CN207686260U CN201721895314.8U CN201721895314U CN207686260U CN 207686260 U CN207686260 U CN 207686260U CN 201721895314 U CN201721895314 U CN 201721895314U CN 207686260 U CN207686260 U CN 207686260U
Authority
CN
China
Prior art keywords
frame
chassis
construction
cornice
upper frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721895314.8U
Other languages
Chinese (zh)
Inventor
张乐
龙陆彬
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Civil Engineering Co Ltd
Original Assignee
China Construction Civil Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Civil Engineering Co Ltd filed Critical China Construction Civil Engineering Co Ltd
Priority to CN201721895314.8U priority Critical patent/CN207686260U/en
Application granted granted Critical
Publication of CN207686260U publication Critical patent/CN207686260U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of overhanging construction systems for building the construction of cornice position comprising:Guide rail, Hanging Basket frame, wheel hub, hub drive device, wheel hub locking device and safety device;Guide rail is mounted on the top surface of building cornice;Hanging Basket frame includes chassis, side frame, upper frame and cat ladder;Chassis fender rod is arranged in chassis;Side frame lower end connects the first side of chassis, and side frame upper end connects the first side of upper frame;Cat ladder is fixedly connected with side frame;Wheel hub is mounted on upper frame, and hub drive device drive hub is walked on guide rail;Wheel hub locking device is mounted on wheel hub;Safety device is connected on Hanging Basket frame or existing structures.By using the mode of suspension, by Hanging Basket frame manufacture at " C " font, facade and bottom surface construction working platform are provided for aloft work, increases hub drive device, meets the automatic transverse horizontal movement of Hanging Basket frame, to reduce the usage quantity of workbench.

Description

A kind of overhanging construction system for building the construction of cornice position
Technical field
The utility model belongs to construction equipment technical field, more particularly to one kind for building the construction of cornice position Overhanging construction system.
Background technology
The outer cornice decoration of building is a complicated comprehensive engineering, and cornice horizontal linearity and bottom surface are linearly great in constructing amount, It with vertical plane all in high-altitude, is constructed for overhanging, polymorphic structure is more, and cornice decorates the features such as majority is C fonts, increases and applies Work difficulty.The outer cornice decoration construction of tradition, which mostly uses, sets up three kinds of floor scaffolding, common electric hanging basket or high-altitude curved arm vehicle sides Formula.Using simple construction nacelle construction, need from top of building hanging steel rope, configuration hangs ship, moves up and down and remove calabash with hand Reed, equipment is simple and crude, inconvenient for use, and no safety guarantee, labor intensity is big, and efficiency is low.The side of scaffold is set up along building facade Method takes a lot of work, is time-consuming, takes up a large area, and needs steel more, and price is high, and freight volume is big.It is occupied using high-altitude curved arm vehicle construction method Road surface influences to overhang the construction of region lower part, and value of leass is higher.
Utility model content
The purpose of this utility model is to provide a kind of overhanging construction system for building the construction of cornice position, to solve field When the class building inner ring cornice decorative panel installation of shop, the universal height of inner ring cornice is higher, and workbench need to meet cornice facade simultaneously And bottom surface work requirements, scaffold building difficulty is big, common hanging basket fixed point free and big, the of high cost problem of demand.
A kind of overhanging construction system for building the construction of cornice position, the cornice side built cornice and include to be onstructed Face and cornice bottom surface;The overhanging construction system includes:Guide rail, Hanging Basket frame, wheel hub, hub drive device, wheel hub locking dress It sets and safety device;The guide rail is mounted on the top surface of building cornice;The Hanging Basket frame includes chassis, side frame, upper frame And cat ladder;Chassis fender rod is arranged in the chassis;The length of the side frame is more than the height of cornice side, and the side frame lower end connects The first side of chassis is connect, side frame upper end connects the first side of upper frame, the second side of chassis and the second side court of upper frame To identical;The cat ladder is fixedly connected with side frame;The wheel hub is mounted on the upper frame, and hub drive device drives the wheel Hub is walked on guide rail;The wheel hub locking device is mounted on the wheel hub;The safety device is connected to Hanging Basket frame On frame or existing structures.
The utility model is used to build the overhanging construction system of cornice position construction, further, the bottom as described above Frame includes chassis cross bar, chassis vertical pole, chassis bracing piece and chassis pedal;The chassis cross bar and chassis vertical pole are mutually perpendicular to connect The frame for constituting rectangular configuration is connect, chassis pedal is installed on said frame, and chassis bracing piece is connected between chassis cross bar.
The utility model is used to build the overhanging construction system of cornice position construction, further, the side as described above Frame includes side frame montant and waling stripe, and the waling stripe is connected between two side frame montants disposed in parallel.
The utility model is used to build the overhanging construction system of cornice position construction as described above, further, described to climb Ladder includes cat ladder montant and cat ladder cross bar, and the cat ladder cross bar is connected between cat ladder montant and side frame montant;Cat ladder cross bar hangs down The plane directly constituted in side frame.
The utility model is used to build the overhanging construction system of cornice position construction, further, the top as described above Frame includes upper frame cross bar, upper frame vertical pole and upper frame bracing piece;The upper frame cross bar and upper frame vertical pole are mutually connected vertically composition square The frame of shape structure, upper frame pedal are installed on said frame, and upper frame bracing piece is connected between upper frame cross bar.
The utility model is used to build the overhanging construction system of cornice position construction as described above, further, described to lead Rail includes the first guide rail and the second guide rail arranged in parallel;The quantity of the wheel hub is four, is pacified on each upper frame vertical pole Fill two.
The utility model is used to build the overhanging construction system of cornice position construction, further, the wheel as described above Hub includes bearing, idler wheel and limited post;The bearing is fixedly connected with upper frame vertical pole;The idler wheel is mounted on the bearing; Described limited post one end is fixedly connected with bearing, makes guide rail between limited post.
The utility model is used to build the overhanging construction system of cornice position construction, further, the peace as described above Full protection device includes safety net and safety rope, and the safety net is covered in the side frame of Hanging Basket frame;One end of the safety rope It connects in main body steel construction, other end connection construction personnel.
The utility model has the beneficial effects that:
It provides facade by Hanging Basket frame manufacture at " C " font by using the mode of suspension for aloft work and bottom surface is applied Work workbench increases hub drive device, meets the automatic transverse horizontal movement of Hanging Basket frame, to reduce the use of workbench Quantity.Two above key technology can reduce labor intensity, and improve working efficiency, can substitute traditional hanging basket, while be building Facade and bottom surface construction provide workbench, and the novel high-rise working equipment that can be reused.
Description of the drawings
By being described in detail made by conjunction with the following drawings, the above-mentioned and/or otherwise advantage of the utility model will It becoming more apparent upon and is easier to understand, these attached drawings are only schematical, are not intended to limit the utility model, wherein:
Fig. 1 is a kind of this overhanging construction system schematic diagram for building the construction of cornice position of embodiment;
Fig. 2 is the tops Fig. 1 enlarged diagram;
Fig. 3 is a kind of safety device connection diagram of embodiment of the utility model.
In attached drawing, parts list represented by the reference numerals are as follows:
1, upper frame, 2, side frame, 3, chassis, 4, cat ladder, 5, wheel hub, 6, safety net, 7, guide rail, 8, safety rope, 9, main body steel Structure, 10, hub drive device, 11, upper frame vertical pole, 12, upper frame cross bar, 13, upper frame bracing piece, 14, upper frame montant, 15, steel Cord, 21, side frame montant, 22, waling stripe, 31, chassis cross bar, 32, chassis vertical pole, 33, chassis bracing piece, 34, chassis it is anti- Guard bar, 41, cat ladder cross bar, 42, cat ladder montant, 51, bearing, 52, limited post, 53, idler wheel, 54, bar, the 71, first guide rail, 72, the second guide rail.
Specific implementation mode
Hereinafter, the overhanging construction system for building the construction of cornice position of the utility model is described with reference to the accompanying drawings Embodiment.
The embodiment recorded herein is the specific specific implementation mode of the utility model, for illustrating the utility model Design, is explanatory and illustrative, should not be construed as the limit to the utility model embodiment and the scope of the utility model System.In addition to the embodiment recorded herein, those skilled in the art can also be based on the application claims and specification institute is public For the content opened using obvious other technical solutions, these technical solutions include doing using the embodiment to recording herein Go out the technical solution of any obvious substitutions and modifications.
The attached drawing of this specification is schematic diagram, aids in illustrating the design of the utility model, it is schematically indicated each section Shape and its correlation.It note that the structure of each component for the ease of clearly showing the utility model embodiment, respectively It is not drawn according to identical ratio between attached drawing.Identical reference marker is for indicating identical part.
Fig. 1 shows a kind of overhanging construction system for building the construction of cornice position of embodiment of the utility model, building Cornice includes cornice side and cornice bottom surface to be onstructed;Overhanging construction system includes:Guide rail 7, Hanging Basket frame, wheel hub 5, wheel hub Driving device 10, wheel hub locking device and safety device;Guide rail 7 is mounted on the top surface of building cornice;Hanging Basket frame includes Chassis 3, side frame 2, upper frame 1 and cat ladder 4;Chassis fender rod 34 is arranged in chassis 3;The length of side frame 2 is more than the height of cornice side, 2 lower end of side frame connects the first side of chassis, and 2 upper end of side frame connects the first side of upper frame, the second side of chassis 3 and upper frame 1 the second side is towards identical;Cat ladder 4 is fixedly connected with side frame 2;Wheel hub 5 is mounted on upper frame 1, and hub drive device 10 drives Runner hub 5 is walked on guide rail 7;Wheel hub locking device is mounted on wheel hub 5;Safety device is connected to Hanging Basket frame or Have in building structure.
It provides facade by Hanging Basket frame manufacture at " C " font by using the mode of suspension for aloft work and bottom surface is applied Work workbench increases hub drive device 10, meets the automatic transverse horizontal movement of Hanging Basket frame, to reduce making for workbench Use quantity.Two above key technology can reduce labor intensity, and improve working efficiency, can substitute traditional hanging basket, while to build It builds facade and bottom surface construction provides workbench, and the novel high-rise working equipment that can be reused.
In a kind of overhanging construction system embodiment being preferably used in the construction of building cornice position, as shown in Figure 1, chassis 3 include chassis cross bar 31, chassis vertical pole 32, chassis bracing piece 33 and chassis pedal;Chassis cross bar 31 and chassis vertical pole 32 are mutual Vertical connection constitutes the frame of rectangular configuration, and chassis pedal is mounted on frame, and chassis bracing piece 33 is connected to chassis cross bar 31 Between.When being constructed, construction personnel stands on chassis pedal, and building cornice position is constructed, chassis fender rod 34 It is fixedly connected with said frame, higher than plane where chassis pedal, can prevent that personnel from falling or construction appliance falls.
In a kind of overhanging construction system embodiment being preferably used in the construction of building cornice position, as shown in Figure 1, side frame 2 include side frame montant 21 and waling stripe 22, and waling stripe 22 is connected between two side frame montants 21 disposed in parallel.Cat ladder 4 include cat ladder montant 42 and cat ladder cross bar 41, and cat ladder cross bar 41 is connected between cat ladder montant 42 and side frame montant 21;Cat ladder is horizontal The plane that bar 41 is constituted perpendicular to side frame.A cat ladder montant is used only in cat ladder in above-described embodiment, makes full use of The side frame montant of existing structure.
In a kind of overhanging construction system embodiment being preferably used in the construction of building cornice position, as shown in Figure 1, upper frame 1 includes upper frame cross bar 12, upper frame vertical pole 11 and upper frame bracing piece 13;Upper frame cross bar 12 and upper frame vertical pole 11 are mutually connected vertically structure The frame of rectangular structure, upper frame pedal are mounted on frame, and upper frame bracing piece 13 is connected between upper frame cross bar 12.In Fig. 2 In the embodiment shown, upper frame further includes upper frame montant 14 and steel wire rope 15, and upper frame montant 14 is vertical and is connected to frame upward Four corner positions, steel wire rope 15 is connected between adjacent upper frame montant 14, is protected as safety of workers.Guide rail 7 includes First guide rail 71 and the second guide rail 72 arranged in parallel;The quantity of wheel hub 5 is four, and two are installed on each upper frame vertical pole 11 It is a.
In a kind of overhanging construction system embodiment being preferably used in the construction of building cornice position, as shown in Fig. 2, wheel hub 5 include bearing 51, idler wheel 53 and limited post 52;Bearing 51 is fixedly connected with upper frame vertical pole 11;Idler wheel 53 is mounted on bearing 51; 52 one end of limited post is fixedly connected with bearing 51, makes guide rail between limited post 52.The effect of limited post is to adjust Hanging Basket to put down Surely.In the embodiment illustrated in figure 2, wheel hub further includes bar 54, and the bar 54 is connected between limited post, guide rail is trapped among Between bearing 51, limited post 52 and bar 54.
In a kind of specific example, by 4 points of rectangle setting wheel hubs between upper frame and guide rail, spacing 2000mm is located at the Two wheel hubs on two guide rails connect hub drive device 10(Such as carry the electric device of variable-frequency motor), realize what overhanging had been hung It moves horizontally;Two, outside wheel hub sets limited post, and it is steady to adjust Hanging Basket.It, can be along rail running after the completion of to be debugged.
In a kind of overhanging construction system embodiment being preferably used in the construction of building cornice position, as shown in figure 3, safety Protective device includes safety net 6 and safety rope 8, and safety net 6 is covered in the side frame of Hanging Basket frame;One end connection master of safety rope 8 On body steel construction 9, other end connection construction personnel.
Each technical characteristic of above-mentioned disclosure is not limited to disclosed and other feature combination, and those skilled in the art are also Other combinations between each technical characteristic can be carried out according to the purpose of invention, be subject to the purpose for realizing the utility model.

Claims (8)

1. a kind of overhanging construction system for building the construction of cornice position, the cornice side built cornice and include to be onstructed With cornice bottom surface;It is characterized in that, the overhanging construction system includes:Guide rail, Hanging Basket frame, wheel hub, hub drive device, wheel Hub locking device and safety device;The guide rail is mounted on the top surface of building cornice;The Hanging Basket frame includes chassis, side Frame, upper frame and cat ladder;Chassis fender rod is arranged in the chassis;The length of the side frame is more than the height of cornice side, the side Frame lower end connects the first side of chassis, and side frame upper end connects the first side of upper frame, and the of the second side of chassis and upper frame Two sides are towards identical;The cat ladder is fixedly connected with side frame;The wheel hub is mounted on the upper frame, and hub drive device drives The wheel hub is moved to walk on guide rail;The wheel hub locking device is mounted on the wheel hub;The safety device connection On Hanging Basket frame or existing structures.
2. the overhanging construction system according to claim 1 for building the construction of cornice position, which is characterized in that the bottom Frame includes chassis cross bar, chassis vertical pole, chassis bracing piece and chassis pedal;The chassis cross bar and chassis vertical pole are mutually perpendicular to connect The frame for constituting rectangular configuration is connect, chassis pedal is installed on said frame, and chassis bracing piece is connected between chassis cross bar.
3. the overhanging construction system according to claim 1 for building the construction of cornice position, which is characterized in that the side Frame includes side frame montant and waling stripe, and the waling stripe is connected between two side frame montants disposed in parallel.
4. the overhanging construction system according to claim 3 for building the construction of cornice position, which is characterized in that described to climb Ladder includes cat ladder montant and cat ladder cross bar, and the cat ladder cross bar is connected between cat ladder montant and side frame montant;Cat ladder cross bar hangs down The plane directly constituted in side frame.
5. the overhanging construction system according to claim 1 for building the construction of cornice position, which is characterized in that the top Frame includes upper frame cross bar, upper frame vertical pole and upper frame bracing piece;The upper frame cross bar and upper frame vertical pole are mutually connected vertically composition square The frame of shape structure, upper frame pedal are installed on said frame, and upper frame bracing piece is connected between upper frame cross bar.
6. the overhanging construction system according to claim 5 for building the construction of cornice position, which is characterized in that described to lead Rail includes the first guide rail and the second guide rail arranged in parallel;The quantity of the wheel hub is four, is pacified on each upper frame vertical pole Fill two.
7. the overhanging construction system according to claim 6 for building the construction of cornice position, which is characterized in that the wheel Hub includes bearing, idler wheel and limited post;The bearing is fixedly connected with upper frame vertical pole;The idler wheel is mounted on the bearing; Described limited post one end is fixedly connected with bearing, makes guide rail between limited post.
8. the overhanging construction system according to claim 1 for building the construction of cornice position, which is characterized in that the peace Full protection device includes safety net and safety rope, and the safety net is covered in the side frame of Hanging Basket frame;One end of the safety rope It connects in main body steel construction, other end connection construction personnel.
CN201721895314.8U 2017-12-29 2017-12-29 A kind of overhanging construction system for building the construction of cornice position Active CN207686260U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721895314.8U CN207686260U (en) 2017-12-29 2017-12-29 A kind of overhanging construction system for building the construction of cornice position

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721895314.8U CN207686260U (en) 2017-12-29 2017-12-29 A kind of overhanging construction system for building the construction of cornice position

Publications (1)

Publication Number Publication Date
CN207686260U true CN207686260U (en) 2018-08-03

Family

ID=62992591

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721895314.8U Active CN207686260U (en) 2017-12-29 2017-12-29 A kind of overhanging construction system for building the construction of cornice position

Country Status (1)

Country Link
CN (1) CN207686260U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110777666A (en) * 2019-11-12 2020-02-11 广州市第一市政工程有限公司 Steel box girder construction platform and use method
CN111206763A (en) * 2020-01-09 2020-05-29 中国五冶集团有限公司 Adjustable section steel suspension hanging basket

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110777666A (en) * 2019-11-12 2020-02-11 广州市第一市政工程有限公司 Steel box girder construction platform and use method
CN111206763A (en) * 2020-01-09 2020-05-29 中国五冶集团有限公司 Adjustable section steel suspension hanging basket

Similar Documents

Publication Publication Date Title
CN103206074B (en) Elevator shaft template construction method, platform and support
CN202144437U (en) Standing type single-person hanging seat device
CN207686260U (en) A kind of overhanging construction system for building the construction of cornice position
CN208948633U (en) A kind of cage top device with pedal for building hoist
CN207363239U (en) A kind of nacelle device for special form building curtain wall construction
CN114645614A (en) Rapid moving aerial work platform based on rail device
CN201083018Y (en) Mobile multipurpose fast mounting scaffold
CN209011528U (en) A kind of all steel attachment type raise scaffold
CN106836785A (en) Possesses the scaffold of rotary work ability
CN204418629U (en) A kind of integrated form climbing frame
CN206053272U (en) A kind of traveling centering
CN207063484U (en) Movable operation platform for corridor construction
CN207144527U (en) The safeguard protection screen system of Steel Structure Installation
CN207108290U (en) High safety protection type gantry crane
CN204754150U (en) Dish -type node formula scaffold
CN201401000Y (en) Special hanging basket for installing noise barrier roof boards
CN211172985U (en) Scaffold for building
CN211257769U (en) Truss bridging based on attached lifting platform
CN2578461Y (en) Liftable scaffold
CN207434909U (en) Lifting/lowering type dedusting tower crane
CN209924409U (en) Wall-attached self-climbing electric lifting platform
CN208648493U (en) A kind of no scaffold installation elevator operation platform device
CN106088564A (en) Track climbing type monolithic architecture construction scaffolding
CN206636152U (en) Double-deck scaffold in simple type room
CN110748140A (en) Track beam hanging basket special for stepped curtain wall

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant