CN111851982A - Scaffold frame liftable prevents weighing down safety device - Google Patents

Scaffold frame liftable prevents weighing down safety device Download PDF

Info

Publication number
CN111851982A
CN111851982A CN202010762448.2A CN202010762448A CN111851982A CN 111851982 A CN111851982 A CN 111851982A CN 202010762448 A CN202010762448 A CN 202010762448A CN 111851982 A CN111851982 A CN 111851982A
Authority
CN
China
Prior art keywords
wire rope
scaffold
steel wire
rope
safety device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202010762448.2A
Other languages
Chinese (zh)
Inventor
左跃华
左慧媛
崔雯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202010762448.2A priority Critical patent/CN111851982A/en
Publication of CN111851982A publication Critical patent/CN111851982A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G5/00Component parts or accessories for scaffolds
    • E04G5/001Safety or protective measures against falling down relating to scaffoldings
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G1/00Scaffolds primarily resting on the ground

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Emergency Lowering Means (AREA)

Abstract

The invention discloses a lifting anti-falling safety device for a scaffold, which comprises: the steel wire rope is arranged on the vertical rods at two ends of the scaffold and connected with the vertical rods through the connecting piece, the limiting buckle is arranged below the joint of the steel wire rope and the vertical rods to prevent the steel wire rope from sliding downwards, and safety belts of constructors are hung on the steel wire rope. The invention solves the problem that the construction of the existing constructors on the scaffold is unsafe.

