CN206721868U - A kind of drain bar piling machine stake mouth - Google Patents
A kind of drain bar piling machine stake mouth Download PDFInfo
- Publication number
- CN206721868U CN206721868U CN201720378235.3U CN201720378235U CN206721868U CN 206721868 U CN206721868 U CN 206721868U CN 201720378235 U CN201720378235 U CN 201720378235U CN 206721868 U CN206721868 U CN 206721868U
- Authority
- CN
- China
- Prior art keywords
- drain bar
- pedestal
- stake mouth
- sleeve pipe
- piling machine
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Underground Or Underwater Handling Of Building Materials (AREA)
Abstract
The utility model discloses a kind of drain bar piling machine stake mouth, including stake mouth main body, sleeve pipe and drain bar, the upper end of the stake mouth main body is installed with pedestal, inner connecting tube is provided with the pedestal, the upper end of the inner connecting tube is provided with hook, the drain bar is connected with each other with hook, the upper surface of the pedestal sets fluted, described sleeve pipe is socketed on groove, mud guard is provided with the outside of the groove, connection chain is connected with by fixture in described sleeve pipe, one end of the connection chain is fixedly connected with pedestal, the lower end of the pedestal is installed with drill bit, spiral drill lip is provided with the drill bit, the both sides of the drill bit are provided with auxiliary sword.The drain bar piling machine stake mouth structure is simple, and practicality is high, can effectively reduce the rate of rewinding, and stake mouth can be used for multiple times, prolonged mechanical service life.
Description
Technical field
Draining sheet pile machine technical field is the utility model is related to, specially a kind of drain bar piling machine stake mouth.
Background technology
Drain bar piling machine is mainly used in coastal treatment of soft foundation, the construction field such as reclaim fields from the sea.Column uses well cabinet frame knot
Structure, there is the characteristics of in light weight, intensity is high;Chassis running gear uses support steel wheel, have it is simple in construction, it is easy to maintenance, turn
The advantages that building site is flexibly convenient is moved, and with the double effects for making plastic draining sheet pile machine and sand wick stake machine, it is particularly suitable
Used in coastal area of china each department, it is deep to be welcome by user, but to rewind rate higher for existing piling machine, generally use deepens to insert
Plate, or method that stake mouth is stayed in soil together with drain bar adjust.
Utility model content
The purpose of this utility model is to provide a kind of drain bar piling machine stake mouth, to solve to propose in above-mentioned background technology
The problem of.
To achieve the above object, the utility model provides following technical scheme:A kind of drain bar piling machine stake mouth, including stake
Mouth main body, sleeve pipe and drain bar, the upper end of the stake mouth main body are installed with pedestal, inner connecting tube are provided with the pedestal,
The upper end of the inner connecting tube is provided with hook, and the drain bar is connected with each other with hook, and the upper surface of the pedestal is provided with recessed
Groove, described sleeve pipe are socketed on groove, and mud guard is provided with the outside of the groove, is connected in described sleeve pipe by fixture
There is connection chain, one end of the connection chain is fixedly connected with pedestal, and the lower end of the pedestal is installed with drill bit, described
Spiral drill lip is provided with drill bit, the both sides of the drill bit are provided with auxiliary sword.
Preferably, fastening bolt is symmetrically installed with the side wall of the pedestal, with being connected the connection of chain on the pedestal
Place is installed with breakthrough sword.
Preferably, the bottom of the drain bar is " V " font structure, and the drain bar is socketed in the inner chamber of sleeve pipe.
Preferably, the hook is L-shaped structure.
Compared with prior art, the beneficial effects of the utility model are:The drain bar piling machine stake mouth structure is simple, practical
Property it is high, drain bar is flexibly connected with stake mouth, and be arranged on cannula cavity, makes it when plugging, more smoothly, avoid underground
The resistance of mud, reduces the rate of rewinding, and avoids the problem of returning slurry, passes through the design of spiral drill lip on drill bit and auxiliary sword
Structure is more favorable for driving piles, and improves efficiency, and the setting by breaking through sword enables it to reduce resistance when stake mouth gos up,
More smooth, in lifting process, due to being provided with longer connection chain, drain bar exposed length is longer, soft with surrounding
Native frictional resistance increase, it can thus play a part of reducing rewinding, and set stake mouth may be reused.
Brief description of the drawings
Fig. 1 is the utility model overall structure diagram;
Fig. 2 is the utility model stake mouth structure schematic diagram;
Fig. 3 is the utility model base construction schematic diagram.
In figure:Sword, 5 drill bits, 6 spiral drill lips, 7 mouth main bodys, 8 bases are broken through in 1 sleeve pipe, 2 fixtures, 3 connection chains, 4
Seat, 9 inner connecting tubes, 10 hooks, 11 auxiliary swords, 12 mud guards, 13 grooves, 14 drain bars, 15 fastening bolts.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out
Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made
The every other embodiment obtained, belong to the scope of the utility model protection.
, it is necessary to explanation in this practical description, the orientation of instruction such as term " vertical ", " on ", " under ", " level " or
Person's position relationship is based on orientation shown in the drawings or position relationship, is for only for ease of and describes this practicality and simplify to describe,
Rather than instruction either implies that signified device or element must have specific orientation, with specific azimuth configuration and behaviour
Make, therefore it is not intended that the limitation practical to this.
In this practical description, it is also necessary to explanation, unless otherwise clear and definite regulation and limitation, term " setting ", " peace
Dress ", " connected ", " connection " should be interpreted broadly, for example, it may be fixedly connected or be detachably connected, or integratedly
Connection, can be mechanical connection or electrical connection, can be directly connected to or be connected by intermediary, can
To be the connection of two element internals.For the ordinary skill in the art, can understand as the case may be above-mentioned
Concrete meaning of the term in this practicality.
Fig. 1-3 are referred to, the utility model provides a kind of technical scheme:A kind of drain bar piling machine stake mouth, including stake mouth
Main body 7, sleeve pipe 1 and drain bar 14, the upper end of the stake mouth main body 7 are installed with pedestal 8, right in the side wall of the pedestal 8
Title is provided with fastening bolt 15, is that structure more fastens, increases the service life, inner connecting tube 9 is provided with the pedestal 8, described
The upper end of inner connecting tube 9 is provided with hook 10, and the hook 10 is L-shaped structure, de- with drain bar 14 when being more favorable for
From the drain bar 14 is connected with each other with hook 10, and the bottom of the drain bar 14 is " V " font structure, is easy to connect, described
Drain bar 14 is socketed in the inner chamber of sleeve pipe 1, and the upper surface of the pedestal 8 sets fluted 13, and described sleeve pipe 1 is socketed in groove
On 13, the outside of the groove 13 is provided with mud guard 12, prevents mud from filling into sleeve pipe 1, passes through fixture in described sleeve pipe 1
2 be connected with connection chain 3, for the stake mouth body 7 that gos up, on the pedestal 8 be connected the junction of chain 3 be installed with it is prominent
Broken sword 4, beneficial to rise, one end of the connection chain 3 is fixedly connected with pedestal 8, and the lower end of the pedestal 8 is installed with brill
First 5, spiral drill lip 6 is provided with the drill bit 5, the both sides of the drill bit 5 are provided with auxiliary sword 11, improve piling efficiency.
Operation principle:In use, being sunk after piling machine is in place by vibration hammer alignment receptacles position, drain bar 14 is from sleeve pipe 1
Interior pass through is connected with the hook 10 in stake mouth main body 7, and sleeve pipe 1 withstands a mouth and drain bar 14 is inserted into design embedded depth, pulls up
After sleeve pipe 1, under the drive of connection chain 3, stake mouth main body 7 starts inclination and lifted, and hook 10 separates with drain bar 14, is rubbing
In the presence of wiping power, drain bar 14 stands in underground, and sleeve pipe 1 returns to ground with stake mouth body 7, starts the next plate of drain bar 14.
While there has been shown and described that embodiment of the present utility model, for the ordinary skill in the art,
It is appreciated that these embodiments can be carried out with a variety of changes in the case where not departing from principle of the present utility model and spirit, repaiied
Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.
Claims (4)
1. a kind of drain bar piling machine stake mouth, including stake mouth main body (7), sleeve pipe (1) and drain bar (14), it is characterised in that:Institute
State a upper end for mouth main body (7) and be installed with pedestal (8), inner connecting tube (9), the inner connecting tube are provided with the pedestal (8)
(9) upper end is provided with hook (10), and the drain bar (14) is connected with each other with hook (10), the upper surface of the pedestal (8)
Set fluted (13), described sleeve pipe (1) is socketed on groove (13), and mud guard is provided with the outside of the groove (13)
(12) connection chain (3), one end of the connection chain (3) and pedestal, are connected with by fixture (2) in described sleeve pipe (1)
(8) it is fixedly connected, the lower end of the pedestal (8) is installed with drill bit (5), and spiral drill lip is provided with the drill bit (5)
(6), the both sides of the drill bit (5) are provided with auxiliary sword (11).
A kind of 2. drain bar piling machine stake mouth according to claim 1, it is characterised in that:In the side wall of the pedestal (8)
It is symmetrically installed with fastening bolt (15), breaks through sword (4) with being connected the junction of chain (3) and being installed with the pedestal (8).
A kind of 3. drain bar piling machine stake mouth according to claim 1, it is characterised in that:The bottom of the drain bar (14)
For " V " font structure, the drain bar (14) is socketed in the inner chamber of sleeve pipe (1).
A kind of 4. drain bar piling machine stake mouth according to claim 1, it is characterised in that:The hook (10) is " L " type
Structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720378235.3U CN206721868U (en) | 2017-04-12 | 2017-04-12 | A kind of drain bar piling machine stake mouth |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720378235.3U CN206721868U (en) | 2017-04-12 | 2017-04-12 | A kind of drain bar piling machine stake mouth |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206721868U true CN206721868U (en) | 2017-12-08 |
Family
ID=60504588
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720378235.3U Expired - Fee Related CN206721868U (en) | 2017-04-12 | 2017-04-12 | A kind of drain bar piling machine stake mouth |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206721868U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108589692A (en) * | 2018-03-29 | 2018-09-28 | 中冶成都勘察研究总院有限公司 | A kind of novel drainage belt board-plugging device conduit device |
CN109024547A (en) * | 2018-10-08 | 2018-12-18 | 中铁六局集团广州工程有限公司 | The shoe of oscillatory type board-plugging device and plastic draining board insert mechanism |
-
2017
- 2017-04-12 CN CN201720378235.3U patent/CN206721868U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108589692A (en) * | 2018-03-29 | 2018-09-28 | 中冶成都勘察研究总院有限公司 | A kind of novel drainage belt board-plugging device conduit device |
CN109024547A (en) * | 2018-10-08 | 2018-12-18 | 中铁六局集团广州工程有限公司 | The shoe of oscillatory type board-plugging device and plastic draining board insert mechanism |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210086275U (en) | Double-wall hollow open caisson foundation | |
CN205369265U (en) | Accessible internal stay draws formula supporting construction that stands vertically outward in hole | |
CN102182180B (en) | Rotary extrusion sleeve anchor rod and construction method thereof | |
CN206721868U (en) | A kind of drain bar piling machine stake mouth | |
CN208701697U (en) | A kind of narrow foundation trench adjustable supporting device | |
CN203584444U (en) | Efficient and simple roofbolter | |
CN103321474B (en) | Hole-drilling pole-erecting vehicle | |
CN201802310U (en) | Excavation drilling machine | |
CN109252809A (en) | A kind of 10KV electric power transmission line foundation excavation device | |
CN210888992U (en) | Mining temporary support device | |
CN212506282U (en) | Deep foundation pit supporting device | |
CN207362864U (en) | A kind of basis for electric power pylon | |
CN201915839U (en) | Drilling tool of salvage rotary drilling rig | |
CN206681002U (en) | A kind of complicated geological soil layer Self-drilling hollow grouting anchoring-bolt | |
CN214366192U (en) | Mine tunnel roof infiltration drainage device | |
CN111576440B (en) | Deep foundation pit supporting bar planting hanging net fixing device | |
CN209385057U (en) | A kind of compound big diameter borehole structure | |
CN209323504U (en) | A kind of continuous underground wall structure | |
CN204676536U (en) | A kind of pile driver of adjustable hammering height | |
CN208870044U (en) | Support system with underground horizontal support | |
CN201747260U (en) | Double-drill pipe well drill rig | |
CN201908316U (en) | Annular cast-in-place concrete sinking well protection wall with plastic mould cavity and steel ribs | |
CN213596986U (en) | Steel sheet pile foundation pit supporting structure for deep foundation pit | |
CN205954609U (en) | High frequency compaction grooving bridge type ground is wall construction professional equipment even | |
CN207420452U (en) | Multi-functional reverse circulation hydraulic submersible drilling machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171208 |