop punching mark, but since there is some strength in coal seam itself, anti-clear water only illustrated at that time with anti-clear water
Coal can not be gone out again, and after a period of time, coal strength reduces, and will continue to collapse, and blocks up real drilling, and coal seam depth gas is difficult to
It migrates to drilling, extraction concentration, flow is caused to be greatly reduced;In coal roadway tunneling and exploitation process, due to feelings such as coal seam variations
Condition locally will appear gas emission and increase phenomenon, influences mining progress.In view of these situations, it is common practice to again into
Row waterpower open-work, current way are that the gas drainage pipe having connected is removed, and use drilling machine jointed rod, open-work drill bit again,
Open-work in drilling is protruded into after firmly believing former drilling, this method benefit is that drill capacity is strong, if having broken spoil to be not easy during open-work
Plug-hole, but disadvantage is obvious, needs to move brill again, and large labor intensity needs personnel more;Need to recognize again hole, drilling machine needs adjusting angle
Degree, drilling rod need to reconnect, open-work inefficiency.
Existing waterpower hole penetrating device technology has the following problems: complex steps when open-work, open-work low efficiency.It needs to move
It bores, waste of manpower.The gas drainage pipe connected need to be removed, material is wasted.When in use simultaneously, because pedestal is fixed
, it is described to be easy when in use so that high pressure water-injection pump damage, delays production efficiency, and waste of resource in this way.
Utility model content
The purpose of this utility model is to provide a kind of novel hydropower hole penetrating devices, to solve to propose in above-mentioned background technique
Delay production efficiency, and waste of resource problem.
To achieve the above object, the utility model provides the following technical solutions: a kind of novel hydropower hole penetrating device, including subtracts
Pedestal and formed punch are shaken, is provided with high pressure water-injection pump, the damping base upper right end position at the end position of the damping base upper left
Place is provided with water storage barrel, and the water storage barrel is fixedly connected by No. two connectors with high pressure water-injection pump, the water storage barrel left upper end
It is provided with water outlet port at position, aluminium-plastic pipe dedicated convert connector, the plastic-aluminum are provided at the water outlet port left position
It is provided with plastic-aluminum open-work pipe at pipe dedicated convert connector left position, is socketed with pumping at outer wall position on the left of the plastic-aluminum open-work pipe
Pipe is put, No.1 connector is provided at the releasing pipe left position, the plastic-aluminum open-work pipe is located at right inside No.1 connector
At side position, it is provided with extraction supervisor at the No.1 connector left position, is provided at the extraction supervisor left position
Formed punch.
Preferably, the damping base includes retractable support wall device, fixing seat, load-bearing adjustable spring and bearing platform, institute
It states and is provided with load-bearing adjustable spring, institute at fixing seat upper end front and rear sides middle position and upper end front and rear sides left-right position
It states and is provided with retractable support wall device, two retractable support wall set at position at left and right sides of load-bearing adjustable spring upper end
In load-bearing adjustable spring towards at external position, bearing platform, the load-bearing are provided at six load-bearing adjustable spring upper end positions
Platform is located at retractable support wall device upper end position, the damping base by bearing platform respectively with high pressure water-injection pump and water storage barrel
It is fixedly connected.
Preferably, the retractable support wall device includes external extension supporting walls, barrier plate and interior retractable support arm, described outer
It is socketed with interior retractable support arm at retractable support pars intramuralis position, is provided with blocking at the interior retractable support arm lower end position
Plate, the barrier plate are located at external extension supporting walls interior location, the retractable support wall device by external extension supporting walls and
Interior retractable support arm is fixedly connected with fixing seat and bearing platform respectively.
Preferably, the water storage barrel is made of ferritic stainless steel, is provided with water inlet at the water storage barrel back-end location,
And water inlet is connect with outer water tube, the water storage barrel internal volume is set as decaliter.
Preferably, the aluminium-plastic pipe dedicated convert connector is made of aluminum plastic material, and the aluminium-plastic pipe dedicated convert connects
Internal screw thread body is provided at the internal left and right sides inner wall position of head.
Preferably, the plastic-aluminum open-work pipe is made of aluminum plastic material, and the plastic-aluminum open-work length of tube is set as ten meters.
Preferably, the releasing pipe is made of ferritic stainless steel, and the extraction length of tube is set as five meters.
Preferably, the formed punch is made of ferritic stainless steel, and there are four high for setting at the outer wall position of the formed punch left end
Press spout.
Compared with prior art, the utility model provides a kind of novel hydropower hole penetrating device, have it is following the utility model has the advantages that
Using the utility model waterpower hole penetrating device labor intensity is reduced, sealing of hole worker's repercussion is good;Open-work efficiency is doubled.By original
Per tour rushes 1~2 hole and is increased to 3~4 holes of per tour punching;Accelerate coal roadway tunneling speed, 21031 before open-work on lane Yin Wasi gush
The big problem of output influences digging footage, per tour 1~1.5m of digging footage, 21031 after open-work on lane per tour digging footage 1.5~
2m, single into effective and safe guarantee is provided to improve, after the utility model waterpower hole penetrating device, Li Goukuang, which is realized, quickly eliminates coal
With Gas Outburst danger, prevent human casualty accident, while height would not be made at work because being equipped with damping base again
The damage of pressure injection water pump, not only increases production efficiency, and also a save resource in this way.
Detailed description of the invention
Attached drawing is used to provide a further understanding of the present invention, and constitutes part of specification, practical with this
Novel embodiment is used to explain the utility model together, does not constitute limitations of the present invention, in the accompanying drawings:
Fig. 1 be the utility model proposes a kind of novel hydropower hole penetrating device structural schematic diagram;
Fig. 2 be the utility model proposes main view schematic diagram;
Fig. 3 be the utility model proposes damping base structural schematic diagram;
Fig. 4 be the utility model proposes retractable support wall device structural schematic diagram;
In figure: 1, formed punch;2, extraction is responsible for;3, No.1 connector;4, releasing pipe;5, plastic-aluminum open-work pipe;6, water outlet port;
7, No. two connectors;8, high pressure water-injection pump;9, damping base;91, retractable support wall device;911, external extension supporting walls;912,
Barrier plate;913, interior retractable support arm;92, fixing seat;93, load-bearing adjustable spring;94, bearing platform;10, water storage barrel;11, plastic-aluminum
Pipe dedicated convert connector.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-4 is please referred to, the utility model provides a kind of technical solution: a kind of novel hydropower hole penetrating device, including damping
Pedestal 9 and formed punch 1 are provided with high pressure water-injection pump 8 at 9 upper left end position of damping base, are arranged at 9 upper right end position of damping base
There is water storage barrel 10, water storage barrel 10 is fixedly connected by No. two connectors 7 with high pressure water-injection pump 8, at 10 upper left end position of water storage barrel
It is provided with water outlet port 6, aluminium-plastic pipe dedicated convert connector 11, aluminium-plastic pipe dedicated convert are provided at 6 left position of water outlet port
It is provided with plastic-aluminum open-work pipe 5 at 11 left position of connector, is socketed with releasing pipe 4, extraction at 5 left side outer wall position of plastic-aluminum open-work pipe
No.1 connector 3 is provided at 4 left position of pipe, plastic-aluminum open-work pipe 5 is located at 3 inner right side position of No.1 connector, No.1
Extraction supervisor 2 is provided at 3 left position of connector, extraction is responsible at 2 left positions and is provided with formed punch 1.
Further, damping base 9 includes retractable support wall device 91, fixing seat 92, load-bearing adjustable spring 93 and bearing platform
94, load-bearing adjustable spring is provided at 92 upper end front and rear sides middle position of fixing seat and upper end front and rear sides left-right position
93, for better damping, it is provided with retractable support wall device 91 at position at left and right sides of 93 upper end of load-bearing adjustable spring, in order to
Preferably support, two retractable support wall devices 91 are located at load-bearing adjustable spring 93 towards at external position, six load-bearing adjustable springs
Bearing platform 94 is provided at 93 upper end positions, bearing platform 94 is located at 91 upper end position of retractable support wall device, and damping base 9 is logical
It crosses bearing platform 94 to be fixedly connected with high pressure water-injection pump 8 and water storage barrel 10 respectively, for preferably fixed and connection.
Further, retractable support wall device 91 includes external extension supporting walls 911, barrier plate 912 and interior retractable support arm
913, interior retractable support arm 913, in order to preferably stretch, interior retractable support are socketed at 911 interior location of external extension supporting walls
It is provided with barrier plate 912 at 913 lower end position of arm, is fallen off in order to prevent, barrier plate 912 is located inside external extension supporting walls 911
At position, retractable support wall device 91 by external extension supporting walls 911 and interior retractable support arm 913 respectively with fixing seat 92 and hold
Weight platform 94 is fixedly connected, for preferably fixed and connection.
Further, water storage barrel 10 is made of ferritic stainless steel, is provided with water inlet at 10 back-end location of water storage barrel, and into
The mouth of a river is connect with outer water tube, and 10 internal volume of water storage barrel is set as decaliter, for better water storage.
Further, aluminium-plastic pipe dedicated convert connector 11 is made of aluminum plastic material, in aluminium-plastic pipe dedicated convert connector 11
It is provided with internal screw thread body at inner wall position at left and right sides of portion, in order to preferably connect.
Further, plastic-aluminum open-work pipe 5 is made of aluminum plastic material, and 5 length of plastic-aluminum open-work pipe is set as ten meters, in order to more
Good work.
Further, releasing pipe 4 is made of ferritic stainless steel, and 4 length of releasing pipe is set as five meters, in order to preferably work
With improve service life.
Further, formed punch 1 is made of ferritic stainless steel, high pressure spout there are four settings at 1 left end outer wall position of formed punch,
In order to preferably work.
The working principle and process for using of the utility model: it after the utility model installs, before open-work, works
Water inlet at 10 back-end location of water storage barrel is first connect by personnel with outer water tube, and opens water valve, later again consolidates releasing pipe 4
It is scheduled in the drilling accomplished fluently, high pressure water-injection pump 8 connects external power supply, and at this time clear water can enter plastic-aluminum from water outlet port 6
Open-work pipe 5, then entered inside extraction supervisor 2 by No.1 connector 3, it is sprayed again by four high-pressure nozzles of formed punch 1 later,
When open-work, disconnects releasing pipe 4 and connect by No.1 connector 3 with extraction supervisor 2, plastic-aluminum open-work pipe 5 is used dedicated turn of aluminium-plastic pipe
Changing-over head 11 and water outlet port 6 are connected to hole penetrating device, and 5 one end of plastic-aluminum open-work pipe is inserted into drilling bottom out of releasing pipe 4,
The other end connects water outlet port 6, opens high pressure water-injection pump 8 later, passes through soft coal body in high hydraulic pressure percussive drilling, the mixing of coal water
Object is flowed out by the gap of plastic-aluminum open-work pipe 5 and releasing pipe 4, stops open-work after returning clear water, extracts plastic-aluminum open-work pipe 5, extraction out
Pipe 4 starts extraction again through No.1 connector 3 and extraction supervisor 2 again, and high pressure water-injection pump 8 will work while work,
At this time the bearing platform 94 in damping base 9 will receive active force, and active force will be acted on retractable support wall by bearing platform 94
On device 91 and load-bearing adjustable spring 93, load-bearing adjustable spring 93 will stretch at this time, and simultaneous retractable supports in wall device 91
Interior retractable support arm 913 can move up and down inside outer retractable support wall 911, thus achieve the effect that damping, here it is
The working principle of entire novel device.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (8)
1. a kind of novel hydropower hole penetrating device, including damping base (9) and formed punch (1), it is characterised in that: the damping base
(9) it is provided at the end position of upper left high pressure water-injection pump (8), is provided with water storage barrel at damping base (9) the upper right end position
(10), the water storage barrel (10) is fixedly connected by No. two connectors (7) with high pressure water-injection pump (8), and the water storage barrel (10) is left
It is provided at upper end position water outlet port (6), is provided with aluminium-plastic pipe dedicated convert connector at water outlet port (6) left position
(11), plastic-aluminum open-work pipe (5), the plastic-aluminum open-work pipe are provided at aluminium-plastic pipe dedicated convert connector (11) left position
(5) it is socketed with releasing pipe (4) at the outer wall position of left side, is provided with No.1 connector (3) at releasing pipe (4) left position,
The plastic-aluminum open-work pipe (5) is located at No.1 connector (3) inner right side position, at No.1 connector (3) left position
It is provided with extraction supervisor (2), is provided with formed punch (1) at described extraction supervisor (2) left position.
2. a kind of novel hydropower hole penetrating device according to claim 1, it is characterised in that: the damping base (9) includes
Retractable support wall device (91), fixing seat (92), load-bearing adjustable spring (93) and bearing platform (94), fixing seat (92) upper end
Load-bearing adjustable spring (93) are provided at front and rear sides middle position and upper end front and rear sides left-right position, the load-bearing is stretched
It is provided with retractable support wall device (91) at position at left and right sides of contracting spring (93) upper end, two retractable support wall devices
(91) it is located at load-bearing adjustable spring (93) towards at external position, is provided with and holds at six load-bearing adjustable spring (93) upper end positions
Weight platform (94), the bearing platform (94) are located at retractable support wall device (91) upper end position, and the damping base (9) is by holding
Weight platform (94) is fixedly connected with high pressure water-injection pump (8) and water storage barrel (10) respectively.
3. a kind of novel hydropower hole penetrating device according to claim 2, it is characterised in that: the retractable support wall device
It (91) include external extension supporting walls (911), barrier plate (912) and interior retractable support arm (913), the external extension supporting walls
(911) it is socketed with interior retractable support arm (913) at interior location, is provided at interior retractable support arm (913) lower end position
Barrier plate (912), the barrier plate (912) are located at external extension supporting walls (911) interior location, the retractable support wall device
(91) fixed with fixing seat (92) and bearing platform (94) respectively by external extension supporting walls (911) and interior retractable support arm (913)
Connection.
4. a kind of novel hydropower hole penetrating device according to claim 1, it is characterised in that: water storage barrel (10) You Tiesu
Body stainless steel is constituted, and is provided with water inlet at water storage barrel (10) back-end location, and water inlet is connect with outer water tube, described
Water storage barrel (10) internal volume is set as decaliter.
5. a kind of novel hydropower hole penetrating device according to claim 1, it is characterised in that: the aluminium-plastic pipe dedicated convert connects
Head (11) is made of aluminum plastic material, is arranged at the internal left and right sides inner wall position of the aluminium-plastic pipe dedicated convert connector (11)
There is internal screw thread body.
6. a kind of novel hydropower hole penetrating device according to claim 1, it is characterised in that: the plastic-aluminum open-work pipe (5) by
Aluminum plastic material is constituted, and plastic-aluminum open-work pipe (5) length is set as ten meters.
7. a kind of novel hydropower hole penetrating device according to claim 1, it is characterised in that: releasing pipe (4) You Tiesu
Body stainless steel is constituted, and releasing pipe (4) length is set as five meters.
8. a kind of novel hydropower hole penetrating device according to claim 1, it is characterised in that: the formed punch (1) is by ferrite
Stainless steel is constituted, and there are four high pressure spouts for setting at the outer wall position of formed punch (1) left end.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821431246.4U CN208816046U (en) | 2018-09-03 | 2018-09-03 | A kind of novel hydropower hole penetrating device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821431246.4U CN208816046U (en) | 2018-09-03 | 2018-09-03 | A kind of novel hydropower hole penetrating device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208816046U true CN208816046U (en) | 2019-05-03 |
Family
ID=66275515
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821431246.4U Expired - Fee Related CN208816046U (en) | 2018-09-03 | 2018-09-03 | A kind of novel hydropower hole penetrating device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208816046U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110821491A (en) * | 2019-11-10 | 2020-02-21 | 徐州秩润矿山设备科技有限公司 | Wireless control's coal seam high pressure water injection car |
-
2018
- 2018-09-03 CN CN201821431246.4U patent/CN208816046U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110821491A (en) * | 2019-11-10 | 2020-02-21 | 徐州秩润矿山设备科技有限公司 | Wireless control's coal seam high pressure water injection car |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204646269U (en) | A kind of steel arch frame lock foot anchor tube device for reinforcing soft stratum tunnel | |
CN103821539B (en) | A kind of shield machine shield tail synchronizes embedded two-liquid grouting device | |
CN204984343U (en) | Split combined type bag hole sealing device | |
CN102996159A (en) | Multiphase medium plugging device and method for gas extraction drill hole | |
CN204267093U (en) | A kind of portable filling in mine barricade | |
CN105133574A (en) | End point closing wall forming device of extrusion type underground diaphragm wall and application method | |
CN208816046U (en) | A kind of novel hydropower hole penetrating device | |
CN206942804U (en) | A kind of novel hydropower punching operation machine | |
CN108086986B (en) | Steel sleeve for shield receiving | |
CN206753527U (en) | A kind of comprehensive coal dust collection device of coal mine drilling | |
CN107217988B (en) | High-pressure hydraulic slotting machine for coal mine driving face | |
CN204851571U (en) | Crawler -type high pressure water pump station | |
CN207715158U (en) | A kind of 12 meters of inverted arch and filling are staggered construction bridge | |
CN117071383A (en) | Auxiliary positioning guide device for grouting drilling | |
CN107938694A (en) | Gravity type water jetting at high pressure percussion mechanism and its help heavy method | |
CN201539278U (en) | Filling formwork support | |
CN203498848U (en) | Light-weight well point downcast pipe hole forming device | |
CN206655676U (en) | A kind of down-hole plugging device of uncoupling plunger tubing pump snubbing serving | |
CN206721868U (en) | A kind of drain bar piling machine stake mouth | |
CN215332937U (en) | Sealed anchor rope that possesses integrated configuration ends thick liquid stopper | |
CN215169845U (en) | Nitrogen foam ground reversing continuous sand washing system | |
CN202170778U (en) | Even-pressure super-long grouting pipe capable of refluxing | |
CN204062016U (en) | A kind of towed underground water draws water and recharges dual-use manual valve | |
CN204002688U (en) | Borehole sealing device | |
CN204152475U (en) | Layer-through drilling list pouch hole sealing device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190503 Termination date: 20190903 |