CN207987960U - A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure - Google Patents

A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure Download PDF

Info

Publication number
CN207987960U
CN207987960U CN201820176798.9U CN201820176798U CN207987960U CN 207987960 U CN207987960 U CN 207987960U CN 201820176798 U CN201820176798 U CN 201820176798U CN 207987960 U CN207987960 U CN 207987960U
Authority
CN
China
Prior art keywords
pile
anchor rod
foundation
friction pile
friction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820176798.9U
Other languages
Chinese (zh)
Inventor
高立
字学强
李正波
王建富
侯云昌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Jiuda Transportation Construction Co ltd
Original Assignee
Yunnan New Innovation Traffic Construction Ltd By Share Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan New Innovation Traffic Construction Ltd By Share Ltd filed Critical Yunnan New Innovation Traffic Construction Ltd By Share Ltd
Priority to CN201820176798.9U priority Critical patent/CN207987960U/en
Application granted granted Critical
Publication of CN207987960U publication Critical patent/CN207987960U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure, including friction pile cantilever segment, antiskid pile foundation top surface platform, antiskid pile foundation, friction pile footing step, vertical anchor rod system, lateral anchor rod system, TGXG system, friction pile cantilever segment main reinforcement, hillside and breast boards, friction pile footing step is provided on hillside, antiskid pile foundation is provided on friction pile footing step, friction pile basis instrument has antiskid pile foundation top surface platform, it is provided with friction pile cantilever segment on the platform of antiskid pile foundation top surface, vertical anchor rod system is provided on the basis of hillside and friction pile, hillside and antiskid pile foundation intersection are provided with lateral anchor rod system;Friction pile cantilever segment is internally provided with breast boards and friction pile cantilever segment main reinforcement;Vertical anchor rod system and lateral anchor rod system are fixedly connected with friction pile cantilever segment main reinforcement;The soil body is backfilled between friction pile cantilever segment and hillside and is laid with TGXG system.The influence that the utility model reduces difficulty of construction, saves project cost, shortens the duration, reducing Engineering.

Description

A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure
Technical field
The present invention relates to highway Steep Slope Embankment supporting construction more particularly to highway hard rock Steep Slope Embankment anchor rod foundation antiskids Stake, belongs to highway subgrade construction technical field.
Background technology
In recent years fast-developing highway engineering construction, makes Southwestern China mountain highway net gradually tend to be perfect, mountain highway Construction should avoid high embankment as far as possible, first, meet using reducing project cost under the premise of function, but high embankment It is serious to environmental disruption, especially it would become hard to restore behind the region of ecological environment frailty, destruction.During highway construction, The coverage that stake reduces high embankment with retaining wall combining form is mostly used, the form of retaining wall mainly has pile plate wall, gravity Formula retaining wall, soil nail wall, the form of stake mainly have a rectangular section artificial digging pile, circular cross-section cast-in-situ bored pile, retaining wall with Anchor pile is combined, and can play good closing slope effect.The anchorage depth of anchor pile should according to cantilever segment length, thrust size and Stake sectional dimension determines that the anchoring section of traditional anchor pile must be designed into certain depth and just can guarantee soil body stability after stake. But when anchoring section is located in hard rock stratum, the excavation difficulty of anchoring section will greatly increase, especially the hard of good integrity Rock, long construction period directly contribute the rise of engineering project overhead cost.The general lateral slope of ground in hard rock location is very steep, excavation Rock And Soil outward transport is difficult, is mostly arbitrarily abandoned the hillside near stake mouth, exerted a certain influence to environment.It is steep to be limited to hard rock Slope embankment friction pile difficulty of construction is big, project cost is high and is influenced caused by environment big so that mountain highway high embankment is set Meter and construction are obstructed again and again, and often high embankment is also the controlling paragraph of highway subgrade construction, it can be seen that, hard rock The design form of section friction pile anchoring section becomes the research emphasis and difficult point of Subgrade in Mountain Area engineering field.
In consideration of it, domestic and foreign scholars have carried out a large amount of research work regarding to the issue above, how to meet design requirement Shortening anchoring depth in range becomes research emphasis.202787236 U of patent CN disclose a kind of novel friction pile, It is mainly characterized in that the bottom of friction pile extends vertically, forms lateral anchoring section, a sectional dimension can be reduced, improve friction pile Can, but transversary is even more to be difficult to excavate in hard rock, and the novel friction pile disclosed in this patent is only applicable to soil-slope. 107447777 A of patent CN, which are disclosed, puts anchor anti-sliding piled barricade in a kind of hole, the form of anchor cable is added by cantilever segment, can be contracted Short anchoring section depth, but anchoring section could meet stability requirement there is still a need for certain depth, especially in steep slope subgrade Section, in order to make Rock And Soil on the outside of stake reach certain thickness, it is necessary to increase the setting of anchoring section.
In conclusion to avoid the high embankment location embankment welding of hard rock, setting retaining wall between piles are to receive well Domatic formula, but the excavation of friction pile anchoring section is answered that difficulty of construction is big, project cost is high, therefore, how rationally to shorten anchoring section It is arranged to for design challenges urgently to be resolved hurrily.
Invention content
Goal of the invention:For overcome existing friction pile anchoring section in hard rock when excavate that difficulty is big, project cost is high not Foot, improves the design form of friction pile, and the present invention provides highway hard rock Steep Slope Embankment anchor rod foundation anti-slide pile structure, anchorings Section is substantially shorter, form is simple, short construction period, effect on environment are small, can efficiently solve highway hard rock abrupt slope road Dike friction pile stability and the big problem of difficulty of construction, are highway engineering field hard rock Steep Slope Embankment support form and friction pile The innovation of design form.
Technical solution:To achieve the above object, technical scheme is as follows:
A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure, including friction pile cantilever segment, friction pile Basic top surface platform, antiskid pile foundation, friction pile footing step, vertical anchor rod system, lateral anchor rod system, TGXG system System, friction pile cantilever segment main reinforcement, hillside and breast boards are provided with friction pile footing step, the antiskid pile foundation on the hillside Antiskid pile foundation is provided on plinth step, the friction pile basis instrument has antiskid pile foundation top surface platform, the antiskid pile foundation It is provided with friction pile cantilever segment on the platform of plinth top surface, vertical anchor rod system is provided on the basis of the hillside and friction pile, it is described Hillside and antiskid pile foundation intersection are provided with lateral anchor rod system;The friction pile cantilever segment is internally provided with breast boards and resists Sliding pile cantilever segment main reinforcement;The vertical anchor rod system and lateral anchor rod system are fixedly connected with friction pile cantilever segment main reinforcement;It is described The soil body is backfilled between friction pile cantilever segment and hillside and is laid with TGXG system.
Highway hard rock Steep Slope Embankment anchor rod foundation anti-slide pile structure of the present invention, including:Friction pile cantilever segment resists Sliding pile basis, foundation anchor system, substrate footing foundation backfill soil body TGXG system after stake.Cantilever segment is according to specific Situation is designed as rectangle(Wall is followed closely suitable for gravity retaining wall between stake and inter-pile soil)With the rectangle with the edge of a wing(Suitable for peg board Wall).Antiskid pile foundation should with pile body synchronize pour, the concrete grade of use is identical as pile body, basis and pile concrete mark Number be not less than C30.Foundation anchor system is divided into lateral anchor rod system and vertical anchor rod system, using the HRB400 of a diameter of Φ 32 Reinforcement fabrication.Footing foundation palpus hand excavation, ensures the smooth of step surface as far as possible.Soil body TGXG system is backfilled after stake Using high density polyvinyl-chloride direction earthwork grille, breadth is not less than 5.0m, 50~80mm of mesh diameter.
The construction method of highway hard rock Steep Slope Embankment anchor rod foundation friction pile of the present invention, the specific steps are: 1. surveying and locating.Friction pile accurate location is determined according to design coordinate scene;2. the table of friction pile construction area is removed in levelling of the land Layer soil, according to wide, the high excavation slope platform of design step, leveling antiskid pile foundation top surface platform indicates four of friction pile Corner location is in order to pile foundation of accurately constructing.The horizontal distance of basic top surface platform outer edge and line of slope is not less than 2.0m, Chipping is answered at platform outer edge to slope surface, and outside 4% weathering is set;3. chisel sets basis.Manually using pneumatic pick or other are small Type rock drilling machine excavation foundation forbids explosion, and foundation excavation is at the stepped form into massif, width height ratio of steps 1.0:1.0. Footing step horizontal width 0.5m, afterbody berm width are not less than 1.0m, and platform classification must not drop below 3 grades;4. constructing Vertical anchor rod system.According to friction pile arrangement of reinforcement, determine that main reinforcement branch position, corresponding main reinforcement position apply vertical armature boring, Boring direction is vertical, drillable length 4.15m.It constructs in time after pore-forming anchor pole, anchor pole exposure length is not less than 2.0m, in order to It is welded with pile body main reinforcement;5. the lateral anchoring-bolt system of construction.The lateral vertical spacing 1.0m of anchor pole, lateral arrangement two arrange, drillable length 12.15m, anchor pole direction and horizontal direction angle are 15 °.After pile body main reinforcement is welded, by lateral termination point of anchor rod and pile body main reinforcement Welding;6. molding and casting concrete.According to pile body sectional dimension molding, concrete grade is not less than C30, and pile body must with basis Palpus one-time-concreting molding, forbids to form horizontal construction joint, such as be poured because construction condition must be segmented, in two-step pouring level The short muscle of cloth is reinforced at interface;7. after pile strength reach design strength 80% after hang breast boards and backfill the soil body after wall, Backfill soil body wide bed TGXG, spacing 0.6m.
Highway hard rock Steep Slope Embankment anchor rod foundation friction pile of the present invention, its main feature is that:It is replaced with anchor rod foundation anti- Sliding pile anchoring section, anchor rod foundation horizontal cross section dimension are determined according to friction pile sectional dimension.Basis passes through horizontal direction anchor pole system System and vertical direction anchor rod system increase bending resistance, anti-pull-out property.Hard rock base surface chisel is set as inside stepped form, to increase The anti-slipping property energy of strong antiskid pile foundation.Laterally, vertical termination point of anchor rod and pile body main reinforcement are welded, so that pile body after casting concrete One is formed with massif.
The beneficial effects of the invention are as follows:1. reducing difficulty of construction, stake holes is excavated in hard rock location must use explosion, difficult To control construction quality, and engineering risk is higher.The present invention only needs artificial chisel to set friction pile basic platform, reduces construction Difficulty and risk are more advantageous to control construction quality;2. saving project cost, many hard rocks intensity itself is high in nature It is traditional to cause economic waste with excavation stake holes in hard rock in general concrete strength.The present invention makes full use of hard Pile body and hard rock mass are linked as entirety by anchor pole, save project cost by rock condition;3. the duration is shortened, since chisel is set Friction pile square foundation amount is small, is not influenced between stake and stake, does not need excavation by troughs, shortens the duration, while also saving engineering Indirect expense;4. reducing the influence of Engineering, the rock mass side's amount excavated needed for the present invention is small, avoid abandon quarrel huddle unrest Phenomenon is put, influence of the engineering to natural environment is reduced from source.
Description of the drawings
Fig. 1 is the structural diagram of the present invention.
Fig. 2 is that hard rock slope excavates schematic diagram.
Fig. 3 is friction pile foundation excavation schematic diagram.
Vertical and lateral anchor pole schematic diagram based on Fig. 4.
Fig. 5 is schematic diagram after the completion of pile body and basis pour.
Fig. 6 is hanging plate and backfills soil body schematic diagram after wall.
Figure label:1 friction pile cantilever segment, 2 antiskid pile foundation top surface platforms, 3 antiskid pile foundations, 4 antiskid pile foundations Plinth step, 5 vertical anchor rod systems, 6 lateral anchor rod systems, 7 hard rock slope excavation lines, 8 TGXG systems, 9 friction piles Cantilever segment main reinforcement, 10 hillside, 11 breast boards.
Specific implementation mode
Embodiment 1
Highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure, including:After excavation slope step 7, chisel sets anti- Sliding pile basis top surface platform 2.After determining four corner locations of friction pile, artificial chisel sets friction pile footing step 4.Construct anchor pole system System, anchor rod system include vertical anchor rod system 5 and lateral anchor rod system 6.Antiskid pile foundation 3 and friction pile cantilever segment 1 are poured, is waited for When pile strength reaches the 80% of design value, hangs breast boards and backfill the soil body after stake, while being laid with TGXG system 8.
Embodiment 2
The construction method of highway hard rock Steep Slope Embankment anchor rod foundation friction pile, the specific steps are:1. surveying and locating.Root Friction pile accurate location is determined according to design coordinate scene;2. levelling of the land removes the topsoil of friction pile construction area, according to design Wide, the high excavation slope platform of step, leveling antiskid pile foundation top surface platform, indicate four corner locations of friction pile in order to Accurate construction pile foundation.The horizontal distance of basic top surface platform outer edge and line of slope is not less than 2.0m, platform outer edge to slope Chipping is answered at face, and outside 4% weathering is set;3. chisel sets basis.Manually excavated using pneumatic pick or other gadding machine devices Explosion is forbidden on basis, and foundation excavation is at the stepped form into massif, width height ratio of steps 1.0:1.0.Footing step is horizontal wide 0.5m is spent, afterbody berm width is not less than 1.0m, and platform classification must not drop below 3 grades;4. vertical anchor rod system of constructing.Root According to friction pile arrangement of reinforcement, determine main reinforcement branch position, corresponding main reinforcement position applies vertical armature boring, boring direction be it is vertical, Drillable length 4.15m.It constructs in time after pore-forming anchor pole, anchor pole exposure length is not less than 2.0m, in order to be welded with pile body main reinforcement; 5. the lateral anchoring-bolt system of construction.The lateral vertical spacing 1.0m of anchor pole, lateral arrangement two arrange, drillable length 12.15m, anchor pole direction It it is 15 ° with horizontal direction angle.After pile body main reinforcement is welded, lateral termination point of anchor rod and pile body main reinforcement are welded;6. molding is simultaneously poured Build concrete.According to pile body sectional dimension molding, concrete grade is not less than C30, and pile body is molded with the necessary one-time-concreting in basis, Forbid to form horizontal construction joint, such as be poured because construction condition must be segmented, the short muscle of cloth at the horizontal interface of two-step pouring It is reinforced;7. after pile strength reach design strength 80% after hang breast boards and backfill the soil body after wall, backfill soil body wide bed soil Work grid, spacing 0.6m.
Embodiment 3
Present invention reinforced earth back-pressure as shown in Figure 1 closes supporting construction, and after hard rock slope excavation line 7, chisel sets antiskid Pile foundation top surface platform 2.After determining four corner locations of friction pile, artificial chisel sets friction pile footing step 4.Construct anchor pole system System, anchor rod system include vertical anchor rod system 5 and lateral anchor rod system 6.The anchoring section of traditional friction pile is replaced with anchor rod foundation, The excavation for ensuring reduction anchoring section while antiskid stake body is stablized, reduces difficulty of construction, saves project cost, while Reduce the destruction to ecological environment.Pile body and basis 1 are poured, when pile strength reaches the 80% of design value, hangs breast boards simultaneously The soil body after backfill stake, while being laid with TGXG system 8.TGXG reduces the soil pressure for directly acting on pile body, favorably In the stability for improving supporting construction.
Certain mountainous area highway roadbed is located at Steep Slope Embankment location, lateral slope of ground 1:0.75, this section of path length is 219m, Stratum is limestone, and rate of decay is weaker, and slope table coating is thin, many places basement rock exposure.If being passed through with bridge or tunnel, engineering is made Valence is high, and the construction period is long.Design scheme is passed through with roadbed semi-filling and semi-excavating, and pile plate wall supporting and retaining system is set on the outside of roadbed.Anchor pile is using this Invention anchor rod foundation Anti-slide Pile Retaining Structure, is as follows:
(1)Surveying and locating.Friction pile accurate location is determined according to design coordinate scene;
(2)Levelling of the land.The topsoil for removing friction pile construction area excavates the massif side within embankment according to design requirement Slope, platform wide 2m, high 1.3m, leveling antiskid pile foundation top surface platform, stake sectional dimension is 1.75m × 2.5m, indicates friction pile Four corner locations in order to pile foundation of accurately constructing.The horizontal distance of basic top surface platform outer edge and line of slope is not less than 2.0m, chipping at platform outer edge to slope surface, and outside 4% weathering is set;
(3)Chisel sets basis.Pneumatic pick excavation foundation is manually used, for foundation excavation at the stepped form into massif, step is wide Height is than being 1.0:1.0.Footing step horizontal width 0.5m, afterbody berm width are 1.25m, and platform is divided into 3 grades;
(4)It constructs vertical anchor rod system.According to friction pile arrangement of reinforcement, determine that main reinforcement branch position, corresponding main reinforcement position are applied Make vertical armature boring, boring direction is vertical, drillable length 4.15m.It constructs in time after pore-forming anchor pole, anchor pole exposure length is not Less than 2.0m, in order to be welded with pile body main reinforcement;
(5)The lateral anchoring-bolt system of construction.The lateral vertical spacing 1.0m of anchor pole, lateral arrangement two arrange, drillable length 12.15m, Anchor pole direction and horizontal direction angle are 15 °.After pile body main reinforcement is bound, lateral termination point of anchor rod and pile body main reinforcement are welded;
(6)Molding and casting concrete.According to pile body sectional dimension molding, concrete grade C35, pile body and basis one Secondary pouring molding;
(7)After pile strength reach design strength 80% after hang breast boards and backfill the soil body after wall, backfill soil body wide bed soil Work grid, spacing 0.6m.Thus the construction of anchor rod foundation friction pile retaining structure is completed.
Embodiment 4
A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure, including friction pile cantilever segment 1, friction pile Basic top surface platform 2, antiskid pile foundation 3, friction pile footing step 4, vertical anchor rod system 5, lateral anchor rod system 6, Tu Gongge Grating system 8, friction pile cantilever segment main reinforcement 9, hillside 10 and breast boards 11 are provided with friction pile footing step 4 on the hillside 10, Antiskid pile foundation 3 is provided on the friction pile footing step 4, it is flat that the antiskid pile foundation 3 is provided with antiskid pile foundation top surface Platform 2 is provided with friction pile cantilever segment 1 on antiskid pile foundation top surface platform 2, is set in the hillside 10 and antiskid pile foundation 3 It is equipped with vertical anchor rod system 5, the hillside 10 and 3 intersection of antiskid pile foundation are provided with lateral anchor rod system 6;
The friction pile cantilever segment 1 is internally provided with breast boards 11 and friction pile cantilever segment main reinforcement 9;
The vertical anchor rod system 5 and lateral anchor rod system 6 are fixedly connected with friction pile cantilever segment main reinforcement 9;
The soil body is backfilled between the friction pile cantilever segment 1 and hillside 10 and is laid with TGXG system 8.
Further, the antiskid pile foundation 3 and pile body synchronize pour, the concrete grade of use is identical as pile body, basis It is not less than C30 with pile concrete label.
Further, the vertical anchor rod system 5 and lateral anchor rod system 6 use the HRB400 reinforcing bar systems of a diameter of Φ 32 Make, vertical rock-bolt length 4m, exposure 2m, lateral anchor pole 12m, exposure to pile body main reinforcement position.
Further, the vertical anchor rod system 5 and lateral anchor rod system 6 are welded with friction pile cantilever segment main reinforcement 9.
Further, the friction pile footing step 4 uses hand excavation, ensures the smooth of step surface, foundation excavation to Stepped form in massif, width height ratio of steps 1.0:1.0, footing step horizontal width 0.5m, afterbody berm width is not Less than 1.0m, platform classification must not drop below 3 grades.
Further, the TGXG system 8 uses high density polyvinyl-chloride direction earthwork grille, breadth to be not less than 5.0m, 50~80mm of mesh diameter.
Further, the friction pile cantilever segment 1 is rectangle or the rectangle with the edge of a wing.

Claims (7)

1. a kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure, which is characterized in that including friction pile cantilever Section(1), antiskid pile foundation top surface platform(2), antiskid pile foundation(3), friction pile footing step(4), vertical anchor rod system(5)、 Lateral anchor rod system(6), TGXG system(8), friction pile cantilever segment main reinforcement(9), hillside(10)And breast boards(11), described Hillside(10)On be provided with friction pile footing step(4), the friction pile footing step(4)On be provided with antiskid pile foundation(3), The antiskid pile foundation(3)It is provided with antiskid pile foundation top surface platform(2), antiskid pile foundation top surface platform(2)Upper setting There is friction pile cantilever segment(1), the hillside(10)With antiskid pile foundation(3)On be provided with vertical anchor rod system(5), the hillside (10)With antiskid pile foundation(3)Intersection is provided with lateral anchor rod system(6);
The friction pile cantilever segment(1)It is internally provided with breast boards(11)With friction pile cantilever segment main reinforcement(9);
The vertical anchor rod system(5)With lateral anchor rod system(6)With friction pile cantilever segment main reinforcement(9)It is fixedly connected;
The friction pile cantilever segment(1)The hillside and(10)Between backfill the soil body and be laid with TGXG system(8).
2. highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure according to claim 1, which is characterized in that The antiskid pile foundation(3)With pile body synchronize pour, the concrete grade of use is identical as pile body, basis and pile concrete mark Number be not less than C30.
3. highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure according to claim 1, which is characterized in that The vertical anchor rod system(5)With lateral anchor rod system(6)Using the HRB400 reinforcement fabrications of a diameter of Φ 32, vertical anchor pole is long Spend 4m, exposure 2m, lateral anchor pole 12m, exposure to pile body main reinforcement position.
4. highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure according to claim 1, which is characterized in that The vertical anchor rod system(5)With lateral anchor rod system(6)With friction pile cantilever segment main reinforcement(9)Welding.
5. highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure according to claim 1, which is characterized in that The friction pile footing step(4)Using hand excavation, ensure the smooth of step surface, foundation excavation is at the step into massif Formula, width height ratio of steps 1.0:1.0, footing step horizontal width 0.5m, afterbody berm width are not less than 1.0m, platform point Grade must not drop below 3 grades.
6. highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure according to claim 1, which is characterized in that The TGXG system(8)Using high density polyvinyl-chloride direction earthwork grille, breadth is not less than 5.0m, and mesh diameter 50~ 80mm。
7. highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure according to claim 1, which is characterized in that The friction pile cantilever segment(1)Rectangle for rectangle or with the edge of a wing.
CN201820176798.9U 2018-02-01 2018-02-01 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure Active CN207987960U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820176798.9U CN207987960U (en) 2018-02-01 2018-02-01 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820176798.9U CN207987960U (en) 2018-02-01 2018-02-01 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure

Publications (1)

Publication Number Publication Date
CN207987960U true CN207987960U (en) 2018-10-19

Family

ID=63822590

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820176798.9U Active CN207987960U (en) 2018-02-01 2018-02-01 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure

Country Status (1)

Country Link
CN (1) CN207987960U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086352A (en) * 2018-02-01 2018-05-29 云南新创新交通建设股份有限公司 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure
CN110820433A (en) * 2019-12-04 2020-02-21 中铁二院工程集团有限责任公司 Hard plastic soil foundation existing high-speed railway embankment force balance side width structure and construction method
CN111118967A (en) * 2019-12-30 2020-05-08 中铁第六勘察设计院集团有限公司 Construction method for filling foam light soil foundation pit of railway roadbed in soft soil area
CN113215995A (en) * 2021-05-11 2021-08-06 广州市市政工程设计研究总院有限公司 Method for constructing bridge road in narrow space
CN113373946A (en) * 2021-04-26 2021-09-10 中国建筑第二工程局有限公司 Mine method tunnel entrance side slope construction platform structure and construction method thereof

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108086352A (en) * 2018-02-01 2018-05-29 云南新创新交通建设股份有限公司 A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure
CN110820433A (en) * 2019-12-04 2020-02-21 中铁二院工程集团有限责任公司 Hard plastic soil foundation existing high-speed railway embankment force balance side width structure and construction method
CN110820433B (en) * 2019-12-04 2024-05-24 中铁二院工程集团有限责任公司 Hard plastic soil foundation existing high-speed railway embankment force balance side width structure and construction method
CN111118967A (en) * 2019-12-30 2020-05-08 中铁第六勘察设计院集团有限公司 Construction method for filling foam light soil foundation pit of railway roadbed in soft soil area
CN113373946A (en) * 2021-04-26 2021-09-10 中国建筑第二工程局有限公司 Mine method tunnel entrance side slope construction platform structure and construction method thereof
CN113373946B (en) * 2021-04-26 2022-12-06 中国建筑第二工程局有限公司 Mine method tunnel entrance side slope construction platform structure and construction method thereof
CN113215995A (en) * 2021-05-11 2021-08-06 广州市市政工程设计研究总院有限公司 Method for constructing bridge road in narrow space
CN113215995B (en) * 2021-05-11 2022-06-10 广州市市政工程设计研究总院有限公司 Method for constructing bridge road in narrow space

Similar Documents

Publication Publication Date Title
CN108086352A (en) A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure
CN207987960U (en) A kind of highway hard rock Steep Slope Embankment anchor rod foundation Anti-slide Pile Retaining Structure
CN106703050A (en) Expansive soil road cutting side slope reinforced soil back-pressure seepage-preventive supporting structure and construction method thereof
CN207003499U (en) A kind of anti-floating lifting device of underground tunnel upper excavation of foundation pit
CN104631468B (en) The method for protecting support of deep excavation project
CN206308569U (en) It is a kind of to reinforce the road structure for punishing the solution cavity that underlies
CN107503362A (en) A kind of compound antiskid piling wall retaining structure and construction method suitable for reservoir stability
CN109441456A (en) A kind of the tunnel structure and its construction method of weakness Facility-sliding strata
CN202430681U (en) Bank protection structure
CN109750571A (en) A kind of road landslide emergency and permanent supporting and retaining system integral structure and construction method
CN113174958A (en) Construction method for foundation pit of adjacent road under poor ground condition
CN211200426U (en) Anti-sliding supporting and retaining structure for miniature steel pipe pile retaining wall
CN108914954A (en) Slope support method of the pre support in conjunction with permanent support
CN106013178B (en) A kind of placement method of shallow buried type Karst surface collapse
CN102817298B (en) Construction method on permafrost
CN109208545B (en) Construction method of artificial landscape overflow dam with energy dissipation effect
CN109898556A (en) A kind of underground pipe gallery structure and sunk type construction method
CN111021378A (en) Highway subgrade slope broken line type anchoring pile retaining structure and construction method thereof
CN110331735A (en) A kind of tower crane mounting structure for coastal region soft layer
CN207878451U (en) A kind of device using hole rising pouring slurry ground-connecting-wall control influence of foundation excavation
CN206768832U (en) Support, anchor cable post-tensioning H type component building enclosures before a kind of steel pipe
CN109610505A (en) A kind of tunnel upper foundation pit construction method
CN211080248U (en) Deep foundation pit supporting structure of adjacent road under complex geological condition
CN209585072U (en) It is a kind of for high slope, the retaining structure in narrow location
CN211773854U (en) Soil retaining structure permeates water with soil nail

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20240201

Address after: Room 828, 8th Floor, Building 2, Yunnan Overseas Returnees Entrepreneurship Park, Guolin Community, Luoyang Street Office, Economic Development Zone, Kunming Area, China (Yunnan) Pilot Free Trade Zone, Kunming City, Yunnan Province, 650000

Patentee after: Yunnan Jiuda Transportation Construction Co.,Ltd.

Country or region after: China

Address before: No. 815, 8th Floor, Building 1, Yunnan Overseas Returnees Entrepreneurship Park, No. 80 Chunman Avenue, Information Industry Base, Economic Development Zone, Kunming City, Yunnan Province, 650000

Patentee before: YUNNAN XINCHUANGXIN TRANSPORTATION CONSTRUCTION CO.,LTD.

Country or region before: China