CN208009260U CN201820182592.7U CN201820182592U CN208009260U CN 208009260 U CN208009260 U CN 208009260U CN 201820182592 U CN201820182592 U CN 201820182592U CN 208009260 U CN208009260 U CN 208009260U
Authority
CN
China
Prior art keywords
reinforcing bar
prefabricated bridge
load
steel plate
type steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820182592.7U
Other languages
Chinese (zh)
Inventor
陈凰琴
胡峰强
刘凯伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanchang University
Original Assignee
Nanchang University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanchang University filed Critical Nanchang University
Priority to CN201820182592.7U priority Critical patent/CN208009260U/en
Application granted granted Critical
Publication of CN208009260U publication Critical patent/CN208009260U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

A kind of special hoisting sling of prefabricated bridge, including:Load-bearing comb type steel plate, lifting rope, reinforcing bar hook, reinforcing bar bolt item and locating part;Load-bearing comb type steel plate upper end both sides are equipped with lifting hole(eyelet), and lifting rope is arranged in lifting hole(eyelet), and load-bearing comb type steel plate lower end is equipped with a plurality of broach;Reinforcing bar welding hook is on the broach of load-bearing comb type steel plate lower end;The reinforcing bar bolt item is set up in reinforcing bar hook, and the locating part is set to reinforcing bar bolt both ends.Using the special hoisting sling of the utility model prefabricated bridge, prefabricated bridge can be facilitated to lift, prefabricated bridge will not be caused to damage, it can avoid in floorings embedded bar hanging ring, reduce follow-up embedded bar hanging ring cutting action, eliminating residual embedded bar, there may be the hidden danger of etching channels, while simplifying prefabricated bridge installing engineering working procedure, and Hoisting Security is efficient.

Description

A kind of special hoisting sling of prefabricated bridge
Technical field
This application involves suspenders, and in particular to a kind of special hoisting sling of prefabricated bridge.
Background technology
Reinforced concrete combination bridge has the advantages of steel bridge and concrete bridge concurrently, is building with fields such as bridge structures It is more and more applied, achieves significant economic benefit and social benefit.Using prefabricated assembled technology, make bridge structure Part batch production, standardization and modularization are conducive to accelerate construction progress, reduce labor intensity, improve construction quality, be conducive to ring Border is protected, and energy-saving and environment-friendly construction concept is embodied.
Currently, in the installation and work progress of prefabricated bridge, it is the embedded bar hanging ring in floorings in advance, is lifting Prefabricated bridge can be damaged in the process, and after floorings are installed in place, need by reinforcing bar hanging ring cut away could normal use, Increase cutting action, extend the construction time, and remains in the reinforcing bar in prefabricated bridge there are the hidden danger of etching channels.
Utility model content
The application provides a kind of special hoisting sling of prefabricated bridge, to avoid prefabricated bridge in hoisting process by To damage.
According in a first aspect, provide a kind of special hoisting sling of prefabricated bridge in a kind of embodiment, including:Load-bearing Comb type steel plate, lifting rope, reinforcing bar hook, reinforcing bar bolt item and locating part;Load-bearing comb type steel plate upper end both sides are equipped with lifting hole(eyelet), and lifting rope is worn In lifting hole(eyelet), load-bearing comb type steel plate lower end is equipped with a plurality of broach;Reinforcing bar welding hook is in the comb of load-bearing comb type steel plate lower end On tooth;The reinforcing bar bolt item is set up in reinforcing bar hook, and the locating part is set to reinforcing bar bolt both ends.
Preferably, silent reinforcing bar hook is welded on the broach at load-bearing comb type steel plate both ends, and open steel is welded on remaining broach Muscle is linked up with.
Preferably, reinforcing bar bolt both ends are equipped with screw thread, and locating part is equipped with and the matched internal thread of reinforcing bar bolt both ends screw thread.
The special hoisting sling of prefabricated bridge according to above-described embodiment, facilitates prefabricated bridge to lift, will not be to pre- Floorings processed cause to damage, and can avoid, in floorings embedded bar hanging ring, reducing follow-up embedded bar hanging ring cutting action, eliminate Remaining embedded bar, there may be the hidden danger of etching channels, while simplifying prefabricated bridge installing engineering working procedure, lift It is safe and efficient.Suspender convenient disassembly after the completion of lifting, it is reusable.
Description of the drawings
Fig. 1 is the lifting schematic diagram using the hoisting prefabricated floorings of the utility model.
Fig. 2 is Figure 1A-A sectional views, is also the utility model hanger structure schematic diagram.
Fig. 3 is reinforcing bar welding hook structure chart.
Fig. 4 is opening reinforcing bar hook structure figure.
Fig. 5 is silent reinforcing bar hook structure figure.
Fig. 6 is reinforcing bar bolt item and locating part combination assumption diagram.
Specific implementation mode
The utility model is described in further detail below by specific implementation mode combination attached drawing.It is wherein different to implement Similar component uses associated similar element numbers in mode.In the following embodiments, many datail descriptions are In order to enable the application can be better understood.However, those skilled in the art can be without lifting an eyebrow recognize, which part Feature is dispensed in varied situations, or can be substituted by other elements, material, method.In some cases, Some relevant operations of the application are there is no display in the description or describe, this is the core in order to avoid the application It is flooded by excessive description, and to those skilled in the art, these relevant operations, which are described in detail, not to be necessary, They can completely understand relevant operation according to the general technology knowledge of description and this field in specification.
It is herein component institute serialization number itself, such as " first ", " second " etc., is only used for distinguishing described object, Without any sequence or art-recognized meanings.And " connection ", " connection " described in the application, unless otherwise instructed, include directly and It is indirectly connected with(Connection).
Please refer to Fig.2-6, the special hoisting sling of prefabricated bridge, including:Load-bearing comb type steel plate 1, lifting rope 7, closed steel Muscle hook 3, opening reinforcing bar hook 2, reinforcing bar bolt item 4 and locating part 5;Load-bearing comb type steel plate upper end both sides are equipped with lifting hole(eyelet) 6, lifting rope 7 are arranged in lifting hole(eyelet) 6, and 1 lower end of load-bearing comb type steel plate is equipped with a plurality of broach 9;Silent reinforcing bar hook 3 is welded in load-bearing comb shape steel On the broach 9 of plate lower end both sides;Opening reinforcing bar hook 2 is welded on the broach 9 among load-bearing comb type steel plate lower end, and use is two-sided Welding manner is welded;Reinforcing bar bolt item 4 is set up in silent reinforcing bar hook and opening reinforcing bar hook, and 4 both ends of reinforcing bar bolt item are set There is screw thread, locating part 5 is equipped with is sheathed on reinforcing bar bolt both ends with the matched internal thread of reinforcing bar bolt both ends screw thread, locating part 5.
Referring to FIG. 1, being illustrated to the service condition of the utility model suspender.
Reinforcing bar bolt item is penetrated into silent reinforcing bar hook and opening reinforcing bar hook successively, is then limited at reinforcing bar bolt both ends Part is fixed on reinforcing bar hook.When lifting, a copy utility model suspender is respectively set at 10 both ends of prefabricated bridge, by the steel of suspender 4 crossbearer of muscle bolt item starts loop wheel machine and lifting rope is pulled to be lifted in the lower section of the protruding bar 8 of prefabricated bridge both ends bottom.It hangs During dress, lifting stable action should be kept, lifting rope can be unlocked after floorings are in place steadily, then unclamps the limit of one end Steel bushing extracts reinforcing bar bolt item out, then slings the dismounting that suspender can be completed in suspender remainder with loop wheel machine.
Since protruding bar is the skeleton structure of prefabricated bridge, it will not be to prefabricated bridge in hoisting process It causes to damage, and the protruding bar for applying prefabricated bridge to carry is lifted, and embedded bar hanging ring is not had to, and is reduced follow-up pre-buried Reinforcing bar hanging ring cutting action, while residual embedded bar is eliminated there may be the hidden danger of etching channels, simplify prefabricated bridge Installing engineering working procedure shortens the construction period.
Since protruding bar is the skeleton of prefabricated bridge, there is no breaking off relations, Hoisting Security is efficient.
Use above specific case is illustrated the utility model, is merely used to help understand the utility model, and Not limiting the utility model.For those skilled in the art of the present invention, the think of according to the utility model Think, several simple deductions, deformation can also be made or replaces.

Claims (3)

1. a kind of special hoisting sling of prefabricated bridge, it is characterised in that including:Load-bearing comb type steel plate, lifting rope, reinforcing bar are hung Hook, reinforcing bar bolt item and locating part;
Load-bearing comb type steel plate upper end both sides are equipped with lifting hole(eyelet), and lifting rope is arranged in lifting hole(eyelet), and load-bearing comb type steel plate lower end is equipped with a plurality of Broach;
Reinforcing bar welding hook is on the broach of load-bearing comb type steel plate lower end;
The reinforcing bar bolt item is set up in reinforcing bar hook, and the locating part is set to reinforcing bar bolt both ends.
2. the special hoisting sling of prefabricated bridge as described in claim 1, it is characterised in that:Load-bearing comb type steel plate both ends Broach on weld silent reinforcing bar hook, welding opening reinforcing bar hook on remaining broach.
3. the special hoisting sling of prefabricated bridge as described in claim 1, it is characterised in that:Reinforcing bar bolt both ends are equipped with Screw thread, locating part are equipped with and the matched internal thread of reinforcing bar bolt both ends screw thread.
CN201820182592.7U 2018-02-02 2018-02-02 A kind of special hoisting sling of prefabricated bridge Expired - Fee Related CN208009260U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820182592.7U CN208009260U (en) 2018-02-02 2018-02-02 A kind of special hoisting sling of prefabricated bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820182592.7U CN208009260U (en) 2018-02-02 2018-02-02 A kind of special hoisting sling of prefabricated bridge

Publications (1)

Publication Number Publication Date
CN208009260U true CN208009260U (en) 2018-10-26

Family

ID=63885904

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820182592.7U Expired - Fee Related CN208009260U (en) 2018-02-02 2018-02-02 A kind of special hoisting sling of prefabricated bridge

Country Status (1)

Country Link
CN (1) CN208009260U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108221696A (en) * 2018-02-02 2018-06-29 南昌大学 A kind of special hoisting sling of prefabricated bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108221696A (en) * 2018-02-02 2018-06-29 南昌大学 A kind of special hoisting sling of prefabricated bridge

Similar Documents

Publication Publication Date Title
CN208009260U (en) A kind of special hoisting sling of prefabricated bridge
CN108221696A (en) A kind of special hoisting sling of prefabricated bridge
CN113137054A (en) Method for setting inverted hoisting power equipment in attached lifting scaffold
CN203173684U (en) Component for hoisting reinforcement cage
CN209277531U (en) It is a kind of to have enough to meet the need template for reinforce expansion joint shear wall
CN106049896A (en) Dismantling method for resisting impact load in high-altitude overhanging steel-structure-platform dismantling process
CN109573813A (en) A kind of handling H profile steel girder steel fixture and its handling method
CN215331379U (en) Elevator shaft lifting operation platform
CN207986495U (en) A kind of Bridge High-pier main reinforcement hanging apparatus
CN209481043U (en) A kind of handling H profile steel girder steel fixture
CN206969990U (en) The special auxiliary hoisting device of steel grating structure workshop construction
CN109747030B (en) Modification auxiliary device and modification method for tunnel secondary lining template
CN210655785U (en) But reuse's pile foundation steel reinforcement cage hangs muscle device
CN209244229U (en) A kind of pin-connected panel suspention steel platform
CN208898385U (en) A kind of concrete prefabricated element hanging device
CN106013819A (en) Hoisting system and method for hoisting prefabricated exterior wall cladding based on overhead hooking exchange
CN202672694U (en) Shaft construction circulation operating platform
CN202687766U (en) Overturn lifting appliance for oversized section cube type component
CN204751876U (en) Simple gate is erected heavy -duty machine swift current tail and is taken off row integration special lifting device
CN207293918U (en) A kind of truss hoisting
CN212450248U (en) Steel reinforcement cage hoisting frame
CN206767423U (en) A kind of shear wall aluminum alloy mould plate fixes hanging apparatus
CN212076157U (en) Single-pile lifting appliance connected by flanges
CN217376980U (en) double-T-beam self-balancing hoisting sling
CN220485048U (en) Special hoisting tool for water spraying component of cooling tower

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee