CN208280165U - Underground external wall post-cast strip shifts to an earlier date enclosed construction - Google Patents

Underground external wall post-cast strip shifts to an earlier date enclosed construction Download PDF

Info

Publication number
CN208280165U
CN208280165U CN201820459775.9U CN201820459775U CN208280165U CN 208280165 U CN208280165 U CN 208280165U CN 201820459775 U CN201820459775 U CN 201820459775U CN 208280165 U CN208280165 U CN 208280165U
Authority
CN
China
Prior art keywords
external wall
steel plate
post
cast strip
underground external
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820459775.9U
Other languages
Chinese (zh)
Inventor
李宁
张洋
田鹏骏
吴俏
肖红飞
刘辉
刘贝贝
宰佳明
何昱
路德川
丁宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN201820459775.9U priority Critical patent/CN208280165U/en
Application granted granted Critical
Publication of CN208280165U publication Critical patent/CN208280165U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The utility model discloses a kind of underground external wall post-cast strips to shift to an earlier date enclosed construction, post-pouring belt of outer wall position is accordingly descended to be equipped with regularization steel plate, the width both ends of the regularization steel plate are greater than post-cast strip width both ends and are fixed on underground external wall with expansion bolt or nailing, the hole location and steel plate that the regularization steel plate passes through in expansion bolt or nailing are sealed with wall joint part using waterproof gasket cement, the underground external wall is equipped with waterproof layer in upstream face, is pasted onto regularization steel plate outer surface when the construction of waterproof layer simultaneously and forms extra play.The utility model closes post-cast strip using regularization steel plate in advance, it can be under the premise of post-cast strip pour, plays a role, intert external wall waterproof and fertile slot backfill construction in advance, shorten the duration, save cost, it is economic, practical, safe, convenient for operation, only can manually it complete, it is easy to operate without mechanical engagement.

Description

Underground external wall post-cast strip shifts to an earlier date enclosed construction
Technical field
The utility model relates to building construction technologies, and in particular to underground external wall construction Technique of Late Poured Band.
Background technique
It at this stage, is to prevent monolithic reinforced concrete structure since autogenous shrinkage is uneven or sedimentation unevenness can in construction The harmful cracks that can be generated stay in sole plate, wall, beam corresponding position according to design or job specfication requirement and set post-cast strip, and Post-cast strip pour need to after main structure terminates and settle it is basicly stable after can just pour, this just make outer wall of basement waterproof and Fertile slot backfill process can carry out after needing main body to complete, and affect construction speed and construction period.
Utility model content
After technical problem to be solved in the utility model is just to provide the underground external wall that one kind can accelerate construction progress It pours band and shifts to an earlier date enclosed construction.
In order to solve the above technical problems, the utility model adopts the following technical solution: closing in advance underground external wall post-cast strip Structure is set to underground external wall post-cast strip position, and post-pouring belt of outer wall position is accordingly descended to be equipped with regularization steel plate, the regularization steel The width both ends of plate are greater than post-cast strip width both ends and are fixed on underground external wall with expansion bolt or nailing, the regularization steel The hole location and steel plate that plate passes through in expansion bolt or nailing are sealed with wall joint part using waterproof gasket cement, the underground Exterior wall is equipped with waterproof layer in upstream face, is pasted onto regularization steel plate outer surface when the construction of waterproof layer simultaneously and forms extra play.
Preferably, the regularization steel plate uses the 5mm thick steel plate greater than post-cast strip width 400mm.
Preferably, the width direction both ends of the regularization steel plate are equipped with bending segment.
Preferably, the bending segment include connect to the inclined tilting section of underground external wall and with tilting section and with outside underground The parallel straightway of wall, the straightway are equipped with the hole passed through for expansion bolt or nailing.
Preferably, an expansion bolt or nailing are correspondingly arranged at interval of 500mm in underground external wall vertical direction.
The technical solution adopted in the utility model closes post-cast strip using regularization steel plate in advance, can not pour in post-cast strip Under the premise of building, playing a role, interts external wall waterproof and fertile slot backfill construction in advance, shorten the duration, saved cost, pass through It helps, is practical, safe, convenient for operation, only can manually complete, being not necessarily to mechanical engagement, it is easy to operate.
Detailed description of the invention
The utility model is further described with reference to the accompanying drawings and detailed description:
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the structural schematic diagram of regularization steel plate.
Specific embodiment
The technical solution of the utility model embodiment is explained below with reference to the attached drawing of the utility model embodiment and Illustrate, but following embodiments are only the preferred embodiment of the utility model, and not all.Based on the implementation example in the implementation mode, Those skilled in the art's obtained other embodiments without making creative work, belong to the utility model Protection scope.
As depicted in figs. 1 and 2, underground external wall post-cast strip shifts to an earlier date enclosed construction, set on the post-cast strip of underground external wall 1 11 It sets, accordingly descends 11 position of post-pouring belt of outer wall to be equipped with regularization steel plate 2, close post-cast strip 11, energy in advance using regularization steel plate 2 Under the premise of post-cast strip 11 does not pour, plays a role, interts external wall waterproof and fertile slot backfill construction in advance, shortens the duration, Cost is saved.Traditional precast concrete cover closing post empiricism process is more, and prefabricated components dead weight is big, needs personnel With mechanical cooperation, it is easy to happen and the safety accidents such as injures, hits by a crashing object, be not easy to construct, using regularization steel plate, shorten work Phase, save cost, it is economic, practical, safe, convenient for operation, it only can manually complete, be not necessarily to mechanical engagement, it is easy to operate.
Wherein, the width both ends of the regularization steel plate 2 are greater than post-cast strip width both ends and with expansion bolt or nailings 22 It is fixed on underground external wall 1, facilitates operation.The hole location and steel that the regularization steel plate 2 passes through in expansion bolt or nailing Plate is sealed with wall joint part using waterproof gasket cement, and the underground external wall 1 is equipped with waterproof layer 12, the waterproof layer in upstream face 2 outer surface of regularization steel plate formation extra play is pasted onto when 12 construction simultaneously to avoid to guarantee the sealing effect of post-cast strip position Leakage.
The present embodiment is preferred, and the regularization steel plate 2 is using the 5mm thick steel plate for being greater than post-cast strip width 400mm.It is described The width direction both ends of regularization steel plate 2 are equipped with bending segment 21.The bending segment 21 includes to the inclined tilting section of underground external wall And connect with tilting section and the straightway parallel with underground external wall, the straightway is equipped with to be passed through for expansion bolt or nailing Hole.An expansion bolt or nailing are correspondingly arranged at interval of 500mm in underground external wall vertical direction.
It is as follows that underground external wall post-cast strip shifts to an earlier date closure construction process: by underground external wall post-cast strip sundries and spillage clear up Completely, the dirt removal on reinforcing bar is clean, and by the concrete dabbing of post-cast strip two sides, with expansion bolt or nailing by regularization steel Plate is fixed on vertical wall post-cast strip, hole for the expansion bolt and steel plate and wall joint part does sealant processing, band external wall waterproof layer When stickup, extra play processing is done at the steel plate of post-cast strip, after the completion of waterproof protective layer, can carry out the construction of next step backfill.
Above description is only a specific implementation of the present invention, but the protection scope of the utility model is not limited to In this, being familiar with the those skilled in the art should be understood that the utility model includes but is not limited to attached drawing and specific embodiment party above Content described in formula.The modification of any function and structure principle without departing from the utility model is intended to be included in claims Range in.

Claims (5)

1. underground external wall post-cast strip shifts to an earlier date enclosed construction, it is set to underground external wall post-cast strip position, it is characterised in that: accordingly lower outer Wall post-cast strip position is equipped with regularization steel plate, and the width both ends of the regularization steel plate are greater than post-cast strip width both ends and with expanding Bolt or nailing are fixed on underground external wall, the hole location and steel plate that the regularization steel plate passes through in expansion bolt or nailing It is sealed with wall joint part using waterproof gasket cement, the underground external wall is equipped with waterproof layer, the construction of waterproof layer in upstream face When simultaneously be pasted onto regularization steel plate outer surface formed extra play.
2. underground external wall post-cast strip according to claim 1 shifts to an earlier date enclosed construction, it is characterised in that: the regularization steel plate Using the 5mm thick steel plate for being greater than post-cast strip width 400mm.
3. underground external wall post-cast strip according to claim 2 shifts to an earlier date enclosed construction, it is characterised in that: the regularization steel plate Width direction both ends be equipped with bending segment.
4. underground external wall post-cast strip according to claim 3 shifts to an earlier date enclosed construction, it is characterised in that: the bending segment includes Connect to the inclined tilting section of underground external wall and with tilting section and the straightway parallel with underground external wall, is set on the straightway There is the hole passed through for expansion bolt or nailing.
5. underground external wall post-cast strip according to claim 4 shifts to an earlier date enclosed construction, it is characterised in that: vertical in underground external wall Direction is correspondingly arranged an expansion bolt or nailing at interval of 500mm.
CN201820459775.9U 2018-03-30 2018-03-30 Underground external wall post-cast strip shifts to an earlier date enclosed construction Expired - Fee Related CN208280165U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820459775.9U CN208280165U (en) 2018-03-30 2018-03-30 Underground external wall post-cast strip shifts to an earlier date enclosed construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820459775.9U CN208280165U (en) 2018-03-30 2018-03-30 Underground external wall post-cast strip shifts to an earlier date enclosed construction

Publications (1)

Publication Number Publication Date
CN208280165U true CN208280165U (en) 2018-12-25

Family

ID=64750295

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820459775.9U Expired - Fee Related CN208280165U (en) 2018-03-30 2018-03-30 Underground external wall post-cast strip shifts to an earlier date enclosed construction

Country Status (1)

Country Link
CN (1) CN208280165U (en)

Similar Documents

Publication Publication Date Title
CN110617083A (en) Real-time intelligent monitoring and alarming construction method for tunnel lining concrete compactness
CN209723052U (en) The prefabricated plate advanced water-stopping of poured band of outer wall of basement backfills structure
CN205296388U (en) Apron is sealed to garage wall post -cast strip
CN216109137U (en) A enclosed construction in advance for building post-cast strip
CN110374138A (en) The waterproof construction and construction method of station main body and accessory channel interface
CN104790436A (en) High-rise building basement roof settlement post-pouring joint advanced water stop construction method
CN205399497U (en) Basement outer wall post -cast strip concrete precast slab
CN201891133U (en) Manual assembled type self-waterproof late poured band prefabricated slab of basement outer wall
CN205134717U (en) Take frame mould integration light antidetonation partition plate of architectural surface
CN213174773U (en) Support system is exempted from to tear open type post-cast strip structure
CN208280165U (en) Underground external wall post-cast strip shifts to an earlier date enclosed construction
CN210713517U (en) Assembled superposed beam structure
CN209323574U (en) Closed basement roof pouring after settlement structure in advance
CN103410172A (en) Construction method for post pouring belt plugging of underground structural roof plate
CN207727733U (en) The spliced gutter that can be had enough to meet the need
CN206655313U (en) A kind of vertical post-cast strip plugging structure of basement
CN203247838U (en) Fully-buried basement side wall post-pouring belt advance water stop formwork
CN203403434U (en) Basement
CN213979911U (en) Basement outer wall post-cast strip template structure
CN208604640U (en) A kind of quick construction structure of post-pouring belt of outer wall
CN112324468B (en) Model of shield tunnel assembled internal structure and test manufacturing method thereof
CN108589793A (en) A kind of poured band of outer wall of basement postposition assembled advance water stop construction method
CN210975900U (en) Basement side wall extra front and back pouring belt periphery protection structure
CN210194691U (en) Protective structure for post-cast strip of settlement of basic raft
CN209538373U (en) A kind of prefabricated overlapping balcony slab of cracking resistance

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181225

Termination date: 20190330