CN208362936U - A kind of bridge construction Bridge Erector - Google Patents

A kind of bridge construction Bridge Erector Download PDF

Info

Publication number
CN208362936U
CN208362936U CN201821015244.7U CN201821015244U CN208362936U CN 208362936 U CN208362936 U CN 208362936U CN 201821015244 U CN201821015244 U CN 201821015244U CN 208362936 U CN208362936 U CN 208362936U
Authority
CN
China
Prior art keywords
bridge
hoisting apparatus
sunpender
hydraulic hoisting
crossbeam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821015244.7U
Other languages
Chinese (zh)
Inventor
赵增洋
韩明利
陈国军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan Henan Wei Crane Co Ltd
Original Assignee
Henan Henan Wei Crane Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan Henan Wei Crane Co Ltd filed Critical Henan Henan Wei Crane Co Ltd
Priority to CN201821015244.7U priority Critical patent/CN208362936U/en
Application granted granted Critical
Publication of CN208362936U publication Critical patent/CN208362936U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of bridge construction Bridge Erectors, including Bridge Erector ontology, shaft, nose girder plate, first sunpender, bridge, bridge pier, supporting leg, second sunpender, control room, battery, first hydraulic hoisting apparatus, flexible bale handle hook, crossbeam, second hydraulic hoisting apparatus and solar panels, the two sides of the bottom of the bridge machine ontology are equipped with bridge pier, the side of the bridge pier is equipped with supporting leg, the top of the supporting leg is equipped with crossbeam, the two sides of the bottom of the crossbeam are equipped with the second hydraulic hoisting apparatus, the side of second hydraulic hoisting apparatus is equipped with shaft, the side of the shaft is equipped with the first sunpender and the second sunpender, this kind of bridge construction Bridge Erector, it is stored in battery using solar power generation, for the electricity usage of control room, it brings conveniently.By the way that inclined nose girder plate is arranged, it can make people are easier bridge is installed on bridge pier, improve efficiency, save the time.

Description

A kind of bridge construction Bridge Erector
Technical field
The utility model relates to a kind of Bridge Erector, in particular to a kind of bridge construction Bridge Erector.
Background technique
Bridge Erector is exactly the equipment that prefabricated beam piece is placed into prefabricated bridge pier and is got on.Bridge Erector belongs to crane Scope is put down after being then transported to position because its major function is to lift beam piece.Bridge Erector and lifting in general sense Machine is very different.Its desired condition is harsh, and there are beam on piece travelings, or cry vertical shift.Bridge Erector is divided into erection Highway bridge, conventional railway bridge, railway of passengers' private line bridge etc. are several.
For existing bridge construction Bridge Erector, it not can use solar energy heat absorbing power generation, used for control room, It is no easier, the time is saved, the bridge improved efficiency places setting, brings inconvenience.
Utility model content
It is mentioned above in the background art to solve the purpose of this utility model is to provide a kind of bridge construction Bridge Erector Problem.
To achieve the above object, the utility model provides the following technical solutions:
A kind of bridge construction Bridge Erector, including Bridge Erector ontology, shaft, nose girder plate, the first sunpender, bridge, bridge pier, support Leg, the second sunpender, control room, battery, the first hydraulic hoisting apparatus, flexible bale handle hook, crossbeam, the second hydraulic hoisting apparatus and Solar panels, the two sides of the bottom of the bridge machine ontology are equipped with bridge pier, and the side of the bridge pier is equipped with supporting leg, the supporting leg Top be equipped with crossbeam, the two sides of the bottom of the crossbeam are equipped with the second hydraulic hoisting apparatus, second hydraulic hoisting apparatus Side be equipped with shaft, the side of the shaft is equipped with the first sunpender and the second sunpender, first sunpender and the second sunpender Side is equipped with nose girder plate, is equipped with the first hydraulic hoisting apparatus in the middle part of the bottom of the crossbeam, first hydraulic hoisting apparatus Side is equipped with flexible bale handle hook, and the side of the flexible bale handle hook is equipped with bridge, and the top of the Bridge Erector ontology is equipped with the sun Energy plate, the side of the solar panels are equipped with battery, and the side of the battery is equipped with control room.
Further, the supporting leg is fixed by welding in the two sides of crossbeam, and the first hydraulic hoisting apparatus passes through bolt It is fixed on the middle part of crossbeam, flexible bale handle hook is bolted on the first hydraulic hoisting apparatus.
Further, second hydraulic hoisting apparatus is bolted on crossbeam, and shaft passes through bolt and second Hydraulic hoisting apparatus is fixedly linked, and the first sunpender and the second sunpender are fixedly linked with shaft and nose girder plate respectively by bolt, leads Beam slab is oblique.
Further, the solar panels are embedded in the top of Bridge Erector ontology, and solar panels are electrical connected with battery.
Compared with prior art, the utility model has the following beneficial effects:
(1) this kind of bridge construction Bridge Erector, is stored in battery using solar power generation, is made for the electric power of control room With, bring conveniently.
(2) this kind of bridge construction Bridge Erector can make people easier by bridge by the way that inclined nose girder plate is arranged It is installed on bridge pier, improves efficiency, save the time.
Detailed description of the invention
Fig. 1 is a kind of overall structure figure of bridge construction Bridge Erector of the utility model.
In figure: 1, Bridge Erector ontology, 2, shaft, 3, nose girder plate, the 4, first sunpender, 5, bridge, 6, bridge pier, 7, supporting leg, 8, the second sunpender, 9, control room, 10, battery, the 11, first hydraulic hoisting apparatus, 12, flexible bale handle hook, 13, crossbeam, 14, the Two hydraulic hoisting apparatus, 15, solar panels.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
In the description of the present invention, it should be noted that term " on ", "lower", "inner", "outside" " end ", " preceding End ", " rear end ", " both ends ", " one end ", the instructions such as " other end " orientation or positional relationship be orientation based on the figure or Positional relationship is merely for convenience of describing the present invention and simplifying the description, rather than the device or member of indication or suggestion meaning Part must have a particular orientation, be constructed and operated in a specific orientation, therefore should not be understood as limiting the present invention. In addition, term " first ", " second " are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance.
In the description of the present invention, it should be noted that unless otherwise clearly defined and limited, term " is pacified Dress ", " be arranged/offer ", " connection ", etc., shall be understood in a broad sense, such as " connection ", may be a fixed connection, being also possible to can Dismantling connection, or be integrally connected;It can be mechanical connection, be also possible to be electrically connected;It can be directly connected, can also pass through Intermediary is indirectly connected, and can be the connection inside two elements.For the ordinary skill in the art, can have Body situation understands the concrete meaning of above-mentioned term in the present invention.
Embodiment:
Referring to Fig. 1, the utility model provides a kind of technical solution:
A kind of bridge construction Bridge Erector, including Bridge Erector ontology 1, shaft 2, nose girder plate 3, the first sunpender 4, bridge 5, bridge pier 6, supporting leg 7, the second sunpender 8, control room 9, battery 10, the first hydraulic hoisting apparatus 11, flexible bale handle hook 12, crossbeam 13, Second hydraulic hoisting apparatus 14 and solar panels 15, the two sides of the bottom of the bridge machine ontology 1 are equipped with bridge pier 6, the bridge pier 6 Side is equipped with supporting leg 7, and the top of the supporting leg 7 is equipped with crossbeam 13, and the two sides of the bottom of the crossbeam 13 are equipped with the second liquid Hoisting apparatus 14 is pressed, the side of second hydraulic hoisting apparatus 14 is equipped with shaft 2, and the side of the shaft 2 is equipped with first and hangs The side of bar 4 and the second sunpender 8, first sunpender 4 and the second sunpender 8 is equipped with nose girder plate 3, the bottom middle part of the crossbeam 13 Equipped with the first hydraulic hoisting apparatus 11, the side of first hydraulic hoisting apparatus 11 is equipped with flexible bale handle hook 12, described flexible The side of bale handle hook 12 is equipped with bridge 5, and the top of the Bridge Erector ontology 1 is equipped with solar panels 15, the solar panels 15 Side is equipped with battery 10, and the side of the battery 10 is equipped with control room 9.
It is more firm in order to make entirely to install, in the present embodiment, it is preferred that the supporting leg 7 is fixed by welding in cross The two sides of beam 13, the first hydraulic hoisting apparatus 11 are bolted on the middle part of crossbeam 13, and flexible bale handle hook 12 passes through bolt It is fixed on the first hydraulic hoisting apparatus 11.
It is more firm in order to make entirely to install, in the present embodiment, it is preferred that second hydraulic hoisting apparatus 14 passes through spiral shell Bolt is fixed on crossbeam 13, and shaft 2 is fixedly linked by bolt with the second hydraulic hoisting apparatus 14, and the first sunpender 4 and second is hung Bar 8 is fixedly linked with shaft 2 and nose girder plate 3 respectively by bolt, and nose girder plate 3 is oblique.
In order to facilitate adjustment, and guarantee the safety being electrically connected, in the present embodiment, it is preferred that the solar panels 15 It is embedded in the top of Bridge Erector ontology 1, solar panels 15 are electrical connected with battery 10.
When using the Bridge Erector, is absorbed heat and generated electricity by the solar panels on Bridge Erector ontology 1, be stored into battery 10 It is interior, for the electricity usage in control room 9, bridge 5 is transported on nose girder plate 3 by beam car, is filled by the first Hydraulic for lifting load It is flexible to set the flexible bale handle hook 12 of 11 drives, so that bridge 5 is driven to increase, the second hydraulic hoisting apparatus 14 drive 4 He of the first sunpender Second sunpender 8 increases nose girder plate 3, then drives nose girder plate 3 to rotate by shaft 2, bridge pier 6 is exposed, then bridge 5 is placed on On bridge pier 6.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (4)

1. a kind of bridge construction Bridge Erector, including Bridge Erector ontology (1), shaft (2), nose girder plate (3), the first sunpender (4), bridge (5), bridge pier (6), supporting leg (7), the second sunpender (8), control room (9), battery (10), the first hydraulic hoisting apparatus (11), Flexible bale handle hook (12), crossbeam (13), the second hydraulic hoisting apparatus (14) and solar panels (15), it is characterised in that: the bridge The two sides of the bottom of machine ontology (1) are equipped with bridge pier (6), and the side of the bridge pier (6) is equipped with supporting leg (7), the supporting leg (7) Top be equipped with crossbeam (13), the two sides of the bottom of the crossbeam (13) are equipped with the second hydraulic hoisting apparatus (14), described second The side of hydraulic hoisting apparatus (14) is equipped with shaft (2), and the side of the shaft (2) is equipped with the first sunpender (4) and the second sunpender (8), the side of first sunpender (4) and the second sunpender (8) is equipped with nose girder plate (3), sets in the middle part of the bottom of the crossbeam (13) Have the first hydraulic hoisting apparatus (11), the side of first hydraulic hoisting apparatus (11) is equipped with flexible bale handle hook (12), described The side of flexible bale handle hook (12) is equipped with bridge (5), and the top of the Bridge Erector ontology (1) is equipped with solar panels (15), described The side of solar panels (15) is equipped with battery (10), and the side of the battery (10) is equipped with control room (9).
2. a kind of bridge construction Bridge Erector according to claim 1, it is characterised in that: the supporting leg (7) passes through welding The two sides of crossbeam (13) are fixed on, the first hydraulic hoisting apparatus (11) is bolted on the middle part of crossbeam (13), flexible to mention Beam hook (12) is bolted on the first hydraulic hoisting apparatus (11).
3. a kind of bridge construction Bridge Erector according to claim 1, it is characterised in that: second hydraulic hoisting apparatus (14) it being bolted on crossbeam (13), shaft (2) is fixedly linked by bolt with the second hydraulic hoisting apparatus (14), the One sunpender (4) and the second sunpender (8) are fixedly linked with shaft (2) and nose girder plate (3) respectively by bolt, and nose girder plate (3) is in incline It is ramp-like.
4. a kind of bridge construction Bridge Erector according to claim 1, it is characterised in that: the solar panels (15) are embedded in The top of Bridge Erector ontology (1), solar panels (15) are electrical connected with battery (10).
CN201821015244.7U 2018-06-29 2018-06-29 A kind of bridge construction Bridge Erector Active CN208362936U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821015244.7U CN208362936U (en) 2018-06-29 2018-06-29 A kind of bridge construction Bridge Erector

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821015244.7U CN208362936U (en) 2018-06-29 2018-06-29 A kind of bridge construction Bridge Erector

Publications (1)

Publication Number Publication Date
CN208362936U true CN208362936U (en) 2019-01-11

Family

ID=64927576

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821015244.7U Active CN208362936U (en) 2018-06-29 2018-06-29 A kind of bridge construction Bridge Erector

Country Status (1)

Country Link
CN (1) CN208362936U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110939073A (en) * 2020-01-15 2020-03-31 夏喜明 A equipment of building bridge for assembled bridge is under construction fast

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110939073A (en) * 2020-01-15 2020-03-31 夏喜明 A equipment of building bridge for assembled bridge is under construction fast
CN110939073B (en) * 2020-01-15 2021-08-20 无锡大诚建设有限公司 A equipment of building bridge for assembled bridge is under construction fast

Similar Documents

Publication Publication Date Title
CN201317631Y (en) Gantry crane used for subway construction
CN208362936U (en) A kind of bridge construction Bridge Erector
CN202080847U (en) Portable foldable lifting device
CN206233099U (en) A kind of Collison fence for bridge construction and security protection platform
CN102190252B (en) Crawler type gantry crane
CN107060478B (en) Upright column system and its construction method
CN204625045U (en) A kind of steel structure hoisting door shaped stent formula hanging apparatus
CN206903347U (en) A kind of Multifunctional communication tower of communication base station
CN203440751U (en) Self-propelled underbridge construction platform
CN202785387U (en) Indoor cantilever crane
CN206088790U (en) Novel hoist dolly
CN208395682U (en) A kind of novel lifting beam machine
CN106869477A (en) Guide rail type electric attached lifting scaffold
CN201647844U (en) Beam lifting station without abutments
CN202467221U (en) Power plant main workshop steel roof truss hoisting lifting device
CN208644514U (en) It is a kind of for welding the operating platform of wind power tower door frame
CN207244453U (en) A kind of suspension bridge light anchorage mast apparatus
CN201999628U (en) Carrying pole beam for integrally hoisting and consigning bridge girder erection machine
CN217264697U (en) Overhauling device for reinforcing converter liquid crown block heat insulation plate
CN206156546U (en) Ore hoisting device is used in mine
CN206091254U (en) Whole construction scaffold frame of track formula of climbing
CN205151579U (en) Two horizontal arm hoists
CN202324777U (en) Reinforced concrete and steel tube combined tower barrel structure
CN218290360U (en) Generating set maintains elevating gear
CN203402903U (en) Two-dimensional automatic double-track external hanging basket device with built-in photovoltaic power supply

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant