CN108755974A - The connection structure and construction method of the integral prefabricated partition plate of cantilever stair - Google Patents

The connection structure and construction method of the integral prefabricated partition plate of cantilever stair Download PDF

Info

Publication number
CN108755974A
CN108755974A CN201810850063.4A CN201810850063A CN108755974A CN 108755974 A CN108755974 A CN 108755974A CN 201810850063 A CN201810850063 A CN 201810850063A CN 108755974 A CN108755974 A CN 108755974A
Authority
CN
China
Prior art keywords
prefabricated partition
partition board
stair
built
embedded
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810850063.4A
Other languages
Chinese (zh)
Inventor
李奎
开前正
张磊
莫雨秋
陈纯刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China City Investment Group Sixth Engineering Bureau Co Ltd
Original Assignee
China City Investment Group Sixth Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China City Investment Group Sixth Engineering Bureau Co Ltd filed Critical China City Investment Group Sixth Engineering Bureau Co Ltd
Priority to CN201810850063.4A priority Critical patent/CN108755974A/en
Publication of CN108755974A publication Critical patent/CN108755974A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/41Connecting devices specially adapted for embedding in concrete or masonry
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/61Connections for building structures in general of slab-shaped building elements with each other
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/02Stairways; Layouts thereof

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Steps, Ramps, And Handrails (AREA)

Abstract

The present invention gives a kind of connection structures of the integral prefabricated partition plate of cantilever stair;Including transversal connecting assembly, several vertical connecting assemblies;The pre- prefabricated partition board of nuzzling of a galvanized steel plain sheet part of transversal connecting assembly, galvanized steel plain sheet another part stretch out outside prefabricated partition board, and two stair stringer built-in fittings are embedded in the stair stringer of both sides in advance respectively, fixed between two stair stringer built-in fittings and galvanized steel plain sheet;Two embedded nuts of vertical connecting assembly are embedded in advance in two prefabricated partition boards, and connection bolt passes through junction steel plate to coordinate with embedded nut.The connection structure improves the connection type of prefabricated partition board, realizes the full prefabrication and assembly construction between cantilever stair.The present invention gives a kind of construction method for realizing above-mentioned connection structure, including:Manufacture prefabricated partition board;Built-in fitting fabrication and installation in stair stringer;Hoisting prefabricated partition plate;Plate stitch processing;Pea gravel concreten is poured to connecting portion.This construction party rule has the advantages that construction efficiency height, stable structure, quality controllable.

Description

The connection structure and construction method of the integral prefabricated partition plate of cantilever stair
Technical field
The present invention relates to a kind of connection structures of the integral prefabricated partition plate of cantilever stair.
The present invention relates to a kind of construction methods of connection structure that realizing the integral prefabricated partition plate of cantilever stair.
Background technology
To meet the requirement of building fire protection specification, fire partition, normal conditions should be set between general two cantilever stairs This lower partition wall is formed by poured in place concrete or wall of laying bricks.In fabricated assembly overall structure, use precast reinforced Concrete staircase, if using the above method again, live formwork supporting plate, assembling reinforcement, casting concrete can reduce the construction of staircase Efficiency influences stair construction period.Scene builds partition wall by laying bricks or stones and is also required to plastering painting, increases artificial and material, and quality is difficult to control. It is easy to cause the damage of finished product stair simultaneously, is unfavorable for the popularization and application of precast stair.
Invention content
Technical problem to be solved by the invention is to provide a kind of cantilever stair simple in structure, rationally distributed is integral prefabricated The connection structure of partition plate.
The technical problem to be solved by the present invention is to also provide a kind of connection for realizing the integral prefabricated partition plate of cantilever stair The construction method of structure.
In order to solve the above technical problems, the present invention provides a kind of connection structures of the integral prefabricated partition plate of cantilever stair;
Including at least for connecting prefabricated partition board and stair stringer transversal connecting assembly, it is several for it is fixed arbitrary up and down The vertical connecting assembly of contiguous prefabricated partition plate;
The transversal connecting assembly includes two galvanized steel plain sheets and two stair stringer built-in fittings, and two galvanized steel plain sheet settings exist Prefabricated partition board both sides upper end, the pre- prefabricated partition board of nuzzling of a galvanized steel plain sheet part, described galvanized steel plain sheet another part are stretched Go out outside prefabricated partition board, two stair stringer built-in fittings correspond to the stair that galvanized steel plain sheet position is embedded in prefabricated partition board both sides in advance respectively In beam, it is fixedly connected between two stair stringer built-in fittings and galvanized steel plain sheet;
The vertical connecting assembly includes junction steel plate, two embedded nuts and two connection bolts, two embedded nuts It is embedded in advance respectively in upper and lower two neighboring prefabricated partition board, two connection bolts are each passed through junction steel plate and match with embedded nut It closes.
After such structure, the connection structure of the integral prefabricated partition plate of this cantilever stair improves prefabricated partition board Connection type installs prefabricated partition board, eliminates pouring for stair division wall beam and building by laying bricks or stones for partition wall after precast stair installation Journey realizes the full prefabrication and assembly construction between cantilever stair, and structure is safe and reliable, saves manually, improves installation effectiveness.
For the clearer technology contents for understanding the present invention, below by the connection of the integral prefabricated partition plate of this cantilever stair Structure is referred to as this connection structure.
The thickness of the prefabricated partition board of this connection structure is more than or equal to 100mm;After such structure, prefabricated partition board Thickness meet the design needs of this connection structure.
This connection structure further includes lifting built-in fitting, and lifting built-in fitting is embedded in prefabricated partition board, on prefabricated partition board End face is preset with lifting groove, and lifting built-in fitting upper end is in lifting groove;After such structure, facilitate prefabricated partition wall Plate lifts.
This connection structure further includes elevation control assembly, and elevation control assembly includes high process control nut and high process control spiral shell Bolt, high process control nut are embedded in prefabricated partition board, high process control bolt and high process control nut coordinate and stretch out it is prefabricated every Wallboard upper surface;After such structure, high process control bolt is screwed into the high process control nut of lower layer's prefabricated partition board, can To achieve the purpose that control this layer of prefabricated partition board bottom surface absolute altitude.
It is sealed using stainless steel box on the outside of the junction steel plate of this connection structure;After such structure, stainless steel box can To play a protective role to junction steel plate.
The galvanized steel plain sheet size of this connection structure is 600mm*100mm*10mm;After such structure, junction steel plate Meet the design needs of this connection structure.
In order to solve the above technical problems, the present invention also provides the companies for realizing the above-mentioned integral prefabricated partition plate of cantilever stair The construction method of binding structure, includes the following steps:
(1) prefabricated partition board is manufactured:
It is preset with lifting groove in prefabricated partition board upper surface, lifting built-in fitting is embedded in prefabricated partition board, and lifting is pre- Embedded part upper end is in lifting slot, and high process control nut is embedded in prefabricated partition board, and the threaded hole of high process control nut extends To prefabricated partition board upper surface, the embedded nut of the vertical connecting assembly is also embedded in prefabricated partition board, embedded nut Threaded hole extends to prefabricated partition board side wall, and a galvanized steel plain sheet part for transversal connecting assembly is nuzzled in prefabricated partition board in advance, institute It states galvanized steel plain sheet another part and stretches out prefabricated partition board upper outside;
(2) built-in fitting fabrication and installation in stair stringer:
A stair stringer built-in fitting part is embedded in every layer of stair stringer, stair stringer built-in fitting and stair in stair stringer Beam reinforcement cages are fixed, and stair stringer built-in fitting another part stretches out outside stair stringer;
(3) hoisting prefabricated partition plate:
Prefabricated partition board is lifted to designated position by lifting built-in fitting, passes through high process control bolt and high process control spiral shell Mother's cooperation, controls this layer of prefabricated partition board bottom surface absolute altitude, the galvanized steel plain sheet of prefabricated partition board both sides and the stair stringer of stair stringer are pre- Embedded part is bolted fixed and welds;Two connection bolts of the vertical connecting assembly pass through junction steel plate and are in upper Under embedded nut cooperation in adjacent two prefabricated partition boards;
(4) plate stitch is handled:
It is filled using polyphenyl in the middle part of gap between arbitrary upper and lower adjacent prefabricated partition board, 20mm* is noted in polyphenyl both sides 20mm fluid sealants, junction steel plate outside are sealed using stainless steel box;
(5) C30 microdilatancy pea gravel concretens are poured to galvanized steel plain sheet and stair stringer built-in fitting connecting portion, C30 microdilatancies are thin The corresponding transversal connecting assembly of stone concrete covering, completes construction operation.
After such method, prefabricated partition board and stair stringer is made to be obtained for specification, phase from pouring to connection construction Live formwork supporting plate, assembling reinforcement, casting concrete can reduce the construction efficiency of staircase than in the prior art, influence stair construction Period, scene build partition wall by laying bricks or stones and are also required to plastering painting, increase artificial and material, the uncontrollable deficiency of quality, and this scissors building The construction party rule of the connection structure of the integral prefabricated partition plate of ladder has construction efficiency height, stable structure, artificial and material cost Low, quality controllable advantage.
Description of the drawings
Fig. 1 is the installation status diagram of this connection structure embodiment.
Fig. 2 is the portions the A enlarged drawing of Fig. 1.
Fig. 3 is the portions the B enlarged drawing of Fig. 1.
Fig. 4 is the portions the C enlarged drawing of Fig. 1.
Fig. 5 is the installation condition sectional view of vertical connecting assembly in this connection structure embodiment.
Specific implementation mode
As shown in Fig. 1 to 5
This connection structure includes that the transversal connecting assembly of prefabricated partition board 5 and stair stringer 6, two groups for fixing for connecting Vertical connecting assembly, two groups of elevation control assemblies and the two lifting built-in fittings 3 of arbitrary neighbouring prefabricated partition board 5;
Transversal connecting assembly includes two galvanized steel plain sheets 11 and two stair stringer built-in fittings 12, and two galvanized steel plain sheets 11 are arranged In 5 left and right end face upper end of prefabricated partition board, 11 part of the galvanized steel plain sheet is nuzzled in prefabricated partition board 5 in advance, the galvanized steel 11 another part of plate stretches out outside prefabricated partition board 5, and 11 size of galvanized steel plain sheet is 600mm*100mm*10mm.
11 position of galvanized steel plain sheet that stair stringer 6 corresponds to prefabricated partition board 5 is equipped with stair stringer built-in fitting 12, stair stringer built-in fitting 12 parts are embedded in stair stringer 6, and 12 another part of stair stringer built-in fitting stretches out 6 upside of stair stringer (in 6 upside of stair stringer Stair stringer built-in fitting 12 be angle bar shape), there are the opening that the galvanized steel plain sheet 11 for prefabricated partition board 5 stretches into, two stair stringers It first passes through to be bolted between built-in fitting 12 and galvanized steel plain sheet 11 and be welded and fixed.
Arbitrary upper and lower two neighboring prefabricated partition board 5 is connected and fixed by two groups of vertical connecting assemblies, and two groups longitudinally connected Component or so be distributed, every group of vertical connecting assembly include 21, two embedded nuts 22 of junction steel plate and two connection bolts 23, two A embedded nut 22 is embedded in advance respectively in upper and lower two neighboring prefabricated partition board 5, and the threaded hole of embedded nut 22 extends to prefabricated On 5 front end face of partition plate, two connection bolts 23 are each passed through the reserved through-hole of junction steel plate 21 and are screwed into embedded nut 22 admittedly Fixed, 21 outside of junction steel plate is sealed using stainless steel box (not shown in FIG.).
Lifting built-in fitting 3 is embedded in prefabricated partition board 5, the default lifting groove 52 in 5 upper surface of prefabricated partition board, and lifting is pre- 3 upper end of embedded part is in lifting groove 52.
Elevation control assembly includes high process control nut 42 and high process control bolt 41, and high process control nut 42 is embedded in pre- In partition plate 5 processed, high process control bolt 41 coordinates with high process control nut 42 and stretches out 5 upper surface of prefabricated partition board.
The construction method for realizing this connection structure is specifically introduced in conjunction with this above-mentioned connection structure, is included the following steps:
(1) prefabricated partition board 5 is made:
It is preset with lifting groove 52 in 5 upper surface of prefabricated partition board, lifting built-in fitting 3 is embedded in prefabricated partition board 5, hangs It fills 3 upper end of built-in fitting to be in lifting slot, high process control nut 42 is embedded in prefabricated partition board 5, high process control nut 42 Threaded hole extends to 5 upper surface of prefabricated partition board, and the embedded nut 22 of the vertical connecting assembly is also embedded in prefabricated partition board 5 Interior, the threaded hole of embedded nut 22 extends to the front end face of prefabricated partition board 5, is equipped in 5 left and right end face upper end of prefabricated partition board 11 one end of galvanized steel plain sheet of the lap segment 51 of protrusion, transversal connecting assembly is stretched into the lap segment 51 of prefabricated partition board 5, and is plated Zinc steel plate 11 is welded and fixed with the framework of steel reinforcement inside prefabricated partition board 5, and 11 other end of galvanized steel plain sheet stretches out prefabricated partition board 5, Prefabricated partition board 5 other pour process and original prefabricated partition board 5 pour that process is consistent, the thickness of prefabricated partition board 5 is big In equal to 100mm;
(2) built-in fitting fabrication and installation in terraced beam:
11 position of galvanized steel plain sheet that every layer of stair stringer 6 all corresponds to prefabricated partition board 5 is equipped with stair stringer built-in fitting 12, stair 12 part of beam built-in fitting is embedded in stair stringer 6, the stair stringer built-in fitting 12 in stair stringer 6 and 6 reinforcing bar of stair stringer Frame is fixed, and 12 another part of stair stringer built-in fitting stretches out outside stair stringer 6;
(3) hoisting prefabricated partition plate 5:
Prefabricated partition board 5 is lifted to designated position by lifting built-in fitting 3, it is program-controlled by high process control bolt 41 and height Nut 42 processed coordinates, and controls this layer of 5 bottom surface absolute altitude of prefabricated partition board, galvanized steel plain sheet 11 and the stair stringer 6 of 5 both sides of prefabricated partition board Stair stringer built-in fitting 12 be bolted fixed and weld;Two connection bolts 23 of the vertical connecting assembly, which pass through, to be connected Steel plate 21 is connect with the embedded nut 22 in two neighbouring prefabricated partition boards 5 to coordinate;
(4) plate stitch is handled:
It is filled using polyphenyl 73 in the middle part of gap between arbitrary upper and lower adjacent prefabricated partition board 5,73 both sides of polyphenyl note 20mm*20mm fluid sealants 72,21 outside of junction steel plate are sealed using stainless steel box;
(5) C30 microdilatancies pea gravel concreten 71, C30 is poured to galvanized steel plain sheet 11 and 12 junction position of stair stringer built-in fitting The corresponding transversal connecting assembly of the covering of microdilatancy pea gravel concreten 71.
Above-described is only one embodiment of the present invention, it is noted that for those of ordinary skill in the art For, without departing from the principle of the present invention, several variations and modifications can also be made, these also should be regarded as belonging to this hair Bright protection domain.

Claims (7)

1. a kind of connection structure of the integral prefabricated partition plate of cantilever stair, it is characterised in that:
Including at least the transversal connecting assembly, several for fixed arbitrary neighbouring for connecting prefabricated partition board and stair stringer The vertical connecting assembly of prefabricated partition board;
The transversal connecting assembly includes two galvanized steel plain sheets and two stair stringer built-in fittings, and two galvanized steel plain sheets are arranged prefabricated Partition plate both sides upper end, the pre- prefabricated partition board of nuzzling of a galvanized steel plain sheet part, described galvanized steel plain sheet another part stretches out pre- Outside partition plate processed, two stair stringer built-in fittings correspond to the stair stringer that galvanized steel plain sheet position is embedded in prefabricated partition board both sides in advance respectively It is interior, it is fixedly connected between two stair stringer built-in fittings and galvanized steel plain sheet;
The vertical connecting assembly includes junction steel plate, two embedded nuts and two connection bolts, two embedded nut difference Pre- to be embedded in upper and lower two neighboring prefabricated partition board, two connection bolts are each passed through junction steel plate and coordinate with embedded nut.
2. a kind of connection structure of the integral prefabricated partition plate of cantilever stair according to claim 1, it is characterised in that:It is described The thickness of prefabricated partition board is more than or equal to 100mm.
3. a kind of connection structure of the integral prefabricated partition plate of cantilever stair according to claim 1, it is characterised in that:
Further include lifting built-in fitting, lifting built-in fitting is embedded in prefabricated partition board, and prefabricated partition board upper surface is preset with lifting Groove, lifting built-in fitting upper end are in lifting groove.
4. a kind of connection structure of the integral prefabricated partition plate of cantilever stair according to claim 1, it is characterised in that:
Further include elevation control assembly, elevation control assembly includes high process control nut and high process control bolt, high process control spiral shell Mother is embedded in prefabricated partition board, and high process control bolt coordinates with high process control nut and stretches out prefabricated partition board upper surface.
5. a kind of connection structure of the integral prefabricated partition plate of cantilever stair according to claim 1, it is characterised in that:
It is sealed using stainless steel box on the outside of junction steel plate.
6. a kind of connection structure of the integral prefabricated partition plate of cantilever stair according to claim 1, it is characterised in that:
Galvanized steel plain sheet size is 600mm*100mm*10mm.
7. a kind of connection structure for realizing the integral prefabricated partition plate of cantilever stair according to any one of claims 1 to 6 is applied Work method, includes the following steps:
(1) prefabricated partition board is manufactured:
It is preset with lifting groove in prefabricated partition board upper surface, lifting built-in fitting is embedded in prefabricated partition board, lifts built-in fitting Upper end is in lifting slot, and high process control nut is embedded in prefabricated partition board, and the threaded hole of high process control nut extends to pre- Partition plate upper surface processed, the embedded nut of the vertical connecting assembly are also embedded in prefabricated partition board, the screw thread of embedded nut Hole extends to prefabricated partition board side wall, and a galvanized steel plain sheet part for transversal connecting assembly is nuzzled in prefabricated partition board in advance, the plating Zinc steel plate another part stretches out prefabricated partition board upper outside;
(2) built-in fitting fabrication and installation in stair stringer:
A stair stringer built-in fitting part is embedded in every layer of stair stringer, the stair stringer built-in fitting in stair stringer and stair joist steel Tendons skeleton is fixed, and stair stringer built-in fitting another part stretches out outside stair stringer;
(3) hoisting prefabricated partition plate:
Prefabricated partition board is lifted to designated position by lifting built-in fitting, is matched by high process control bolt and high process control nut It closes, controls this layer of prefabricated partition board bottom surface absolute altitude, the galvanized steel plain sheet of prefabricated partition board both sides and the stair stringer built-in fitting of stair stringer It is bolted fixed and welds;Two connection bolts of the vertical connecting assembly pass through junction steel plate and are in phase up and down Embedded nut cooperation in two adjacent prefabricated partition boards;
(4) plate stitch is handled:
It is filled using polyphenyl in the middle part of gap between arbitrary upper and lower adjacent prefabricated partition board, it is close that 20mm*20mm is noted in polyphenyl both sides Sealing, junction steel plate outside are sealed using stainless steel box;
(5) C30 microdilatancy pea gravel concretens are poured to galvanized steel plain sheet and stair stringer built-in fitting connecting portion, C30 microdilatancy microliths are mixed The solidifying corresponding transversal connecting assembly of soil covering, completes construction operation.
CN201810850063.4A 2018-07-28 2018-07-28 The connection structure and construction method of the integral prefabricated partition plate of cantilever stair Pending CN108755974A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810850063.4A CN108755974A (en) 2018-07-28 2018-07-28 The connection structure and construction method of the integral prefabricated partition plate of cantilever stair

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810850063.4A CN108755974A (en) 2018-07-28 2018-07-28 The connection structure and construction method of the integral prefabricated partition plate of cantilever stair

Publications (1)

Publication Number Publication Date
CN108755974A true CN108755974A (en) 2018-11-06

Family

ID=63971710

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810850063.4A Pending CN108755974A (en) 2018-07-28 2018-07-28 The connection structure and construction method of the integral prefabricated partition plate of cantilever stair

Country Status (1)

Country Link
CN (1) CN108755974A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111188458A (en) * 2020-01-09 2020-05-22 付萍 Method for constructing concrete shear stair fire-proof partition wall by applying prefabricated concrete beams
CN113026959A (en) * 2019-12-24 2021-06-25 成都建工第二建筑工程有限公司 Installation method of prefabricated staircase

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10060528A1 (en) * 2000-12-06 2002-06-27 Iff Weimar Connection for transferring shear forces from one precast component to another comprises connecting part consisting of two individual crossing connecting elements fixed to precast component at their ends via connector elements
CN201007041Y (en) * 2007-02-08 2008-01-16 周嵬 Concrete prefabricated element hanging connecting mechanism
CN204662717U (en) * 2015-02-16 2015-09-23 中国建筑股份有限公司 A kind of staircase prefabricated reinforced concrete fire barrier structure
CN204753834U (en) * 2015-06-26 2015-11-11 南京长江都市建筑设计股份有限公司 Partition plate of scissors stair and connection structure of floor roof beam
CN205475728U (en) * 2016-03-29 2016-08-17 山东安泰克工程材料有限公司 Rapid Assembly crab -bolt and shedder
CN107178184A (en) * 2017-05-27 2017-09-19 江苏龙腾工程设计股份有限公司 Cantilever stair and its installation method
CN108149784A (en) * 2018-01-31 2018-06-12 山东海龙建筑科技有限公司 Premade closure balcony and its construction method
CN207538350U (en) * 2017-10-08 2018-06-26 四川宜宾仁铭住宅工业技术有限公司 A kind of assembled cantilever stair
CN208633283U (en) * 2018-07-28 2019-03-22 中城投集团第六工程局有限公司 The connection structure of the integral prefabricated partition plate of cantilever stair

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE10060528A1 (en) * 2000-12-06 2002-06-27 Iff Weimar Connection for transferring shear forces from one precast component to another comprises connecting part consisting of two individual crossing connecting elements fixed to precast component at their ends via connector elements
CN201007041Y (en) * 2007-02-08 2008-01-16 周嵬 Concrete prefabricated element hanging connecting mechanism
CN204662717U (en) * 2015-02-16 2015-09-23 中国建筑股份有限公司 A kind of staircase prefabricated reinforced concrete fire barrier structure
CN204753834U (en) * 2015-06-26 2015-11-11 南京长江都市建筑设计股份有限公司 Partition plate of scissors stair and connection structure of floor roof beam
CN205475728U (en) * 2016-03-29 2016-08-17 山东安泰克工程材料有限公司 Rapid Assembly crab -bolt and shedder
CN107178184A (en) * 2017-05-27 2017-09-19 江苏龙腾工程设计股份有限公司 Cantilever stair and its installation method
CN207538350U (en) * 2017-10-08 2018-06-26 四川宜宾仁铭住宅工业技术有限公司 A kind of assembled cantilever stair
CN108149784A (en) * 2018-01-31 2018-06-12 山东海龙建筑科技有限公司 Premade closure balcony and its construction method
CN208633283U (en) * 2018-07-28 2019-03-22 中城投集团第六工程局有限公司 The connection structure of the integral prefabricated partition plate of cantilever stair

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113026959A (en) * 2019-12-24 2021-06-25 成都建工第二建筑工程有限公司 Installation method of prefabricated staircase
CN111188458A (en) * 2020-01-09 2020-05-22 付萍 Method for constructing concrete shear stair fire-proof partition wall by applying prefabricated concrete beams

Similar Documents

Publication Publication Date Title
CN106013454B (en) Building and method of construction based on large spatial structure body and free-standing peripheral structure
CN105952061B (en) Precast shear wall steel reinforcement cage component, column steel reinforcement cage component and manufacture assembly method
CN106555453A (en) A kind of prefabricated overlapped hollow plate of prestressing force and its construction method
CN102661017A (en) Quick-mounting type concrete stair and mounting method thereof
CN109083320A (en) Combine prefabricated panel and laminated floor slab structure and laminated floor slab construction method
CN108149819B (en) Integrated superposed outer wall of building bottom reinforcing area and production and construction method thereof
CN107859206A (en) Pre-manufactured steel structure overlapped shear wall and its construction method
CN108265623A (en) A kind of prefabricated superposed type anti-collision wall and its construction method for urban viaduct
CN208633283U (en) The connection structure of the integral prefabricated partition plate of cantilever stair
CN106948598A (en) A kind of aluminum alloy formwork system and its construction method for variable cross-section rectangular column
CN109235702B (en) Assembled double-steel-plate combined shear wall structure with ribs and construction method thereof
CN106088493A (en) A kind of pin key connects mounting structure and the construction thereof of prefabricated bench
CN107143076A (en) A kind of Prefabricated stacking floor with side flanging and its construction method for being used to drop plate region
CN108755974A (en) The connection structure and construction method of the integral prefabricated partition plate of cantilever stair
CN113250494A (en) Assembled integrated toilet and construction method
CN109895239B (en) Fabricated concrete stair slow platform beam slab and construction method thereof
CN110005200B (en) Construction process for concrete pouring compaction of horizontal hidden beam
CN110644662A (en) Prefabricated flat slab composite slab based on stress and splitting method thereof
CN207944339U (en) A kind of prefabricated superposed type anti-collision wall for urban viaduct
CN105040823A (en) Partition plate and floor beam connecting structure for scissors staircase and construction method of partition plate and floor beam connecting structure
CN113123504A (en) Laminated floor slab with detachable additional rigidity device
CN204753834U (en) Partition plate of scissors stair and connection structure of floor roof beam
CN111663794A (en) Wall body leveling mechanism for longitudinal rib superposed shear wall and construction method
CN105696453B (en) A kind of steel-concrete combination beam
CN207244961U (en) A kind of Prefabricated stacking floor with side flanging for being used to drop plate region

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination