CN206646795U - Housing construction is greatly across double-deck moving operation car device - Google Patents

Housing construction is greatly across double-deck moving operation car device Download PDF

Info

Publication number
CN206646795U
CN206646795U CN201720290184.9U CN201720290184U CN206646795U CN 206646795 U CN206646795 U CN 206646795U CN 201720290184 U CN201720290184 U CN 201720290184U CN 206646795 U CN206646795 U CN 206646795U
Authority
CN
China
Prior art keywords
bar
vertical
frame
support frame
type bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720290184.9U
Other languages
Chinese (zh)
Inventor
王山峰
方容
齐特
王廷湖
于小洋
孙永鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN201720290184.9U priority Critical patent/CN206646795U/en
Application granted granted Critical
Publication of CN206646795U publication Critical patent/CN206646795U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

Housing construction is greatly across double-deck moving operation car device, including support frame, support frame left bottom and bottom right side are respectively arranged with the scaffold universal wheel with locking structure, flat board is equipped with the top of support frame, front side edge edge and rear lateral edge have been arranged in vertical a guard rail at the top of support frame, protection network is provided between the top of two guard rails, lower frame is provided with least two layers along left and right horizontal direction and reinforces hanging bar, every layer of reinforcing hangs bar at least provided with two, the construction operation platform for being respectively adjacent to left side wall and right side wall is connected with hanging on adjacent two reinforcings hanging bar of layer.The utility model has the fixation and movement that the scaffold universal wheel of locking structure can carry out construction location, by setting arched girder to set a roof beam in place, improves the safety coefficient of upper operating platform, it can be constructed simultaneously with Dual-layer, the time is saved, accelerating construction progress is cost-effective.

Description

Housing construction is greatly across double-deck moving operation car device
Technical field
The utility model belongs to technical field of building construction, more particularly to a kind of housing construction greatly across the mobile behaviour of bilayer Make car device.
Background technology
Housing construction Mobile operating platform, it is divided into English truss formula operating platform, operation of encorbelmenting according to structural form Platform.English truss formula operating platform, in field fabrication and installation complete, need to carry out truss Force Calculation, it is cumbersome for installation, waste material Matter, adaptation span is little, construction speed is slow;Suitable for extensive size single encorbelment lateral edges decorations and regular shape The installation of lighting roof and keel.
Overhanging type operating platform, field fabrication are completed, and assembling and disassembling convenience, platform conveniently moving, operation are flexible, working face Smaller, safety coefficient of encorbelmenting is had a great influence by constructing operation state, and integral stability factor is not high, function is single, is applicable small-scale Encorbelment lateral edges decorations construction.
Utility model content
The utility model is in order to solve weak point of the prior art, there is provided a kind of boundary of works area is big, construction speed is fast, The strong housing construction of security reliability is greatly across double-deck moving operation car device.
In order to solve the above technical problems, the utility model adopts the following technical scheme that:Housing construction moves greatly across bilayer Dynamic operation car device, including support frame, support frame left bottom and bottom right side are respectively arranged with locking structure Scaffold universal wheel, the vestibule that the scaffold universal wheel in left side is supported on wall on the left of house are chosen on hollow plate, the scaffold on right side The vestibule that universal wheel is supported on wall on the right side of house is chosen on hollow plate, is equipped with flat board at the top of support frame, at the top of support frame before Side edge and rear lateral edge have been arranged in vertical a guard rail, and protection is provided between the top of two guard rails Net, lower frame are provided with least two layers along left and right horizontal direction and reinforce hanging bar, and every layer of reinforcing hangs bar at least provided with two Root, the constructing operation of wall and right side wall on the left of being respectively adjacent to is connected with hanging on adjacent two reinforcings hanging bar of layer and is put down Platform.
Construction operation platform includes four vertical rods being arranged in vertical, and the line of the horizontal cross-section of four vertical rods is in Rectangle, horizontally disposed between adjacent two vertical rods to have connecting rod, the upper end of two vertical rods of front side is hinged with preceding L-type bar, The upper end of two vertical rods of rear side has been fixedly connected with rear L-type bar, and preceding L-type bar and rear L-type bar include horizontal segment and vertical section, The horizontal segment of two preceding L-type bars is articulated in one and reinforced on hanging bar, and the horizontal segment of L-type bar is articulated in another reinforcing after two Hang on bar, the horizontal segment rear end of preceding L-type bar is hinged on the vertical rod upper end of front side, and the vertical section of preceding L-type bar is located at the vertical of front side On front side of bar, connected between the vertical rod of front side and the vertical pars infrasegmentalis of preceding L-type bar by fastening bolt;Afterwards before the horizontal segment of L-type bar The vertical rod upper end of rear side is fixedly connected on, the vertical section of rear L-type bar is located on rear side of the vertical rod of rear side;
Four vertical rod lower ends are fixedly connected with horizontal frame, and pedal is equipped with horizontal frame, and horizontal frame sidepiece is set There is the open fence in side.
Support frame includes rectangle frame and arched girder is set a roof beam in place, and the left end and right-hand member that arched girder is set a roof beam in place are respectively fixedly connected with upper Layer reinforces the left end and right-hand member of hanging bar, is fixedly connected on the upside of the middle part that arched girder is set a roof beam in place with downside in the middle part of rectangle frame, flat board paving It is located on rectangle frame, guard rail is fixedly installed on rectangle frame;The reinforcing hanging bar on upper strata, the reinforcing hanging bar and arch of lower floor Connected between the middle part of girder truss by the support beam that is arranged in vertical, the reinforcing hanging bar that arched girder is set a roof beam in place with upper strata it Between be provided with hound.
The left side and right side of support frame are respectively equipped with a position-limited rack, and the position-limited rack in left side and the vestibule in left side choose hollow plate Right edge between there is gap, the position-limited rack on right side and the vestibule on right side to have gap between choosing the left side edge of hollow plate.
Using above-mentioned technical proposal, construction worker station carries out construction operation, flat board and pedal difference on flat board and pedal Make the platform of double-deck construction, and scaffold universal wheel can be chosen in vestibule and be moved on hollow plate, and scaffold is locked after moving into place Universal wheel, it is ensured that stability during construction operation.The specific regulation process of construction operation platform height is:First rear L-type bar is hung It is connected to one to reinforce on hanging bar, then preceding L-type bar corresponding rotation is reinforced on hanging bar to another, using fastening bolt by before Connected between the vertical pars infrasegmentalis of the vertical rod of side and preceding L-type bar, reuse rope and vertical rod is bonded in support frame, so can be with Prevent that construction operation platform is swung in construction operation.
The utility model has the advantages that:
The 1st, arch truss girder construction is set in the support frame in the utility model, it is more flat than other operations of the prior art Platform safety coefficient is higher, and stress is more reasonable;
2nd, support frame bottom is set at least two layers and reinforces hanging bar, and construction operation platform can be hung in difference respectively The reinforcing hanging bar of layer, to adjust the height of pedal, can expand the area of construction operation;
3rd, the utility model top sets the flat board on upper strata, and vestibule chooses symmetrical one construction of setting respectively below hollow plate Operating platform, while this layer of constructing chooses dead zone edge, the lower floor that can construct chooses dead zone edge trim, decoration construction, accelerates to apply Work progress, shorten the duration, it is cost-effective;
4th, position-limited rack, which plays a part of limiting support frame, does not move left and right, to avoid the scaffold universal wheel vestibule that drops from choosing Hollow plate.Play good safety guarantee effect;
In summary, the utility model have the scaffold universal wheel of locking structure can carry out construction location fixation and It is mobile, by setting arched girder to set a roof beam in place, the safety coefficient of upper operating platform is improved, can be constructed simultaneously with Dual-layer, saved Time, accelerating construction progress are cost-effective.
Brief description of the drawings
Fig. 1 is structural representation of the present utility model;
Fig. 2 is the right view of construction operation platform in Fig. 1.
Embodiment
As depicted in figs. 1 and 2, housing construction of the present utility model is greatly across double-deck moving operation car device, including branch Support frame frame 1, the left bottom of support frame 1 and bottom right side are respectively arranged with the scaffold universal wheel 2 with locking structure, left side Scaffold universal wheel 2 be supported on the vestibule of wall on the left of house and choose on hollow plate 3, the scaffold universal wheel 2 on right side is supported on room The vestibule of wall is chosen on hollow plate 3 on the right side of room, and the top of support frame 1 is equipped with flat board, the top front side edge edge of support frame 1 and rear side Edge has been arranged in vertical a guard rail 4, and protection network, lower frame are provided between the top of two guard rails 4 At least two layers is provided with along left and right horizontal direction and reinforces hanging bar 5, and every layer of reinforcing hangs bar 5 at least provided with two, with layer Reinforce hanging on hanging bar 5 for adjacent two and be connected with the construction operation platform for being respectively adjacent to left side wall and right side wall.
Construction operation platform includes four vertical rods 6 being arranged in vertical, the line of the horizontal cross-section of four vertical rods 6 Rectangular, horizontally disposed between adjacent two vertical rods 6 to have connecting rod 7, the upper end of two vertical rods 6 of front side is hinged with preceding L Type bar 8, the upper end of two vertical rods 6 of rear side have been fixedly connected with rear L-type bar 9, and preceding L-type bar 8 and rear L-type bar 9 include level Section and vertical section, the horizontal segment of two preceding L-type bars 8 are articulated in one and reinforced on hanging bar 5, and the horizontal segment of L-type bar 9 is hung after two It is connected on another to reinforce on hanging bar 5, the horizontal segment rear end of preceding L-type bar 8 is hinged on the upper end of vertical rod 6 of front side, preceding L-type bar 8 Vertical section is located at the front side of vertical rod 6 of front side, passes through fastening bolt 17 between the vertical rod 6 of front side and the vertical pars infrasegmentalis of preceding L-type bar 8 Connection;The upper end of vertical rod 6 of rear side is fixedly connected on before the horizontal segment of L-type bar 9 afterwards, the vertical section of rear L-type bar 9 is located at the vertical of rear side The rear side of bar 6;Four lower ends of vertical rod 6 are fixedly connected with horizontal frame 10, and pedal, the side of horizontal frame 10 are equipped with horizontal frame 10 Portion is provided with the open fence 11 in side.
Support frame 1 includes rectangle frame 12 and arched girder and sets a roof beam in place 13, and arched girder sets a roof beam in place 13 left end and right-hand member is fixed respectively Be connected to left end and right-hand member that upper strata reinforces hanging bar 5, arched girder set a roof beam in place 13 middle part on the upside of it is solid with the middle part of rectangle frame 12 downside Fixed connection, flat board are laid on rectangle frame 12, and guard rail 4 is fixedly installed on rectangle frame 12;Upper strata reinforcing hanging bar 5, under Layer reinforcing hanging bar 5 and arched girder set a roof beam in place 13 middle part between connected by the support beam 14 being arranged in vertical, arch Hound 15 is provided between the reinforcing hanging bar 5 on girder truss 13 and upper strata.
The left side and right side of support frame 1 are respectively equipped with a position-limited rack 16, the position-limited rack 16 in left side and the vestibule in left side Choosing between the right edge of hollow plate 3 has gap, and the position-limited rack 16 on right side and the vestibule on right side are chosen between the left side edge of hollow plate 3 With gap;Gap digit 1-5cm.
Construction worker station carries out construction operation on flat board and pedal, and flat board and pedal make the platform of double-deck construction respectively, And scaffold universal wheel 2 can be chosen in vestibule and be moved on hollow plate 3, scaffold universal wheel 2 is locked after moving into place, it is ensured that construction Stability during operation.The specific regulation process of construction operation platform height is:Rear L-type bar 9 is first articulated to a reinforcing to hang On peg 5, then the preceding corresponding rotation of L-type bar 8 to another reinforce hanging bar 5 on, using fastening bolt by the vertical rod 6 of front side with Connected between the vertical pars infrasegmentalis of preceding L-type bar 8, reuse rope and vertical rod 6 is bonded in support frame 1, can so prevent Construction operation platform is swung during construction operation.
The present embodiment not makees any formal limitation, every foundation to shape of the present utility model, material, structure etc. Any simple modification, equivalent change and modification that the technical essence of the utility model is made to above example, belongs to this reality With the protection domain of new technique scheme.

Claims (4)

1. housing construction is greatly across double-deck moving operation car device, it is characterised in that:Including support frame, support frame left side Bottom and bottom right side are respectively arranged with the scaffold universal wheel with locking structure, and the scaffold universal wheel in left side is supported on room The vestibule of wall is chosen on hollow plate on the left of room, and the vestibule that the scaffold universal wheel on right side is supported on wall on the right side of house is chosen on hollow plate, Flat board is equipped with the top of support frame, support frame top front side edge edge and rear lateral edge have been arranged in vertical one and prevented Guardrail, protection network is provided between the top of two guard rails, lower frame is along left and right horizontal direction provided with least two layers reinforcing Bar is hung, every layer of reinforcing hangs bar at least provided with two, and reinforcing hanging on hanging bar with adjacent two of layer is connected with point Not adjacent to left side wall and the construction operation platform of right side wall.
2. housing construction according to claim 1 is greatly across double-deck moving operation car device, it is characterised in that:Construction behaviour Making platform includes four vertical rods being arranged in vertical, and the line of the horizontal cross-section of four vertical rods is rectangular, adjacent two Horizontally disposed between vertical rod to have connecting rod, the upper end of two vertical rods of front side is hinged with preceding L-type bar, two vertical rods of rear side Upper end be fixedly connected with rear L-type bar, preceding L-type bar and rear L-type bar include horizontal segment and vertical section, two preceding L-type bars Horizontal segment is articulated in one and reinforced on hanging bar, and the horizontal segment of L-type bar is articulated in another and reinforced on hanging bar after two, preceding L The horizontal segment rear end of type bar is hinged on the vertical rod upper end of front side, and the vertical section of preceding L-type bar is located on front side of the vertical rod of front side, front side Connected between the vertical pars infrasegmentalis of vertical rod and preceding L-type bar by fastening bolt;Rear side is fixedly connected on before the horizontal segment of L-type bar afterwards Vertical rod upper end, the vertical section of rear L-type bar is located on rear side of the vertical rod of rear side;
Four vertical rod lower ends are fixedly connected with horizontal frame, and pedal is equipped with horizontal frame, and horizontal frame sidepiece is provided with one The open fence in side.
3. housing construction according to claim 2 is greatly across double-deck moving operation car device, it is characterised in that:Carriage Frame includes rectangle frame and arched girder is set a roof beam in place, and the left end and right-hand member that arched girder is set a roof beam in place, which are respectively fixedly connected with, reinforces hanging bar on upper strata Left end and right-hand member, the middle part upside that arched girder is set a roof beam in place are fixedly connected with downside in the middle part of rectangle frame, and flat board is laid on rectangle frame, is prevented Guardrail is fixedly installed on rectangle frame;The reinforcing hanging bar on upper strata, the reinforcing hanging bar of lower floor and the middle part set a roof beam in place of arched girder it Between connected by the support beam that is arranged in vertical, be provided with diagonal brace between the reinforcing hanging bar that arched girder is set a roof beam in place with upper strata Bar.
4. housing construction according to claim 2 is greatly across double-deck moving operation car device, it is characterised in that:Carriage The left side and right side of frame are respectively equipped with a position-limited rack, and the position-limited rack in left side and the vestibule in left side are chosen between the right edge of hollow plate With gap, the position-limited rack on right side and the vestibule on right side have gap between choosing the left side edge of hollow plate.
CN201720290184.9U 2017-03-23 2017-03-23 Housing construction is greatly across double-deck moving operation car device Active CN206646795U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720290184.9U CN206646795U (en) 2017-03-23 2017-03-23 Housing construction is greatly across double-deck moving operation car device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720290184.9U CN206646795U (en) 2017-03-23 2017-03-23 Housing construction is greatly across double-deck moving operation car device

Publications (1)

Publication Number Publication Date
CN206646795U true CN206646795U (en) 2017-11-17

Family

ID=60279203

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720290184.9U Active CN206646795U (en) 2017-03-23 2017-03-23 Housing construction is greatly across double-deck moving operation car device

Country Status (1)

Country Link
CN (1) CN206646795U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111502223A (en) * 2020-03-24 2020-08-07 中国化学工程第三建设有限公司 Method for decorating and maintaining wall above beam rail by using travelling crane beam
CN112696053A (en) * 2020-12-21 2021-04-23 中国二十冶集团有限公司 Arch-shaped support system and support method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111502223A (en) * 2020-03-24 2020-08-07 中国化学工程第三建设有限公司 Method for decorating and maintaining wall above beam rail by using travelling crane beam
CN112696053A (en) * 2020-12-21 2021-04-23 中国二十冶集团有限公司 Arch-shaped support system and support method

Similar Documents

Publication Publication Date Title
US9016025B2 (en) Constructing method for concrete cylinder of construction steel bar of high-rise steel structure
CN207484964U (en) Side form structure at post-cast strip in concrete pouring construction
CN207813203U (en) A kind of reusable Combined construction surrounding retainer
CN106592826A (en) Construction method for cylindrical frame supporting type hydraulic-climbing integral steel platform formwork shear steel plate layer
CN103603496B (en) A kind of off normal integrally hoisting steel vestibule enters the method for position
CN109594479A (en) A kind of parallel overpass center anticollision barrier of double width while construct mould bases and method
CN202544854U (en) Lining trolley for subway station
CN206646795U (en) Housing construction is greatly across double-deck moving operation car device
CN102268858B (en) Cradle for suspension pouring of arch-type bridge
CN103572707B (en) Case girder steel outer template and construction method
CN202000265U (en) Concrete construction formwork for high pier of bridge
CN113404281A (en) Climbing type scaffold, climbing and mounting method thereof and construction method of fabricated building
CN108005373A (en) A kind of integrated form lifting platform system and its assembling method
CN202108241U (en) Movable hanging frame for assembling spherical storage tank
CN205857697U (en) The anti-form bracing constructing device hanging template
CN205100543U (en) Novel construction system of commercial mansion
CN207044363U (en) A kind of new precast beam protection and operating platform
CN211257769U (en) Truss bridging based on attached lifting platform
CN203394008U (en) Suspension type hanging bracket used on plane truss
CN203769283U (en) Adaptive angle self-climbing construction platform
CN106939697A (en) A kind of gang form and its construction method of Core Walls Structure of constructing
CN209799320U (en) Integral steel platform for multi-cylinder steel plate shear wall
CN209397925U (en) It is a kind of apply to concrete barrier formwork peace tear open packaged type peace tear frame open
CN107816132B (en) High-level tower crane single-row frame attachment structure without floor slab and construction method thereof
CN216405142U (en) Along with hanging gliding continuous web's of basket fitment platform structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant