CN208514750U CN201820980706.2U CN201820980706U CN208514750U CN 208514750 U CN208514750 U CN 208514750U CN 201820980706 U CN201820980706 U CN 201820980706U CN 208514750 U CN208514750 U CN 208514750U
Authority
CN
China
Prior art keywords
sliding sleeve
column
pedestal
building block
sizing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820980706.2U
Other languages
Chinese (zh)
Inventor
杨耀增
张栋梁
雷霆
原增欢
杜世涛
刘亚楠
李喆
樊琳
李小艳
陈喆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhengzhou Yijian Group Co Ltd
Original Assignee
Zhengzhou No1 Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhengzhou No1 Construction Engineering Co Ltd filed Critical Zhengzhou No1 Construction Engineering Co Ltd
Priority to CN201820980706.2U priority Critical patent/CN208514750U/en
Application granted granted Critical
Publication of CN208514750U publication Critical patent/CN208514750U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of secondary structure pipeline burying building block drilling equipments, including sizing pedestal, column and water drilling, sliding sleeve is housed in column outer sheath, water drilling is fixed on the side of sliding sleeve, the left or right side of sizing pedestal is provided with pedestal and traveling wheel is installed, the lower edge height of traveling wheel is higher than sizing base end face height.The utility model can realize control water drilling lifting carriage operation by the guiding relationship between sliding sleeve and column.Water drilling elevating translational is controlled using composite bushing and sliding sleeve guiding slide construction.Simple to operate, Quick labor-saving can significantly improve working efficiency, improve the precise degrees of drilling, improve construction quality.

Description

Secondary structure pipeline burying building block drilling equipment
Technical field:
The utility model belongs to building engineering construction structure masonry project technical field, and in particular to a kind of secondary structure pipe Line secretly buries building block drilling equipment.
Background technique:
After traditional secondary piping construction needs masonry construction, fluting carries out pipeline burying operation on blockwork, Because fluting vibration causes to destroy wall integrity in later period fluting operation process, after pipeline is embedded, since pipeline surface is smooth, It is not easy to combine with closed material, causes bad sealing close, the defects of leakiness;In later period plastering construction, even if pasting alkaline-resisting Glass fiber reticular cloth, but there are still very big rendering layer crackings, hollowing hidden danger at pipeline embedding place.
Therefore BIM technology is combined in the masonry project construction stage now, it accurately determines pipeline position, work is secretly buried to pipeline Industry, it is more demanding to borehole perpendicularity because being multiple building block bonds when pipeline burying operation;But existing building block water drilling bores When the operation of hole, the bad grasp of verticality be easy to cause perpendicularity deviation after Completion of Drilling Hole larger, and bore operation low efficiency.
Utility model content:
In order to overcome the shortcomings of in above-mentioned existing building block water drilling boring procedure, the utility model provides a kind of structure letter It is single, it is easy for operation, service life is long, greatly improve a kind of building block drilling dress of building block drilling efficiency and borehole perpendicularity It sets.
Solution adopted by the utility model to solve its technical problems is that: a kind of secondary structure pipeline burying building block drilling dress It sets, including sizing pedestal, column and water drilling, sliding sleeve is housed in column outer sheath, water drilling is fixed on the side of sliding sleeve, at sizing bottom The left or right side of seat is provided with pedestal and is equipped with traveling wheel, and the lower edge height of traveling wheel is higher than sizing base end face height.
The front side or rear side of the sizing pedestal is provided with pedestal and traveling wheel is installed, the lower edge height of traveling wheel is high In sizing base end face height.
On the outside of the column and sliding sleeve inner sleeve is equipped with compound sleeve, while column lower part being provided with support block machine, institute The lower end for stating compound sleeve is located on the upside of support block machine;Locking pin is set between compound sleeve and column, is set between compound sleeve and sliding sleeve Set convex-concave guide rail.
Tension spring is connected between the column and sliding sleeve or between compound sleeve and sliding sleeve.
The utility model has the advantages that the utility model can rapidly and accurately determine bore position by the sizing pedestal of rectangle, and it is Water drilling provides stable constraint and positioning.The utility model can realize control by the guiding relationship between sliding sleeve and column The operation of water drilling lifting carriage.The utility model guarantees the stationarity of water drilling motion profile by the way of compound sleeve, and Control and constraint to water drilling operative orientation are realized by adjusting compound sleeve angle.By the way that row can be passed through after tilting the device Wheel translation is walked, simple to operate, Quick labor-saving can significantly improve working efficiency, improve the precise degrees of drilling, and raising is applied Working medium amount.
It is drilled by the utility model to masonry and carries out operation, ensure that the verticality quality of pore-forming;Improve building block brill The efficiency of hole ancestors' meritorious achievements reduces the investment of human resources, reduces labor intensity.
Detailed description of the invention
Fig. 1 is one of structural schematic diagram of the utility model.
Fig. 2 is the second structural representation of the utility model.
Fig. 3 is the A of Fig. 1 to schematic diagram.
Figure label 1 is sizing pedestal, and 2 be column, and 3 be sliding sleeve, and 4 be water drilling, and 5 be pedestal, and 6 be traveling wheel, and 7 be compound Set, 8 be guide rail, and 9 be support block machine, and 10 be locking pin.
Specific embodiment
Embodiment 1: the first secondary structure pipeline burying building block drilling equipment is as shown in figures 1 and 3, and main includes sizing The components such as pedestal 1, column 2 and water drilling 4.Each side of the sizing pedestal 1 of rectangle is convenient for judgement, Yi Jirong parallel with room metope Easily cooperate with surface drilling mark line, achievees the purpose that rapidly and accurately determining bore position, be conducive to provide stabilization for water drilling 4 Constraint and positioning.Wherein, column (1600mm high, diameter 25mm stainless-steel pipe) and sizing pedestal 1 form, pedestal 1 of being formed It is to be made of 2 500mm long diameter 25mm stainless-steel pipes and 3 300mm long diameter 25mm stainless-steel pipes, column 2 welds In the sizing unilateral middle position of pedestal 1.
As shown in Figure 1: connector of the water drilling 4 between sliding sleeve 3 be by bolt together with 16 reinforcement welding of 50mm long φ, Connector is and sliding sleeve 3(diameter 32mm stainless-steel pipe) weld together, there are three handle spiral shells for water drilling the machine upper, left and right It is tightened by the screw rod of connector fixed whole with sliding sleeve (diameter 32mm stainless-steel pipe) formation using screw hole at the top of water drilling in hole Body.
Sliding sleeve 3 is housed in 2 outer sheath of column, water drilling 4 is fixed on the side of sliding sleeve 3, can by sliding sleeve 3 and column 2 it Between guiding relationship, realize control 4 lifting carriage of water drilling operation.
The left or right side of sizing pedestal 1 is provided with pedestal 5 again and traveling wheel 6 is installed, the lower edge height of traveling wheel 6 Higher than sizing 1 floor height of pedestal.The front side or rear side of sizing pedestal 1 can also be provided with pedestal 5 simultaneously and row is installed Wheel 6 is walked, the lower edge height of traveling wheel 6 is higher than sizing 1 floor height of pedestal.
This system in actual application, must first combine BIM technology before masonry project construction starts, accurate to determine Pipeline position marks out pipeline position on masonry typesetting figure, and according to typesetting figure and material list, determines that concealed piping is corresponding Building block, and the bore position at the mark of building block upper surface carry out bore operation using the present apparatus.It through this embodiment being capable of building block The low problem of drilling efficiency;The labor intensity for alleviating bore operation improves the construction efficiency of bore operation.Solves building block The problem of borehole perpendicularity bad grasp: water drilling is connected by connector, sliding sleeve and column, by the application to the present apparatus, is mentioned High building block bore operation is at hole perpendicularity.
2: second secondary structure pipeline burying building block drilling equipment of embodiment, referring to fig. 2, on that basis of example 1, again Compound sleeve 7 is housed in 2 outside of column and 3 inner sleeve of sliding sleeve, while 2 lower part of column being provided with support block machine 9, the compound sleeve 7 lower end is located at 9 upside of support block machine;Locking pin 10 is set between compound sleeve 7 and column 2, is set between compound sleeve 7 and sliding sleeve 3 Set convex-concave guide rail.Such as guide rail 8 is set on 7 surface of compound sleeve, then sliding slot is arranged in sliding sleeve inner wall again.Using compound sleeve 7 Mode realize to guarantee the stationarity of 4 motion profile of water drilling, and by adjusting 7 angle of compound sleeve to 4 side of work of water drilling To control and constraint.
Embodiment 3: on the basis of embodiment 1 or 2, and between the column 2 and sliding sleeve 3 or compound sleeve 7 and sliding sleeve 3 it Between be connected with tension spring.It is acted on by tension spring, is able to maintain 4 automatic reduction of water drilling, further improves convenient construction degree.

Claims (4)

1. a kind of secondary structure pipeline burying building block drilling equipment, including sizing pedestal, column and water drilling, it is characterized in that: vertical Column outer sheath is equipped with sliding sleeve, and water drilling is fixed on the side of sliding sleeve, and the left or right side of sizing pedestal is provided with pedestal and installs There is traveling wheel, the lower edge height of traveling wheel is higher than sizing base end face height.
2. secondary structure pipeline burying building block drilling equipment according to claim 1, it is characterized in that: in the sizing pedestal Front side or rear side be provided with pedestal and traveling wheel be installed, the lower edge height of traveling wheel is higher than sizing base end face height.
3. secondary structure pipeline burying building block drilling equipment according to claim 1, it is characterized in that: on the outside of the column Compound sleeve is housed with sliding sleeve inner sleeve, while column lower part being provided with support block machine, the lower end of the compound sleeve is located at support On the upside of block machine;Locking pin is set between compound sleeve and column, convex-concave guide rail is set between compound sleeve and sliding sleeve.
4. secondary structure pipeline burying building block drilling equipment according to claim 1, it is characterized in that: in the column and cunning Tension spring is connected between set or between compound sleeve and sliding sleeve.
CN201820980706.2U 2018-06-25 2018-06-25 Secondary structure pipeline burying building block drilling equipment Expired - Fee Related CN208514750U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820980706.2U CN208514750U (en) 2018-06-25 2018-06-25 Secondary structure pipeline burying building block drilling equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820980706.2U CN208514750U (en) 2018-06-25 2018-06-25 Secondary structure pipeline burying building block drilling equipment

Publications (1)

Publication Number Publication Date
CN208514750U true CN208514750U (en) 2019-02-19

Family

ID=65336842

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820980706.2U Expired - Fee Related CN208514750U (en) 2018-06-25 2018-06-25 Secondary structure pipeline burying building block drilling equipment

Country Status (1)

Country Link
CN (1) CN208514750U (en)

Similar Documents

Publication Publication Date Title
CN205976476U (en) Movement joint template is propped up and is established structure and stupefied subassembly of back of body and stencil assembly thereof
CN105762728A (en) Method for pre-burying of strong and weak electricity box and electrical tubing
CN208514750U (en) Secondary structure pipeline burying building block drilling equipment
CN205557938U (en) Aerated concrete externally -hanging wallboard's spiral anchor node that slides
CN218912845U (en) Portable drilling and cutting integrated device
CN105291180B (en) Two-way porous jewel hole machine
CN213361303U (en) Pipeline buries puts support convenient to piping erection municipal works are used
CN109332743A (en) Independent feeding multi-hole drill
CN207123231U (en) A kind of positioning rule of embedded sleeve barrel and reserving hole channel after being used for prefabricated part hanging
CN205605114U (en) Karst karst area prestressed anchorage cable drilling equipment
CN205857693U (en) A kind of canalization template being applied to movement joint both sides shear wall synchronous construction
CN204126079U (en) A kind of bolt welds T-shaped steel wallboard post
CN108839264A (en) Secondary structure pipeline burying building block drilling equipment
CN204430367U (en) Simple laser based on Magnetic gauge stand is auxiliary to heart drilling equipment
CN205503041U (en) Guider is right in drilling
CN212718427U (en) Line pipe connection fixer
CN210172932U (en) Auxiliary jig for assembling branch pipe and main pipe of pipeline
CN205370596U (en) Steelframe refining methods line traffic control ware
CN209110216U (en) Independent feeding multi-hole drill
CN208358161U (en) Rectangular air duct welds side wall Anti-deformation support structure
CN203157154U (en) Hole expander for plastic pipe fitting
CN106337653B (en) Perforation drills through device and method in a kind of vertical drilling
CN106996103B (en) Built-in pipe construction method in concrete cut based on detachable machine straightening device
CN205914795U (en) A electric hand drill auxiliary device for vertical hole processing
CN218265936U (en) Leading little pipe location leading truck device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: 450000 Shangxian Street, Longzihu Wisdom Island, Zhengdong New District, Zhengzhou City, Henan Province

Patentee after: Zhengzhou Yijian Group Co.,Ltd.

Address before: 450000, No. 91, Bauhinia Road, Zhengzhou City, Henan Province

Patentee before: ZHENGZHOU NO.1 CONSTRUCTION ENGINEERING GROUP Co.,Ltd.

CP03 Change of name, title or address
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190219

Termination date: 20210625

CF01 Termination of patent right due to non-payment of annual fee