CN211257769U - A Truss Bridge Based on Attached Lifting Platform - Google Patents

A Truss Bridge Based on Attached Lifting Platform Download PDF

Info

Publication number
CN211257769U
CN211257769U CN201922011320.8U CN201922011320U CN211257769U CN 211257769 U CN211257769 U CN 211257769U CN 201922011320 U CN201922011320 U CN 201922011320U CN 211257769 U CN211257769 U CN 211257769U
Authority
CN
China
Prior art keywords
platform
truss
fixed
attached lifting
lifting platform
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922011320.8U
Other languages
Chinese (zh)
Inventor
俞坤军
赵洪礼
杨飞飞
王贺
徐晨光
王雪莉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Building Decoration Co ltd
China State Decoration Group Co Ltd
Original Assignee
China Building Decoration Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Building Decoration Co ltd filed Critical China Building Decoration Co ltd
Priority to CN201922011320.8U priority Critical patent/CN211257769U/en
Application granted granted Critical
Publication of CN211257769U publication Critical patent/CN211257769U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

本实用新型提供一种基于附着式升降平台的桁架搭桥,包括附着式升降平台,所述附着式升降平台设有两个,两个所述附着式升降平台之间滑动安装桁架梁框架,所述桁架梁框架上端铺装木脚手板,所述桁架梁框架周边位置固定护栏板且护栏板安装在木脚手板四周,所述桁架梁框架上端固定拉结组件,本实用新型提高了工作效率,便于物料运输以及存放,且提高了使用安全性。

Figure 201922011320

The utility model provides a truss bridge based on an attached lifting platform, which comprises an attached lifting platform, two attached lifting platforms are provided, and a truss girder frame is slidably installed between the two attached lifting platforms. The upper end of the truss beam frame is paved with wooden scaffolding boards, guardrail boards are fixed at the periphery of the truss beam frame and the guardrail boards are installed around the wooden scaffolding boards, and the tie-tie assemblies are fixed on the upper end of the truss beam frame. The utility model improves work efficiency and is convenient for Material transportation and storage, and improve the safety of use.

Figure 201922011320

Description

一种基于附着式升降平台的桁架搭桥A Truss Bridge Based on Attached Lifting Platform

技术领域technical field

本实用新型是一种基于附着式升降平台的桁架搭桥,属于建筑器械技术领域。The utility model relates to a truss bridge based on an attached lifting platform, which belongs to the technical field of construction equipment.

背景技术Background technique

附着式电动施工平台是一种大型自升降式高空作业平台。它仅需搭设一个平台,沿附着在建筑物上的立柱通过齿轮齿条传动方式实现升降,平台运行平稳,且可节省大量材料,操作控制箱安装在工作平台上,操作方便,相较于传统的脚手架搭设来说,附着式电动施工平台无需搭设传统脚手架,也无需利用大量吊篮,不仅可以缩短施工工期,保证施工质量,还能够保证安全,并且取得较好经济效益和社会效益。The attached electric construction platform is a large-scale self-elevating aerial work platform. It only needs to set up a platform, which can be lifted and lowered along the column attached to the building by means of rack and pinion transmission. The platform runs smoothly and can save a lot of materials. The operation control box is installed on the working platform, which is easy to operate. Compared with traditional In terms of scaffolding construction, the attached electric construction platform does not need to set up traditional scaffolding, nor does it need to use a large number of hanging baskets, which can not only shorten the construction period, ensure construction quality, but also ensure safety, and achieve better economic and social benefits.

在现有的施工技术条件下,搭设脚手架的墙面、吊顶施工方式较为普遍,它适用于面积较小,工期充裕的施工情况,对于主屋面高度较大且面积较大的情况下,若搭设脚手架实现墙壁以及屋顶的施工,则搭设拆除租赁费用昂贵,且搭设拆除周期较长,影响工期,且脚手架的搭设影响首层大堂的物料运输以及堆放,此外搭建高度较大的脚手架在安全无法保证,安装效率降低,质量难以把关。Under the existing construction technology conditions, the wall and ceiling construction methods for erecting scaffolding are more common. It is suitable for the construction situation with a small area and a sufficient construction period. Scaffolding realizes the construction of walls and roofs, but the rental cost of erection and demolition is expensive, and the erection and demolition cycle is long, which affects the construction period. Moreover, the erection of scaffolding affects the transportation and stacking of materials in the lobby on the first floor. In addition, the safety of scaffolding with a large height cannot be guaranteed. , the installation efficiency is reduced, and the quality is difficult to check.

实用新型内容Utility model content

针对现有技术存在的不足,本实用新型目的是提供一种基于附着式升降平台的桁架搭桥,以解决上述背景技术中提出的主屋面高度较大且面积较大的情况下,若搭设脚手架实现墙壁以及屋顶的施工,则搭设拆除租赁费用昂贵,且搭设拆除周期较长,影响工期,且脚手架的搭设影响首层大堂的物料运输以及堆放,此外搭建高度较大的脚手架在安全无法保证,安装效率降低,质量难以把关的问题,本实用新型提高了工作效率,便于物料运输以及存放,且提高了使用安全性。In view of the deficiencies in the prior art, the purpose of this utility model is to provide a truss bridge based on an attached lifting platform, so as to solve the problem of the large height and large area of the main roof proposed in the above-mentioned background technology. For the construction of walls and roofs, the rental cost of erection and demolition is expensive, and the erection and demolition cycle is long, which affects the construction period, and the erection of scaffolding affects the transportation and stacking of materials in the lobby on the first floor. In addition, the safety of scaffolding with a large height cannot be guaranteed. In order to solve the problems of low efficiency and difficult quality control, the utility model improves work efficiency, facilitates material transportation and storage, and improves use safety.

为了实现上述目的,本实用新型是通过如下的技术方案来实现:一种基于附着式升降平台的桁架搭桥,包括附着式升降平台,所述附着式升降平台设有两个,两个所述附着式升降平台之间滑动安装桁架梁框架,所述桁架梁框架上端铺装木脚手板,所述桁架梁框架周边位置固定护栏板且护栏板安装在木脚手板四周,所述桁架梁框架上端固定拉结组件。In order to achieve the above purpose, the present utility model is realized by the following technical solutions: a truss bridge based on an attached lifting platform, including an attached lifting platform, the attached lifting platform is provided with two, and two of the attached lifting platforms are provided. A truss beam frame is slidably installed between the truss beam frame, the upper end of the truss beam frame is paved with wooden scaffolding, the peripheral position of the truss beam frame is fixed with a guardrail plate and the guardrail plate is installed around the wooden scaffolding plate, and the upper end of the truss beam frame is fixed Pull knot assembly.

进一步地,所述拉结组件设有三组,三组所述拉结组件等距固定在桁架梁框架上端。Further, there are three sets of the tie assemblies, and the three sets of the tie assemblies are equidistantly fixed on the upper end of the truss beam frame.

进一步地,所述拉结组件包括两个第二钢丝绳,两个所述第二钢丝绳环形外端前后两部位置均套装U形中空块,四个所述U形中空块均固定在建筑物的顶棚上,两个所述第二钢丝绳靠近的部位共同固定连接导向块,所述导向块下端前后对称固定两个第三钢丝绳,两个所述第三钢丝绳前后对称固定在桁架梁框架前后两端。Further, the tie assembly includes two second steel wire ropes, and U-shaped hollow blocks are sheathed at the front and rear positions of the annular outer ends of the two second steel wire ropes, and the four U-shaped hollow blocks are fixed on the building. On the ceiling, the adjacent parts of the two second steel wire ropes are fixed and connected to the guide block together, the lower end of the guide block is symmetrically fixed to the front and rear of the two third steel wire ropes, and the two third steel wire ropes are symmetrically fixed to the front and rear ends of the truss beam frame. .

进一步地,所述U形中空块内部均设有通孔,所述U形中空块通过通孔与封闭的第二钢丝绳活动连接,所述导向块内部设有两个圆孔,所述导向块通过圆孔与两个第二钢丝绳固定连接。Further, the inside of the U-shaped hollow block is provided with through holes, and the U-shaped hollow block is movably connected with the closed second steel wire rope through the through holes, and two circular holes are arranged inside the guide block, and the guide block It is fixedly connected with the two second steel wire ropes through the round holes.

进一步地,所述附着式升降平台包括双柱平台,所述双柱平台远离桁架梁框架一端前后对称固定两个防护网,两个所述防护网远离双柱平台一端均滑动安装立柱。Further, the attached lifting platform includes a double-column platform, and two protective nets are symmetrically fixed front and rear at one end of the double-column platform away from the truss girder frame, and two ends of the two protective nets away from the double-column platform are slidably installed with uprights.

进一步地,两个所述立柱均由至少两节标准节竖直依次固定连接在一起且每节标准节均通过附墙框与建筑内壁的墙面固定连接,两个所述立柱上端均固定限位立柱,两个所述立柱上均固定齿条,两个所述防护网靠近立柱一端均固定齿轮,所述齿轮侧端固定电机,所述齿轮与齿条啮合安装,两个所述立柱下端均固定平台底座且平台底座固定安装在地面上。Further, both of the two uprights are fixed and connected vertically and sequentially by at least two standard sections, and each standard section is fixedly connected to the wall of the inner wall of the building through the wall frame, and the upper ends of the two uprights are fixed to a limit. A rack is fixed on the two columns, a gear is fixed at one end of the two protective nets near the column, a motor is fixed at the side end of the gear, the gear is meshed with the rack, and the lower ends of the two columns are fixed. The platform base is fixed and the platform base is fixedly installed on the ground.

进一步地,所述双柱平台上端固定导轨,所述桁架梁框架下端四角位置均固定支撑板,四个所述支撑板下端均通过U形架安装两个移动轮,八个所述移动轮分别安装在位于两个双柱平台上的两个导轨内部,两个所述导轨中同一位置上的两个移动轮与伺服电机固定连接。Further, the upper end of the double-column platform is fixed with guide rails, the four corners of the lower end of the truss girder frame are fixed with support plates, and the lower ends of the four support plates are equipped with two moving wheels through the U-shaped frame, and the eight moving wheels are respectively It is installed inside the two guide rails located on the two double-column platforms, and the two moving wheels at the same position in the two guide rails are fixedly connected with the servo motor.

进一步地,所述桁架梁框架包括四个呈立方形布置的第一方管,相邻两个所述第一方管之间通过至少两个第二方管固定连接。Further, the truss beam frame includes four first square tubes arranged in a cubic shape, and two adjacent first square tubes are fixedly connected by at least two second square tubes.

进一步地,所述第一方管由至少两根方管固定连接,相邻两个所述方管连接部位通过法兰固定四根高强螺栓。Further, the first square pipe is fixedly connected by at least two square pipes, and four high-strength bolts are fixed by flanges at the connecting parts of the adjacent two square pipes.

进一步地,两个所述双柱平台前后两端均通过第一钢丝绳与建筑物的顶棚固定连接。Further, both the front and rear ends of the two double-column platforms are fixedly connected to the ceiling of the building through the first steel wire rope.

本实用新型的有益效果:本实用新型的一种基于附着式升降平台的桁架搭桥,Beneficial effects of the utility model: the utility model is a truss bridge based on an attached lifting platform,

1、本实用新型在现两道附着式升降平台之间安装搭设桁架梁框架,桁架梁框架通过移动轮与导轨滑动连接,且经过伺服电机驱动移动轮在导轨内部转动并移动,带动桁架梁框架前后移动,桁架梁框架横向具有较大的长度且能够在前后方向移动,故而便于对跨度大且面积大的建筑顶棚进行施工,对附着式升降平台功能性进行进一步拓展,提高了使用效果。1. The utility model installs a truss girder frame between the existing two attached lifting platforms. The truss girder frame is slidably connected to the guide rail through a moving wheel, and the moving wheel is driven by a servo motor to rotate and move inside the guide rail to drive the truss girder frame. Moving back and forth, the truss girder frame has a large horizontal length and can move in the front and rear directions, so it is convenient for the construction of the building ceiling with a large span and a large area, and the functionality of the attached lifting platform is further expanded to improve the use effect.

2、建筑的顶棚通过拉结组件以及第一钢丝绳分别与桁架梁框架以及双柱平台进行拉结,提高了桁架梁框架以及双柱平台的支撑稳定性,提高了使用安全性,拉结组件由两个第二钢丝绳组成,两个第二钢丝绳能够沿着U形中空块移动,从而导向块以及第三钢丝绳能够随着桁架梁框架进行前后移动,只需在顶棚施工前以及顶棚完成后对拉结组件与桁架梁框架进行固定安装以及拆卸即可,施工过程中无需对拉结组件以及桁架梁框架进行组装以及拆卸,提高了工作效率。2. The roof of the building is tied with the truss girder frame and the double-column platform through the tie-tie assembly and the first wire rope respectively, which improves the support stability of the truss girder frame and the double-column platform, and improves the safety of use. The tie-tie assembly consists of It is composed of two second steel wire ropes, which can move along the U-shaped hollow block, so that the guide block and the third steel wire rope can move forward and backward with the truss girder frame, and only need to be pulled before the roof construction and after the roof is completed. The knot assembly and the truss beam frame can be fixedly installed and disassembled, and the tie assembly and the truss beam frame need not be assembled and disassembled during the construction process, which improves the work efficiency.

附图说明Description of drawings

通过阅读参照以下附图对非限制性实施例所作的详细描述,本实用新型的其它特征、目的和优点将会变得更明显:Other features, objects and advantages of the present invention will become more apparent by reading the detailed description of non-limiting embodiments with reference to the following drawings:

图1为本实用新型一种基于附着式升降平台的桁架搭桥的主视图;1 is a front view of a truss bridge based on an attached lifting platform of the present utility model;

图2为本实用新型一种基于附着式升降平台的桁架搭桥的俯视图;2 is a top view of a truss bridge based on an attached lifting platform of the present utility model;

图3为本实用新型一种基于附着式升降平台的桁架搭桥中附着式升降平台的示意图;3 is a schematic diagram of an attached lifting platform in a truss bridge based on the attached lifting platform of the present invention;

图4为本实用新型一种基于附着式升降平台的桁架搭桥中拉结组件的示意图;4 is a schematic diagram of a tie assembly in a truss bridge based on an attached lifting platform of the present invention;

图5为本实用新型一种基于附着式升降平台的桁架搭桥中桁架梁框架的主视图;5 is a front view of a truss girder frame in a truss bridge based on an attached lifting platform of the present invention;

图6为本实用新型一种基于附着式升降平台的桁架搭桥中桁架梁框架的侧视图;6 is a side view of a truss girder frame in a truss bridge based on an attached lifting platform of the present invention;

图7为图5中A的局部放大图。FIG. 7 is a partial enlarged view of A in FIG. 5 .

图中:1-附着式升降平台、2-双柱平台、3-桁架梁框架、4-木脚手板、5-护栏板、6-拉结组件、7-第一钢丝绳、8-导轨、11-立柱、12-限位立柱、21-防护网、61-U形中空块、62-第二钢丝绳、63-导向块、64-第三钢丝绳、31-第一方管、32-第二方管、91-支撑板、92-U形架、93-移动轮、94-伺服电机。In the picture: 1-attached lifting platform, 2-double-column platform, 3-truss beam frame, 4-wooden scaffolding board, 5-guardrail board, 6-knot assembly, 7-first steel wire rope, 8-guide rail, 11 -Column, 12-Limiting column, 21-Protective net, 61-U-shaped hollow block, 62-Second wire rope, 63-Guide block, 64-Third wire rope, 31-First square tube, 32-Second square Tube, 91-support plate, 92-U-shaped frame, 93-moving wheel, 94-servo motor.

具体实施方式Detailed ways

为使本实用新型实现的技术手段、创作特征、达成目的与功效易于明白了解,下面结合具体实施方式,进一步阐述本实用新型。In order to make the technical means, creation features, achievement goals and effects of the present invention easy to understand and understand, the present invention will be further described below with reference to the specific embodiments.

请参阅图1-图7,本实用新型提供一种技术方案:一种基于附着式升降平台的桁架搭桥,包括附着式升降平台1,附着式升降平台1设有两个,两个附着式升降平台1之间安装桁架梁框架3且桁架梁框架3能够沿着附着式升降平台1前后移动,桁架梁框架3上端通过铁丝铺装木脚手板4,桁架梁框架3周边位置焊接护栏板5且护栏板5安装在木脚手板4四周,桁架梁框架3上端固定拉结组件6,具体地,人员站立在铺装的木脚手板4上端,利用护栏板5对人员以及物料进行防护,提高了使用安全性,桁架梁框架3能够在两个附着式升降平台1之间前后移动,从而便于对跨度较大且面积较大的建筑顶棚进行施工。Please refer to FIG. 1 to FIG. 7 , the present utility model provides a technical solution: a truss bridge based on an attached lifting platform, including an attached lifting platform 1, two attached lifting platforms 1, two attached lifting platforms The truss girder frame 3 is installed between the platforms 1 and the truss girder frame 3 can move forward and backward along the attached lifting platform 1. The upper end of the truss girder frame 3 is paved with wooden scaffolding boards 4 through iron wires, and the guardrail plate 5 is welded at the peripheral position of the truss girder frame 3. The guardrail board 5 is installed around the wooden scaffolding board 4, and the upper end of the truss beam frame 3 is fixed with the knot assembly 6. Specifically, the personnel stand on the upper end of the paved wooden scaffolding board 4, and the guardrail board 5 is used to protect the personnel and materials. For safety in use, the truss girder frame 3 can move back and forth between the two attached lifting platforms 1 , thereby facilitating the construction of a building ceiling with a large span and a large area.

拉结组件6设有三组,三组拉结组件6等距固定在桁架梁框架3上端,拉结组件6便于对桁架梁框架3进行辅助支撑,提高了桁架梁框架3的放置安全性。There are three sets of tie assemblies 6 , and the three sets of tie assemblies 6 are equidistantly fixed on the upper end of the truss girder frame 3 .

拉结组件6包括两个第二钢丝绳62,两个第二钢丝绳62环形外端前后两部位置均套装U形中空块61,四个U形中空块61均固定在建筑物的顶棚上,两个第二钢丝绳62靠近的部位共同固定连接导向块63,导向块63下端前后对称固定两个第三钢丝绳64,两个第三钢丝绳64前后对称固定在桁架梁框架3前后两端,第三钢丝绳64能够对桁架梁框架3进行悬挂,且第三钢丝绳64能够随着桁架梁框架3前后移动,在顶棚施工前对三组U形中空块61与顶棚进行固定连接,并将六个第三钢丝绳64与桁架梁框架3固定连接,在施工过程中移动桁架梁框架3的位置时无需进行其他的钢丝绳解除以及固定,提高了操作便捷性。The tie assembly 6 includes two second steel wire ropes 62. The two second steel wire ropes 62 are sheathed with U-shaped hollow blocks 61 at the front and rear positions of the annular outer ends. The four U-shaped hollow blocks 61 are fixed on the ceiling of the building. The adjacent parts of the second wire ropes 62 are fixed and connected to the guide block 63 together. The lower end of the guide block 63 is symmetrically fixed to the front and rear of the two third wire ropes 64. The two third wire ropes 64 are symmetrically fixed to the front and rear ends of the truss beam frame 3. The third wire rope 64 can suspend the truss girder frame 3, and the third wire ropes 64 can move back and forth with the truss girder frame 3, before the construction of the ceiling, the three groups of U-shaped hollow blocks 61 are fixedly connected to the ceiling, and the six third steel wire ropes are connected. The 64 is fixedly connected with the truss girder frame 3, and when moving the position of the truss girder frame 3 during the construction process, there is no need to remove and fix other wire ropes, which improves the convenience of operation.

U形中空块61内部均设有通孔,U形中空块61通过通孔与封闭的第二钢丝绳62活动连接,导向块63内部设有两个圆孔,导向块63通过圆孔与两个第二钢丝绳62固定连接,第二钢丝绳62能够沿着U形中空块61进行移动,使导向块63随着桁架梁框架3进行前后移动,导向块63与第二钢丝绳62固定连接,可同步移动。The U-shaped hollow block 61 is provided with through holes inside, and the U-shaped hollow block 61 is movably connected with the closed second wire rope 62 through the through holes. The second wire rope 62 is fixedly connected, and the second wire rope 62 can move along the U-shaped hollow block 61, so that the guide block 63 moves back and forth with the truss girder frame 3, and the guide block 63 is fixedly connected with the second wire rope 62 and can move synchronously .

附着式升降平台1包括双柱平台2,双柱平台2远离桁架梁框架3一端前后对称固定两个防护网21,两个防护网21远离双柱平台2一端均滑动安装立柱11,双柱平台2通过防护网21与立柱11滑动安装,便于沿着立柱11进行上下移动。The attached lifting platform 1 includes a double-column platform 2, one end of the double-column platform 2 away from the truss girder frame 3 is symmetrically fixed with two protective nets 21 front and rear, and the two protective nets 21 are slidably installed at one end away from the double-column platform 2. The column 11, the double-column platform 2. The protective net 21 is slidably installed with the column 11, which is convenient for moving up and down along the column 11.

两个立柱11均由至少两节标准节竖直依次固定连接在一起且每节标准节均通过附墙框与建筑内壁的墙面固定连接,两个立柱11上端均固定用于限位功能的限位立柱12,两个立柱11上均固定齿条,两个防护网21靠近立柱11一端均固定齿轮,齿轮侧端固定电机,齿轮与齿条啮合安装,两个立柱11下端均固定平台底座且平台底座固定安装在地面上,电机工作带动齿轮转动,通过齿轮与齿条的啮合,实现带动防护网21向上移动或向下移动。The two uprights 11 are fixed and connected vertically and sequentially by at least two standard sections, and each standard section is fixedly connected to the wall of the inner wall of the building through the wall frame, and the upper ends of the two uprights 11 are fixed for the limit function. The limit column 12, the racks are fixed on the two columns 11, the gears are fixed on one end of the two protective nets 21 near the column 11, the motor is fixed on the side of the gears, the gears are meshed with the racks, and the lower ends of the two columns 11 are fixed on the platform base And the platform base is fixedly installed on the ground, the motor works to drive the gear to rotate, and through the meshing of the gear and the rack, the protective net 21 is driven to move up or down.

双柱平台2上端固定导轨8,桁架梁框架3下端四角位置均固定支撑板91,四个支撑板91下端均通过U形架92安装两个移动轮93,八个移动轮93分别安装在位于两个双柱平台2上的两个导轨8内部,两个导轨8中同一位置上的两个移动轮93与伺服电机固定连接,两个伺服电机串联连接,二者规格相同且工作同步,驱动移动轮93沿着导轨8进行前后移动,从而带动桁架梁框架3进行前后移动。The upper end of the double-column platform 2 is fixed with the guide rail 8, and the four corners of the lower end of the truss girder frame 3 are fixed with support plates 91. The lower ends of the four support plates 91 are installed with two moving wheels 93 through the U-shaped frame 92, and the eight moving wheels 93 are respectively installed in Inside the two guide rails 8 on the two double-column platforms 2, the two moving wheels 93 at the same position in the two guide rails 8 are fixedly connected with the servo motors, and the two servo motors are connected in series. The two have the same specifications and work synchronously. The moving wheel 93 moves back and forth along the guide rail 8 , thereby driving the truss beam frame 3 to move back and forth.

桁架梁框架3包括四个呈立方形布置的第一方管31,相邻两个第一方管31之间通过至少两个第二方管32固定连接,保证桁架梁框架3的结构稳定性以及紧固性。The truss girder frame 3 includes four first square tubes 31 arranged in a cubic shape, and two adjacent first square tubes 31 are fixedly connected by at least two second square tubes 32 to ensure the structural stability of the truss girder frame 3 and tightness.

第一方管31由少两根方管固定连接,相邻两个方管连接部位通过法兰固定四根高强螺栓,第一方管31的具体长度根据实际进行设计,由此根据实际将合适数量的方管固定连接。The first square pipe 31 is fixedly connected by at least two square pipes, and four high-strength bolts are fixed at the connecting parts of the adjacent two square pipes through flanges. The specific length of the first square pipe 31 is designed according to the actual situation. A number of square tubes are fixedly connected.

两个双柱平台2前后两端均通过第一钢丝绳7与建筑物的顶棚固定连接,提高了本实用新型的安全性。The front and rear ends of the two double-column platforms 2 are fixedly connected to the ceiling of the building through the first wire rope 7, which improves the safety of the present invention.

工作原理:本实用新型基于现有技术中的附着式升降平台1,附着式升降平台1由立柱11、双柱平台2、防护网21以及限位立柱12等零部件构成,且在双柱平台2上端安装脚手板以及防护栏,人员站立在脚手板上端,实现对附着式升降平台所附着的墙壁进行施工,但是附着式升降平台1只能对于墙壁进行施工,并不能对跨度以及面积都较大的建筑物顶棚进行施工,故而本实用新型去除原附着式升降平台中双柱平台2上端的脚手板以及防护栏,在两个相对的墙壁上固定相同规格的附着式升降平台1,然后在两个相对的双柱平台2上端固定导轨8,并在两个附着式升降平台1之间搭设桁架梁框架3,桁架梁框架3通过移动轮93与导轨8滑动连接,且经过伺服电机94驱动移动轮93在导轨8内部转动并移动,带动桁架梁框架3前后移动,桁架梁框架3横向具有较大的长度且能够在前后方向移动,故而便于对跨度大且面积大的建筑顶棚进行施工,对现有技术的附着式升降平台功能性进行进一步拓展,提高了使用效果。Working principle: The utility model is based on the attached lifting platform 1 in the prior art. The attached lifting platform 1 is composed of components such as a column 11, a double column platform 2, a protective net 21 and a limit column 12, and is installed on the double column platform. 2 Scaffolding boards and guardrails are installed on the upper end, and personnel stand on the upper end of the scaffolding board to realize construction on the wall attached to the attached lifting platform, but the attached lifting platform 1 can only be used for construction on the wall, and cannot be used for the span and area. The construction is carried out on the ceiling of a large building, so the utility model removes the scaffolding board and the guardrail on the upper end of the double-column platform 2 in the original attached lifting platform, and fixes the attached lifting platform 1 of the same specification on the two opposite walls, and then installs the lifting platform 1 on the two opposite walls. The upper ends of the two opposing double-column platforms 2 are fixed with guide rails 8, and a truss beam frame 3 is erected between the two attached lifting platforms 1. The truss beam frame 3 is slidably connected to the guide rail 8 through a moving wheel 93, and is driven by a servo motor 94. The moving wheel 93 rotates and moves inside the guide rail 8 to drive the truss girder frame 3 to move forward and backward. The truss girder frame 3 has a large lateral length and can move in the front and rear directions, so it is convenient for the construction of the building ceiling with a large span and a large area. The function of the attached lifting platform in the prior art is further expanded, and the use effect is improved.

建筑的顶棚通过拉结组件6以及第一钢丝绳7分别与桁架梁框架3以及双柱平台2进行拉结,提高了桁架梁框架3以及双柱平台2的支撑稳定性,提高了使用安全性,由于桁架梁框架3需要前后移动,为了避免在移动一个位置时就需要重新更换与桁架梁框架3拉结的拉结组件6,本实用新型中的拉结组件6由两个第二钢丝绳62组成,两个第二钢丝绳62能够沿着U形中空块61移动,从而导向块63以及第三钢丝绳64能够随着桁架梁框架3进行前后移动,只需在顶棚施工前以及顶棚完成后对拉结组件6与桁架梁框架3进行固定安装以及拆卸即可,施工过程中无需对拉结组件6以及桁架梁框架3进行组装以及拆卸,提高了工作效率。The ceiling of the building is tied with the truss girder frame 3 and the double-column platform 2 through the tie-tie assembly 6 and the first wire rope 7 respectively, which improves the support stability of the truss girder frame 3 and the double-column platform 2 and improves the safety in use. Since the truss girder frame 3 needs to move back and forth, in order to avoid the need to replace the tie assembly 6 tied with the truss girder frame 3 when moving one position, the tie assembly 6 in the present invention is composed of two second steel wire ropes 62 , the two second wire ropes 62 can move along the U-shaped hollow block 61, so that the guide block 63 and the third wire rope 64 can move back and forth with the truss girder frame 3, and only need to tie the knot before the ceiling construction and after the ceiling is completed. The assembly 6 and the truss girder frame 3 can be fixedly installed and disassembled, and the tie assembly 6 and the truss girder frame 3 need not be assembled and disassembled during the construction process, which improves the work efficiency.

以上显示和描述了本实用新型的基本原理和主要特征和本实用新型的优点,对于本领域技术人员而言,显然本实用新型不限于上述示范性实施例的细节,而且在不背离本实用新型的精神或基本特征的情况下,能够以其他的具体形式实现本实用新型。因此,无论从哪一点来看,均应将实施例看作是示范性的,而且是非限制性的,本实用新型的范围由所附权利要求而不是上述说明限定,因此旨在将落在权利要求的等同要件的含义和范围内的所有变化囊括在本实用新型内。不应将权利要求中的任何附图标记视为限制所涉及的权利要求。The basic principles and main features of the present invention and the advantages of the present invention have been shown and described above. For those skilled in the art, it is obvious that the present invention is not limited to the details of the above-mentioned exemplary embodiments, and does not deviate from the present invention. The present invention can be implemented in other specific forms under the condition of the spirit or basic features. Therefore, the embodiments are to be considered in all respects as exemplary and not restrictive, and the scope of the present invention is defined by the appended claims rather than the foregoing description, and it is therefore intended that the All changes within the meaning and range of the required equivalents are embraced within the present invention. Any reference signs in the claims shall not be construed as limiting the involved claim.

此外,应当理解,虽然本说明书按照实施方式加以描述,但并非每个实施方式仅包含一个独立的技术方案,说明书的这种叙述方式仅仅是为清楚起见,本领域技术人员应当将说明书作为一个整体,各实施例中的技术方案也可以经适当组合,形成本领域技术人员可以理解的其他实施方式。In addition, it should be understood that although this specification is described in terms of embodiments, not each embodiment only includes an independent technical solution, and this description in the specification is only for the sake of clarity, and those skilled in the art should take the specification as a whole , the technical solutions in each embodiment can also be appropriately combined to form other implementations that can be understood by those skilled in the art.

Claims (10)

1. The utility model provides a truss bridges based on attached lift platform which characterized in that: including adhering to formula lift platform (1), adhering to formula lift platform (1) is equipped with two, two slidable mounting truss girder frame (3) between adhering to formula lift platform (1), truss girder frame (3) upper end wood scaffold board (4) of mating formation, truss girder frame (3) peripheral position is fixed guardrail board (5) and is installed around wood scaffold board (4), truss girder frame (3) upper end is fixed and is drawed knot subassembly (6).
2. The truss bridge based on the attached lifting platform as claimed in claim 1, wherein: the drawknot components (6) are provided with three groups, and the drawknot components (6) are equidistantly fixed at the upper end of the truss girder framework (3).
3. The truss bridge based on the attached lifting platform as claimed in claim 2, wherein: drawknot subassembly (6) include two second wire rope (62), two the U-shaped hollow block (61) of two position equipartition suit around second wire rope (62) annular outer end, four U-shaped hollow block (61) all fix on the ceiling of building, two the common fixed connection guide block (63) in position that second wire rope (62) are close to, two third wire rope (64) of symmetry around guide block (63) lower extreme front and back symmetry are fixed both ends around truss girder frame (3) two third wire rope (64).
4. The truss bridge based on the attached lifting platform as claimed in claim 3, wherein: the U-shaped hollow block (61) is internally provided with a through hole, the U-shaped hollow block (61) is movably connected with a closed second steel wire rope (62) through the through hole, two round holes are formed in the guide block (63), and the guide block (63) is fixedly connected with the two second steel wire ropes (62) through the round holes.
5. The truss bridge based on the attached lifting platform as claimed in claim 1, wherein: attached lift platform (1) includes twin columns platform (2), two fixed protection networks (21) of truss girder frame (3) one end front and back symmetry are kept away from in twin columns platform (2), two the equal slidable mounting stand (11) of twin columns platform (2) one end are kept away from in protection network (21).
6. The truss bridge based on the attached lifting platform as claimed in claim 5, wherein: two stand (11) are together and every section of standard festival all through the wall fixed connection who attaches wall frame and building inner wall, two by two at least standard festival is vertical fixed connection in proper order stand (12), two on stand (11) equal fixed rack, two on stand (11) protection network (21) are close to the equal fixed gear of stand (11) one end, the fixed motor of gear side end, wheel and rack meshing installation, two equal fixed platform base and platform base fixed mounting of stand (11) lower extreme are subaerial.
7. The truss bridge based on the attached lifting platform as claimed in claim 5, wherein: double-column platform (2) upper end fixed guide (8), equal fixed support board (91), four in truss girder frame (3) lower extreme four corners position backup pad (91) are all removed wheel (93), eight through U-shaped frame (92) installation two removal wheel (93) in backup pad (91) lower extreme are installed respectively inside two guide rail (8) that are located on two double-column platform (2), two on same position remove wheel (93) and servo motor fixed connection in guide rail (8).
8. The truss bridge based on the attached lifting platform as claimed in claim 1, wherein: the truss girder framework (3) comprises four first square pipes (31) which are arranged in a cubic shape, and every two adjacent first square pipes (31) are fixedly connected through at least two second square pipes (32).
9. The truss bridge based on the attached lifting platform as claimed in claim 8, wherein: the first square pipe (31) is fixedly connected with at least two square pipes, and four high-strength bolts are fixed at the connecting parts of the square pipes through flanges.
10. The truss bridge based on the attached lifting platform as claimed in claim 5, wherein: the front end and the rear end of each of the two double-column platforms (2) are fixedly connected with a ceiling of a building through first steel wire ropes (7).
CN201922011320.8U 2019-11-20 2019-11-20 A Truss Bridge Based on Attached Lifting Platform Active CN211257769U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922011320.8U CN211257769U (en) 2019-11-20 2019-11-20 A Truss Bridge Based on Attached Lifting Platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922011320.8U CN211257769U (en) 2019-11-20 2019-11-20 A Truss Bridge Based on Attached Lifting Platform

Publications (1)

Publication Number Publication Date
CN211257769U true CN211257769U (en) 2020-08-14

Family

ID=71984478

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922011320.8U Active CN211257769U (en) 2019-11-20 2019-11-20 A Truss Bridge Based on Attached Lifting Platform

Country Status (1)

Country Link
CN (1) CN211257769U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012462A (en) * 2020-08-19 2020-12-01 龙口矿业集团有限公司 Attached electric lifting platform for coal tower

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012462A (en) * 2020-08-19 2020-12-01 龙口矿业集团有限公司 Attached electric lifting platform for coal tower

Similar Documents

Publication Publication Date Title
CN204151692U (en) A kind of modular assembly formula connection system for guide rail
CN114961334B (en) High-altitude large-span overhanging structure closed protection dismantling system and construction method thereof
CN106320713B (en) 3D building printing operation platform
CN113789948A (en) A large-span roofed atrium side wall slide rail hanging basket and its construction method
CN114150857A (en) Construction method of attached type automatic climbing elevator shaft safety protection platform
CN211338618U (en) A kind of tower crane upper passage
CN219196727U (en) Simple assembling bracket for high formwork
CN206053279U (en) Tool type scaffold unit and tool type scaffold
CN111305433A (en) Construction structure and construction method of inclined glass curtain wall of roof steel structure platform
CN111636667A (en) Construction method and operating platform of high-altitude operating platform applied to large-span workshop
CN213654364U (en) Many function combination formula removes protection canopy
CN104278830A (en) Integral combined scaffold
CN205575534U (en) Lattice formula groined type support body lifting means
CN204876577U (en) Building construction system
CN107720580B (en) Quick construction hoisting device and method for boiler construction water-cooled wall
CN220599110U (en) Movable bridge type operation platform
CN207934531U (en) A kind of Novel underground garage parking
CN210002826U (en) detachable welding platform for steel column construction
CN206376880U (en) A kind of roadway construction workbench
CN213297074U (en) A convenient outer wall cantilever operation frame
CN115627709A (en) A steel bar binding platform for box-shaped pier body construction
CN219805569U (en) Steel construction arched bridge arch rib section installation welding operation platform
CN209261192U (en) A portable scaffolding
CN211201305U (en) Protection rack of submarine cable terminal preparation
CN115726805A (en) Tunnel variable trolley and installation and transformation method thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
PP01 Preservation of patent right
PP01 Preservation of patent right

Effective date of registration: 20251223