CN207686260U - A kind of overhanging construction system for building the construction of cornice position - Google Patents
A kind of overhanging construction system for building the construction of cornice position Download PDFInfo
- Publication number
- CN207686260U CN207686260U CN201721895314.8U CN201721895314U CN207686260U CN 207686260 U CN207686260 U CN 207686260U CN 201721895314 U CN201721895314 U CN 201721895314U CN 207686260 U CN207686260 U CN 207686260U
- Authority
- CN
- China
- Prior art keywords
- frame
- chassis
- construction
- cornice
- upper frame
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model discloses a kind of overhanging construction systems for building the construction of cornice position comprising:Guide rail, Hanging Basket frame, wheel hub, hub drive device, wheel hub locking device and safety device;Guide rail is mounted on the top surface of building cornice;Hanging Basket frame includes chassis, side frame, upper frame and cat ladder;Chassis fender rod is arranged in chassis;Side frame lower end connects the first side of chassis, and side frame upper end connects the first side of upper frame;Cat ladder is fixedly connected with side frame;Wheel hub is mounted on upper frame, and hub drive device drive hub is walked on guide rail;Wheel hub locking device is mounted on wheel hub;Safety device is connected on Hanging Basket frame or existing structures.By using the mode of suspension, by Hanging Basket frame manufacture at " C " font, facade and bottom surface construction working platform are provided for aloft work, increases hub drive device, meets the automatic transverse horizontal movement of Hanging Basket frame, to reduce the usage quantity of workbench.
Description
Technical field
The utility model belongs to construction equipment technical field, more particularly to one kind for building the construction of cornice position
Overhanging construction system.
Background technology
The outer cornice decoration of building is a complicated comprehensive engineering, and cornice horizontal linearity and bottom surface are linearly great in constructing amount,
It with vertical plane all in high-altitude, is constructed for overhanging, polymorphic structure is more, and cornice decorates the features such as majority is C fonts, increases and applies
Work difficulty.The outer cornice decoration construction of tradition, which mostly uses, sets up three kinds of floor scaffolding, common electric hanging basket or high-altitude curved arm vehicle sides
Formula.Using simple construction nacelle construction, need from top of building hanging steel rope, configuration hangs ship, moves up and down and remove calabash with hand
Reed, equipment is simple and crude, inconvenient for use, and no safety guarantee, labor intensity is big, and efficiency is low.The side of scaffold is set up along building facade
Method takes a lot of work, is time-consuming, takes up a large area, and needs steel more, and price is high, and freight volume is big.It is occupied using high-altitude curved arm vehicle construction method
Road surface influences to overhang the construction of region lower part, and value of leass is higher.
Utility model content
The purpose of this utility model is to provide a kind of overhanging construction system for building the construction of cornice position, to solve field
When the class building inner ring cornice decorative panel installation of shop, the universal height of inner ring cornice is higher, and workbench need to meet cornice facade simultaneously
And bottom surface work requirements, scaffold building difficulty is big, common hanging basket fixed point free and big, the of high cost problem of demand.
A kind of overhanging construction system for building the construction of cornice position, the cornice side built cornice and include to be onstructed
Face and cornice bottom surface;The overhanging construction system includes:Guide rail, Hanging Basket frame, wheel hub, hub drive device, wheel hub locking dress
It sets and safety device;The guide rail is mounted on the top surface of building cornice;The Hanging Basket frame includes chassis, side frame, upper frame
And cat ladder;Chassis fender rod is arranged in the chassis;The length of the side frame is more than the height of cornice side, and the side frame lower end connects
The first side of chassis is connect, side frame upper end connects the first side of upper frame, the second side of chassis and the second side court of upper frame
To identical;The cat ladder is fixedly connected with side frame;The wheel hub is mounted on the upper frame, and hub drive device drives the wheel
Hub is walked on guide rail;The wheel hub locking device is mounted on the wheel hub;The safety device is connected to Hanging Basket frame
On frame or existing structures.
The utility model is used to build the overhanging construction system of cornice position construction, further, the bottom as described above
Frame includes chassis cross bar, chassis vertical pole, chassis bracing piece and chassis pedal;The chassis cross bar and chassis vertical pole are mutually perpendicular to connect
The frame for constituting rectangular configuration is connect, chassis pedal is installed on said frame, and chassis bracing piece is connected between chassis cross bar.
The utility model is used to build the overhanging construction system of cornice position construction, further, the side as described above
Frame includes side frame montant and waling stripe, and the waling stripe is connected between two side frame montants disposed in parallel.
The utility model is used to build the overhanging construction system of cornice position construction as described above, further, described to climb
Ladder includes cat ladder montant and cat ladder cross bar, and the cat ladder cross bar is connected between cat ladder montant and side frame montant;Cat ladder cross bar hangs down
The plane directly constituted in side frame.
The utility model is used to build the overhanging construction system of cornice position construction, further, the top as described above
Frame includes upper frame cross bar, upper frame vertical pole and upper frame bracing piece;The upper frame cross bar and upper frame vertical pole are mutually connected vertically composition square
The frame of shape structure, upper frame pedal are installed on said frame, and upper frame bracing piece is connected between upper frame cross bar.
The utility model is used to build the overhanging construction system of cornice position construction as described above, further, described to lead
Rail includes the first guide rail and the second guide rail arranged in parallel;The quantity of the wheel hub is four, is pacified on each upper frame vertical pole
Fill two.
The utility model is used to build the overhanging construction system of cornice position construction, further, the wheel as described above
Hub includes bearing, idler wheel and limited post;The bearing is fixedly connected with upper frame vertical pole;The idler wheel is mounted on the bearing;
Described limited post one end is fixedly connected with bearing, makes guide rail between limited post.
The utility model is used to build the overhanging construction system of cornice position construction, further, the peace as described above
Full protection device includes safety net and safety rope, and the safety net is covered in the side frame of Hanging Basket frame;One end of the safety rope
It connects in main body steel construction, other end connection construction personnel.
The utility model has the beneficial effects that:
It provides facade by Hanging Basket frame manufacture at " C " font by using the mode of suspension for aloft work and bottom surface is applied
Work workbench increases hub drive device, meets the automatic transverse horizontal movement of Hanging Basket frame, to reduce the use of workbench
Quantity.Two above key technology can reduce labor intensity, and improve working efficiency, can substitute traditional hanging basket, while be building
Facade and bottom surface construction provide workbench, and the novel high-rise working equipment that can be reused.
Description of the drawings
By being described in detail made by conjunction with the following drawings, the above-mentioned and/or otherwise advantage of the utility model will
It becoming more apparent upon and is easier to understand, these attached drawings are only schematical, are not intended to limit the utility model, wherein:
Fig. 1 is a kind of this overhanging construction system schematic diagram for building the construction of cornice position of embodiment;
Fig. 2 is the tops Fig. 1 enlarged diagram;
Fig. 3 is a kind of safety device connection diagram of embodiment of the utility model.
In attached drawing, parts list represented by the reference numerals are as follows:
1, upper frame, 2, side frame, 3, chassis, 4, cat ladder, 5, wheel hub, 6, safety net, 7, guide rail, 8, safety rope, 9, main body steel
Structure, 10, hub drive device, 11, upper frame vertical pole, 12, upper frame cross bar, 13, upper frame bracing piece, 14, upper frame montant, 15, steel
Cord, 21, side frame montant, 22, waling stripe, 31, chassis cross bar, 32, chassis vertical pole, 33, chassis bracing piece, 34, chassis it is anti-
Guard bar, 41, cat ladder cross bar, 42, cat ladder montant, 51, bearing, 52, limited post, 53, idler wheel, 54, bar, the 71, first guide rail,
72, the second guide rail.
Specific implementation mode
Hereinafter, the overhanging construction system for building the construction of cornice position of the utility model is described with reference to the accompanying drawings
Embodiment.
The embodiment recorded herein is the specific specific implementation mode of the utility model, for illustrating the utility model
Design, is explanatory and illustrative, should not be construed as the limit to the utility model embodiment and the scope of the utility model
System.In addition to the embodiment recorded herein, those skilled in the art can also be based on the application claims and specification institute is public
For the content opened using obvious other technical solutions, these technical solutions include doing using the embodiment to recording herein
Go out the technical solution of any obvious substitutions and modifications.
The attached drawing of this specification is schematic diagram, aids in illustrating the design of the utility model, it is schematically indicated each section
Shape and its correlation.It note that the structure of each component for the ease of clearly showing the utility model embodiment, respectively
It is not drawn according to identical ratio between attached drawing.Identical reference marker is for indicating identical part.
Fig. 1 shows a kind of overhanging construction system for building the construction of cornice position of embodiment of the utility model, building
Cornice includes cornice side and cornice bottom surface to be onstructed;Overhanging construction system includes:Guide rail 7, Hanging Basket frame, wheel hub 5, wheel hub
Driving device 10, wheel hub locking device and safety device;Guide rail 7 is mounted on the top surface of building cornice;Hanging Basket frame includes
Chassis 3, side frame 2, upper frame 1 and cat ladder 4;Chassis fender rod 34 is arranged in chassis 3;The length of side frame 2 is more than the height of cornice side,
2 lower end of side frame connects the first side of chassis, and 2 upper end of side frame connects the first side of upper frame, the second side of chassis 3 and upper frame
1 the second side is towards identical;Cat ladder 4 is fixedly connected with side frame 2;Wheel hub 5 is mounted on upper frame 1, and hub drive device 10 drives
Runner hub 5 is walked on guide rail 7;Wheel hub locking device is mounted on wheel hub 5;Safety device is connected to Hanging Basket frame or
Have in building structure.
It provides facade by Hanging Basket frame manufacture at " C " font by using the mode of suspension for aloft work and bottom surface is applied
Work workbench increases hub drive device 10, meets the automatic transverse horizontal movement of Hanging Basket frame, to reduce making for workbench
Use quantity.Two above key technology can reduce labor intensity, and improve working efficiency, can substitute traditional hanging basket, while to build
It builds facade and bottom surface construction provides workbench, and the novel high-rise working equipment that can be reused.
In a kind of overhanging construction system embodiment being preferably used in the construction of building cornice position, as shown in Figure 1, chassis
3 include chassis cross bar 31, chassis vertical pole 32, chassis bracing piece 33 and chassis pedal;Chassis cross bar 31 and chassis vertical pole 32 are mutual
Vertical connection constitutes the frame of rectangular configuration, and chassis pedal is mounted on frame, and chassis bracing piece 33 is connected to chassis cross bar 31
Between.When being constructed, construction personnel stands on chassis pedal, and building cornice position is constructed, chassis fender rod 34
It is fixedly connected with said frame, higher than plane where chassis pedal, can prevent that personnel from falling or construction appliance falls.
In a kind of overhanging construction system embodiment being preferably used in the construction of building cornice position, as shown in Figure 1, side frame
2 include side frame montant 21 and waling stripe 22, and waling stripe 22 is connected between two side frame montants 21 disposed in parallel.Cat ladder
4 include cat ladder montant 42 and cat ladder cross bar 41, and cat ladder cross bar 41 is connected between cat ladder montant 42 and side frame montant 21;Cat ladder is horizontal
The plane that bar 41 is constituted perpendicular to side frame.A cat ladder montant is used only in cat ladder in above-described embodiment, makes full use of
The side frame montant of existing structure.
In a kind of overhanging construction system embodiment being preferably used in the construction of building cornice position, as shown in Figure 1, upper frame
1 includes upper frame cross bar 12, upper frame vertical pole 11 and upper frame bracing piece 13;Upper frame cross bar 12 and upper frame vertical pole 11 are mutually connected vertically structure
The frame of rectangular structure, upper frame pedal are mounted on frame, and upper frame bracing piece 13 is connected between upper frame cross bar 12.In Fig. 2
In the embodiment shown, upper frame further includes upper frame montant 14 and steel wire rope 15, and upper frame montant 14 is vertical and is connected to frame upward
Four corner positions, steel wire rope 15 is connected between adjacent upper frame montant 14, is protected as safety of workers.Guide rail 7 includes
First guide rail 71 and the second guide rail 72 arranged in parallel;The quantity of wheel hub 5 is four, and two are installed on each upper frame vertical pole 11
It is a.
In a kind of overhanging construction system embodiment being preferably used in the construction of building cornice position, as shown in Fig. 2, wheel hub
5 include bearing 51, idler wheel 53 and limited post 52;Bearing 51 is fixedly connected with upper frame vertical pole 11;Idler wheel 53 is mounted on bearing 51;
52 one end of limited post is fixedly connected with bearing 51, makes guide rail between limited post 52.The effect of limited post is to adjust Hanging Basket to put down
Surely.In the embodiment illustrated in figure 2, wheel hub further includes bar 54, and the bar 54 is connected between limited post, guide rail is trapped among
Between bearing 51, limited post 52 and bar 54.
In a kind of specific example, by 4 points of rectangle setting wheel hubs between upper frame and guide rail, spacing 2000mm is located at the
Two wheel hubs on two guide rails connect hub drive device 10(Such as carry the electric device of variable-frequency motor), realize what overhanging had been hung
It moves horizontally;Two, outside wheel hub sets limited post, and it is steady to adjust Hanging Basket.It, can be along rail running after the completion of to be debugged.
In a kind of overhanging construction system embodiment being preferably used in the construction of building cornice position, as shown in figure 3, safety
Protective device includes safety net 6 and safety rope 8, and safety net 6 is covered in the side frame of Hanging Basket frame;One end connection master of safety rope 8
On body steel construction 9, other end connection construction personnel.
Each technical characteristic of above-mentioned disclosure is not limited to disclosed and other feature combination, and those skilled in the art are also
Other combinations between each technical characteristic can be carried out according to the purpose of invention, be subject to the purpose for realizing the utility model.
Claims (8)
1. a kind of overhanging construction system for building the construction of cornice position, the cornice side built cornice and include to be onstructed
With cornice bottom surface;It is characterized in that, the overhanging construction system includes:Guide rail, Hanging Basket frame, wheel hub, hub drive device, wheel
Hub locking device and safety device;The guide rail is mounted on the top surface of building cornice;The Hanging Basket frame includes chassis, side
Frame, upper frame and cat ladder;Chassis fender rod is arranged in the chassis;The length of the side frame is more than the height of cornice side, the side
Frame lower end connects the first side of chassis, and side frame upper end connects the first side of upper frame, and the of the second side of chassis and upper frame
Two sides are towards identical;The cat ladder is fixedly connected with side frame;The wheel hub is mounted on the upper frame, and hub drive device drives
The wheel hub is moved to walk on guide rail;The wheel hub locking device is mounted on the wheel hub;The safety device connection
On Hanging Basket frame or existing structures.
2. the overhanging construction system according to claim 1 for building the construction of cornice position, which is characterized in that the bottom
Frame includes chassis cross bar, chassis vertical pole, chassis bracing piece and chassis pedal;The chassis cross bar and chassis vertical pole are mutually perpendicular to connect
The frame for constituting rectangular configuration is connect, chassis pedal is installed on said frame, and chassis bracing piece is connected between chassis cross bar.
3. the overhanging construction system according to claim 1 for building the construction of cornice position, which is characterized in that the side
Frame includes side frame montant and waling stripe, and the waling stripe is connected between two side frame montants disposed in parallel.
4. the overhanging construction system according to claim 3 for building the construction of cornice position, which is characterized in that described to climb
Ladder includes cat ladder montant and cat ladder cross bar, and the cat ladder cross bar is connected between cat ladder montant and side frame montant;Cat ladder cross bar hangs down
The plane directly constituted in side frame.
5. the overhanging construction system according to claim 1 for building the construction of cornice position, which is characterized in that the top
Frame includes upper frame cross bar, upper frame vertical pole and upper frame bracing piece;The upper frame cross bar and upper frame vertical pole are mutually connected vertically composition square
The frame of shape structure, upper frame pedal are installed on said frame, and upper frame bracing piece is connected between upper frame cross bar.
6. the overhanging construction system according to claim 5 for building the construction of cornice position, which is characterized in that described to lead
Rail includes the first guide rail and the second guide rail arranged in parallel;The quantity of the wheel hub is four, is pacified on each upper frame vertical pole
Fill two.
7. the overhanging construction system according to claim 6 for building the construction of cornice position, which is characterized in that the wheel
Hub includes bearing, idler wheel and limited post;The bearing is fixedly connected with upper frame vertical pole;The idler wheel is mounted on the bearing;
Described limited post one end is fixedly connected with bearing, makes guide rail between limited post.
8. the overhanging construction system according to claim 1 for building the construction of cornice position, which is characterized in that the peace
Full protection device includes safety net and safety rope, and the safety net is covered in the side frame of Hanging Basket frame;One end of the safety rope
It connects in main body steel construction, other end connection construction personnel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721895314.8U CN207686260U (en) | 2017-12-29 | 2017-12-29 | A kind of overhanging construction system for building the construction of cornice position |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721895314.8U CN207686260U (en) | 2017-12-29 | 2017-12-29 | A kind of overhanging construction system for building the construction of cornice position |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207686260U true CN207686260U (en) | 2018-08-03 |
Family
ID=62992591
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721895314.8U Active CN207686260U (en) | 2017-12-29 | 2017-12-29 | A kind of overhanging construction system for building the construction of cornice position |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207686260U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110777666A (en) * | 2019-11-12 | 2020-02-11 | 广州市第一市政工程有限公司 | Steel box girder construction platform and use method |
CN111206763A (en) * | 2020-01-09 | 2020-05-29 | 中国五冶集团有限公司 | Adjustable section steel suspension hanging basket |
-
2017
- 2017-12-29 CN CN201721895314.8U patent/CN207686260U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110777666A (en) * | 2019-11-12 | 2020-02-11 | 广州市第一市政工程有限公司 | Steel box girder construction platform and use method |
CN111206763A (en) * | 2020-01-09 | 2020-05-29 | 中国五冶集团有限公司 | Adjustable section steel suspension hanging basket |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103206074B (en) | Elevator shaft template construction method, platform and support | |
CN202144437U (en) | Standing type single-person hanging seat device | |
CN207686260U (en) | A kind of overhanging construction system for building the construction of cornice position | |
CN208948633U (en) | A kind of cage top device with pedal for building hoist | |
CN207363239U (en) | A kind of nacelle device for special form building curtain wall construction | |
CN114645614A (en) | Rapid moving aerial work platform based on rail device | |
CN201083018Y (en) | Mobile multipurpose fast mounting scaffold | |
CN209011528U (en) | A kind of all steel attachment type raise scaffold | |
CN106836785A (en) | Possesses the scaffold of rotary work ability | |
CN204418629U (en) | A kind of integrated form climbing frame | |
CN206053272U (en) | A kind of traveling centering | |
CN207063484U (en) | Movable operation platform for corridor construction | |
CN207144527U (en) | The safeguard protection screen system of Steel Structure Installation | |
CN207108290U (en) | High safety protection type gantry crane | |
CN204754150U (en) | Dish -type node formula scaffold | |
CN201401000Y (en) | Special hanging basket for installing noise barrier roof boards | |
CN211172985U (en) | Scaffold for building | |
CN211257769U (en) | Truss bridging based on attached lifting platform | |
CN2578461Y (en) | Liftable scaffold | |
CN207434909U (en) | Lifting/lowering type dedusting tower crane | |
CN209924409U (en) | Wall-attached self-climbing electric lifting platform | |
CN208648493U (en) | A kind of no scaffold installation elevator operation platform device | |
CN106088564A (en) | Track climbing type monolithic architecture construction scaffolding | |
CN206636152U (en) | Double-deck scaffold in simple type room | |
CN110748140A (en) | Track beam hanging basket special for stepped curtain wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |