CN203498848U - Light-weight well point downcast pipe hole forming device - Google Patents

Light-weight well point downcast pipe hole forming device Download PDF

Info

Publication number
CN203498848U
CN203498848U CN201320544899.4U CN201320544899U CN203498848U CN 203498848 U CN203498848 U CN 203498848U CN 201320544899 U CN201320544899 U CN 201320544899U CN 203498848 U CN203498848 U CN 203498848U
Authority
CN
China
Prior art keywords
pipe
downcomer
downcast
well point
forming device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201320544899.4U
Other languages
Chinese (zh)
Inventor
刘刚
刘晓军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Construction Group Co Ltd
Original Assignee
China Railway Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Construction Group Co Ltd filed Critical China Railway Construction Group Co Ltd
Priority to CN201320544899.4U priority Critical patent/CN203498848U/en
Application granted granted Critical
Publication of CN203498848U publication Critical patent/CN203498848U/en
Anticipated expiration legal-status Critical
Withdrawn - After Issue legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

The utility model relates to a light-weight well point downcast pipe hole forming device, which comprises a downcast pipe and a hammering sinking device matched with the downcast pipe to be used, wherein the top end of the downcast pipe is provided with an opening, water penetration holes are distributed at the lower part of the downcast pipe, the bottom end of the downcast pipe is a sealed end, the hammering sinking device comprises a hammering device and an air compressor, and a pressure hose is connected between the air compressor and the hammering device. The light-weight well point downcast pipe hole forming device has the beneficial effects that the structure is simple, the cost is low, the use is convenient, the well completion is fast, the light-weight well point downcast pipe hole forming device can also be used in a well forming region with hole punching inconvenience, the downcast pipe is utilized as a water pumping pipe and a soil penetrating hole forming protecting wall, one pipe has two purposes, and the pipe body meets the requirements of vacuum water pumping and soil penetrating intensity stability.

Description

A kind of Application of light well point precipitation pipe hole-forming device
Technical field
The utility model relates to technical field of construction, relates in particular to a kind of Application of light well point precipitation pipe hole-forming device.
Background technology
At present, well-points dewatering pore-forming generally adopts impact type or rotary drill pore-forming.Impact type is to utilize high-pressure hydraulic pump, by flexible pipe, is connected with the steel pipe of a Gent system, and steel tube end part is provided with hole for water spraying, by two hand-held steel pipes of operator, in header position, twitched up and down, until pore-forming, depth of pore forming is generally dark than chimney filter, should be noted that jet water spout vertically inserts in water during punching, and swing up and down about doing, after pore-forming, to extract immediately jet water spout, insert downcomer, in order to avoid cave in, complicated operation, pore-forming is slow.And utilize the similar pile foundation construction of slewing drilling machine pore-forming, and needing mud pit or place, machinery requires relatively high.
Utility model content
The purpose of this utility model is to provide a kind of Application of light well point precipitation pipe hole-forming device, the problems referred to above that exist to solve prior art.
The purpose of this utility model is to be achieved through the following technical solutions:
An Application of light well point precipitation pipe hole-forming device, comprises downcomer and the hammering sinking device being used in conjunction with, and described downcomer top is provided with opening, and downcomer bottom is distributed with permeable hole, and downcomer bottom is blind end; Described hammering sinking device comprises hammer and air compressor, between air compressor and described hammer, is connected with pressure hose.
Further, described permeable hole is plum blossom-shaped distribution.
Further, the blind end of described downcomer bottom is conical.
Application of light well point precipitation pipe hole forming method comprises the following steps:
1) according to engine request, prepare downcomer;
2) utilize external force strong rammer downcomer to bury: to use air compressor as dynamic power machine, with hammer, downcomer is hammered in the soil body, between air compressor and hammer, by flexible pipe, be connected, hammer directly acts on downcomer, operating personnel's operation is on scaffold, and scaffold is selected door-type scaffold platform;
3) utilize water under high pressure to carry out well-flushing to downcomer: with flexible pipe, inserts in downcomer, utilize water under high pressure to pour into downcomer, and then groundwater abstraction is with the water outlet of tiny disturbed soil particle, repeatedly operation until the water yield evenly or go out clear water;
4) adopt rubber hose to be connected to house steward each downcomer, with vacuum pump, try to take out.
The beneficial effects of the utility model are: simple in structure, cheap, easy to use, become well rapid, being not easy to punching becomes well area also can use, utilize downcomer to be used as drinking-water pipe and the hole retaining wall that buries, a pipe is dual-purpose, and body meets the vacuum strength stability requirement of drawing water and bury.
Accompanying drawing explanation
With reference to the accompanying drawings the utility model is described in further detail below.
Fig. 1 is the structural representation of Application of light well point precipitation pipe hole-forming device described in the utility model embodiment.
In figure:
1, downcomer; 2, opening; 3, permeable hole; 4, hammer; 5, air compressor; 6, pressure hose; 7, door-type scaffold.
The specific embodiment
As shown in Figure 1, Application of light well point precipitation pipe hole-forming device described in the utility model embodiment, comprises downcomer 1 and the hammering sinking device being used in conjunction with, and described downcomer 1 top is provided with opening 2, downcomer 1 bottom is distributed with permeable hole 3, and downcomer 1 bottom is blind end; Described hammering sinking device comprises hammer 4 and air compressor 5, between air compressor 5 and described hammer 4, is connected with pressure hose 6; Described permeable hole 3 is plum blossom-shaped and distributes; It is conical that the blind end of described downcomer 1 bottom is.
Application of light well point precipitation pipe hole forming method described in the utility model embodiment, comprises the following steps:
1) according to engine request, prepare downcomer: be about 6m, diameter 48.3mm, wall thickness 3.5mm, is drilled with the permeable hole of spacing 100mm quincuncial arrangement in the 0.7m of bottom, and the taper shape of sealing is made in downcomer lower end.
2) use air compressor (75m3/min) as dynamic power machine, with special hammer, downcomer is hammered in the soil body, between air compressor and hammer, by diameter 50mm flexible pipe, be connected, hammer directly acts on downcomer, operating personnel's operation on scaffold, the protection of taking care during operation.
3) with the PVC flexible pipe of diameter 32 or 25, inserts in the welded steel pipe downcomer of being driven underground, utilize water under high pressure to pour into downcomer, and then groundwater abstraction is with the water outlet of tiny disturbed soil particle, repeatedly operation until the water yield evenly or go out clear water.
4) between downcomer and house steward, adopt L=1.2m, the rubber hose of Φ 40 connects, and tighten with iron wire at two, smears yellow mud outward, with anti-gas-leak, finally connects vacuum pump and try to take out.
Downcomer 1 adopts 6 meters of above welded steel pipes of left and right Φ 48.3 * 3.0mm wall thickness, is drilled with the steel pipe of permeable hole in the 0.7m of bottom, permeable hole spacing 100mm, and quincunx pore-forming, the taper shape that sealing is made in steel pipe lower end is convenient to hammer.Hammer 4 directly acts on downcomer 1, with the air compressor 5 compressed air impulse forces that adopt 75 to 150kw, be converted into the power that 1 hammering is sunk to downcomer, downcomer 1 use hammer 4 hammerings are buried, realization is suppressed downcomer and is buried and get rid of without mud, without big machinery, operate, use door-type scaffold 7 as the support that hammers of downcomer 1, the high about 5m of frame simultaneously.
Washing well process is because downcomer 1 hammering is buried in process, in downcomer 1, may have silt etc. and infiltrate inside, and the downcomer original soil layer construction balance of disturbance of burying in addition, unclear hole can affect later stage outlet effect.The sebific duct of diameter 30mm is inserted to downcomer 1 bottom and carry out water filling cleaning, until flow out clear water, should clean by root, avoid occurring " extremely pipe ".
When examination is taken out, the effect of vacuum pump is to provide negative pressure underground water in the soil body is retracted to earth's surface by downcomer 1, connecting hose, house steward, reach the effect of dewatering, the vacuum of general well point system should remain on 55.3 ~ 66.7kPa, pressure should remain on 0.16MPa, herein because vacuum pump provides vacuum ability reason, the general Application of light well point precipitation degree of depth only has 6 ~ 9m, cannot extract dark water out again.
The utility model is not limited to above-mentioned preferred forms; anyone can draw other various forms of products under enlightenment of the present utility model; no matter but do any variation in its shape or structure; every have identical with a application or akin technical scheme, within all dropping on protection domain of the present utility model.

Claims (3)

1. an Application of light well point precipitation pipe hole-forming device, comprise downcomer (1) and the hammering sinking device being used in conjunction with, it is characterized in that: described downcomer (1) top is provided with opening (2), downcomer (1) bottom is distributed with permeable hole (3), and downcomer (1) bottom is blind end; Described hammering sinking device comprises hammer (4) and air compressor (5), between air compressor (5) and described hammer (4), is connected with pressure hose (6).
2. according to the Application of light well point precipitation pipe hole-forming device described in claim 1, it is characterized in that: the permeable hole that is drilled with spacing 100mm quincuncial arrangement in the long 6m of described downcomer (1), diameter 48.3mm, wall thickness 3.5mm and bottom 0.7m.
3. according to the Application of light well point precipitation pipe hole-forming device described in claim 2, it is characterized in that: the blind end of described downcomer (1) bottom is conical.
CN201320544899.4U 2013-09-03 2013-09-03 Light-weight well point downcast pipe hole forming device Withdrawn - After Issue CN203498848U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201320544899.4U CN203498848U (en) 2013-09-03 2013-09-03 Light-weight well point downcast pipe hole forming device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201320544899.4U CN203498848U (en) 2013-09-03 2013-09-03 Light-weight well point downcast pipe hole forming device

Publications (1)

Publication Number Publication Date
CN203498848U true CN203498848U (en) 2014-03-26

Family

ID=50329840

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201320544899.4U Withdrawn - After Issue CN203498848U (en) 2013-09-03 2013-09-03 Light-weight well point downcast pipe hole forming device

Country Status (1)

Country Link
CN (1) CN203498848U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485357A (en) * 2013-09-03 2014-01-01 中铁建设集团有限公司 Light well point precipitation pipe pore-forming device and method thereof
CN106245661A (en) * 2016-08-28 2016-12-21 神翼航空器科技(天津)有限公司 Buried pipe and the method burying buried pipe underground thereof
CN106284388A (en) * 2016-08-28 2017-01-04 神翼航空器科技(天津)有限公司 Well casing and the method burying well casing underground thereof

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103485357A (en) * 2013-09-03 2014-01-01 中铁建设集团有限公司 Light well point precipitation pipe pore-forming device and method thereof
CN106245661A (en) * 2016-08-28 2016-12-21 神翼航空器科技(天津)有限公司 Buried pipe and the method burying buried pipe underground thereof
CN106284388A (en) * 2016-08-28 2017-01-04 神翼航空器科技(天津)有限公司 Well casing and the method burying well casing underground thereof
CN106284388B (en) * 2016-08-28 2019-04-05 神翼航空器科技(天津)有限公司 The method of well casing and its embedded well casing

Similar Documents

Publication Publication Date Title
CN102330424B (en) Vacuum preloading consolidation method for duplex vacuum tube well of blowing filling soft soil
CN103883796B (en) Silt particle mud district hand pick formula jacking construction device and method
CN101368386A (en) Pile extractor and construction method for pile extraction
CN203498848U (en) Light-weight well point downcast pipe hole forming device
CN201074340Y (en) Pile-drawing machine
CN202176819U (en) Pressure balance pipe jacking device head
CN206204972U (en) A kind of prefabricated tubular pile as well-points dewatering
CN103485357B (en) A kind of Application of light well point precipitation pipe hole-forming device and method thereof
CN102767174A (en) Dynamic and static water-discharging vibration method
CN104975611B (en) The heavy of the well-points dewatering pipe of liquid soil layer sets device and heavy equipment, method
CN203755310U (en) Pile washing nozzle of self-elevating platform pile shoe
CN103615014B (en) A kind of dewatering device of soft soil foundation pit and using method thereof
CN208472692U (en) A kind of inclinometer pipe protective device for dam facing pipe connection method
CN112195945A (en) Deep foundation pit construction method for keeping groundwater dynamically balanced
CN203583501U (en) Deep-layer shear resistant device capable of preventing rock sliding
CN202546006U (en) High pressure-resistant sealing device used for intermediate jacking station of pipe jacking equipment
CN102116019A (en) Method for rapidly treating soft foundation through high vacuum densification
CN201232184Y (en) Pile-formation device of steel tube breast wall filling pile with soil drawn out drily
CN205348204U (en) Light well point precipitation system
CN203891045U (en) Leakage blocking and grouting device between deep foundation pit fender posts
CN202450511U (en) Grouting device
CN208885185U (en) A kind of jetting drilling hole device
CN109356211B (en) High-rise deviation-correcting drainage well construction device, relief well construction device and deviation correcting method
CN102758434A (en) Pile-sinking device for centrally driving prestressed centrifugal pipe pile (square pile) and novel pile-sinking method thereof
CN103274329B (en) A kind of top draws jack for the construction method of pile-anchor retaining

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20140326

Effective date of abandoning: 20150909

AV01 Patent right actively abandoned

Granted publication date: 20140326

Effective date of abandoning: 20150909

RGAV Abandon patent right to avoid regrant