CN208415116U - A kind of suspension platform for stone bridge guardrail power construction - Google Patents

A kind of suspension platform for stone bridge guardrail power construction Download PDF

Info

Publication number
CN208415116U
CN208415116U CN201821051203.3U CN201821051203U CN208415116U CN 208415116 U CN208415116 U CN 208415116U CN 201821051203 U CN201821051203 U CN 201821051203U CN 208415116 U CN208415116 U CN 208415116U
Authority
CN
China
Prior art keywords
bridge guardrail
counterweight
sole
support bracket
power construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821051203.3U
Other languages
Chinese (zh)
Inventor
王峰
石增辉
王文义
谭钲
孙如霜
苑志红
陈凤伟
王袁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Feixian Power Supply Co Of State Grid Shandong Electronic Power Co
Original Assignee
Feixian Power Supply Co Of State Grid Shandong Electronic Power Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Feixian Power Supply Co Of State Grid Shandong Electronic Power Co filed Critical Feixian Power Supply Co Of State Grid Shandong Electronic Power Co
Priority to CN201821051203.3U priority Critical patent/CN208415116U/en
Application granted granted Critical
Publication of CN208415116U publication Critical patent/CN208415116U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The utility model discloses a kind of suspension platforms for stone bridge guardrail power construction, it includes counterweight sole;Counterweight sole is fixedly connected with one end of load bearing cross beam;The other end of load bearing cross beam is connect with overhead support bracket;The bottom end of overhead support bracket is equipped with job platform;The middle part of overhead support bracket is equipped with adjustable guide bars, and adjustable guide bars are equipped with guide roller corresponding with Bridge guardrail.Counterweight sole is used to place counterweight, to play the role of support, prevents job platform from being toppled over again;One end of load bearing cross beam is connect with counterweight sole, the other end is connect with overhead support bracket, middle part can be used to the guardrail of interspersed bridge, i.e. job platform is corresponding with the outside of Bridge guardrail, counterweight sole is corresponding with the inside of Bridge guardrail, the state for straddling Bridge guardrail is formed, balance is conducive to construction operation well.The adjustable guide bars position lateral by guide roller adjustment, adjusts horizontal position convenient for operator, is convenient for operation.

Description

A kind of suspension platform for stone bridge guardrail power construction
Technical field
The utility model belongs to power equipment high-altitude working safety engineering device technique field, and in particular to one kind is protected for stone bridge The suspension platform of column power construction.
Background technique
In the prior art, it is laid in Poling Construction in stone bridge guardrail excessively along bridge in power cable and communication line, in city During stone bridge guardrail streetlamp cable in city's road is set up, and in job executions processes such as Bridge guardrail illuminator route installations Middle that operator is needed to carry out operation in the outside of Bridge guardrail, traditional mode of operation is to bundle worker with hawser, personnel The mobile installation of guardrail outer ledge is trampled, there is no dedicated security apparatus at present;Service personnel walks in implementation operation or movement When, it is likely to step on sky at any time, falls the danger fallen, power equipment also has the danger for falling damage, gives maintenance construction personnel Safety brings greatly inconvenient and hidden danger.
For the risk of stone bridge guardrail high altitude operation, prevents people and equipment from high falling, design a kind of place adaptation Ability is strong, compact-sized, lightweight and portable in volume, robust safety-type stone bridge guardrail aerial suspension job platform easy for installation, side It helps construction personnel's standing platform to carry out high altitude operation, the generation of the accident of falling at high altitude is avoided to seem very necessary.
Summary of the invention
The purpose of this utility model is the technical problem for solving the prior art and there is operation transhipment inconvenience and safety difference, is mentioned For a kind of suspension platform for stone bridge guardrail power construction, with overcome the deficiencies in the prior art.
To achieve the goals above, a kind of suspension platform for stone bridge guardrail power construction of the utility model, it includes Counterweight sole;
The counterweight sole is mutually permanently connected by one end of support frame and the load bearing cross beam being disposed there above;Institute The other end for stating load bearing cross beam is connected with each other by locking hook and the top for the overhead support bracket being placed on the outside of Bridge guardrail; The bottom end of the overhead support bracket is equipped with job platform;The middle part of the overhead support bracket is equipped with adjustable guide bars, and adjustable leads Draw beam equipped with guide roller corresponding with Bridge guardrail.
For the ease of mobile operation, the bottom end of the counterweight sole is equipped with the universal wheel of strap brake.
In order to improve operational security, the counterweight sole passes through safety cable and earth anchor and the fixed company of ground limit It connects.
For the ease of climbing, the overhead support bracket is equipped with ladder.
It falls in order to prevent, the job platform is equipped with fence.
The structure design of the utility model is reasonable, easy to use, and counterweight sole is used to place counterweight, to play support Effect, prevents job platform from being toppled over again, safety is effectively ensured;Cooperation safety cable and earth anchor securely connect with ground It connects, safety is reliable.One end of load bearing cross beam is connect with counterweight sole, and the other end is connect with overhead support bracket, and middle part can be used Intert the guardrail of bridge, i.e. job platform is corresponding with the outside of Bridge guardrail, the inside of counterweight sole and Bridge guardrail is right It answers, forms the state for straddling Bridge guardrail, balance is conducive to construction operation well.Adjustable guide bars are adjusted horizontal by guide roller To position, convenient for operator adjust horizontal position, be convenient for operation.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
1 in figure, it is latched hook 2, ladder 3, load bearing cross beam 4, overhead support bracket 5, adjustable guide bars 6, Bridge guardrail 7, universal wheel 8, guide roller 9, fence 10, support frame 11, safety cable 12, earth anchor 13, counterweight sole 14, Job platform.
Specific embodiment
Referring to Fig.1, the utility model it include counterweight sole 13;
The counterweight sole 13 is fixed to each other company by support frame 10 with the one end of load bearing cross beam 3 being disposed there above It connects;The top that the other end of the load bearing cross beam 3 passes through locking hook 1 and the overhead support bracket 4 for being placed on 6 outside of Bridge guardrail It is connected with each other;The bottom end of the overhead support bracket 4 is equipped with job platform 14;The middle part of the overhead support bracket 4 is equipped with adjustable lead Draw beam 5, and adjustable guide bars 5 are equipped with guide roller 8 corresponding with Bridge guardrail 6.
For the ease of mobile operation, the bottom end of the counterweight sole 13 is equipped with the universal wheel 7 of strap brake.
In order to improve operational security, the counterweight sole 13 is solid by safety cable 11 and earth anchor 12 and ground limit Fixed connection.
For the ease of climbing, the overhead support bracket 4 is equipped with ladder 2.
It falls in order to prevent, the job platform 14 is equipped with fence 9.
The structure design of the utility model is reasonable, easy to use, and counterweight sole is used to place counterweight, to play support Effect, prevents job platform from being toppled over again, safety is effectively ensured;Cooperation safety cable and earth anchor securely connect with ground It connects, safety is reliable.One end of load bearing cross beam is connect with counterweight sole, and the other end is connect with overhead support bracket, and middle part can be used Intert the guardrail of bridge, i.e. job platform is corresponding with the outside of Bridge guardrail, the inside of counterweight sole and Bridge guardrail is right It answers, forms the state for straddling Bridge guardrail, balance is conducive to construction operation well.Adjustable guide bars are adjusted horizontal by guide roller To position, convenient for operator adjust horizontal position, be convenient for operation.

Claims (5)

1. a kind of suspension platform for stone bridge guardrail power construction, it is characterized in that: it includes counterweight sole (13);
The counterweight sole (13) is fixed to each other by support frame (10) and the one end for the load bearing cross beam (3) being disposed there above Connection;The other end of the load bearing cross beam (3) is supported by locking hook (1) with the suspention being placed on the outside of Bridge guardrail (6) The top of frame (4) is connected with each other;The bottom end of the overhead support bracket (4) is equipped with job platform (14);The overhead support bracket (4) Middle part be equipped with adjustable guide bars (5), and adjustable guide bars (5) be equipped with guide roller corresponding with Bridge guardrail (6) (8).
2. a kind of suspension platform for stone bridge guardrail power construction according to claim 1, it is characterized in that the counterweight The bottom end of sole (13) is equipped with the universal wheel (7) of strap brake.
3. a kind of suspension platform for stone bridge guardrail power construction according to claim 1, it is characterized in that the counterweight Sole (13) is fixedly connected by safety cable (11) and earth anchor (12) with ground limit.
4. a kind of suspension platform for stone bridge guardrail power construction according to claim 1, it is characterized in that the suspention Support frame (4) is equipped with ladder (2).
5. a kind of suspension platform for stone bridge guardrail power construction according to claim 1, it is characterized in that the operation Platform (14) is equipped with fence (9).
CN201821051203.3U 2018-07-04 2018-07-04 A kind of suspension platform for stone bridge guardrail power construction Expired - Fee Related CN208415116U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821051203.3U CN208415116U (en) 2018-07-04 2018-07-04 A kind of suspension platform for stone bridge guardrail power construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821051203.3U CN208415116U (en) 2018-07-04 2018-07-04 A kind of suspension platform for stone bridge guardrail power construction

Publications (1)

Publication Number Publication Date
CN208415116U true CN208415116U (en) 2019-01-22

Family

ID=65124981

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821051203.3U Expired - Fee Related CN208415116U (en) 2018-07-04 2018-07-04 A kind of suspension platform for stone bridge guardrail power construction

Country Status (1)

Country Link
CN (1) CN208415116U (en)

Similar Documents

Publication Publication Date Title
US10030397B2 (en) Fall protection system
CN104288935A (en) Wire rope anti-falling system and installation method thereof
CN210698685U (en) Climbing assisting device for power transmission line tower
CN210084788U (en) Tower crane for building
CN104291222B (en) The inner hard protection of a kind of high-rise building Core Walls Structure hangs integrated system with row
CN205188839U (en) Movably -assembled anti -collision bridge wall construction hanging basket
CN204170002U (en) A kind of artificial digging pile safety apparatus
CN208415116U (en) A kind of suspension platform for stone bridge guardrail power construction
CN204418629U (en) A kind of integrated form climbing frame
CN209637672U (en) Leak cable bracket installation exercise tower wagon in tunnel
JP2019127750A (en) Installation method for hanging scaffolding in bridge structure and hanging scaffolding
CN205171979U (en) Integrated form all steel lift platform
CN111851982A (en) Scaffold frame liftable prevents weighing down safety device
CN207827621U (en) A kind of movable ultrahigh layer construction elevator guide rail bracket attachment device
CN203800449U (en) Overhaul platform of equipment on transformer station pillar
CN111056447A (en) Tower crane climbing system
CN206487129U (en) Safety hanging cradle for industrial premises Construction of Steel Structure
CN211775606U (en) Regularization assembled that can have enough to meet need climbs frame and goes up people's passageway
CN215717106U (en) Hanging basket with protective structure
CN213087488U (en) Portable high elasticity construction safety protection network of supporting
CN205873594U (en) Special construction elevator of cooling tower section of thick bamboo wall
CN204038917U (en) Dismountable external hanging service platform
CN208844441U (en) Bridge beam body operation platform
CN204073183U (en) A kind of cable wire drop preventer
CN207785698U (en) A kind of training vertical safe anti-falling line of steel tower climbing

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190122

Termination date: 20190704

CF01 Termination of patent right due to non-payment of annual fee