CN207701147U - A kind of automatic butt shunt conduit device of tunnel lining trolley - Google Patents

A kind of automatic butt shunt conduit device of tunnel lining trolley Download PDF

Info

Publication number
CN207701147U
CN207701147U CN201820028274.5U CN201820028274U CN207701147U CN 207701147 U CN207701147 U CN 207701147U CN 201820028274 U CN201820028274 U CN 201820028274U CN 207701147 U CN207701147 U CN 207701147U
Authority
CN
China
Prior art keywords
pipeline
frame body
trolley
pours
lining trolley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820028274.5U
Other languages
Chinese (zh)
Inventor
黄高飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Luoyang Gaofei Bridges And Tunnels Machinery Co ltd
Original Assignee
Luoyang Fly Bridge Machinery Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Luoyang Fly Bridge Machinery Co Ltd filed Critical Luoyang Fly Bridge Machinery Co Ltd
Priority to CN201820028274.5U priority Critical patent/CN207701147U/en
Application granted granted Critical
Publication of CN207701147U publication Critical patent/CN207701147U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

A kind of automatic butt shunt conduit device of tunnel lining trolley, ground concrete delivery pump is set between the lining trolley frame body of lining trolley side two, setting intelligent concrete pours control system on the inside of the platform building cart frame body of the lining trolley other side, frame body crossbeam is respectively set above lining trolley frame body, front end, both sides are symmetrical arranged two frame body longerons between above the frame body crossbeam of rear end, two backform crossbeams are laterally arranged in both ends above frame body longeron, both sides are symmetrical arranged two delivery pump device sliding rails between two root backform crossbeams, moving trolley is set above delivery pump device sliding rail;Delivery pump device sliding rail both sides both sides both sides top template pillar, which leads to above beam, is symmetrically uniformly arranged top template pillar upper end setting top template;The tunnel lining trolley shunt conduit docking of the utility model carries out pouring lining construction using moving trolley driving positioning, classification;Intelligence programming, can largely reduce working at height staff use and improve construction quality.

