CN208201795U - A kind of concrete slab pours surface heat preservation material layering device - Google Patents

A kind of concrete slab pours surface heat preservation material layering device Download PDF

Info

Publication number
CN208201795U
CN208201795U CN201820577277.4U CN201820577277U CN208201795U CN 208201795 U CN208201795 U CN 208201795U CN 201820577277 U CN201820577277 U CN 201820577277U CN 208201795 U CN208201795 U CN 208201795U
Authority
CN
China
Prior art keywords
coiled material
main shaft
left support
concrete slab
heat preservation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201820577277.4U
Other languages
Chinese (zh)
Inventor
吴高见
田中涛
刚永才
巫世奇
张正勇
张新峰
刘丽
石永刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sinohydro Bureau 5 Co Ltd
Original Assignee
Sinohydro Bureau 5 Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sinohydro Bureau 5 Co Ltd filed Critical Sinohydro Bureau 5 Co Ltd
Priority to CN201820577277.4U priority Critical patent/CN208201795U/en
Application granted granted Critical
Publication of CN208201795U publication Critical patent/CN208201795U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

Surface heat preservation material layering device is poured the utility model discloses a kind of concrete slab, including structure is identical and left support disposed in parallel and right support;Left support includes braced frame and idler wheel, and idler wheel is set to the bottom of braced frame;Pass through two truss connections disposed in parallel between left support and right support;The lower section of truss is equipped with coiled material and installs main shaft, and the end of coiled material installation main shaft is rotationally connected on left support and right support.The utility model can install two kinds of thermal insulation materials simultaneously, and position in storehouse is followed to pour synchronous rising under the traction of external force, can be realized the automatic laying of thermal insulation material coiled material;It can avoid in the laying operation of large span position in storehouse and slope realization thermal insulation material and manually carry out materials handling and coiled material laying on slope, improve operating efficiency, reduce the labor intensity manually on slope, reduce security risk.

Description

A kind of concrete slab pours surface heat preservation material layering device
Technical field
The utility model relates to a kind of thermal insulation material laying apparatus, and in particular to pour surface to a kind of concrete slab and protect Adiabator laying apparatus.
Background technique
Concrete face rockfill dam due to its structure is simple, gather materials on the spot the features such as, be widely used.Concrete As important water-retaining structure, appearance phenomena such as in order to reduce board cracking generally will do it panel in low temperature season and pours panel Construction is built, so proposing higher curing requirements to the heat and moisture preserving of concrete slab.It is supported according to the panel in extremely frigid zones Shield test carries out covering curing using composite geo-membrane and the double-deck bubble chamber film, can reach curing requirements.But concrete slab is It constructs on steeper slope, single storehouse width, length are larger.It is laid with using maintenance coiled material is manually carried out, construction intensity is big, Low efficiency, security risk are high.The utility model aim is to design and produce a kind of coiled material paving device, is poured in panel concrete Laying is synchronized in journey,
Utility model content
The utility model provides a kind of concrete slab and pours surface heat preservation material layering device, in concrete surface It realizes that the synchronous of thermal insulation material is laid in the casting process of plate, reaches the requirement of timely insulated curing, so that it is guaranteed that concrete Construction quality.
In order to solve the above technical problems, the technology employed by the present utility model is
A kind of concrete slab pours surface heat preservation material layering device, including structure is identical and left support disposed in parallel And right support;Left support includes braced frame and idler wheel, and idler wheel is set to the bottom of braced frame;Lead between left support and right support Cross two truss connections disposed in parallel;The lower section of truss is equipped with coiled material and installs main shaft, and the end that coiled material installs main shaft, which rotates, to be connected It is connected on left support and right support.
According to above scheme, the two sides of the coiled material installation main shaft are respectively provided with a reinforcing rod, and reinforcing rod is parallel to coiled material Main shaft setting is installed, the end of reinforcing rod is fixedly attached on left support and right support.
Further, the left end and right end of coiled material installation main shaft and two reinforcing rods pass through Coupling and are connected to one It rises;The top of Coupling is equipped with hanging ring, and the bottom of truss is equipped with sliding slot, is equipped with pulley in sliding slot;The upper end of sunpender and pulley connect It connects, lower end is articulated in hanging ring, so as to drive Coupling to slide along the chute.
According to above scheme, the mounting height of two coiled materials installation main shaft is inconsistent, wherein a coiled material installation master The mounting height of axis is higher than the mounting height of another coiled material installation main shaft.
According to above scheme, support is detachably connected between the left support and the braced frame and idler wheel of right support Column.
Compared with prior art, the utility model has the beneficial effects that two kinds of thermal insulation materials can be installed simultaneously, in external force It follows position in storehouse to pour synchronous rising under traction, can be realized the automatic laying of thermal insulation material coiled material;Can large span position in storehouse with And slope realizes the laying operation of thermal insulation material, avoids and manually carries out materials handling and coiled material laying on slope, mentions High operating efficiency, reduces the labor intensity manually on slope, reduces security risk.
Detailed description of the invention
Fig. 1 is the schematic perspective view of the utility model;
Fig. 2 is the positive structure diagram of the utility model;
Fig. 3 is the left view structural representation of the utility model;
Fig. 4 is the plane connection relationship of the components such as truss in the utility model, coiled material installation main shaft, reinforcing rod, Coupling Schematic diagram;
Fig. 5 is the three-dimensional connection relationship of the components such as truss in the utility model, coiled material installation main shaft, reinforcing rod, Coupling Schematic diagram (part);
Fig. 6 is the connection relationship diagram of sliding slot, pulley and sunpender in the utility model.
Specific embodiment
Specific embodiment of the present utility model is described further with reference to the accompanying drawing, the paraphrase of each label in figure Are as follows: 1- idler wheel, 2- support column, 3- braced frame, 4- truss, 5- Coupling, 6- pulley, 7- coiled material installation main shaft, 8- reinforcing rod, 9- hanging ring, 10- sunpender, 11- sliding slot.
The utility model includes identical structure and left support disposed in parallel and right support.Left support includes support frame Frame 3 and idler wheel 1, idler wheel 1 are connected to the bottom of braced frame 3.Pass through two purlins disposed in parallel between left support and right support Frame 4 connects, and truss 4 is located at the top of left support and right support.Coiled material installation main shaft 7, coiled material installation are additionally provided with below truss 4 The end of main shaft 7 is rotationally connected on left support and right support by bearing.The two sides of coiled material installation main shaft 7 are respectively provided with one and add Strong bar 8, reinforcing rod 8 are parallel to coiled material installation main shaft 7 and are arranged, and the end of reinforcing rod 8 is fixedly attached on left support and right support. The utility model can install a kind of thermal insulation material on every coiled material installation main shaft 7, can install two kinds of thermal insulation materials simultaneously.? Under the traction of external force, the utility model follows position in storehouse to pour synchronous rising, and thermal insulating coiled material carries out passive rotation exhibition in uphill process It opens, to achieve the purpose that laying.The utility model can be laid with two kinds of thermal insulation materials simultaneously, time saving and energy saving.Reinforcing rod 8 can guarantee Stability of the thermal insulation material when crimping and being laid on coiled material installation main shaft 7, avoids coiled material from stacking mutually, guarantees the smooth of coiled material Property.
In order to avoid two kinds of coiled materials generate interference in process of deployment, the mounting height of two coiled material installation main shafts 7 is different, Wherein the mounting height of a coiled material installation main shaft 7 is higher than the mounting height of another coiled material installation main shaft 7.
For the ease for use for further promoting the utility model, between the braced frame 3 and idler wheel 1 of left support and right support also Support column 2 has been bolted.By disassembly support column 2 to the adjusting of realization device height, work is poured to adapt to jump storehouse The thermal insulation material of skill is laid with.
The left end and right end of coiled material installation main shaft 7 and two reinforcing rods 8 are logical as a further improvement of the utility model, Coupling 5 is crossed to connect together.The top of Coupling 5 is equipped with hanging ring 9, and the bottom of truss 4 is equipped with sliding slot 11, is equipped in sliding slot 11 Pulley 6.The upper end of sunpender 10 is connect with pulley 6, and lower end is articulated in hanging ring 9, to drive 11 sliding along the chute of Coupling 5. The utility model can be enabled to be adapted to the thermal insulation material of curling any width by slidable Coupling 5, and can guarantee The case where capable of remaining that same straight line is laid with when the laying of thermal insulation material, being not in inclination.

Claims (5)

1. a kind of concrete slab pours surface heat preservation material layering device, it is characterised in that: identical including structure and set in parallel The left support and right support set;Left support includes braced frame (3) and idler wheel (1), and idler wheel (1) is set to the bottom of braced frame (3) Portion;Pass through two truss (4) connections disposed in parallel between left support and right support;It is installed equipped with coiled material the lower section of truss (4) The end of main shaft (7), coiled material installation main shaft (7) is rotationally connected on left support and right support.
2. a kind of concrete slab according to claim 1 pours surface heat preservation material layering device, it is characterised in that: institute The two sides for stating coiled material installation main shaft (7) are respectively provided with a reinforcing rod (8), and reinforcing rod (8) is parallel to coiled material installation main shaft (7) and sets It sets, the end of reinforcing rod (8) is fixedly attached on left support and right support.
3. a kind of concrete slab according to claim 2 pours surface heat preservation material layering device, it is characterised in that: institute Coiled material installation main shaft (7) is stated to pass through Coupling (5) with the left end of two reinforcing rods (8) with right end and connect together;Coupling (5) top is equipped with hanging ring (9), and the bottom of truss (4) is equipped with sliding slot (11), is equipped with pulley (6) in sliding slot (11);Sunpender (10) Upper end connect with pulley (6), lower end is articulated in hanging ring (9), so as to drive Coupling (5) to slide along the chute (11).
4. a kind of concrete slab according to claim 1 pours surface heat preservation material layering device, it is characterised in that: institute The mounting height for stating two coiled material installations main shaft (7) is inconsistent, wherein the mounting height of coiled material installation main shaft (7) is higher than separately The mounting height of piece coiled material installation main shaft (7).
5. a kind of concrete slab according to claim 1 pours surface heat preservation material layering device, it is characterised in that: institute It states and is detachably connected with support column (2) between left support and the braced frame (3) and idler wheel (1) of right support.
CN201820577277.4U 2018-04-23 2018-04-23 A kind of concrete slab pours surface heat preservation material layering device Withdrawn - After Issue CN208201795U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820577277.4U CN208201795U (en) 2018-04-23 2018-04-23 A kind of concrete slab pours surface heat preservation material layering device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820577277.4U CN208201795U (en) 2018-04-23 2018-04-23 A kind of concrete slab pours surface heat preservation material layering device

Publications (1)

Publication Number Publication Date
CN208201795U true CN208201795U (en) 2018-12-07

Family

ID=64523901

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820577277.4U Withdrawn - After Issue CN208201795U (en) 2018-04-23 2018-04-23 A kind of concrete slab pours surface heat preservation material layering device

Country Status (1)

Country Link
CN (1) CN208201795U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108360468A (en) * 2018-04-23 2018-08-03 中国水利水电第五工程局有限公司 A kind of concrete slab pours surface heat preservation material layering device
WO2020044287A1 (en) * 2018-08-29 2020-03-05 Saviv Publicidad Y Cia S.A.S Support frame system for transportation and surface rotation of structures, and pivoting support method for lifting structures

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108360468A (en) * 2018-04-23 2018-08-03 中国水利水电第五工程局有限公司 A kind of concrete slab pours surface heat preservation material layering device
CN108360468B (en) * 2018-04-23 2023-09-26 中国水利水电第五工程局有限公司 Concrete panel pouring surface heat insulation material laying device
WO2020044287A1 (en) * 2018-08-29 2020-03-05 Saviv Publicidad Y Cia S.A.S Support frame system for transportation and surface rotation of structures, and pivoting support method for lifting structures

Similar Documents

Publication Publication Date Title
CN208201795U (en) A kind of concrete slab pours surface heat preservation material layering device
CN108385528B (en) A kind of application method of low temperature season pier stud concrete heat-insulating health preserving equipment
CN103240800A (en) Composite insulation board production line
CN105780612B (en) A kind of prefabricated subway assembled track plate and its construction method
CN205475851U (en) Energy -conserving walling system of modularization detaching -free formwork
CN108360468A (en) A kind of concrete slab pours surface heat preservation material layering device
CN2888855Y (en) Assembled sunlight green house
CN104876161B (en) A kind of a kind of rhyme scheme in Chinese operas serving as the prelude to a complete score for voices flap device and its control method
CN205969448U (en) Hollow brick blank cutter
CN208934160U (en) A kind of Composite insulation board production line
CN204640502U (en) A kind of surface reinforces the production equipment of warming plate
CN106739348A (en) A kind of heat insulation decoration integrated plate and its processing technology
CN207015985U (en) One kind insulation plate conveying device
CN206487076U (en) A kind of novel pressboard for non-woven fabrics planting technology
CN206123904U (en) Prefabricated component produces die platform
CN108824106A (en) Intelligent section of track nail connection production line
CN101509286B (en) Producing and installing technique for integral cement composite heat preserving external wall and matched panel spreading and applying machine
CN204997651U (en) Fishplate bar composite set in succession rises automatically
CN211466782U (en) Prefabricated plate body production system
CN103569618B (en) The production line of processing wall floor decoration module
CN209257210U (en) A kind of curing kilns with heat-proof device
CN209289503U (en) A kind of prefabricated simple supported box beam template of Winter protection heating
CN207509936U (en) Hot pressing subsystem in hot pressing hybrid system
CN102409117A (en) Slag grating group assembly device for slag ladle
CN208023874U (en) A kind of stone decoration board with pendant

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20181207

Effective date of abandoning: 20230926

AV01 Patent right actively abandoned

Granted publication date: 20181207

Effective date of abandoning: 20230926

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned