CN208633283U - The connection structure of the integral prefabricated partition plate of cantilever stair - Google Patents

The connection structure of the integral prefabricated partition plate of cantilever stair Download PDF

Info

Publication number
CN208633283U
CN208633283U CN201821208712.2U CN201821208712U CN208633283U CN 208633283 U CN208633283 U CN 208633283U CN 201821208712 U CN201821208712 U CN 201821208712U CN 208633283 U CN208633283 U CN 208633283U
Authority
CN
China
Prior art keywords
prefabricated partition
partition board
stair
embedded
built
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821208712.2U
Other languages
Chinese (zh)
Inventor
李奎
开前正
张磊
莫雨秋
陈纯刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China City Investment Group Sixth Engineering Bureau Co Ltd
Original Assignee
China City Investment Group Sixth Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China City Investment Group Sixth Engineering Bureau Co Ltd filed Critical China City Investment Group Sixth Engineering Bureau Co Ltd
Priority to CN201821208712.2U priority Critical patent/CN208633283U/en
Application granted granted Critical
Publication of CN208633283U publication Critical patent/CN208633283U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Steps, Ramps, And Handrails (AREA)

Abstract

The utility model gives a kind of connection structure of integral prefabricated partition plate of cantilever stair;Including transversal connecting assembly, several vertical connecting assemblies;The pre- prefabricated partition board of nuzzling of galvanized steel plain sheet a part of transversal connecting assembly, galvanized steel plain sheet another part stretch out outside prefabricated partition board, and two stair stringer built-in fittings are embedded in advance respectively in the stair stringer of two sides, fixed between two stair stringer built-in fittings and galvanized steel plain sheet;Two embedded nuts of vertical connecting assembly are embedded in advance in two prefabricated partition boards, and connection bolt passes through junction steel plate and embedded nut cooperates.The connection structure improves the connection type of prefabricated partition board, realizes the full prefabrication and assembly construction between cantilever stair.The utility model gives a kind of construction method for realizing above-mentioned connection structure, comprising: manufacture prefabricated partition board;Built-in fitting fabrication and installation in stair stringer;Hoisting prefabricated partition plate;Plate stitch processing;Pea gravel concreten is poured to connecting portion.This construction party rule has the advantages that construction efficiency height, stable structure, quality controllable.

Description

The connection structure of the integral prefabricated partition plate of cantilever stair
Technical field
The utility model relates to a kind of connection structures of the integral prefabricated partition plate of cantilever stair.
Background technique
For the requirement for meeting building fire protection specification, fire partition, usual situation should be set between general two cantilever stairs This lower partition wall is formed by poured in place concrete or wall of laying bricks.In fabricated assembly overall structure, use precast reinforced Concrete staircase, if using the above method again, live formwork supporting plate, assembling reinforcement, casting concrete can reduce the construction of staircase Efficiency influences stair construction period.Scene builds partition wall and is also required to plastering painting, increases artificial and material, and quality is difficult to control. It is easy to cause finished product stair to damage simultaneously, is unfavorable for the popularization and application of precast stair.
Utility model content
The technical problem to be solved by the utility model is to provide a kind of structures, and simple, rationally distributed cantilever stair is whole The connection structure of prefabricated partition board.
In order to solve the above technical problems, the utility model provides a kind of connection knot of integral prefabricated partition plate of cantilever stair Structure;
Including at least for connecting prefabricated partition board and stair stringer transversal connecting assembly, it is several for it is fixed any up and down The vertical connecting assembly of contiguous prefabricated partition plate;
The transversal connecting assembly includes two galvanized steel plain sheets and two stair stringer built-in fittings, and two galvanized steel plain sheet settings exist Prefabricated partition board two sides upper end, the pre- prefabricated partition board of nuzzling of galvanized steel plain sheet a part, described galvanized steel plain sheet another part are stretched Out outside prefabricated partition board, two stair stringer built-in fittings respectively correspond the stair that galvanized steel plain sheet position is embedded in prefabricated partition board two sides in advance In beam, it is fixedly connected between two stair stringer built-in fittings and galvanized steel plain sheet;
The vertical connecting assembly includes junction steel plate, two embedded nuts and two connection bolts, two embedded nuts It is embedded in advance in upper and lower two neighboring prefabricated partition board respectively, two connection bolts are each passed through junction steel plate and match with embedded nut It closes.
With such a structure, the connection structure of the integral prefabricated partition plate of this cantilever stair improves prefabricated partition board Connection type installs prefabricated partition board, eliminates pouring and the masonry of partition wall for stair division wall beam after precast stair installation Journey realizes the full prefabrication and assembly construction between cantilever stair, and structure is safe and reliable, saves manually, improves installation effectiveness.
For the clearer technology contents for understanding the utility model, below by the integral prefabricated partition plate of this cantilever stair Connection structure is referred to as this connection structure.
The thickness of the prefabricated partition board of this connection structure is more than or equal to 100mm;With such a structure, prefabricated partition board Thickness meet the design needs of this connection structure.
This connection structure further includes lifting built-in fitting, and lifting built-in fitting is embedded in prefabricated partition board, on prefabricated partition board End face is preset with lifting groove, and lifting built-in fitting upper end is in lifting groove;With such a structure, facilitate prefabricated partition wall Plate lifting.
This connection structure further includes elevation control assembly, and elevation control assembly includes high process control nut and high process control spiral shell Bolt, high process control nut are embedded in prefabricated partition board, high process control bolt and high process control nut cooperate and stretch out it is prefabricated every Wallboard upper surface;With such a structure, high process control bolt is screwed into the high process control nut of lower layer's prefabricated partition board, can To achieve the purpose that control this layer of prefabricated partition board bottom surface absolute altitude.
It is sealed on the outside of the junction steel plate of this connection structure using stainless steel box;With such a structure, stainless steel box can To play a protective role to junction steel plate.
The galvanized steel plain sheet of this connection structure is having a size of 600mm*100mm*10mm;With such a structure, junction steel plate Meet the design needs of this connection structure.
Detailed description of the invention
Fig. 1 is the installation status diagram of this connection structure embodiment.
Fig. 2 is the portion the A enlarged drawing of Fig. 1.
Fig. 3 is the portion the B enlarged drawing of Fig. 1.
Fig. 4 is the portion the C enlarged drawing of Fig. 1.
Fig. 5 is the installation condition sectional view of vertical connecting assembly in this connection structure embodiment.
Specific embodiment
As shown in Fig. 1 to 5
This connection structure includes that the transversal connecting assembly of prefabricated partition board 5 and stair stringer 6, two groups for fixing for connecting Vertical connecting assembly, two groups of elevation control assemblies and the two lifting built-in fittings 3 of any neighbouring prefabricated partition board 5;
Transversal connecting assembly includes two galvanized steel plain sheets 11 and two stair stringer built-in fittings 12, and two galvanized steel plain sheets 11 are arranged In the left and right end face upper end of prefabricated partition board 5, described 11 a part of galvanized steel plain sheet is nuzzled in prefabricated partition board 5 in advance, the galvanized steel 11 another part of plate stretches out outside prefabricated partition board 5, and galvanized steel plain sheet 11 is having a size of 600mm*100mm*10mm.
11 position of galvanized steel plain sheet of the corresponding prefabricated partition board 5 of stair stringer 6 is equipped with stair stringer built-in fitting 12, stair stringer built-in fitting 12 a part are embedded in stair stringer 6, and 12 another part of stair stringer built-in fitting stretches out 6 upside of stair stringer (in 6 upside of stair stringer Stair stringer built-in fitting 12 be angle bar shape), there are the opening that the galvanized steel plain sheet 11 for prefabricated partition board 5 protrudes into, two stair stringers It first passes through to be bolted between built-in fitting 12 and galvanized steel plain sheet 11 and be welded and fixed.
Any upper and lower two neighboring prefabricated partition board 5 is connected and fixed by two groups of vertical connecting assemblies, and two groups longitudinally connected Component or so distribution, every group of vertical connecting assembly includes 21, two embedded nuts 22 of junction steel plate and two connection bolts 23, and two A embedded nut 22 is embedded in advance respectively in upper and lower two neighboring prefabricated partition board 5, and the threaded hole of embedded nut 22 extends to prefabricated On 5 front end face of partition plate, two connection bolts 23 are each passed through the reserved through-hole of junction steel plate 21 and are screwed into embedded nut 22 admittedly It is fixed, it is sealed on the outside of junction steel plate 21 using stainless steel box (not shown in FIG.).
Lifting built-in fitting 3 is embedded in prefabricated partition board 5, the default lifting groove 52 in 5 upper surface of prefabricated partition board, and lifting is pre- 3 upper end of embedded part is in lifting groove 52.
Elevation control assembly includes high process control nut 42 and high process control bolt 41, and high process control nut 42 is embedded in pre- In partition plate 5 processed, high process control bolt 41 cooperates with high process control nut 42 and stretches out 5 upper surface of prefabricated partition board.
It is specifically introduced in conjunction with this above-mentioned connection structure and realizes construction method, comprising the following steps:
(1) prefabricated partition board 5 is made:
It is preset with lifting groove 52 in 5 upper surface of prefabricated partition board, lifting built-in fitting 3 is embedded in prefabricated partition board 5, hangs It fills 3 upper end of built-in fitting to be in lifting slot, high process control nut 42 is embedded in prefabricated partition board 5, high process control nut 42 Threaded hole extends to 5 upper surface of prefabricated partition board, and the embedded nut 22 of the vertical connecting assembly is also embedded in prefabricated partition board 5 Interior, the threaded hole of embedded nut 22 extends to the front end face of prefabricated partition board 5, is equipped in the left and right end face upper end of prefabricated partition board 5 11 one end of galvanized steel plain sheet of the lap segment 51 of protrusion, transversal connecting assembly is protruded into the lap segment 51 of prefabricated partition board 5, and is plated Zinc steel plate 11 is welded and fixed with the framework of steel reinforcement inside prefabricated partition board 5, and 11 other end of galvanized steel plain sheet stretches out prefabricated partition board 5, Prefabricated partition board 5 other pour process and original prefabricated partition board 5 pour that process is consistent, the thickness of prefabricated partition board 5 is big In equal to 100mm;
(2) built-in fitting fabrication and installation in terraced beam:
11 position of galvanized steel plain sheet that every layer of stair stringer 6 all corresponds to prefabricated partition board 5 is equipped with stair stringer built-in fitting 12, stair 12 a part of beam built-in fitting is embedded in stair stringer 6, the stair stringer built-in fitting 12 in stair stringer 6 and 6 reinforcing bar of stair stringer Frame is fixed, and 12 another part of stair stringer built-in fitting stretches out outside stair stringer 6;
(3) hoisting prefabricated partition plate 5:
Prefabricated partition board 5 is lifted to designated position by lifting built-in fitting 3, it is program-controlled by high process control bolt 41 and height Nut 42 processed cooperates, and controls 5 bottom surface absolute altitude of this layer of prefabricated partition board, the galvanized steel plain sheet 11 and stair stringer 6 of 5 two sides of prefabricated partition board Stair stringer built-in fitting 12 be bolted fixed and weld;Two connection bolts 23 of the vertical connecting assembly, which pass through, to be connected Steel plate 21 is connect to cooperate with the embedded nut 22 in two neighbouring prefabricated partition boards 5;
(4) plate stitch is handled:
It is filled in the middle part of gap between any upper and lower adjacent prefabricated partition board 5 using polyphenyl 73,73 two sides of polyphenyl note 20mm*20mm sealant 72 is sealed using stainless steel box on the outside of junction steel plate 21;
(5) C30 microdilatancy pea gravel concreten 71, C30 is poured to galvanized steel plain sheet 11 and 12 junction position of stair stringer built-in fitting Microdilatancy pea gravel concreten 71 covers corresponding transversal connecting assembly.
Above-described is only a kind of embodiment of the utility model, it is noted that for the ordinary skill of this field For personnel, without departing from the principle of this utility model, several variations and modifications can also be made, these also should be regarded as Belong to the protection scope of the utility model.

Claims (6)

1. a kind of connection structure of the integral prefabricated partition plate of cantilever stair, it is characterised in that:
Including at least the transversal connecting assembly, several for fixed any neighbouring for connecting prefabricated partition board and stair stringer The vertical connecting assembly of prefabricated partition board;
The transversal connecting assembly includes two galvanized steel plain sheets and two stair stringer built-in fittings, and two galvanized steel plain sheets are arranged prefabricated Partition plate two sides upper end, the pre- prefabricated partition board of nuzzling of galvanized steel plain sheet a part, described galvanized steel plain sheet another part stretches out pre- Outside partition plate processed, two stair stringer built-in fittings respectively correspond the stair stringer that galvanized steel plain sheet position is embedded in prefabricated partition board two sides in advance It is interior, it is fixedly connected between two stair stringer built-in fittings and galvanized steel plain sheet;
The vertical connecting assembly includes junction steel plate, two embedded nuts and two connection bolts, two embedded nut difference It is embedded in upper and lower two neighboring prefabricated partition board in advance, two connection bolts are each passed through junction steel plate and embedded nut cooperates.
2. a kind of connection structure of the integral prefabricated partition plate of cantilever stair according to claim 1, it is characterised in that: described The thickness of prefabricated partition board is more than or equal to 100mm.
3. a kind of connection structure of the integral prefabricated partition plate of cantilever stair according to claim 1, it is characterised in that:
It further include lifting built-in fitting, lifting built-in fitting is embedded in prefabricated partition board, and prefabricated partition board upper surface is preset with lifting Groove, lifting built-in fitting upper end are in lifting groove.
4. a kind of connection structure of the integral prefabricated partition plate of cantilever stair according to claim 1, it is characterised in that:
It further include elevation control assembly, elevation control assembly includes high process control nut and high process control bolt, high process control spiral shell Mother is embedded in prefabricated partition board, and high process control bolt and high process control nut cooperate and stretch out prefabricated partition board upper surface.
5. a kind of connection structure of the integral prefabricated partition plate of cantilever stair according to claim 1, it is characterised in that:
It is sealed on the outside of junction steel plate using stainless steel box.
6. a kind of connection structure of the integral prefabricated partition plate of cantilever stair according to claim 1, it is characterised in that:
Galvanized steel plain sheet is having a size of 600mm*100mm*10mm.
CN201821208712.2U 2018-07-28 2018-07-28 The connection structure of the integral prefabricated partition plate of cantilever stair Active CN208633283U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821208712.2U CN208633283U (en) 2018-07-28 2018-07-28 The connection structure of the integral prefabricated partition plate of cantilever stair