Description

A kind of automatic butt shunt conduit device of tunnel lining trolley
Technical field
The utility model is related to the shuntings of tunnel lining trolley concrete shunt conduit device to pour, especially a kind of tunnel The automatic butt shunt conduit device of lining trolley.
Background technology
Currently, the trolley both sides of lining construction are equipped with concrete diversion channel and pipeline, the outer side mold of lining trolley Have, pour working window, in work progress, concrete is built by diversion channel and pipeline to carrying out concrete on the outside of working window Pour, concrete is built pour after the completion of, concrete build pours needs by manually high-altitude carry out coordinative construction, due to concrete diversion channel Big with the range of pipeline, the tool and component of construction are mixed and disorderly, the security needs guarantee of the upper lower frame of high-altitude construction personnel, and construction is difficult The slow of the difficulty and duration for causing construction greatly is spent, causes construction period length, concrete to build and pours quality decline, operating expenses Height, in view of the foregoing, it is proposed that a kind of automatic butt shunt conduit device of tunnel lining trolley.
Utility model content
The purpose of this utility model is to overcome the trolley both sides of lining construction be equipped with concrete diversion channel and Pipeline, the outside mould of lining trolley pour working window, and in work progress, concrete is by diversion channel and pipeline to work Make side outside window and carry out concrete to build and pours, concrete is built pour after the completion of, concrete, which is built, pours needs by manually being coordinated in high-altitude Construction, since the range of concrete diversion channel and pipeline is big, the tool and component of construction are mixed and disorderly, the upper lower frame of high-altitude construction personnel Security needs guarantee, difficulty of construction is big, cause construction difficulty and the duration it is slow, cause that the construction period is long, concrete It builds and pours quality decline, operating expenses is high, by reasonably designing, provides a kind of automatic butt shunt conduit of tunnel lining trolley The tunnel lining trolley shunt conduit docking of device, the utility model is driven using moving trolley driving positioning by docking pipeline Dynamic device makes overturning pipeline be overturn, it is flexible respectively with pour pipeline interface docked, pass through shunting after the completion of docking Pipeline classification carries out pouring lining construction;Intelligence programming, setting install the fortune that detector controls moving trolley by operation window Row, the positioning turning of infrared detection control overturning pipeline stretch, and enable tunnel lining trolley automatic butt shunt conduit device Intelligence completes docking placement layer by layer, can largely reduce the use of the staff of working at height, it is ensured that safe construction is accelerated to apply Work progress improves the quality of construction.
The utility model to achieve the goals above, adopts the following technical scheme that:A kind of tunnel lining trolley it is automatic right Connect shunt conduit device, be by:Lining trolley frame body, frame body crossbeam, side template, top template, moving trolley, trolley power dress It sets, pneumatic device, car wheel, concrete conveyance mechanism, ground concrete delivery pump, head conduit, top isocon Road, middle part shunt conduit, top pours pipeline, middle part pours pipeline, lower part pours pipeline, adjustable pipe connects valve port, lead screw, work Window, overturning docking plumbing installation, angular movement conveyance conduit, delivery pump device sliding rail, to pour pipeline logical to interface, top template pillar Beam, rotating pipe import, rotating pipe outlet, motion tubes adapter assembly, overturning pipe outlet, backform crossbeam, intelligent coagulation Soil pours control system composition;Lining trolley sets at least to three lining trolley frame bodies, front end, rear end lining trolley frame body Running gear is arranged in lower section;Ground concrete delivery pump, lining cutting platform are set between the lining trolley frame body of lining trolley side two Setting intelligent concrete pours control system on the inside of the lining trolley frame body of the vehicle other side, and intelligent concrete pours set-up of control system To be portable or fixed, intelligent concrete, which pours, is equipped with wireless signal or wire signal module in control system;Lining trolley Be respectively set frame body crossbeam above frame body, front end, rear end frame body crossbeam above between both sides be symmetrical arranged two frame body longerons, Two backform crossbeams are laterally arranged in both ends above frame body longeron, and both sides are symmetrical arranged two delivery pumps between two root backform crossbeams Moving trolley is arranged in device sliding rail, delivery pump device sliding rail top;
Delivery pump device sliding rail both sides both sides are symmetrical arranged top template pillar and lead to beam, and both sides top template pillar leads to right above beam Title is uniformly arranged top template pillar, top template pillar upper end setting top template, top template middle part longitudinal reserved at least three Top working window;The lining trolley frame body both sides of lining trolley are respectively set side template, lining trolley frame body both sides respectively with side Lead screw is set between template, the uniformly staggeredly reserved work of the top, middle part, lower part on the side template of lining trolley frame body both sides Window;
Rotating pipe import, rotating pipe import and ground concrete delivery pump are set above the sides top template pillar Tong Liang Between head conduit is set;Two both sides top template pillar Tong Liang are symmetrically respectively set at least two groups and pour pipeline docking Mouthful, the both sides that each top template pillar leads to beam are symmetrically respectively set to two and a pair of pour pipeline to interface, two a pair The pipeline that pours pipe joint is set between interface;
Two upper lateral part of lining trolley frame body is symmetrical arranged top shunt conduit, and two middle side part of lining trolley frame body is symmetrically distinguished Setting middle part shunt conduit;Outside pours pipeline to top shunt conduit is respectively set in interface;Below the shunt conduit of top Outlet end be set as top and pour pipeline, top shunt conduit pours provided pipe road junction below the switching phase of pipeline with top, Setting middle part shunt conduit in pipeline opening, middle part shunt conduit middle part setting middle part pour pipeline, are brought out under the shunt conduit of middle part Mouth is set as lower part and pours pipeline;Top pours pipeline, middle part pours pipeline, lower part pour lower end of duct pipe outlet difference Working window is reserved in corresponding top, middle part, lower part;Top pours pipeline, middle part pours pipeline, lower part pours the pipe outlet of pipeline Adjustable pipe is respectively set and connects valve port;
The front and back end of both sides corresponds to delivery pump device sliding rail and is respectively set car wheel below moving trolley, in moving trolley Trolley power plant, pneumatic device, coagulation is respectively set in square side setting concrete conveyance mechanism, the moving trolley top other side Side setting rotating pipe exports above native conveying mechanism, and setting angular movement is defeated between rotating pipe outlet and rotating pipe import Pipeline, the pipeline above angular movement conveyance conduit is sent to be set as pipeline large arm, the pipeline below angular movement conveyance conduit is set as Motion tubes adapter assembly is arranged in forearm between the large arm and forearm of angular movement conveyance conduit;
The concrete conveyance mechanism side setting overturning docking plumbing installation of moving trolley, concrete conveyance mechanism and overturning Setting overturns pipe outlet between docking plumbing installation, and telescopic pipes are equipped in overturning docking plumbing installation;
Retarder is set in trolley power plant, the retarder in trolley power plant respectively with pneumatic device, trolley vehicle Transmission device is set between wheel, overturning pipe outlet, high pressure gas is set between take over road pneumatic device and overturning pipe outlet Pipeline.
Operation principle:When lining construction casting concrete, tunnel lining concrete pours intelligent concrete and pours control System processed is opened, and by being programmed into mode of operation, intelligent concrete pours control system startup trolley power plant band and takes offence Dynamic device, meanwhile, concrete tank inputs concrete in ground concrete delivery pump.
Intelligent concrete pours control system instruction trolley power plant and drives moving trolley movement by car wheel, moves Dynamic trolley is moved to overturning docking plumbing installation correspondence and pours pipeline to stopping when interface, confirms overturning docking by infrared detection Positioning signal, is sent to intelligent concrete and pours control by the position of plumbing installation and after pouring pipeline to the positioning of the position of interface System, intelligent concrete pour control system instruction pneumatic device and push overturning to dock the telescoping tube in plumbing installation by air pressure Road, which enters, pours pipeline to carrying out Butt sealing in interface.
After overturning docks plumbing installation and pours pipeline to interface Butt sealing, ground concrete delivery pump delivering concrete After being entered in concrete conveyance mechanism by head conduit;Concrete conveyance mechanism delivering concrete sequentially enters part Pipeline is poured by the working window of side template lower part to carrying out coagulation on the outside of side template to lower part after flow tube road, middle part shunt conduit Soil pours;The top below interface is shunted by the pipeline that pours of each in each group respectively according to above workflow Pipeline, middle part shunt conduit, lower part pour pipeline and are poured by the working window of side template lower part carrying out concrete on the outside of side template It builds;After the completion of the working window of lower part on the outside of side template to carrying out concreting, lower part pours the movable tube connecting valve of pipeline nozzle Mouth is shunk, and the working window of lower part is closed.
After the working window of lower part is closed, pipeline docking is poured to each in each group respectively according to above workflow Top shunt conduit, middle part shunt conduit below mouthful, middle part pour pipeline by the working window in the middle part of side template to side template Outside carries out concreting;After the completion of the working window at middle part on the outside of side template to carrying out concreting, middle part pours pipeline The adjustable pipe of nozzle connects valve port contraction, and the working window at middle part is closed.
After the working window at middle part is closed, pipeline docking is poured to each in each group respectively according to above workflow Top shunt conduit, middle part shunt conduit below mouthful, top pour pipeline by the working window on side template top to side template Outside carries out concreting;After the completion of the working window on top on the outside of side template to carrying out concreting, top pours pipeline The adjustable pipe of nozzle connects valve port contraction, and the working window on top is closed.
After the working window at middle part is closed, pipeline docking is poured to each in each group respectively according to above workflow Top shunt conduit, middle part shunt conduit below mouthful, top pour pipeline by the working window on side template top to side template Outside carries out concreting;After the completion of the working window on top on the outside of side template to carrying out concreting, top pours pipeline The adjustable pipe of nozzle connects valve port contraction, and the working window on top is closed;According to above workflow to the lining cutting platform of lining trolley On the outside of the side template of the vehicle frame other side respectively under by working window carry out concreting.
On the outside of the side template of the other side respectively under by working window carry out concreting after the completion of, the other side Side template top working window close after, intelligent concrete pour control system instruction trolley power plant pass through car wheel Moving trolley movement is driven, moving trolley, which is moved to when overturning docking plumbing installation corresponds to the top working window of top template, stops Only, intelligent concrete pours control system instruction overturning docking plumbing installation and carries out overturning corresponding top working window, by infrared After detection confirms the position of overturning docking plumbing installation and the position positioning of top working window, it is mixed that positioning signal is sent to intelligence Solidifying soil pours control system, and intelligent concrete pours control system instruction pneumatic device and pushes overturning docking pipeline dress by air pressure The telescopic pipes set, which enter in the working window of top, to be sealed;After the working window sealing of top, the conveying of concrete conveyance mechanism is mixed Solidifying soil docks plumbing installation by overturning and carries out concreting to top template outside, and concreting is complete on the outside of the template of top Cheng Hou, the telescopic pipes of overturning docking plumbing installation, which shrink, exits top working window, and top working window is closed;According to above Workflow respectively by top working window to concreting on the outside of the template of top;Concreting is complete on the outside of the template of top At completing whole lining concrete in tunnel construction.
Advantageous effect:The tunnel lining trolley shunt conduit docking of the utility model is led to using moving trolley driving positioning Cross docking pipeline driving device overturning pipeline made to be overturn, it is flexible respectively with pour pipeline interface docked, docked It carries out pouring lining construction by shunt conduit classification at rear;Intelligence programming, setting install detector control by operation window The operation of moving trolley, the positioning turning of infrared detection control overturning pipeline stretch, and tunnel lining trolley automatic butt is made to shunt Plumbing installation can intelligently complete docking placement layer by layer, can largely reduce the use of the staff of working at height, it is ensured that peace Full construction, accelerates construction progress, improves the quality of construction.
Description of the drawings
The utility model is described in further detail below in conjunction with the accompanying drawings:
Fig. 1 is general assembly structural schematic diagram;
Fig. 2 is the moving trolley overlooking structure diagram of Fig. 1;
Fig. 3 is the partial structural diagram of Fig. 2;
Fig. 4 is the moving trolley side structure schematic view of Fig. 2;
In Fig. 1,2,3,4:Lining trolley frame body 1, frame body crossbeam 2, side template 3, top template 4, moving trolley 5, trolley Power plant 5-1, pneumatic device 5-2, car wheel 5-3, concrete conveyance mechanism 5-4, ground concrete delivery pump 6, pressure Conveyance conduit 7, top shunt conduit 8, middle part shunt conduit 9, top pours pipeline 10, middle part pours pipeline 11, lower part pours Pipeline 12, adjustable pipe connect valve port 13, lead screw 14, working window 15, overturning docking plumbing installation 16, angular movement conveyance conduit 17, defeated It send pump installation sliding rail 18, pour pipeline to interface 19, the logical beam 20 of top template pillar, rotating pipe import 21, rotating pipe outlet 22, motion tubes adapter assembly 23, overturning pipe outlet 24, backform crossbeam 25, intelligent concrete pour control system 26.
Specific implementation mode
The utility model is described in further detail with specific implementation mode below in conjunction with the accompanying drawings:
Lining trolley sets at least to three lining trolley frame bodies 1, the 1 lower section setting of lining trolley frame body of front end, rear end Running gear;Ground concrete delivery pump 6 is set between the lining trolley frame body 1 of lining trolley side two, and lining trolley is another Lining trolley frame body 1 inside setting intelligent concrete in side pours control system 26, and intelligent concrete pours the setting of control system 26 To be portable or fixed, intelligent concrete, which pours, is equipped with wireless signal or wire signal module in control system 26;Lining cutting platform The top of vehicle frame 1 is respectively set frame body crossbeam 2, front end, rear end 2 top of frame body crossbeam between both sides be symmetrical arranged two frame bodies Two backform crossbeams 25 are laterally arranged in longeron, frame body longeron top both ends, and both sides are symmetrical arranged between two root backform crossbeams 25 Moving trolley 5 is arranged in two delivery pump device sliding rails 18,18 top of delivery pump device sliding rail;
18 both sides both sides of delivery pump device sliding rail are symmetrical arranged top template pillar and lead to beam 20, and both sides top template pillar leads to beam 20 Top is symmetrically uniformly arranged top template pillar, and top template pillar upper end setting top template 4, template 4 middle part in top is longitudinal to be reserved At least three top working windows;Side template 3,1 liang of lining trolley frame body is respectively set in 1 both sides of lining trolley frame body of lining trolley Lead screw 14 is arranged in side between side template 3 respectively, and top, middle part, the lower part on the side template 3 of 1 both sides of lining trolley frame body are equal Cloth staggeredly reserves working window 15;
Top template pillar leads to setting rotating pipe import 21, rotating pipe import 21 and ground concrete above 20 side of beam Head conduit 7 is set between delivery pump 6;Logical 20 both sides of beam of two top template pillars are symmetrically respectively set at least two groups and pour To interface 19, the both sides that each top template pillar leads to beam 20 are symmetrically respectively set to two a pair of pipelines that pour and dock pipeline Mouth 19, pipe joint is arranged between interface 19 in two a pair of pipelines that pour;
1 liang of upper lateral part of lining trolley frame body is symmetrical arranged top shunt conduit 8, and 1 liang of middle side part of lining trolley frame body is symmetrical Middle part shunt conduit 9 is respectively set;Outside pours pipeline to top shunt conduit 8 is respectively set in interface 19;Top shunts The outlet end of 8 lower section of pipeline is set as top and pours pipeline 10, and top shunt conduit 8 is poured with top under the switching phase of pipeline 10 Square provided pipe road junction, setting middle part shunt conduit 9 in pipeline opening, 9 middle part setting middle part of middle part shunt conduit pour pipeline 11, in The outlet of 9 lower end of portion's shunt conduit is set as lower part and pours pipeline 12;Top pours pipeline 10, middle part pours pipeline 11, lower part is poured The pipe outlet for building 12 lower end of pipeline corresponds to top respectively, working window 15 is reserved in middle part, lower part;Top pours pipeline 10, middle part Pour pipeline 11, lower part pours the pipe outlet of pipeline 12 and adjustable pipe is respectively set connects valve port 13;
The front and back end of 5 lower section both sides of moving trolley corresponds to delivery pump device sliding rail 18 and car wheel 5-3 is respectively set, mobile Concrete conveyance mechanism 5-4 is arranged in 5 upper side of trolley, and trolley power plant 5- is respectively set in the 5 top other side of moving trolley 1, side setting rotating pipe exports 22 above pneumatic device 5-2, concrete conveyance mechanism 5-4, and rotating pipe exports 22 and rotation Turn that angular movement conveyance conduit 17 is arranged between conduit entrance 21, it is big that the pipeline above angular movement conveyance conduit 17 is set as pipeline The pipeline of arm, 17 lower section of angular movement conveyance conduit is set as forearm, is arranged between the large arm and forearm of angular movement conveyance conduit 17 Motion tubes adapter assembly 23;
The sides the concrete conveyance mechanism 5-4 setting overturning docking plumbing installation 16 of moving trolley 5, concrete conveyance mechanism Setting overturning pipe outlet 24 between 5-4 docks plumbing installation 16 with overturning, overturning, which is docked, is equipped with telescoping tube in plumbing installation 16 Road;
Retarder is set in trolley power plant 5-1, the retarder in trolley power plant 5-1 respectively with pneumatic device 5- 2, transmission device, take over road pneumatic device 5-2 and overturning pipe outlet are set between car wheel 5-3, overturning pipe outlet 24 High-pressure gas pipelines are set between 24.

Claims (8)

1. a kind of automatic butt shunt conduit device of tunnel lining trolley, be by:Lining trolley frame body (1), frame body crossbeam (2), side template (3), top template (4), moving trolley (5), trolley power plant (5-1), pneumatic device (5-2), trolley vehicle Take turns (5-3), concrete conveyance mechanism (5-4), ground concrete delivery pump (6), head conduit (7), top shunt conduit (8), middle part shunt conduit (9), top pours pipeline (10), middle part pours pipeline (11), lower part pours pipeline (12), adjustable pipe Connect valve port (13), lead screw (14), working window (15), overturning docking plumbing installation (16), angular movement conveyance conduit (17), delivery pump Device sliding rail (18) pours pipeline to interface (19), the logical beam (20) of top template pillar, rotating pipe import (21), rotating pipe Outlet (22), motion tubes adapter assembly (23), overturning pipe outlet (24), backform crossbeam (25), intelligent concrete pour control System (26) processed is constituted;It is characterized in that:Lining trolley sets at least to three lining trolley frame bodies (1), front end, rear end lining Running gear is set below platform building cart frame body (1);Ground coagulation is set between the lining trolley frame body (1) of lining trolley side two Native delivery pump (6), lining trolley other side lining trolley frame body (1) inside setting intelligent concrete pour control system (26), Intelligent concrete pours control system (26) and is set as portable or fixed, and intelligent concrete pours to be set in control system (26) There are wireless signal or wire signal module;Be respectively set frame body crossbeam (2) above lining trolley frame body (1), front end, rear end frame Both sides are symmetrical arranged two frame body longerons between above body crossbeam (2), and two backform cross are laterally arranged in both ends above frame body longeron Beam (25), both sides are symmetrical arranged two delivery pump device sliding rails (18) between two root backform crossbeams (25), and delivery pump device is slided Setting moving trolley (5) above rail (18).
2. a kind of automatic butt shunt conduit device of tunnel lining trolley according to claim 1, it is characterised in that:It is defeated It send pump installation sliding rail (18) both sides both sides to be symmetrical arranged top template pillar and leads to beam (20), both sides top template pillar leads to above beam (20) Symmetrical to be uniformly arranged top template pillar, top template (4) is arranged in top template pillar upper end, and longitudinal direction is reserved in the middle part of top template (4) At least three top working windows;Side template (3), lining trolley frame is respectively set in lining trolley frame body (1) both sides of lining trolley Lead screw (14) is arranged in body (1) both sides between side template (3) respectively, upper on the side template (3) of lining trolley frame body (1) both sides Working window (15) is uniformly staggeredly reserved in portion, middle part, lower part.
3. a kind of automatic butt shunt conduit device of tunnel lining trolley according to claim 1, it is characterised in that:Top Stud leads to setting rotating pipe import (21) above beam (20) side, and rotating pipe import (21) is conveyed with ground concrete Setting head conduit (7) between pump (6);Logical beam (20) both sides of two top template pillars are symmetrically respectively set at least two groups and pour Pipeline is built to interface (19), the both sides that each top template pillar leads to beam (20) are symmetrically respectively set to two and a pair of pour pipe Pipe joint is arranged between interface (19) to interface (19), two a pair of pipelines that pour in road.
4. a kind of automatic butt shunt conduit device of tunnel lining trolley according to claim 1, it is characterised in that:Lining (1) two upper lateral part of platform building cart frame body is symmetrical arranged top shunt conduit (8), and (1) two middle side part of lining trolley frame body is symmetrically distinguished Setting middle part shunt conduit (9);Outside pours pipeline to top shunt conduit (8) is respectively set in interface (19);Upper part Outlet end below flow tube road (8) is set as top and pours pipeline (10), and top shunt conduit (8) pours pipeline (10) with top Switching phase below provided pipe road junction, setting middle part shunt conduit (9) in pipeline opening, in the middle part of middle part shunt conduit (9) in setting Portion pours pipeline (11), and the outlet of middle part shunt conduit (9) lower end is set as lower part and pours pipeline (12);Top pours pipeline (10), middle part pours pipeline (11), lower part pours the pipe outlet of pipeline (12) lower end to correspond to top, middle part, lower part respectively pre- Stay working window (15);Top pours pipeline (10), middle part pours pipeline (11), lower part pour pipeline (12) pipe outlet difference Setting adjustable pipe connects valve port (13).
5. a kind of automatic butt shunt conduit device of tunnel lining trolley according to claim 1, it is characterised in that:It moves The front and back end of both sides corresponds to delivery pump device sliding rail (18) and car wheel (5-3), moving trolley is respectively set below dynamic trolley (5) (5) trolley power plant is respectively set in upper side setting concrete conveyance mechanism (5-4), moving trolley (5) the top other side (5-1), pneumatic device (5-2), concrete conveyance mechanism (5-4) rotating pipe of side setting above export (22), rotating pipe It exports and angular movement conveyance conduit (17) is set between (22) and rotating pipe import (21), above angular movement conveyance conduit (17) Pipeline is set as pipeline large arm, and the pipeline below angular movement conveyance conduit (17) is set as forearm, angular movement conveyance conduit (17) Large arm and forearm between setting motion tubes adapter assembly (23).
6. a kind of automatic butt shunt conduit device of tunnel lining trolley according to claim 1, it is characterised in that:It moves The side concrete conveyance mechanism (5-4) setting overturning docking plumbing installation (16) of dynamic trolley (5), concrete conveyance mechanism (5- 4) setting overturning pipe outlet (24) between docking plumbing installation (16) with overturning, overturning, which docks to be equipped in plumbing installation (16), stretches Pipe.
7. a kind of automatic butt shunt conduit device of tunnel lining trolley according to claim 1, it is characterised in that:It is small Retarder is set in vehicle power plant (5-1), the retarder in trolley power plant (5-1) respectively with pneumatic device (5-2), small Transmission device is set between vehicle wheel (5-3), overturning pipe outlet (24), and take over road pneumatic device (5-2) goes out with overturning pipeline High-pressure gas pipelines are set between mouth (24).
8. a kind of automatic butt shunt conduit device of tunnel lining trolley according to claim 1, it is characterised in that:Tunnel When road lining construction casting concrete, tunnel lining concrete pours intelligent concrete and pours control system (26) unlatching, passes through It is programmed into mode of operation, intelligent concrete pours control system (26) and starts trolley power plant (5-1) drive pneumatic device (5-2), meanwhile, concrete tank will be in concrete input ground concrete delivery pump (6).
CN201820028274.5U 2018-01-08 2018-01-08 A kind of automatic butt shunt conduit device of tunnel lining trolley Active CN207701147U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820028274.5U CN207701147U (en) 2018-01-08 2018-01-08 A kind of automatic butt shunt conduit device of tunnel lining trolley

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820028274.5U CN207701147U (en) 2018-01-08 2018-01-08 A kind of automatic butt shunt conduit device of tunnel lining trolley

Publications (1)

Publication Number Publication Date
CN207701147U true CN207701147U (en) 2018-08-07

Family

ID=63033912

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820028274.5U Active CN207701147U (en) 2018-01-08 2018-01-08 A kind of automatic butt shunt conduit device of tunnel lining trolley

Country Status (1)

Country Link
CN (1) CN207701147U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108412516A (en) * 2018-01-08 2018-08-17 洛阳高飞桥隧机械有限公司 A kind of interconnection method of tunnel lining trolley automatic butt shunt conduit device
CN113958340A (en) * 2020-07-21 2022-01-21 中铁一局集团有限公司 Pouring mechanism and method for rotary lining trolley

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108412516A (en) * 2018-01-08 2018-08-17 洛阳高飞桥隧机械有限公司 A kind of interconnection method of tunnel lining trolley automatic butt shunt conduit device
CN113958340A (en) * 2020-07-21 2022-01-21 中铁一局集团有限公司 Pouring mechanism and method for rotary lining trolley
CN113958340B (en) * 2020-07-21 2024-01-23 中铁一局集团有限公司 Rotary lining trolley pouring mechanism and method

Similar Documents

Publication Publication Date Title
CN108412516A (en) A kind of interconnection method of tunnel lining trolley automatic butt shunt conduit device
CN207063993U (en) Placement layer by layer material distributing machine and the lining trolley comprising this material distributing machine
CN208364141U (en) A kind of automatic walking trolley device of tunnel lining trolley material distributing machine
CN207701147U (en) A kind of automatic butt shunt conduit device of tunnel lining trolley
WO2021218065A1 (en) Use method of rotary pouring distributing machine of gantry-free lining trolley
CN108798709A (en) Placement layer by layer material distributing machine and lining trolley comprising this material distributing machine
CN107269296A (en) One kind two serves as a contrast chassis and carries concrete curing device and its application method
CN105736012B (en) A kind of tunnel lining concrete grouting device
CN208364143U (en) A kind of flexible docking plumbing installation of the automatic turning of tunnel lining trolley material distributing machine
CN110039650A (en) A kind of nut locking device for tubular piles stretching
CN110273695A (en) A kind of Tunnel Second Lining formwork jumbo and its stage molding pouring procedure
CN208008450U (en) Truss-like pitch entrucking oil filling riser
CN207190117U (en) A kind of seat foaming production line
CN108150194A (en) A kind of casting method of tunnel lining trolley concrete shunt conduit device
CN201586656U (en) Ingot mold cleaning device
CN207647520U (en) A kind of concrete shunt conduit device of tunnel lining trolley
CN203583439U (en) Concrete faced rockfill dam plastic water stop construction trolley
CN206873382U (en) A kind of highway repairing sprinkler
CN109736853A (en) A kind of jet mould trolley for tunnel concrete injection
CN212021137U (en) Bridge rail type automatic spraying maintenance trolley
CN206186075U (en) Prefab production line
CN105645131B (en) A kind of train coke car unloader and application method
CN210858805U (en) Slurry blocking or coal blocking robot
CN208502794U (en) A kind of pneumatic intelligence of tunnel lining trolley material distributing machine, which shunts, pours device
CN214362820U (en) Pier stud automatic spray health preserving machine

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 471000 No. 16, Longteng North Road, Xiagou Village, Hongshan Township, Xigong District, Luoyang City, Henan Province

Patentee after: Luoyang Gaofei Bridges and Tunnels Machinery Co.,Ltd.

Address before: 471000 No. 16, Longteng North Road, Xiagou Village, Hongshan Township, Xigong District, Luoyang City, Henan Province

Patentee before: LUOYANG GAOFEI BRIDGE AND TUNNEL MACHINERY Co.,Ltd.

CP01 Change in the name or title of a patent holder