CN108839264A - Secondary structure pipeline burying building block drilling equipment - Google Patents
Secondary structure pipeline burying building block drilling equipment Download PDFInfo
- Publication number
- CN108839264A CN108839264A CN201810659942.9A CN201810659942A CN108839264A CN 108839264 A CN108839264 A CN 108839264A CN 201810659942 A CN201810659942 A CN 201810659942A CN 108839264 A CN108839264 A CN 108839264A
- Authority
- CN
- China
- Prior art keywords
- pedestal
- building block
- sizing
- column
- seat
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28D—WORKING STONE OR STONE-LIKE MATERIALS
- B28D1/00—Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor
- B28D1/14—Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor by boring or drilling
- B28D1/146—Tools therefor
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B28—WORKING CEMENT, CLAY, OR STONE
- B28D—WORKING STONE OR STONE-LIKE MATERIALS
- B28D7/00—Accessories specially adapted for use with machines or devices of the preceding groups
Abstract
The invention discloses a kind of secondary structure pipeline burying building block drilling equipments, including sizing pedestal, column and water drilling, sliding sleeve are housed in column outer sheath, water drilling is fixed on the side of sliding sleeve, and the upper sliding seat of sliding sleeve lower part passes through push-pull rod and the hinged lower slider seat of pin shaft;It is fixed with movable rod in the lower end of lower slider seat, fixes preceding footstock and rear footstock respectively before and after the downside of movable rod;Pedestal and rear base before being respectively fixed with before and after the upside of sizing pedestal;It is hinged with front roll bar between footstock and preceding pedestal before surely, swing rod after being hinged between rear footstock and rear base;Handle or foot pedal are connected in the side of movable rod.The present invention can realize control water drilling lifting carriage operation by the guiding relationship between sliding sleeve and column.Water drilling elevating translational is controlled using handle or foot-operated linkage structure.Simple to operate, Quick labor-saving can significantly improve working efficiency, improve the precise degrees of drilling, improve construction quality.
Description
Technical field:
The invention belongs to building engineering construction structure masonry project technical fields, and in particular to a kind of secondary structure pipeline burying block
Block drilling equipment.
Background technique:
After traditional secondary piping construction needs masonry construction, fluting carries out pipeline burying operation on blockwork, rear
Because fluting vibration causes to destroy wall integrity in phase fluting operation process, after pipeline is embedded, since pipeline surface is smooth, with envelope
It closes material to be not easy to combine, causes bad sealing close, the defects of leakiness;In later period plastering construction, even if pasting alkali-resisting glass fiber
Grid cloth, but there are still very big rendering layer crackings, hollowing hidden danger at pipeline embedding place.
Therefore BIM technology is combined in the masonry project construction stage now, it accurately determines pipeline position, work is secretly buried to pipeline
Industry, it is more demanding to borehole perpendicularity because being multiple building block bonds when pipeline burying operation;But existing building block water drilling bores
When the operation of hole, the bad grasp of verticality be easy to cause perpendicularity deviation after Completion of Drilling Hole larger, and bore operation low efficiency.
Summary of the invention:
In order to overcome the shortcomings of in above-mentioned existing building block water drilling boring procedure, the present invention provides a kind of structure is simple, operation makes
With convenient, service life is long, a kind of building block drilling equipment of building block drilling efficiency and borehole perpendicularity is greatly improved.
The present invention solves scheme used by its technical problem:A kind of secondary structure pipeline burying building block drilling equipment,
Including sizing pedestal, column and water drilling, sliding sleeve is housed in column outer sheath, water drilling is fixed on the side of sliding sleeve, in the another of sliding sleeve
One side lower part is fixed with sliding seat, and by the hinged push-pull rod of pin shaft, push-pull rod lower end is hinged on down upper sliding seat by pin shaft
In sliding seat;Be fixed with movable rod in the lower end of lower slider seat, it is fixed respectively before and after the downside of movable rod before footstock and
Footstock afterwards;Pedestal and rear base before being respectively fixed with before and after the upside of the sizing pedestal;At the fixed preceding footstock and preceding bottom
It is hinged with front roll bar between seat, swing rod after being hinged between the rear footstock and rear base;In the side of the movable rod
It is connected with handle or foot pedal.
The left or right side of the sizing pedestal is provided with pedestal and traveling wheel is installed, the lower edge height of traveling wheel is high
In sizing base end face height.
The front side or rear side of the sizing pedestal is provided with pedestal and traveling wheel is installed, the lower edge height of traveling wheel is high
In sizing base end face height.
Convex-concave guide rail is set between the column and sliding sleeve.
The column bottom is provided with rotation seat, the upper section of column is sleeved in the rotation seat of its bottom, while being turned
Dynamic seat side is provided with retaining mechanism.
Between the sizing pedestal and front roll bar or rear swing rod, or in the movable rod and front roll bar or rear swing rod
Between be connected with tension spring.
Beneficial effect:The present invention can rapidly and accurately determine bore position by the sizing pedestal of rectangle, and be water drilling
Stable constraint and positioning are provided.The present invention can realize control water drilling lifting by the guiding relationship between sliding sleeve and column
Slide.And present invention employs handles or foot-operated linkage structure to control water drilling elevating translational.By tilting the dress
Postponing can be translated by traveling wheel, simple to operate, Quick labor-saving, can be significantly improved working efficiency, be improved drilling
Precise degrees improve construction quality.
It drills through the invention to masonry and carries out operation, ensure that the verticality quality of pore-forming;Improve building block drilling ancestral
The efficiency of industry reduces the investment of human resources, reduces labor intensity.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the invention.
Fig. 2 is the schematic top plan view of Fig. 1.
Fig. 3 is the structure schematic diagram of Fig. 1.
Fig. 4 is the status diagram half-compressed of Fig. 3.
Fig. 5 is the full compression status diagram of Fig. 3.
Figure label 1 is sizing pedestal, and 2 be column, and 3 be sliding sleeve, and 4 be water drilling, and 5 be pedestal, and 6 be traveling wheel, and 7 be preceding bottom
Seat, 8 be rear base, and 9 be preceding footstock, and 10 be rear footstock, and 11 be front roll bar, and 12 be rear swing rod, and 13 be movable rod, and 14 be handle
Hand, 15 be upper sliding seat, and 16 be lower slider seat, and 17 be push-pull rod, and 18 be fixed traction point, and 19 be tension spring.
Specific embodiment
Embodiment 1:Secondary structure pipeline burying building block drilling equipment as depicted in figs. 1 and 2, main includes sizing pedestal
1, the components such as column 2 and water drilling 4.Rectangle sizing pedestal 1 each side convenient for judge it is parallel with room metope, and be easy and
The cooperation of surface drilling mark line, achievees the purpose that rapidly and accurately determining bore position, is conducive to provide stable pact for water drilling 4
Beam and positioning.Wherein, column(1600mm high, diameter 25mm stainless-steel pipe)It is formed with sizing pedestal 1, sizing pedestal 1 is that have 2
Root 500mm long diameter 25mm stainless-steel pipe and 3 300mm long diameter 25mm stainless-steel pipes form, and column 2 is welded on sizing
The unilateral middle position of pedestal 1.
As shown in Figure 3:Connector of the water drilling 4 between sliding sleeve 3 be by bolt together with 16 reinforcement welding of 50mm long φ,
Connector is and sliding sleeve 3(Diameter 32mm stainless-steel pipe)Weld together, water drilling the machine it is upper, left and right there are three handle spiral shell
Fixed and sliding sleeve is tightened by the screw rod of connector using screw hole at the top of water drilling in hole(Diameter 32mm stainless-steel pipe)It is formed whole
Body.
Sliding sleeve 3 is housed in 2 outer sheath of column, water drilling 4 is fixed on the side of sliding sleeve 3, can by sliding sleeve 3 and column 2 it
Between guiding relationship, realize control 4 lifting carriage of water drilling operation.
4 elevating translational of water drilling is controlled using handle 14 or foot-operated linkage structure.It can after the device by tilting
It is translated by traveling wheel 6.As shown in Figure 3-Figure 5, upper sliding seat 15, upper sliding seat 15 are fixed in another side lower part of sliding sleeve 3
By the hinged push-pull rod 17 of pin shaft, 17 lower end of push-pull rod is hinged in lower slider seat 16 by pin shaft.Again in lower slider seat 16
Lower end is fixed with movable rod 13, fixes preceding footstock 9 and rear footstock 10 respectively before and after the downside of movable rod 13.
Meanwhile pedestal 7 and rear base 8 before being respectively fixed with before and after the upside of sizing pedestal 1.Footstock 9 is with before before surely
Front roll bar 11 is hinged between pedestal 7, swing rod 12 after being hinged between rear footstock 10 and rear base 8.It can connect in activity
The side of bar 13 is connected with handle 14 or foot pedal.It is simple to operate by the working method of handle 14 or foot pedal,
Quick labor-saving can significantly improve working efficiency, improve the precise degrees of drilling, improve construction quality.
This system in actual application, must first combine BIM technology before masonry project construction starts, accurate to determine
Pipeline position marks out pipeline position on masonry typesetting figure, and according to typesetting figure and material list, determines that concealed piping is corresponding
Building block, and the bore position at the mark of building block upper surface carry out bore operation using the present apparatus.
The left or right side of sizing pedestal 1 is provided with pedestal 5 again and traveling wheel 6 is installed, the lower edge height of traveling wheel 6
Higher than sizing 1 floor height of pedestal.The front side or rear side of sizing pedestal 1 can also be provided with pedestal 5 simultaneously and row is installed
Wheel 6 is walked, the lower edge height of traveling wheel 6 is higher than sizing 1 floor height of pedestal.
It through this embodiment being capable of the low problem of building block drilling efficiency;The labor intensity of bore operation is alleviated, drilling is improved
The construction efficiency of operation.Solves the problems, such as the bad grasp of building block borehole perpendicularity:Water drilling is connected by connector, sliding sleeve and column
It connects, by the application to the present apparatus, improves building block bore operation into hole perpendicularity.
Embodiment 2:On that basis of example 1, and between column 2 and sliding sleeve 3 convex-concave guide rail is set.Column and bottom
Seat is made of the stainless-steel pipe of diameter 25mm, pedestal long 500mm, wide 300mm;Casing is the stainless steel steel of diameter 32mm
Pipe, water drilling pass through screw rod and casing connection.
Meanwhile 2 bottom of column being provided with rotation seat, the upper section of column 2 is sleeved in the rotation seat of its bottom, while
Rotation seat side is provided with retaining mechanism.It is constrained by the rotation of rotation seat column 2, and passes through convex-concave guided way
The positioning action in road can prevent water drilling 4 from occurring swinging situation in dropping process.And it is waited if necessary by adjusting rotation
The angle of seat controls the operative orientation of water drilling 4.
Embodiment 3:On the basis of embodiment 1 or 2, and between sizing pedestal 1 and front roll bar 11 or rear swing rod 12, or
Tension spring 19 is connected between the movable rod 13 and front roll bar 11 or rear swing rod 12.It is acted on, is able to maintain by tension spring 19
Water drilling 4 and swinging frame automatic reduction, further improve convenient construction degree.
Claims (6)
1. a kind of secondary structure pipeline burying building block drilling equipment, including sizing pedestal, column and water drilling, it is characterized in that:Vertical
Column outer sheath is equipped with sliding sleeve, and water drilling is fixed on the side of sliding sleeve, is fixed with upper sliding seat, upper sliding in another side lower part of sliding sleeve
By the hinged push-pull rod of pin shaft, push-pull rod lower end is hinged in lower slider seat seat by pin shaft;It is fixed in the lower end of lower slider seat
There is movable rod, fixes preceding footstock and rear footstock respectively before and after the downside of movable rod;Before the upside of the sizing pedestal
After be respectively fixed with before pedestal and rear base;It is hinged with front roll bar between the fixed preceding footstock and preceding pedestal, the top after described
Rear swing rod is hinged between seat and rear base;Handle or foot pedal are connected in the side of the movable rod.
2. secondary structure pipeline burying building block drilling equipment according to claim 1, it is characterized in that:In the sizing pedestal
Left or right side be provided with pedestal and traveling wheel be installed, the lower edge height of traveling wheel is higher than sizing base end face height.
3. secondary structure pipeline burying building block drilling equipment according to claim 1 or 2, it is characterized in that:In the sizing
The front side or rear side of pedestal is provided with pedestal and is equipped with traveling wheel, and it is high that the lower edge height of traveling wheel is higher than sizing base end face
Degree.
4. secondary structure pipeline burying building block drilling equipment according to claim 1, it is characterized in that:In the column and cunning
Convex-concave guide rail is set between set.
5. secondary structure pipeline burying building block drilling equipment according to claim 1, it is characterized in that:In the column bottom
It is provided with rotation seat, the upper section of column is sleeved in the rotation seat of its bottom, while rotation seat side being provided with retaining mechanism.
6. secondary structure pipeline burying building block drilling equipment according to claim 1, it is characterized in that:In the sizing pedestal
Tension spring is connected between front roll bar or rear swing rod, or between the movable rod and front roll bar or rear swing rod.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810659942.9A CN108839264B (en) | 2018-06-25 | 2018-06-25 | Secondary structure pipeline secretly buries building block drilling equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810659942.9A CN108839264B (en) | 2018-06-25 | 2018-06-25 | Secondary structure pipeline secretly buries building block drilling equipment |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108839264A true CN108839264A (en) | 2018-11-20 |
CN108839264B CN108839264B (en) | 2020-11-13 |
Family
ID=64203525
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810659942.9A Active CN108839264B (en) | 2018-06-25 | 2018-06-25 | Secondary structure pipeline secretly buries building block drilling equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108839264B (en) |
Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2642283Y (en) * | 2003-07-23 | 2004-09-22 | 杨军立 | Portable folding type stretcher wheel-chair |
JP2004345221A (en) * | 2003-05-22 | 2004-12-09 | Mitsubishi Materials Corp | Core drill device |
CN101074556A (en) * | 2007-06-09 | 2007-11-21 | 徐西元 | Automatical-cap liftable road-sweeping lorry |
JP2008012686A (en) * | 2006-07-03 | 2008-01-24 | East Japan Railway Co | Dustproof cover |
CN202423532U (en) * | 2011-12-12 | 2012-09-05 | 南京恩瑞特实业有限公司 | Hydraulic-drive collapsible radar antenna elevating mechanism |
CN202439125U (en) * | 2012-02-21 | 2012-09-19 | 山东博特精工股份有限公司 | Drilling machine for prefabricated foundation bolt holes |
CN203568775U (en) * | 2013-12-06 | 2014-04-30 | 河北联合大学 | Lifting translation device formed by double parallelogram four-linkages |
CN203592172U (en) * | 2013-12-03 | 2014-05-14 | 兖矿东华建设有限公司 | Movable type top plate drilling telescopic frame |
CN203817459U (en) * | 2014-05-08 | 2014-09-10 | 嘉兴职业技术学院 | Supporting device of pipe puncher |
CN204396705U (en) * | 2015-01-21 | 2015-06-17 | 周兰菊 | A kind of diel guider |
CN205949919U (en) * | 2016-08-31 | 2017-02-15 | 东亚装饰股份有限公司 | Four connecting rod electric drill strutting arrangement |
CN206063691U (en) * | 2016-08-29 | 2017-04-05 | 青岛三山机电科技发展有限公司 | A kind of liftable basketball stands |
CN106584229A (en) * | 2017-02-23 | 2017-04-26 | 管大海 | Decorative wall grinding device |
CN206548734U (en) * | 2016-11-17 | 2017-10-13 | 张家港市航天医疗电器有限公司 | Extraordinary care bed |
CN207108350U (en) * | 2017-06-23 | 2018-03-16 | 重庆小金人电子商务有限公司 | A kind of hydraulic pressure lifting device for being used to move lifting machine |
-
2018
- 2018-06-25 CN CN201810659942.9A patent/CN108839264B/en active Active
Patent Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004345221A (en) * | 2003-05-22 | 2004-12-09 | Mitsubishi Materials Corp | Core drill device |
CN2642283Y (en) * | 2003-07-23 | 2004-09-22 | 杨军立 | Portable folding type stretcher wheel-chair |
JP2008012686A (en) * | 2006-07-03 | 2008-01-24 | East Japan Railway Co | Dustproof cover |
CN101074556A (en) * | 2007-06-09 | 2007-11-21 | 徐西元 | Automatical-cap liftable road-sweeping lorry |
CN202423532U (en) * | 2011-12-12 | 2012-09-05 | 南京恩瑞特实业有限公司 | Hydraulic-drive collapsible radar antenna elevating mechanism |
CN202439125U (en) * | 2012-02-21 | 2012-09-19 | 山东博特精工股份有限公司 | Drilling machine for prefabricated foundation bolt holes |
CN203592172U (en) * | 2013-12-03 | 2014-05-14 | 兖矿东华建设有限公司 | Movable type top plate drilling telescopic frame |
CN203568775U (en) * | 2013-12-06 | 2014-04-30 | 河北联合大学 | Lifting translation device formed by double parallelogram four-linkages |
CN203817459U (en) * | 2014-05-08 | 2014-09-10 | 嘉兴职业技术学院 | Supporting device of pipe puncher |
CN204396705U (en) * | 2015-01-21 | 2015-06-17 | 周兰菊 | A kind of diel guider |
CN206063691U (en) * | 2016-08-29 | 2017-04-05 | 青岛三山机电科技发展有限公司 | A kind of liftable basketball stands |
CN205949919U (en) * | 2016-08-31 | 2017-02-15 | 东亚装饰股份有限公司 | Four connecting rod electric drill strutting arrangement |
CN206548734U (en) * | 2016-11-17 | 2017-10-13 | 张家港市航天医疗电器有限公司 | Extraordinary care bed |
CN106584229A (en) * | 2017-02-23 | 2017-04-26 | 管大海 | Decorative wall grinding device |
CN207108350U (en) * | 2017-06-23 | 2018-03-16 | 重庆小金人电子商务有限公司 | A kind of hydraulic pressure lifting device for being used to move lifting machine |
Also Published As
Publication number | Publication date |
---|---|
CN108839264B (en) | 2020-11-13 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201115893Y (en) | Saddle port cutting machine | |
LU501708B1 (en) | Positioning device and positioning method for anchor rod drilling of steel arch of tunnel primary support | |
CN111958259A (en) | Angle-adjustable pipeline butt joint device and elbow butt joint method | |
CN205309390U (en) | Water bores tapping machine trompil angle adjusting mechanism | |
CN108839264A (en) | Secondary structure pipeline burying building block drilling equipment | |
CN205289841U (en) | Water bores tapping machine trompil fixing device | |
CN105291180B (en) | Two-way porous jewel hole machine | |
CN217683563U (en) | Connecting device of municipal water supply pipeline | |
CN208514750U (en) | Secondary structure pipeline burying building block drilling equipment | |
CN218912845U (en) | Portable drilling and cutting integrated device | |
CN207123231U (en) | A kind of positioning rule of embedded sleeve barrel and reserving hole channel after being used for prefabricated part hanging | |
CN210264751U (en) | Lock foot anchor pipe positioner | |
CN206556910U (en) | A kind of accurate guiding concrete coring machine for being used to detect engineering surface | |
CN106592985A (en) | Binding system for concrete hollow building block wall piece in agglomeration building and binding method thereof | |
CN206337814U (en) | A kind of plumbing hole to be provided sleeve pipe | |
CN105089056B (en) | A kind of rapid constructing method of deep covering layer grouting | |
CN212217758U (en) | Angle-adjustable pipeline butt joint device | |
CN205503041U (en) | Guider is right in drilling | |
CN204284655U (en) | Direct-burried underground spigot and socket type concrete pressure pipeline pushing installation machine | |
CN207988499U (en) | A kind of building template supporting rod | |
CN207026190U (en) | The equipment for reversely restoring notch after steel pipe indent | |
CN207296884U (en) | A kind of cut-pff wall slot deviation controlling auxiliary device | |
CN106996103B (en) | Built-in pipe construction method in concrete cut based on detachable machine straightening device | |
CN207188519U (en) | Simple steel pipe straightener | |
CN103924564A (en) | Single rack pile leg folding method and tool |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||