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821208712.2U CN208633283U (en) 2018-07-28 2018-07-28 The connection structure of the integral prefabricated partition plate of cantilever stair

Publications (1)

Publication Number Publication Date
CN208633283U true CN208633283U (en) 2019-03-22

Family

ID=65740320

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821208712.2U Active CN208633283U (en) 2018-07-28 2018-07-28 The connection structure of the integral prefabricated partition plate of cantilever stair

Country Status (1)

Country Link
CN (1) CN208633283U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755974A (en) * 2018-07-28 2018-11-06 中城投集团第六工程局有限公司 The connection structure and construction method of the integral prefabricated partition plate of cantilever stair
CN111456740A (en) * 2019-10-12 2020-07-28 中国建筑股份有限公司 Prefabricated bearing middle partition wall structure of rectangular pipe jacking gallery and construction method thereof

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108755974A (en) * 2018-07-28 2018-11-06 中城投集团第六工程局有限公司 The connection structure and construction method of the integral prefabricated partition plate of cantilever stair
CN111456740A (en) * 2019-10-12 2020-07-28 中国建筑股份有限公司 Prefabricated bearing middle partition wall structure of rectangular pipe jacking gallery and construction method thereof
CN111456740B (en) * 2019-10-12 2022-02-11 中国建筑股份有限公司 Prefabricated bearing middle partition wall structure of rectangular pipe jacking gallery and construction method thereof

Similar Documents

Publication Publication Date Title
CN106013454B (en) Building and method of construction based on large spatial structure body and free-standing peripheral structure
RU2525407C2 (en) Design of form to make stairs and stair platforms, method to manufacture such form and method of its usage
CN102031866B (en) A kind of disassembly-free heat-insulation decoration formwork and installation method thereof
CN103374986B (en) A kind of multifunction combined light weight concrete construction curtain wall and preparation method thereof
CN108149819B (en) Integrated superposed outer wall of building bottom reinforcing area and production and construction method thereof
CN208633283U (en) The connection structure of the integral prefabricated partition plate of cantilever stair
CN107859206A (en) Pre-manufactured steel structure overlapped shear wall and its construction method
CN107401217A (en) A kind of beamless hollow floor chamber concrete-filled steel tube shear wall combined structure system and method
CN109235702B (en) Assembled double-steel-plate combined shear wall structure with ribs and construction method thereof
CN106948598A (en) A kind of aluminum alloy formwork system and its construction method for variable cross-section rectangular column
CN107989238A (en) A kind of cast-in-place sandwiched heat-preservation shear wall structure, assembled architecture and engineering method
CN106088493A (en) A kind of pin key connects mounting structure and the construction thereof of prefabricated bench
CN107143076A (en) A kind of Prefabricated stacking floor with side flanging and its construction method for being used to drop plate region
CN108755974A (en) The connection structure and construction method of the integral prefabricated partition plate of cantilever stair
CN109895239B (en) Fabricated concrete stair slow platform beam slab and construction method thereof
CN105040823A (en) Partition plate and floor beam connecting structure for scissors staircase and construction method of partition plate and floor beam connecting structure
CN207761103U (en) Prefabricated assembled concrete composite thermo-insulating wall board
CN114164977A (en) Method for combining construction of aluminum template and laminated slab
CN107237448B (en) The prefabricated interior fill concrete wallboard of one kind and its manufacturing method
CN204753834U (en) Partition plate of scissors stair and connection structure of floor roof beam
CN113123504A (en) Laminated floor slab with detachable additional rigidity device
CN102230339A (en) Prefabricated kitchen and construction and installation method thereof
CN111441796A (en) Shield tunnel segment and manufacturing method thereof
CN207878750U (en) A kind of laminated floor slab prefabricated board
CN106032705A (en) Integrated casting molding construction method of reinforced concrete floor system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PP01 Preservation of patent right

Effective date of registration: 20200717

Granted publication date: 20190322

PP01 Preservation of patent right
PD01 Discharge of preservation of patent

Date of cancellation: 20230717

Granted publication date: 20190322

PD01 Discharge of preservation of patent
PP01 Preservation of patent right

Effective date of registration: 20230717

Granted publication date: 20190322

PP01 Preservation of patent right