CN208415116U - A kind of suspension platform for stone bridge guardrail power construction - Google Patents
A kind of suspension platform for stone bridge guardrail power construction Download PDFInfo
- Publication number
- CN208415116U CN208415116U CN201821051203.3U CN201821051203U CN208415116U CN 208415116 U CN208415116 U CN 208415116U CN 201821051203 U CN201821051203 U CN 201821051203U CN 208415116 U CN208415116 U CN 208415116U
- Authority
- CN
- China
- Prior art keywords
- bridge guardrail
- counterweight
- sole
- support bracket
- power construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)
Abstract
The utility model discloses a kind of suspension platforms for stone bridge guardrail power construction, it includes counterweight sole;Counterweight sole is fixedly connected with one end of load bearing cross beam;The other end of load bearing cross beam is connect with overhead support bracket;The bottom end of overhead support bracket is equipped with job platform;The middle part of overhead support bracket is equipped with adjustable guide bars, and adjustable guide bars are equipped with guide roller corresponding with Bridge guardrail.Counterweight sole is used to place counterweight, to play the role of support, prevents job platform from being toppled over again;One end of load bearing cross beam is connect with counterweight sole, the other end is connect with overhead support bracket, middle part can be used to the guardrail of interspersed bridge, i.e. job platform is corresponding with the outside of Bridge guardrail, counterweight sole is corresponding with the inside of Bridge guardrail, the state for straddling Bridge guardrail is formed, balance is conducive to construction operation well.The adjustable guide bars position lateral by guide roller adjustment, adjusts horizontal position convenient for operator, is convenient for operation.
Description
Technical field
The utility model belongs to power equipment high-altitude working safety engineering device technique field, and in particular to one kind is protected for stone bridge
The suspension platform of column power construction.
Background technique
In the prior art, it is laid in Poling Construction in stone bridge guardrail excessively along bridge in power cable and communication line, in city
During stone bridge guardrail streetlamp cable in city's road is set up, and in job executions processes such as Bridge guardrail illuminator route installations
Middle that operator is needed to carry out operation in the outside of Bridge guardrail, traditional mode of operation is to bundle worker with hawser, personnel
The mobile installation of guardrail outer ledge is trampled, there is no dedicated security apparatus at present;Service personnel walks in implementation operation or movement
When, it is likely to step on sky at any time, falls the danger fallen, power equipment also has the danger for falling damage, gives maintenance construction personnel
Safety brings greatly inconvenient and hidden danger.
For the risk of stone bridge guardrail high altitude operation, prevents people and equipment from high falling, design a kind of place adaptation
Ability is strong, compact-sized, lightweight and portable in volume, robust safety-type stone bridge guardrail aerial suspension job platform easy for installation, side
It helps construction personnel's standing platform to carry out high altitude operation, the generation of the accident of falling at high altitude is avoided to seem very necessary.
Summary of the invention
The purpose of this utility model is the technical problem for solving the prior art and there is operation transhipment inconvenience and safety difference, is mentioned
For a kind of suspension platform for stone bridge guardrail power construction, with overcome the deficiencies in the prior art.
To achieve the goals above, a kind of suspension platform for stone bridge guardrail power construction of the utility model, it includes
Counterweight sole;
The counterweight sole is mutually permanently connected by one end of support frame and the load bearing cross beam being disposed there above;Institute
The other end for stating load bearing cross beam is connected with each other by locking hook and the top for the overhead support bracket being placed on the outside of Bridge guardrail;
The bottom end of the overhead support bracket is equipped with job platform;The middle part of the overhead support bracket is equipped with adjustable guide bars, and adjustable leads
Draw beam equipped with guide roller corresponding with Bridge guardrail.
For the ease of mobile operation, the bottom end of the counterweight sole is equipped with the universal wheel of strap brake.
In order to improve operational security, the counterweight sole passes through safety cable and earth anchor and the fixed company of ground limit
It connects.
For the ease of climbing, the overhead support bracket is equipped with ladder.
It falls in order to prevent, the job platform is equipped with fence.
The structure design of the utility model is reasonable, easy to use, and counterweight sole is used to place counterweight, to play support
Effect, prevents job platform from being toppled over again, safety is effectively ensured;Cooperation safety cable and earth anchor securely connect with ground
It connects, safety is reliable.One end of load bearing cross beam is connect with counterweight sole, and the other end is connect with overhead support bracket, and middle part can be used
Intert the guardrail of bridge, i.e. job platform is corresponding with the outside of Bridge guardrail, the inside of counterweight sole and Bridge guardrail is right
It answers, forms the state for straddling Bridge guardrail, balance is conducive to construction operation well.Adjustable guide bars are adjusted horizontal by guide roller
To position, convenient for operator adjust horizontal position, be convenient for operation.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
1 in figure, it is latched hook 2, ladder 3, load bearing cross beam 4, overhead support bracket 5, adjustable guide bars 6, Bridge guardrail
7, universal wheel 8, guide roller 9, fence 10, support frame 11, safety cable 12, earth anchor 13, counterweight sole 14,
Job platform.
Specific embodiment
Referring to Fig.1, the utility model it include counterweight sole 13;
The counterweight sole 13 is fixed to each other company by support frame 10 with the one end of load bearing cross beam 3 being disposed there above
It connects;The top that the other end of the load bearing cross beam 3 passes through locking hook 1 and the overhead support bracket 4 for being placed on 6 outside of Bridge guardrail
It is connected with each other;The bottom end of the overhead support bracket 4 is equipped with job platform 14;The middle part of the overhead support bracket 4 is equipped with adjustable lead
Draw beam 5, and adjustable guide bars 5 are equipped with guide roller 8 corresponding with Bridge guardrail 6.
For the ease of mobile operation, the bottom end of the counterweight sole 13 is equipped with the universal wheel 7 of strap brake.
In order to improve operational security, the counterweight sole 13 is solid by safety cable 11 and earth anchor 12 and ground limit
Fixed connection.
For the ease of climbing, the overhead support bracket 4 is equipped with ladder 2.
It falls in order to prevent, the job platform 14 is equipped with fence 9.
The structure design of the utility model is reasonable, easy to use, and counterweight sole is used to place counterweight, to play support
Effect, prevents job platform from being toppled over again, safety is effectively ensured;Cooperation safety cable and earth anchor securely connect with ground
It connects, safety is reliable.One end of load bearing cross beam is connect with counterweight sole, and the other end is connect with overhead support bracket, and middle part can be used
Intert the guardrail of bridge, i.e. job platform is corresponding with the outside of Bridge guardrail, the inside of counterweight sole and Bridge guardrail is right
It answers, forms the state for straddling Bridge guardrail, balance is conducive to construction operation well.Adjustable guide bars are adjusted horizontal by guide roller
To position, convenient for operator adjust horizontal position, be convenient for operation.
Claims (5)
1. a kind of suspension platform for stone bridge guardrail power construction, it is characterized in that: it includes counterweight sole (13);
The counterweight sole (13) is fixed to each other by support frame (10) and the one end for the load bearing cross beam (3) being disposed there above
Connection;The other end of the load bearing cross beam (3) is supported by locking hook (1) with the suspention being placed on the outside of Bridge guardrail (6)
The top of frame (4) is connected with each other;The bottom end of the overhead support bracket (4) is equipped with job platform (14);The overhead support bracket (4)
Middle part be equipped with adjustable guide bars (5), and adjustable guide bars (5) be equipped with guide roller corresponding with Bridge guardrail (6)
(8).
2. a kind of suspension platform for stone bridge guardrail power construction according to claim 1, it is characterized in that the counterweight
The bottom end of sole (13) is equipped with the universal wheel (7) of strap brake.
3. a kind of suspension platform for stone bridge guardrail power construction according to claim 1, it is characterized in that the counterweight
Sole (13) is fixedly connected by safety cable (11) and earth anchor (12) with ground limit.
4. a kind of suspension platform for stone bridge guardrail power construction according to claim 1, it is characterized in that the suspention
Support frame (4) is equipped with ladder (2).
5. a kind of suspension platform for stone bridge guardrail power construction according to claim 1, it is characterized in that the operation
Platform (14) is equipped with fence (9).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821051203.3U CN208415116U (en) | 2018-07-04 | 2018-07-04 | A kind of suspension platform for stone bridge guardrail power construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821051203.3U CN208415116U (en) | 2018-07-04 | 2018-07-04 | A kind of suspension platform for stone bridge guardrail power construction |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208415116U true CN208415116U (en) | 2019-01-22 |
Family
ID=65124981
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821051203.3U Expired - Fee Related CN208415116U (en) | 2018-07-04 | 2018-07-04 | A kind of suspension platform for stone bridge guardrail power construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208415116U (en) |
-
2018
- 2018-07-04 CN CN201821051203.3U patent/CN208415116U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US10030397B2 (en) | Fall protection system | |
CN104288935A (en) | Wire rope anti-falling system and installation method thereof | |
CN210698685U (en) | Climbing assisting device for power transmission line tower | |
CN210084788U (en) | Tower crane for building | |
CN104291222B (en) | The inner hard protection of a kind of high-rise building Core Walls Structure hangs integrated system with row | |
CN205188839U (en) | Movably -assembled anti -collision bridge wall construction hanging basket | |
CN204170002U (en) | A kind of artificial digging pile safety apparatus | |
CN208415116U (en) | A kind of suspension platform for stone bridge guardrail power construction | |
CN204418629U (en) | A kind of integrated form climbing frame | |
CN209637672U (en) | Leak cable bracket installation exercise tower wagon in tunnel | |
JP2019127750A (en) | Installation method for hanging scaffolding in bridge structure and hanging scaffolding | |
CN205171979U (en) | Integrated form all steel lift platform | |
CN111851982A (en) | Scaffold frame liftable prevents weighing down safety device | |
CN207827621U (en) | A kind of movable ultrahigh layer construction elevator guide rail bracket attachment device | |
CN203800449U (en) | Overhaul platform of equipment on transformer station pillar | |
CN111056447A (en) | Tower crane climbing system | |
CN206487129U (en) | Safety hanging cradle for industrial premises Construction of Steel Structure | |
CN211775606U (en) | Regularization assembled that can have enough to meet need climbs frame and goes up people's passageway | |
CN215717106U (en) | Hanging basket with protective structure | |
CN213087488U (en) | Portable high elasticity construction safety protection network of supporting | |
CN205873594U (en) | Special construction elevator of cooling tower section of thick bamboo wall | |
CN204038917U (en) | Dismountable external hanging service platform | |
CN208844441U (en) | Bridge beam body operation platform | |
CN204073183U (en) | A kind of cable wire drop preventer | |
CN207785698U (en) | A kind of training vertical safe anti-falling line of steel tower climbing |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190122 Termination date: 20190704 |
|
CF01 | Termination of patent right due to non-payment of annual fee |