CN208103037U - Cargo unit buffer storage and warehousing system - Google Patents

Cargo unit buffer storage and warehousing system Download PDF

Info

Publication number
CN208103037U
CN208103037U CN201820454304.9U CN201820454304U CN208103037U CN 208103037 U CN208103037 U CN 208103037U CN 201820454304 U CN201820454304 U CN 201820454304U CN 208103037 U CN208103037 U CN 208103037U
Authority
CN
China
Prior art keywords
unit
cargo
cargo unit
pipeline
outbound
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820454304.9U
Other languages
Chinese (zh)
Inventor
徐丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Jingdong Qianshi Technology Co Ltd
Original Assignee
Beijing Jingdong Century Trading Co Ltd
Beijing Jingdong Shangke Information Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Jingdong Century Trading Co Ltd, Beijing Jingdong Shangke Information Technology Co Ltd filed Critical Beijing Jingdong Century Trading Co Ltd
Priority to CN201820454304.9U priority Critical patent/CN208103037U/en
Application granted granted Critical
Publication of CN208103037U publication Critical patent/CN208103037U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Warehouses Or Storage Devices (AREA)

Abstract

The utility model relates to a kind of cargo unit buffer storage and warehousing systems.Cargo unit buffer storage includes:Shelf (1), have a plurality of caching road (11), and a plurality of caching road (11) is configured as carrying out position adjustment to the cargo unit to be cached of input automatically;With input carrier, in the temporary storage location (53) and a plurality of caching road (11) before operating in restocking between the input terminal of every caching road (11), for transporting the cargo unit to be cached.The utility model is transported cargo unit to be cached by input carrier, and the multiple caching roads for carrying out position adjustment to the cargo unit of input automatically are set in shelf, by carrying out automatic position adjustment to cargo unit in caching road, the caching that more cargo units can be realized in caching road, effectively improves space utilization rate.