Description

Scaffold frame liftable prevents weighing down safety device
Technical Field
The invention relates to the field of construction safety guarantee equipment, in particular to a lifting anti-falling safety device for a scaffold.
Background
The existing scaffold operating personnel are arranged and dismantled on a scaffold body (the scaffold body refers to the whole scaffold body of the scaffold, and comprises a scaffold foundation and a scaffold body which is formed by erecting rod pieces such as vertical rods, longitudinal rods, transverse rods and cross braces and the like, and the like), and because the operating personnel are always positioned at the topmost end of the scaffold, a safety belt is hung everywhere. The safety belt is hung on a vertical rod or a vertical and horizontal rod under the feet of an operator in the prior art, the method is inconvenient for hanging and taking the safety belt, the operator cannot walk on a frame body conveniently, a new potential safety hazard is formed under the feet of the operator, and in addition, the method also does not accord with the national use principle of high hanging and low using in the safety belt use regulations. Meanwhile, because the safety belt is hung at a low position, when the safety belt falls carelessly in the operation process of personnel, the height difference of at least more than two meters exists, even if the safety belt can pull the personnel, all the periphery of the operation is various frame body pipe fittings due to falling from a high position, and casualty accidents are easily caused. Due to the reasons, under most conditions, the existing operators do not hang safety belts or only carry the safety belts on their backs to risk the operation, so that the safety hazards are greatly brought to the life safety of the operators, and the safety risks are also greatly brought to the safety management work of enterprises.
Disclosure of Invention
Therefore, the invention provides a lifting anti-falling safety device for a scaffold, which aims to solve the problem that the existing constructors are unsafe to construct on the scaffold.
In order to achieve the above purpose, the invention provides the following technical scheme:
the invention discloses a lifting anti-falling safety device for a scaffold, which comprises: the steel wire rope is arranged on the vertical rods at two ends of the scaffold and connected with the vertical rods through the connecting piece, the limiting buckle is arranged below the joint of the steel wire rope and the vertical rods to prevent the steel wire rope from sliding downwards, and safety belts of constructors are hung on the steel wire rope.
Furthermore, the scaffold comprises vertical rods, longitudinal horizontal rods and small cross rods, wherein the vertical rods, the longitudinal horizontal rods and the small cross rods are perpendicular to each other two by two and are connected through cross fasteners, and the vertical rods are uniformly connected with the vertical rods at equal intervals.
Furthermore, the longitudinal horizontal rod is fixedly connected with the building through a scaffold wall connecting piece, and one end of the scaffold wall connecting piece is inserted into the building and connected with an embedded rod piece in the building.
Furthermore, the two ends of the steel wire rope are respectively fixed on the vertical rods at the two ends of the scaffold, and the middle of the steel wire rope is lapped on the small cross rod in the middle of the scaffold to prevent the steel wire rope from bending and falling.
Furthermore, the steel wire rope is 1500mm-2000mm higher than a standing working surface of a constructor, and one end of a safety belt on the constructor is sleeved on the steel wire rope and can freely move along the steel wire rope.
Further, the connecting piece includes main rope, vice rope and wire rope buckle, and the pole setting that scaffold was walked around to wire rope's one end becomes vice rope, and vice rope is walked around and is formed oval space with main rope after the pole setting, installs the wire rope lantern ring in the space, and the pole setting is lived to the wire rope lantern ring cover, has the 10mm space between the wire rope lantern ring and the pole setting, the wire rope rebound of being convenient for, and main rope passes through wire rope buckle fixed connection with vice rope.
Further, the connecting piece can be on the pole setting height-adjusting, along with the adjustment of scaffold frame height, changes wire rope's height.
The invention has the following advantages:
the invention discloses a lifting anti-falling safety device for a scaffold, which is characterized in that steel wire ropes are connected to vertical rods at two ends of the scaffold, the steel wire ropes penetrate through the top working surface of the whole scaffold at a position which is 1500-2000 mm higher than the standing working surface of a constructor, the safety ropes of the constructor can be hung on the steel wire ropes, and the safety of the constructor is ensured. The condition that the safety rope is hung on the standing working face of the sole of the constructor is avoided, the safety rope can freely slide along the steel wire rope, the constructor can conveniently change construction operation points, and construction requirements are met.
Drawings
In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings used in the description of the embodiments or the prior art will be briefly described below. It should be apparent that the drawings in the following description are merely exemplary, and that other embodiments can be derived from the drawings provided by those of ordinary skill in the art without inventive effort.
The structures, ratios, sizes, and the like shown in the present specification are only used for matching with the contents disclosed in the specification, so as to be understood and read by those skilled in the art, and are not used to limit the conditions that the present invention can be implemented, so that the present invention has no technical significance, and any structural modifications, changes in the ratio relationship, or adjustments of the sizes, without affecting the effects and the achievable by the present invention, should still fall within the range that the technical contents disclosed in the present invention can cover.
FIG. 1 is a schematic side view of an installation of a lifting anti-falling safety device of a scaffold provided by an embodiment of the invention;
FIG. 2 is a schematic view of a top-down installation of a scaffold liftable fall-prevention safety device provided by an embodiment of the invention;
FIG. 3 is a schematic view of a connecting member structure of a scaffold lifting anti-falling safety device provided by an embodiment of the invention;
in the figure: 1-steel wire rope, 2-limit buckle, 3-vertical rod, 4-longitudinal horizontal rod, 5-scaffold wall connecting piece, 6-embedded rod piece, 7-main rope, 8-auxiliary rope, 9-steel wire rope buckle, 10-steel wire rope lantern ring, 11-small cross rod and 12-cross fastener.
Detailed Description
The present invention is described in terms of particular embodiments, other advantages and features of the invention will become apparent to those skilled in the art from the following disclosure, and it is to be understood that the described embodiments are merely exemplary of the invention and that it is not intended to limit the invention to the particular embodiments disclosed. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Examples
This embodiment discloses a scaffold frame liftable prevents weighing down safety device, the device includes: wire rope 1 and spacing buckle 2, wire rope 1 installs on the pole setting 3 at scaffold frame both ends, and wire rope 1 passes through the connecting piece to be connected with pole setting 3, is provided with spacing buckle 2 below wire rope 1 and 3 junctions of pole setting, prevents that wire rope 1 from gliding, and constructor's safety belt hangs on wire rope 1. Spacing buckle 2 fixed joint is on pole setting 3, and wire rope 1 is spacing by spacing buckle 2, avoids wire rope 1 gliding to appear, reduces the condition of wire rope 1 height. The diameter of the steel wire rope is selected autonomously according to actual use requirements, and the construction safety requirements are met.
The scaffold comprises upright rods 3, longitudinal horizontal rods 4 and small cross rods 11, wherein the upright rods 3, the longitudinal horizontal rods 4 and the small cross rods 11 are perpendicular to each other two by two and are connected through cross fasteners 12, and a plurality of upright rods 3 are uniformly connected on the longitudinal horizontal rods 4 at equal intervals. The longitudinal horizontal rod 4 is fixedly connected with a building through a scaffold wall connecting piece 5, and one end of the scaffold wall connecting piece 5 is inserted into the building and is connected with an embedded rod piece 6 in the building. The scaffold is wall spare 5 even and is played the effect of fixed scaffold, avoids the scaffold to rock, the skew position.
Two ends of a steel wire rope 1 are respectively fixed on upright posts 3 at two ends of the scaffold through connecting pieces, the connecting positions of the steel wire rope and connecting rods at two ends can be selected to be in diagonal connection or linear connection, and the middle of the steel wire rope 1 is lapped on a small cross rod 11 in the middle of the scaffold, so that the steel wire rope is prevented from bending and falling too much, and the height of the safety rope cannot be hung. The height of the steel wire rope 1 is 1500-2000 mm higher than the standing working surface of a constructor, and one end of a safety belt on the constructor is sleeved on the steel wire rope 1 and can freely move along the steel wire rope 1.
The connecting piece includes main rope 7, vice rope 8 and wire rope buckle 9, pole setting 3 that the scaffold was walked around to wire rope 1's one end becomes vice rope 8, 3 backs of pole setting and main rope 7 formation oval spaces are walked around to vice rope 8, installation wire rope lantern ring 10 in the space, pole setting 3 is entangled to wire rope lantern ring 10, 10mm spaces have between wire rope lantern ring 10 and the pole setting 3, the wire rope rebound of being convenient for, the space between wire rope lantern ring 10 and the pole setting 3 is less than the diameter of spacing buckle 2, so spacing buckle 2 can avoid the wire rope gliding, can realize wire rope freedom rebound again, the height adjustment, main rope 7 passes through wire rope buckle 9 fixed connection with vice rope 8. The connecting piece can be at pole setting 3 go up height-adjusting, along with the adjustment of scaffold frame height, changes wire rope 1's height.
The specific operation flow is as follows: erecting a single-side scaffold, aligning the farthest end to the corner upright rod 3, wherein the height is not less than 2000mm of the scaffold of the next step, and sleeving a special safety steel wire rope on the upright rod 3; the special steel wire rope 1 is adjusted to be 1500mm to 2000mm higher than the scaffold of the lower step, and is fixed at the lower part by a limit buckle 2. A small cross bar 11 is arranged in the middle of the steel wire rope 1 every 15000mm to 20000mm to prevent the steel wire rope 1 from overhung. The operator hangs the safety rope on the special steel wire rope 1 for operation. After the scaffold of the step is erected, the safety steel wire rope slides upwards along the vertical direction of the upright rod 3; when the scaffold is dismantled, the scaffold slides downwards, and the upright rods 3 on the two sides meet the requirement that the special safety steel wire rope 1 is hung at a certain height, and the scaffold is descended to the safety height of 2000 mm.
Although the invention has been described in detail above with reference to a general description and specific examples, it will be apparent to one skilled in the art that modifications or improvements may be made thereto based on the invention. Accordingly, such modifications and improvements are intended to be within the scope of the invention as claimed.

Claims (7)

1. The utility model provides a scaffold frame liftable prevent weighing down safety device which characterized in that, the device includes: the steel wire rope is arranged on the vertical rods at two ends of the scaffold and connected with the vertical rods through the connecting piece, the limiting buckle is arranged below the joint of the steel wire rope and the vertical rods to prevent the steel wire rope from sliding downwards, and safety belts of constructors are hung on the steel wire rope.
2. The liftable fall-preventing safety device of a scaffold as claimed in claim 1, wherein the scaffold comprises vertical rods, longitudinal horizontal rods and small cross rods, the vertical rods, the longitudinal horizontal rods and the small cross rods are perpendicular to each other in pairs and are connected through cross fasteners, and the vertical rods are uniformly connected with a plurality of vertical rods at equal intervals.
3. The scaffold liftable fall prevention safety device according to claim 2, wherein the longitudinal horizontal rod is fixedly connected with the building through a scaffold wall connecting piece, and one end of the scaffold wall connecting piece is inserted into the building and connected with an embedded rod in the building.
4. The liftable fall-preventing safety device for the scaffold as claimed in claim 1, wherein two ends of the wire rope are respectively fixed on the vertical rods at two ends of the scaffold, and the middle of the wire rope is lapped on the small cross rod at the middle part of the scaffold to prevent the wire rope from bending and falling down.
5. The liftable fall prevention safety device for the scaffold as claimed in claim 1, wherein the wire rope is 1500mm-2000mm higher than the standing working surface of the constructor, and one end of the safety belt on the constructor is sleeved on the wire rope and can freely move along the wire rope.
6. The liftable fall-preventing safety device of a scaffold as claimed in claim 1, wherein the connecting member comprises a main rope, an auxiliary rope and a steel wire rope buckle, one end of the steel wire rope is wound around the vertical rod of the scaffold to form the auxiliary rope, the auxiliary rope is wound around the vertical rod to form an oval gap with the main rope, a steel wire rope sleeve ring is installed in the gap, the vertical rod is sleeved by the steel wire rope sleeve ring, a 10mm gap is formed between the steel wire rope sleeve ring and the vertical rod to facilitate the upward movement of the steel wire rope, and the main rope and the auxiliary rope are fixedly connected through the steel.
7. A scaffold liftable fall arrest safety device according to claim 1, wherein the connectors are adjustable in height on the uprights to vary the height of the wire rope as the scaffold is adjusted.
CN202010762448.2A 2020-07-31 2020-07-31 Scaffold frame liftable prevents weighing down safety device Withdrawn CN111851982A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010762448.2A CN111851982A (en) 2020-07-31 2020-07-31 Scaffold frame liftable prevents weighing down safety device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010762448.2A CN111851982A (en) 2020-07-31 2020-07-31 Scaffold frame liftable prevents weighing down safety device

Publications (1)

Publication Number Publication Date
CN111851982A true CN111851982A (en) 2020-10-30

Family

ID=72954084

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010762448.2A Withdrawn CN111851982A (en) 2020-07-31 2020-07-31 Scaffold frame liftable prevents weighing down safety device

Country Status (1)

Country Link
CN (1) CN111851982A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113638593A (en) * 2021-06-18 2021-11-12 珠海华金开发建设有限公司 Safety belt fastening method in whole process of scaffold assembling and disassembling
CN115463355A (en) * 2022-09-29 2022-12-13 中国五冶集团有限公司 Safety rope fixing device used during erection and dismantling of high-altitude frame body

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113638593A (en) * 2021-06-18 2021-11-12 珠海华金开发建设有限公司 Safety belt fastening method in whole process of scaffold assembling and disassembling
CN115463355A (en) * 2022-09-29 2022-12-13 中国五冶集团有限公司 Safety rope fixing device used during erection and dismantling of high-altitude frame body

Similar Documents

Publication Publication Date Title
CN106958346B (en) Intelligent attached lifting scaffold equipment for curved surface super high-rise building and construction method
CN206016226U (en) Tool type scaffold interlayer guard system
CN111851982A (en) Scaffold frame liftable prevents weighing down safety device
CN107090968A (en) Integrated form attached lifting scaffold and its elevating method
CN112681714A (en) Construction method of steel wire rope lengthened rear support type hanging basket
CN104674992A (en) Supporting method and structure of suspended steel bar truss deck
CN205822747U (en) Architectural engineering scaffold
CN213418441U (en) Safety protection and operation platform for light production well
CN207620384U (en) Jack device for discharging
CN201649607U (en) Overhung-type outer wall scaffold
CN204038917U (en) Dismountable external hanging service platform
CN210342619U (en) Connecting piece of integral lifting scaffold
CN209760761U (en) Construction platform and elevator core section of thick bamboo construction structures in a core section of thick bamboo
CN207513201U (en) A kind of roofing cornices installation mobile device
CN207144444U (en) A kind of Super High scaffold used for outwall construction
CN219158495U (en) Anti-falling device for elevator shaft construction
CN110565931A (en) Assembled scaffold for road construction
CN110748140A (en) Track beam hanging basket special for stepped curtain wall
CN203878962U (en) Independent supporting device for high-place operation hanging basket cantilever
CN214498459U (en) Turnover elevator shaft protection device
CN212406019U (en) Adjustable regularization safety operation platform construction equipment
CN218668452U (en) Slidingtype hanging flower basket construction equipment
CN221031305U (en) Overhanging operation platform device
CN216739315U (en) Arch bridge construction frame
CN210396065U (en) Outer balcony masonry operation frame

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication
WW01 Invention patent application withdrawn after publication

Application publication date: 20201030