Description

Cargo unit buffer storage and warehousing system
Technical field
The utility model relates to warehouse logistics field more particularly to a kind of cargo unit buffer storage and warehousing systems.
Background technique
With the development of electric business industry, order volume and the corresponding commodity scale of construction of order are huge, and storage area is more and more therewith Greatly.How on tens of thousands of or even ten tens of thousands of square metres of area timely by order-picking, be packaged and be dealt into client's hand, become guarantor The most important thing demonstrate,proved timeliness, promote customer experience.
Currently, the work pattern in single warehouse is:By one 1.2 ten thousand square metres or 2.4 ten thousand square metres of building root Multiple fire prevention zones are divided into according to fire-fighting requirements;Subregion sorts cargo, then to the article joining of sorting, to overcome because of Ground The too big problem of product labor intensity that is excessive and causing picking personnel's whole audience to be run.
In the material for being put in storage with being conveyed successively using Multilayer shuttle car and elevator to front end pipeline in outbound link Case is carried, and is sent to shelf and is cached.After the single corresponding hopper of a set collects neat on shelf, then by being somebody's turn to do Multilayer shuttle car and elevator are carried to outbound position.
Utility model content
Through inventor the study found that under the limitation of the transporting capacity of Multilayer shuttle car, shelf at most do deep position in pairs Road is cached, space utilization rate is relatively limited, and shuttle outbound ability is poor.
In view of this, the embodiment of the present disclosure provides a kind of cargo unit buffer storage and warehousing system, it can be improved shelf Space utilization rate.
In the one aspect of the utility model, a kind of cargo unit buffer storage is proposed, including:
Shelf have a plurality of caching road, and a plurality of caching road is configured as the cargo unit to be cached to input automatically Carry out position adjustment;With
Input carrier, in temporary storage location before operating in restocking and a plurality of caching road input terminal in every caching road it Between, for transporting the cargo unit to be cached.
In some embodiments, a plurality of caching road is distributed in at least one layer of the shelf, and input carrier includes point Not in the shuttle of each layer operation of the shelf.
In some embodiments, further include:
Running track is respectively arranged on each layer of the shelf, for providing carrying and guiding role to the shuttle.
In some embodiments, power-driven mechanism is equipped in a plurality of caching road, it is described wait cache for driving Cargo unit moves in the caching road.
In some embodiments, unpowered driving mechanism is equipped in a plurality of caching road, it is described to slow for utilizing The gravitional force or kinetic energy for depositing cargo unit move in the caching road.
In some embodiments, the unpowered driving mechanism includes:The unpowered roller being laid in the caching road, And it is described caching road input terminal be higher than output end, so as to the cargo unit to be cached can under the action of gravitional force edge The unpowered roller moves to the output end side.
In some embodiments, the one or both sides of the delivery line of the input carrier are arranged in the shelf.
In some embodiments, it is described it is a plurality of caching road in every caching road be configured as in cache set list it is multiple to Cache cargo unit.
In the other side of the utility model, a kind of warehousing system, including cargo unit buffer storage above-mentioned are proposed.
In some embodiments, further include:
Cargo unit loading device, for the cargo unit of storage to be transported to the temporary storage location before the restocking;And/or
Cargo unit outbound device, for the cargo unit cached in the shelf to be transported to outbound position.
In some embodiments, a plurality of caching road is distributed in at least one layer of the shelf, and the cargo unit enters Library device includes:
Be put in storage elevator, connect with goods pipeline is carried out, for will through it is described come the goods pipeline cargo list that conveys and be put in storage Member is transported to the temporary storage location before the restocking along the vertical direction, and the temporary storage location before the restocking is located at the cargo unit pair Layer where the caching road answered.
In some embodiments, the cargo unit outbound device includes:
Carrying platform, for being carried to multiple cargo units on shelf to outbound;With
Driving device, for driving the carrying platform to move between the shipment position and outbound position of the shelf.
In some embodiments, the carrying platform includes one or more pipeline units, is used for the shelf The multiple cargo unit be input on the pipeline unit, and along the conveying direction of the pipeline unit arrange, with It will pass through the pipeline unit to carry the multiple cargo unit, and/or will be carried on the pipeline unit The multiple cargo unit is output to the outbound position.
In some embodiments, the multiple pipeline unit is linked in sequence along the conveying direction, positioned at input side The input direction of the pipeline unit and the shipment direction of the shelf be parallel, positioned at the pipeline unit of outlet side Outbound course is parallel with the outbound direction of the outbound position.
It in some embodiments, is that bending roller pipeline or bent belt are defeated positioned at the pipeline unit of input side Line sending, the pipeline unit positioned at outlet side are linear belt pipeline or straight line roller pipeline.
In some embodiments, linear belt pipeline or straight line roller pipeline that the pipeline unit is whole section, And the shipment direction of the shelf is parallel with the outbound direction of the outbound position.
In some embodiments, every layer of the shelf is corresponding with the first track, and the driving device includes:
Railcar is drivingly connected, for driving the carrying platform in the first track uplink with the carrying platform It walks;With
Switching mechanism, for driving the carrying platform to switch between each goods yard layer and the outbound position.
In some embodiments, the switching mechanism includes:
Platform is promoted, second rail can be arrived for carrying walking with the second track of first orbital docking by having The railcar in road;With
Outbound elevator is drivingly connected with the promotion platform, for driving the promotion platform to change height and position.
In some embodiments, the shape of the horizontal cross-section of the cargo unit is rectangle, and the cargo unit is described It is adjacent to cache long side in road, and is exported outward along short side direction from the output end for caching road.
Therefore, according to the utility model embodiment, cargo unit to be cached is transported by input carrier, and is set in shelf The multiple caching roads for carrying out position adjustment to the cargo unit of input automatically are set, by carrying out certainly in caching road to cargo unit Dynamic position adjustment can realize the caching of more cargo units in caching road, effectively improve space utilization rate.
Detailed description of the invention
Attached drawing described herein is used to provide a further understanding of the present invention, and is constituted part of this application, The exemplary embodiment of the utility model and the description thereof are used to explain the utility model, does not constitute to the improper of the utility model It limits.In the accompanying drawings:
Fig. 1 is the structural schematic diagram of some embodiments of the utility model cargo unit buffer storage.
Fig. 2 is the structural schematic diagram of some embodiments of the utility model warehousing system.
Fig. 3 is the structural schematic diagram of outbound link in some embodiments of the utility model warehousing system.
Fig. 4 is carrying platform and the signal of the mounting structure of railcar in some embodiments of the utility model warehousing system Figure.
Fig. 5 is the structural schematic diagram of switching mechanism in some embodiments of the utility model warehousing system.
It should be understood that the size of various pieces shown in attached drawing is not to draw according to actual proportionate relationship. In addition, same or similar reference label indicates same or similar component.
Specific embodiment
The various exemplary embodiments of the disclosure are described in detail now with reference to attached drawing.Description to exemplary embodiment It is merely illustrative, never as to the disclosure and its application or any restrictions used.The disclosure can be with many differences Form realize, be not limited to the embodiments described herein.These embodiments are provided so that the disclosure is thorough and complete, and The scope of the present disclosure is given full expression to those skilled in the art.It should be noted that:Unless specifically stated otherwise, otherwise in these implementations Component described in example and positioned opposite, material component, numerical expression and the numerical value of step should be construed as merely and show Example property, not as limitation.
" first ", " second " used in the disclosure and similar word are not offered as any sequence, quantity or again The property wanted, and be used only to distinguish different parts.The similar word such as " comprising " or "comprising" means the element before the word Cover the element enumerated after the word, it is not excluded that be also covered by the possibility of other element."upper", "lower", "left", "right" etc. are only used In indicating relative positional relationship, after the absolute position for being described object changes, then the relative positional relationship may also be correspondingly Change.
In the disclosure, when being described to certain device between the first device and the second device, in the certain device There may be devices between two parties between the first device or the second device, and device between two parties can also be not present.When being described to specific device When part connects other devices, which can be directly connected to without device between two parties with the other devices, can also be with It is not directly connected to the other devices and there is device between two parties.
All terms (including technical term or scientific term) that the disclosure uses are common with disclosure fields The meaning that technical staff understands is identical, unless otherwise specifically defined.It is also understood that in term such as defined in the general dictionary The meaning consistent with their meanings in the context of the relevant technologies should be interpreted as having, without application idealization or The meaning of extremely formalization explains, unless being clearly defined herein.
Technology, method and apparatus known to person of ordinary skill in the relevant may be not discussed in detail, but suitable In the case of, the technology, method and apparatus should be considered as part of specification.
Some in the related technology, storage and outbound link be all made of Multilayer shuttle car and elevator.It is shuttled by multilayer The hopper that vehicle and elevator convey front end pipeline successively is carried, and hopper feeding shelf are cached.And It is removed after the single corresponding hopper of a set collects neat on shelf, then through the Multilayer shuttle car and elevator to outbound position Fortune.
For these the relevant technologies, the transporting capacity that inventor studies discovery Multilayer shuttle car is relatively limited, is typically only capable to Carry one to two hoppers.Correspondingly, the shelf of caching hopper also can only at most do the caching road of deep position in pairs, this causes shelf Space utilization rate it is relatively limited.In addition, shuttle in the related art should often carry out in-stockroom operation, also to be gone out Library operation, along with the transporting capacity of shuttle is limited, causes whole outbound ability poor.
In view of this, the utility model embodiment provides cargo unit buffer storage, warehousing system and inventory's method, to mention The space utilization rate of high shelf.
As shown in Figure 1, the structural schematic diagram of some embodiments for the utility model cargo unit buffer storage.In Fig. 1 In, cargo unit buffer storage includes:Shelf 1 and input carrier with a plurality of caching road 11.A plurality of caching road 11 is configured To carry out position adjustment to the cargo unit 23 to be cached of input automatically.Input carrier operates in the temporary storage location 53 before restocking (referring to fig. 2) and in a plurality of caching road 11 between the input terminal in every caching road 11, for transporting the goods to be cached Object unit 23.
In the present embodiment, one or more cargo units may be implemented in every caching road 11 in a plurality of caching road 11 Caching needs.The quantity for the cargo unit 24 that caching road 11 is cached can be associated with the single corresponding car loading of set.Some In embodiment, each caching road 11 is configured as multiple cargo units to be cached in cache set list.Such as gather at one Six cargo units involved in list then correspondingly cache six cargo units in some caching road 11 in shelf 1.Six A cargo unit executes outbound operation after caching is completed in the caching road 11, to the cargo unit in the caching road 11.
Cargo unit refers to caching and the object integrally conveyed during storage and outbound on shelf, with set Single-phase association.In some embodiments, cargo unit includes cargo or the material etc. by packaging;In other embodiments In, cargo unit also includes the cargo or material contained by hopper or pallet.Set singly can be order for goods, be also possible to The set of multiple order for goods.
In order to facilitate understanding, in the description of various embodiments of the utility model, to the cargo unit point in various process It has not carried out different numbers (referring to fig. 2), including:Carried out cargo unit 21 that goods pipeline 51 conveys and be put in storage, in upper The cargo unit 22 of temporary storage location 53 before frame, carried by input carrier or input-buffer road 11 and position adjustment do not complete When cargo unit 23 to be cached, cached in caching road 11 cargo unit 24, be output to the cargo list of carrying platform 4 Member 25 and the cargo unit 26 that outbound operation is carried out through shipment pipeline 35,36.
A plurality of caching road 11 is arranged in shelf 1 can increase the storage capacity of shelf.And in order to enable to cache road 11 More cargo units 23 are accommodated, caching road 11 is configured as carrying out position tune to the cargo unit 23 to be cached of input automatically It is whole.That is, cargo unit 23 is caching road 11 after entering caching road 11, without inputting the driving effect of carrier Position is completed under the auxiliary for the mechanism that can be inside arranged in caching road 11 to adjust.
For example, power-driven mechanism can be set in a plurality of caching road 11, for driving the goods to be cached Object unit 23 moves in the caching road 11, to increase the controllability adjusted to 23 position of cargo unit.The power-driven machine The modes such as power roller, air-leg, driving belt can be used in structure.Cargo unit 23 to be cached can be adjusted to close to defeated The cache location of outlet side.
In another embodiment, the settable unpowered driving mechanism in a plurality of caching road 11, it is described to slow for utilizing The gravitional force or kinetic energy for depositing cargo unit move in the caching road 11, to save the energy.For example, unpowered driving mechanism Specifically include the unpowered roller 14 being laid in the caching road 11.The input terminal in caching road 11 is disposed above output end, So that the cargo unit to be cached can move to the output along the unpowered roller 14 under the action of gravitional force Hold side.
In another example unpowered driving mechanism specifically includes the unpowered roller 14 being laid in the caching road 11.Cargo Unit 23 is entered carrier and provides a biggish initial velocity when being input into caching road 11.And unpowered roller 14 is then Cargo unit 23 provides the support surface of low-frictional force, and cargo unit 23 moves under kinetic energy effect along unpowered roller defeated Outlet side.Level can be set into unpowered roller in caching road 11, input terminal can also be can be set into and is higher than Output end.
With reference to Fig. 1, in some embodiments, a plurality of caching road 11 can be distributed in the multilayer of the shelf 1.Such as Fig. 1 In, a plurality of caching road 11 is distributed on five layers of shelf 1.In further embodiments, more layers or fewer layers can also be set Caching road 11, or even one layer of caching road 11 is only set.Correspondingly, input carrier may include running respectively in each layer of shelf 1 Shuttle 12.
In order to enable the shuttle 12 of each layer to stablize quick operation, operation can be respectively set in each layer of shelf 1 Track 13.The running track 13 can be used for providing carrying and guiding role to shuttle 12.
It, in some embodiments, can be on the transport road of input carrier in order to make full use of the conveying capacity of input carrier Shelf 1 are arranged in the two sides of line.In Fig. 1, shelf 1 are each provided with positioned at shuttle 12 and 13 left and right side of running track, this The shuttle of every layer of sample can carry out the input of cargo unit 23 according to certain the caching road 11 in instruction selection left side or right side. Certainly, in other embodiments, goods can also be set in certain side (such as left or right side) of the delivery line of input carrier Frame 1.In addition, one or more shelf 1 can be set along the direction of the delivery line of input carrier, these shelf 1 can be shared together One input carrier.
The above mentioned goods unit caches device of the utility model is applicable to all kinds of fields for needing to carry out cargo unit caching It closes, such as warehousing system.Therefore it includes that aforementioned any cargo unit is slow that some embodiments of the utility model, which additionally provides, The warehousing system of cryopreservation device embodiment.
As shown in Fig. 2, the structural schematic diagram of some embodiments for the utility model warehousing system.In the present embodiment, Warehousing system includes cargo unit buffer storage and cargo unit loading device and/or cargo unit outbound device above-mentioned. Illustrating for cargo unit buffer storage can refer to above, wouldn't repeat here.Cargo unit loading device will be for that will be put in storage Cargo unit 21 be transported to the temporary storage location 53 before the restocking.And cargo unit outbound device is for will be in the shelf 1 The cargo unit 24 cached is transported to outbound position.Later, review or production ring can be output to through outbound pipeline 35 or 36 Section.
It, can setting according to cargo unit buffer storage, cargo unit loading device and cargo unit outbound device in Fig. 2 Multiple regions are arranged in seated position in depot area.Such as cargo unit loading device is set in storage area, it is arranged in buffer area Two groups of cargo unit outbound devices are arranged in left outbound area and right outbound area in cargo unit buffer storage.
With reference to Fig. 2, in some embodiments, a plurality of caching road 11 is distributed in at least one layer of the shelf 1.Cargo Unit loading device include storage elevator 52, storage elevator 52 connect with goods pipeline 51 is carried out, for will through it is described come goods Pipeline 51 conveys and the cargo unit 21 being put in storage is transported to the temporary storage location 53 before the restocking along the vertical direction.Before the restocking Temporary storage location 53 be located at the corresponding 11 place layer of caching road of cargo unit 22.For example, multiple cargo lists in multiple set lists Member 21 is carried out goods pipeline 51 and is transported to storage elevator 52 successively.It is corresponding slow according to the cargo unit 21 to be put in storage elevator 52 11 place layers are deposited to promote cargo unit 21 to the layer.Then, by transplanter by cargo unit 21 from storage elevator 52 Temporary storage location 53 before being moved to restocking.
In view of shuttle leads to whole outbound because transporting capacity is limited when carrying out outbound operation in the related technology Ability is poor.Therefore in some embodiments of the utility model warehousing system, cargo unit outbound device includes carrying platform 4 And driving device.Carrying platform 4 is for carrying multiple cargo units 24 on shelf 1 to outbound.Driving device is used for Drive shipment position (cache the output end in road 11) and outbound position (i.e. shipment pipeline of the carrying platform 4 in shelf 1 35,36) between move.In Fig. 2, a carrying platform 4 can be respectively arranged in left outbound area and right outbound area, to realize a left side respectively The outbound on side and right side operates.
The horizontal cross-section of cargo unit it is preferably rectangular in shape.In order to increase cacheable hopper number in caching road 11 Amount, promoted shelf 1 amount of storage, hopper long side in the caching road 11 can be made adjacent, and along short side direction from cache road 11 Output end exported outward.In this way, cargo unit is on storage pipeline 51 along goods before cargo unit enters banked cache The long side extending direction of object unit conveys.Carrying platform 4 is output to and from carrying platform 4 to out from road 11 is cached in cargo unit During library pipeline 35,36, cargo unit is conveyed along short side extending direction.The conveying of this short side mode of movement Amount is more than length mode of movement, therefore the efficiency of batch outbound can be improved.
The basic function of carrying platform 4 is multiple cargo units 25 of the carrying to outbound.Compared to being adopted in the related technology Shuttle transports the mode of cargo, can execute outbound operation with the more cargo units 25 of integrated carrying, greatly mention High outbound efficiency.In order to enable the multiple cargo units 24 cached on shelf 1 to be easily input to the carrying of carrying platform 4 On surface, power or motorless pipeline unit can be set on carrying platform 4, come realize multiple cargo units relative to The input and/or output of the carrying platform 4 itself.
As shown in figure 3, for the structural schematic diagram of outbound link in some embodiments of the utility model warehousing system.Join again The structural schematic diagram for examining carrying platform and railcar and switching mechanism that Fig. 4 and Fig. 5 are shown respectively is held in some embodiments Carrying platform 4 includes one or more pipeline units 41,42, for inputting the multiple cargo unit on the shelf 1 It is arranged onto the pipeline unit 41,42, and along the conveying direction of the pipeline unit 41,42, it is described defeated will pass through 41,42 pairs of the multiple cargo units of line sending unit carry.Here power form can be used in pipeline unit 41,42, The carrying position that multiple cargo units 24 are input to carrying platform 4 is run by power drive pipeline unit, such as The uper side surface of pipeline unit 41,42.
One or more pipeline units 41,42 that carrying platform 4 includes are also used to will be on the pipeline unit 41,42 The multiple cargo unit of carrying is output to the outbound position.Here power transmission can be used in pipeline unit 41,42 Line unit drives the operation of pipeline unit that multiple cargo units 25 are output to out warehouse compartment from carrying platform 4 by taking offence It sets.
In further embodiments, auxiliary input device, such as manipulator or push rod etc. can also be provided, it will be on shelf 1 Multiple cargo units 24 of caching are input to the carrying position of carrying platform 4.Or provide auxiliary output gear, such as manipulator Or push rod etc., multiple cargo units 25 on carrying platform 4 are output to outbound position.In these cases, pipeline unit 41,42 unpowered form can be used.
When arranging multiple pipeline unit 41,42 on carrying platform 4, multiple pipeline units 41,42 can be along described Conveying direction is linked in sequence, positioned at the input direction of the pipeline unit 41,42 of input side and the cargo interests out of the shelf 1 To parallel, so that carrying platform 4 is when docking the output port of shelf 11, multiple cargo units 24 can be more advantageously realized Input.Outbound course positioned at the pipeline unit 41,42 of outlet side is parallel with the outbound direction of the outbound position, with Just carrying platform 4 can more advantageously realize the output of multiple cargo units 25 when docking outbound position.
In Fig. 4, the input direction and outbound course of carrying platform 4 are located at there are when angle (such as 90 degree of angles etc.) Bending roller pipeline can be used in the pipeline unit 41 of input side, adjusts corner to meet multiple cargo units 24 in input Demand.In further embodiments, bent belt pipeline can also be used positioned at the pipeline unit 41 of input side.Separately It outside, can be linear belt pipeline or straight line roller pipeline positioned at the pipeline unit 42 of outlet side.In other implementations In example, the pipeline unit 42 positioned at outlet side can also be using bending roller pipeline or bent belt pipeline.Another In a little embodiments, the shipment direction of shelf 1 is parallel with the outbound direction of the outbound position, and correspondingly pipeline unit can be with Using whole section of linear belt pipeline or straight line roller pipeline.
With reference to Fig. 2-Fig. 4, in some embodiments, every layer of shelf 1 is corresponding with the first track 31.First track 31 can lead to Bracket 32 is crossed to be supported.Driving device may particularly include railcar 44 and switching mechanism.Railcar 44 and the carrying platform 4 It is drivingly connected, for driving the carrying platform 4 to walk on first track 31.Railcar 41 has can be along described first The wheel that track 31 is walked.One or more pipeline units 41,42 that carrying platform 4 includes can be solid by installation frame 43 It is scheduled on the upper surface of the railcar 41, to ensure stability of multiple cargo units in input/output and transport.
Switching mechanism is for driving the carrying platform 4 to switch between each goods yard layer and the outbound position.With reference to Fig. 5, in some embodiments, switching mechanism includes:Promote platform 37 and outbound elevator 34.Promotion platform 37 has can be with institute The second track 33 for stating the docking of the first track 31 arrives the railcar 44 of second track 33 for carrying walking.Outbound is promoted Machine 34 and the promotion platform 37 are drivingly connected, for driving the promotion platform 37 to change height and position.
When executing outbound operation to multiple cargo units 24 in shelf 1, driving mechanism can be according to multiple cargo units 24 place layer and shipment position driving carrying platform 4 reach the shipment position of this layer.If carrying platform 4 with to the more of outbound A cargo unit 24 is in same layer, then carrying platform 4 is moved in this layer to shipment along the first track 31 by railcar 44 The shipment position of multiple cargo units 24.
If carrying platform 4 is in different layers with multiple cargo units 24 to outbound, adjust outbound elevator 34 The current layer where platform 37 to railcar 44 is promoted, and docks the first track 31 of current layer with the second track 33.Then, Carrying platform 4 is sent into along the first track 31 and the second track 33 by railcar 44 and is promoted on platform 37.Outbound elevator 34 will It promotes platform 37 and is adjusted to the 24 place layer of multiple cargo units to outbound, then is along the first track 31 that carrying is flat by railcar 44 Platform 4 is moved to the shipment position in this layer to multiple cargo units 24 of shipment.
When multiple cargo units 24 in shelf 1 enter on carrying platform 4, railcar 44 is along the first track 31 Carrying platform 4 is moved to and is promoted on platform 37.Then, outbound elevator 34 is adjusted to platform 37 is promoted where outbound position Height.Next, multiple cargo units 25 on carrying platform 4 are output to outbound position, to complete outbound operation.
Each embodiment of warehousing system based on above-mentioned the utility model, corresponding inventory's method may include following multiple streams Journey, such as caching process, i.e., it is right in shelf 1 to be input to according to the single cargo unit by the temporary storage location 53 before restocking of set Gather described in Ying Yu and is cached in single caching road 11.In another example outbound process, i.e., in the single corresponding cargo list of the set After member collects neat in the caching road 11, the cargo unit concentration cached in the caching road 11 is transported to outbound position, with Just cargo unit is transported to review or production link etc. by outbound pipeline 35,36, to complete outbound operation.In other realities It applies in example, inventory's method further includes storage process, i.e., will be carried out the conveying of goods pipeline 51 and the cargo unit being put in storage is transported to institute Temporary storage location 53 before stating restocking.
So far, the presently disclosed embodiments is described in detail.In order to avoid covering the design of the disclosure, do not describe Some details known in the field.Those skilled in the art as described above, completely it can be appreciated how implement here Disclosed technical solution.
Although being described in detail by some specific embodiments of the example to the disclosure, the skill of this field Art personnel it should be understood that above example merely to be illustrated, rather than in order to limit the scope of the present disclosure.The skill of this field Art personnel it should be understood that can not depart from the scope of the present disclosure and spirit in the case where, modify to above embodiments or Some technical features can be equivalently replaced.The scope of the present disclosure is defined by the following claims.

Claims (19)

1. a kind of cargo unit buffer storage, including:
Shelf (1), have a plurality of caching road (11), and a plurality of caching road (11) is configured as the goods to be cached to input automatically Object unit carries out position adjustment;With
Input carrier, every caching road (11) in temporary storage location (53) before operating in restocking and a plurality of caching road (11) Between input terminal, for transporting the cargo unit to be cached.
2. cargo unit buffer storage according to claim 1, wherein a plurality of caching road (11) is distributed in the goods At least one layer of frame (1), input carrier include respectively in the shuttle (12) of each layer operation of the shelf (1).
3. cargo unit buffer storage according to claim 2, wherein further include:
Running track (13) is respectively arranged on each layer of the shelf (1), for providing carrying and guiding to the shuttle (12) Effect.
4. cargo unit buffer storage according to claim 1, wherein be equipped with power in a plurality of caching road (11) Driving mechanism, for driving the cargo unit to be cached movement in the caching road (11).
5. cargo unit buffer storage according to claim 1, wherein be equipped in a plurality of caching road (11) without dynamic Power drive mechanism, for gravitional force or the kinetic energy movement in the caching road (11) using the cargo unit to be cached.
6. cargo unit buffer storage according to claim 5, wherein the unpowered driving mechanism includes:It is laid on Unpowered roller (14) in caching road (11), and the input terminal of caching road (11) is higher than output end, so as to described Cargo unit to be cached can move to the output end side along the unpowered roller (14) under the action of gravitional force.
7. cargo unit buffer storage according to claim 1, wherein the shelf (1) are arranged in the input carrier Delivery line one or both sides.
8. cargo unit buffer storage according to claim 1, wherein every caching road in a plurality of caching road (11) (11) the multiple cargo units to be cached being configured as in cache set list.
9. a kind of warehousing system, including any cargo unit buffer storage of claim 1~7.
10. warehousing system according to claim 9, wherein further include:
Cargo unit loading device, for the cargo unit of storage to be transported to the temporary storage location before the restocking (53);And/or
Cargo unit outbound device, for the cargo unit cached in the shelf (1) to be transported to outbound position (35).
11. warehousing system according to claim 10, wherein a plurality of caching road (11) is distributed in the shelf (1) At least one layer, the cargo unit loading device includes:
Be put in storage elevator (52), connect with goods pipeline (51) is carried out, for will through it is described come goods pipeline (51) conveying and be put in storage Cargo unit be transported to the temporary storage location (53) before the restocking along the vertical direction, temporary storage location (53) position before the restocking The layer where the corresponding caching road (11) of the cargo unit.
12. warehousing system according to claim 10, wherein the cargo unit outbound device includes:
Carrying platform (4), for being carried to multiple cargo units on shelf (1) to outbound;With
Driving device, for driving the carrying platform (4) to transport between the shipment position and outbound position of the shelf (1) It is dynamic.
13. warehousing system according to claim 12, wherein the carrying platform (4) includes one or more pipelines Unit (41,42), for the multiple cargo unit on the shelf (1) to be input to the pipeline unit (41,42) On, and arranged along the conveying direction of the pipeline unit (41,42), will pass through the pipeline unit (41,42) to institute It states multiple cargo units to be carried, and/or the multiple cargo unit carried on the pipeline unit (41,42) is defeated The outbound position is arrived out.
14. warehousing system according to claim 13, wherein the multiple pipeline unit (41,42) is along the conveying Direction is linked in sequence, positioned at the input direction of the pipeline unit (41,42) of input side and the cargo interests out of the shelf (1) It is flat positioned at the outbound course of the pipeline unit (41,42) of outlet side and the outbound direction of the outbound position to parallel Row.
15. warehousing system according to claim 13, wherein the pipeline unit (41,42) positioned at input side is It is bent roller pipeline or bent belt pipeline, the pipeline unit (41,42) positioned at outlet side is that linear belt is defeated Line sending or straight line roller pipeline.
16. warehousing system according to claim 13, wherein the linear belt that the pipeline unit (41,42) is whole section Formula pipeline or straight line roller pipeline, and the shipment direction of the shelf (1) is parallel with the outbound direction of the outbound position.
17. warehousing system according to claim 12, wherein every layer of the shelf (1) is corresponding with the first track (31), The driving device includes:
Railcar (44) is drivingly connected, for driving the carrying platform (4) in first rail with the carrying platform (4) It walks on (31) in road;With
Switching mechanism, for driving the carrying platform (4) to switch between each goods yard layer and the outbound position.
18. warehousing system according to claim 17, wherein the switching mechanism includes:
It is promoted platform (37), there is the second track (33) that can be docked with first track (31), arrive institute for carrying walking State the railcar (44) of the second track (33);With
Outbound elevator (34) is drivingly connected with the promotion platform (37), high for driving the promotion platform (37) to change Spend position.
19. warehousing system according to claim 9, wherein the shape of the horizontal cross-section of the cargo unit is rectangle, institute State that cargo unit is adjacent in the interior long side of the caching road (11), and along short side direction from the output end of caching road (11) by Outer output.
CN201820454304.9U 2018-04-02 2018-04-02 Cargo unit buffer storage and warehousing system Active CN208103037U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820454304.9U CN208103037U (en) 2018-04-02 2018-04-02 Cargo unit buffer storage and warehousing system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820454304.9U CN208103037U (en) 2018-04-02 2018-04-02 Cargo unit buffer storage and warehousing system

Publications (1)

Publication Number Publication Date
CN208103037U true CN208103037U (en) 2018-11-16

Family

ID=64119615

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820454304.9U Active CN208103037U (en) 2018-04-02 2018-04-02 Cargo unit buffer storage and warehousing system

Country Status (1)

Country Link
CN (1) CN208103037U (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109607022A (en) * 2019-01-07 2019-04-12 昆山圣炬智能系统技术有限公司 A kind of chemicals empty barrel storage system
CN110342163A (en) * 2018-04-02 2019-10-18 北京京东尚科信息技术有限公司 Cargo unit buffer storage, warehousing system and inventory's method
CN110589330A (en) * 2019-09-10 2019-12-20 厦门博耐特工贸有限公司 Loft type goods shelf
CN111738636A (en) * 2019-03-25 2020-10-02 北京京东尚科信息技术有限公司 Multi-floor building warehouse and production method thereof, goods elevator and warehouse management system
CN112239043A (en) * 2019-07-16 2021-01-19 北京京东尚科信息技术有限公司 Logistics sorting method and device, warehousing system and storage medium
CN112278692A (en) * 2019-07-23 2021-01-29 北京京东尚科信息技术有限公司 Storage processing method, device, equipment and medium based on stereoscopic warehouse
CN112488601A (en) * 2019-09-11 2021-03-12 北京京东乾石科技有限公司 Logistics system, material conveying method, storage medium and electronic equipment

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110342163A (en) * 2018-04-02 2019-10-18 北京京东尚科信息技术有限公司 Cargo unit buffer storage, warehousing system and inventory's method
CN109607022A (en) * 2019-01-07 2019-04-12 昆山圣炬智能系统技术有限公司 A kind of chemicals empty barrel storage system
CN111738636A (en) * 2019-03-25 2020-10-02 北京京东尚科信息技术有限公司 Multi-floor building warehouse and production method thereof, goods elevator and warehouse management system
CN111738636B (en) * 2019-03-25 2024-03-08 北京京东振世信息技术有限公司 Multi-storey building warehouse, production method thereof, goods elevator and warehouse management system
CN112239043A (en) * 2019-07-16 2021-01-19 北京京东尚科信息技术有限公司 Logistics sorting method and device, warehousing system and storage medium
CN112278692A (en) * 2019-07-23 2021-01-29 北京京东尚科信息技术有限公司 Storage processing method, device, equipment and medium based on stereoscopic warehouse
CN112278692B (en) * 2019-07-23 2024-03-01 北京京东乾石科技有限公司 Warehouse processing method and device based on stereoscopic warehouse, equipment and medium
CN110589330A (en) * 2019-09-10 2019-12-20 厦门博耐特工贸有限公司 Loft type goods shelf
CN112488601A (en) * 2019-09-11 2021-03-12 北京京东乾石科技有限公司 Logistics system, material conveying method, storage medium and electronic equipment

Similar Documents

Publication Publication Date Title
CN208103037U (en) Cargo unit buffer storage and warehousing system
US7991506B2 (en) Automated order-picking system having an integrated sorting function and method for operating the system
JP6461359B2 (en) Sequencing system and method for at least one preparatory station
KR101940608B1 (en) Picking system and picking method
TWI718321B (en) Article rearranging device and article storage facility including same
JP6279730B2 (en) Order procurement method by preparing storage unit at sorting station
EP3044139B1 (en) Transfer system and material-handling system and method using such transfer system
JP6995466B2 (en) Three-dimensional automated warehouse
US9499349B2 (en) Picking station and method for picking articles
CN105392719B (en) By the order fulfillment method for preparing storage element at selection station
JP7268267B2 (en) Three-dimensional automated warehouse
CN107555056A (en) Hopper stores radio frequency and storage divides integral system
CN106276190B (en) A kind of multilayer two-wire circulation conveying line
JP2015524374A (en) Method for providing a transport unit from a storage facility
CN110342163A (en) Cargo unit buffer storage, warehousing system and inventory's method
US20140178161A1 (en) Conveyor technology supported commissioning of articles
JP6231168B2 (en) 3D automatic warehouse
JP7147112B2 (en) Logistics system
JP2018008775A (en) Multi-tier automatic warehouse
KR20210011915A (en) Picking system
CN106743785A (en) A kind of band classify automatically pipeline auxiliary material storage logistics system
CN113772303A (en) Cache sorting system and method
JP7247435B2 (en) Logistics system
JP7247436B2 (en) Logistics system
JP7234470B2 (en) Three-dimensional automated warehouse

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20210315

Address after: 101, 1st floor, building 2, yard 20, Suzhou street, Haidian District, Beijing 100080

Patentee after: Beijing Jingbangda Trading Co.,Ltd.

Address before: 100195 Beijing Haidian Xingshikou Road 65 West Cedar Creative Garden 4 District 11 Building East 1-4 Floor West 1-4 Floor

Patentee before: BEIJING JINGDONG SHANGKE INFORMATION TECHNOLOGY Co.,Ltd.

Patentee before: BEIJING JINGDONG CENTURY TRADING Co.,Ltd.

Effective date of registration: 20210315

Address after: Room a1905, 19 / F, building 2, No. 18, Kechuang 11th Street, Daxing District, Beijing, 100176

Patentee after: Beijing Jingdong Qianshi Technology Co.,Ltd.

Address before: 101, 1st floor, building 2, yard 20, Suzhou street, Haidian District, Beijing 100080

Patentee before: Beijing Jingbangda Trading Co.,Ltd.

TR01 Transfer of patent right