CN207620845U - A kind of coal mine roadway blows out waste rock blocking curtain - Google Patents

A kind of coal mine roadway blows out waste rock blocking curtain Download PDF

Info

Publication number
CN207620845U
CN207620845U CN201721804404.1U CN201721804404U CN207620845U CN 207620845 U CN207620845 U CN 207620845U CN 201721804404 U CN201721804404 U CN 201721804404U CN 207620845 U CN207620845 U CN 207620845U
Authority
CN
China
Prior art keywords
cash body
gear cash
coal mine
waste rock
blows out
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721804404.1U
Other languages
Chinese (zh)
Inventor
李存禄
张茂伟
高敬东
范吉宏
孙世民
孙富兴
杨现贵
王传庆
李国辉
孙玉超
徐国华
杨尊胜
孙成强
方志明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Dongshan Xinyi Coal Mine Co Ltd
Original Assignee
Shandong Dongshan Xinyi Coal Mine Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Dongshan Xinyi Coal Mine Co Ltd filed Critical Shandong Dongshan Xinyi Coal Mine Co Ltd
Priority to CN201721804404.1U priority Critical patent/CN207620845U/en
Application granted granted Critical
Publication of CN207620845U publication Critical patent/CN207620845U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Slide Fasteners (AREA)

Abstract

The utility model provides a kind of coal mine roadway and blows out waste rock blocking curtain, including keeping off cash body, on the top of gear cash body, multiple suppending holes are set, it is provided in suppending hole and the matched hook of suppending hole, the both sides of gear cash body and bottom are provided with multiple mounting holes, cover strip is both provided on mounting hole and suppending hole, upper end and the gear cash body of the cover strip are fixed.The waste rock blocking curtain has hook that can be hung between, use easy to operation, and has gear cash body that can be compared comprehensive covering, reduces the avalanche of spoil.

Description

A kind of coal mine roadway blows out waste rock blocking curtain
Technical field
The utility model relates to coal mine total rock tunnelling field, especially a kind of coal mine roadway blows out waste rock blocking curtain.
Background technology
At present when coal mine roadway tunnels, most of using the method drilled and blasted, a large amount of cash can all be had every time by blowing out Stone is dished out, and easily damages the metal mesh etc. of the circuit in tunnel, pipeline and construction site in this way, there is the protection using net formula at present Structure, but some big spoils can only be blocked in this way, the small spoil of diameter can not be blocked, and fixed net is also required to expend For a long time, this is existing deficiencies in the technology.
Invention content
The purpose of this utility model aiming at deficiency of the prior art, and provides a kind of coal mine roadway and blows out Waste rock blocking curtain, the waste rock blocking curtain have hook that can be hung between, use easy to operation, and have gear cash body that can be compared entirely The covering in face reduces the avalanche of spoil.
This programme is achieved by the following technical measures:A kind of coal mine roadway blows out waste rock blocking curtain, including gear cash body, Multiple suppending holes are arranged in the top for keeping off cash body, be provided in suppending hole with the matched hook of suppending hole, in the both sides of gear cash body Bottom is provided with multiple mounting holes, cover strip, the upper end of the cover strip and gear are both provided on mounting hole and suppending hole Cash body is fixed.
The hook is S-shaped, a diameter of 6mm of hook.
The gear cash body is that belt keeps off cash body.It is provided with fixed strip above gear cash body, the suppending hole passes through Fixed strip.
The height of the gear cash body is 100cm, and the width of gear cash body is 200cm.
The advantageous effect of this programme can according to the description of the above program, due to there is gear cash body can be in this scenario Spoil is stopped, the avalanche of spoil is reduced;Suppending hole is arranged at the top of gear cash body, has hook to match use with suppending hole, this Sample is convenient for suspension gear cash body, before blowing out, can be suspended on gear cash body on meeting head on so that gear cash body blocks borehole;In gear cash The both sides and bottom of body are provided with multiple mounting holes, and scene is blown out what is met head on, whether will can keep off the four of cash body as needed Week is fixed;It is both provided with cover strip on mounting hole and suppending hole, can prevent spoil from passing through mounting hole or suspension in this way Hole avalanche;The upper end of cover strip is fixed with gear cash body rather than is all fixed, and is convenient for link up with across suppending hole in this way, or not Fixed equipment pass through mounting hole, link up with as S-shaped, can be slid from hook to avoid gear cash body in this way;That links up with is a diameter of 6mm is convenient for gathering materials on the spot in this way, a diameter of 6mm reinforcing bars may be used and directly make;It is that belt keeps off cash body to keep off cash body, so both It ensure that the intensity of gear cash body can stop cash body, it, can be with but also gear cash body has certain flexibility, and convenient for gathering materials on the spot Use belt waste and old in tunnel;Fixed strip is provided with above gear cash body, suppending hole passes through fixed strip, is both convenient for hanging in this way Hook passes through gear cash body and fixed strip, but also fold does not occur when gear cash body suspension, fixed strip also increases the intensity of gear cash body, Hook is avoided to pull open suppending hole so that the situation that gear cash body falls off;The height for keeping off cash body is 100cm, and the width of gear cash body is 200cm is adapted to most borehole in this way.It can be seen that the utility model is compared with prior art, have substantive special Point and progress, beneficial effects of its implementation are also obvious.
Description of the drawings
Fig. 1 is the structural schematic diagram of specific embodiment of the present invention.
Fig. 2 is the schematic diagram with hook.
In figure, 1 is gear cash body, and 2 be suppending hole, and 3 be mounting hole, and 4 be fixed strip, and 5 be cover strip, and 6 be hook.
Specific implementation mode
In order to clarify the technical characteristics of the invention, below by a specific implementation mode, and its attached drawing is combined, it is right This programme is illustrated.
By attached drawing as can be seen that a kind of coal mine roadway of this programme blows out waste rock blocking curtain, including gear cash body 1, in gear cash body 1 Top multiple suppending holes 2 are set, be provided in suppending hole 2 with the matched hook 6 of suppending hole 2, the hook 6 is S-shaped, A diameter of 6mm of hook 6.The both sides of gear cash body 1 and bottom are provided with multiple mounting holes 3, on mounting hole 3 and suppending hole 2 It is both provided with cover strip 5, upper end and the gear cash body 1 of the cover strip 5 are fixed.The height of the gear cash body 1 is 100cm, gear The width of cash body 1 is 200cm.
The gear cash body 1 is that belt keeps off cash body.The top of gear cash body 1 is provided with fixed strip 4, the suppending hole 2 Across fixed strip 4.

Claims (5)

1. a kind of coal mine roadway blows out waste rock blocking curtain, it is characterized in that:Including keeping off cash body, multiple suspensions are set on the top of gear cash body Hole, be provided in suppending hole with the matched hook of suppending hole, gear cash body both sides and bottom be provided with multiple mounting holes, Cover strip is both provided on mounting hole and suppending hole, upper end and the gear cash body of the cover strip are fixed.
2. coal mine roadway according to claim 1 blows out waste rock blocking curtain, it is characterized in that:The hook be S-shaped, hook it is straight Diameter is 6mm.
3. coal mine roadway according to claim 1 blows out waste rock blocking curtain, it is characterized in that:The gear cash body is that belt keeps off cash Body.
4. coal mine roadway according to claim 1 or 3 blows out waste rock blocking curtain, it is characterized in that:It is provided with above gear cash body Fixed strip, the suppending hole pass through fixed strip.
5. coal mine roadway according to claim 1 blows out waste rock blocking curtain, it is characterized in that:The height of the gear cash body is The width of 100cm, gear cash body are 200cm.
CN201721804404.1U 2017-12-21 2017-12-21 A kind of coal mine roadway blows out waste rock blocking curtain Active CN207620845U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721804404.1U CN207620845U (en) 2017-12-21 2017-12-21 A kind of coal mine roadway blows out waste rock blocking curtain

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721804404.1U CN207620845U (en) 2017-12-21 2017-12-21 A kind of coal mine roadway blows out waste rock blocking curtain

Publications (1)

Publication Number Publication Date
CN207620845U true CN207620845U (en) 2018-07-17

Family

ID=62820818

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721804404.1U Active CN207620845U (en) 2017-12-21 2017-12-21 A kind of coal mine roadway blows out waste rock blocking curtain

Country Status (1)

Country Link
CN (1) CN207620845U (en)

Similar Documents

Publication Publication Date Title
RU2348811C1 (en) Method of supporting mine tunnels
CN103089279B (en) The method that between crossheading lane, a kind of many lanes, bog-head coal post is reinforced
CN107387083A (en) A kind of medium-thickness seam gob side entry retaining roadside support body construction method supported using spoil
CN205172609U (en) Asymmetric supporting device in tunnel
CN207620845U (en) A kind of coal mine roadway blows out waste rock blocking curtain
CN107575227A (en) A kind of coal-mining method and roof controlling method
CN206769931U (en) A kind of bottom arch supporting construction of baseboard of coal mine roadway
CN104989402A (en) Medium-deep hole room pillar mining method for limestone underground mine mining
CN104100290B (en) The through middle gas preventing and control technique of a kind of coal seam digging laneway
CN205225291U (en) Coal road tunnelling temporary support device
CN203430546U (en) Roadway roof protective net of coal face
CN206753622U (en) A kind of bar-mat reinforcement for coal mine roadway bolt-mesh-spurting supporting
CN103742193A (en) Mounting method for hydraulic filling soft strainer pipe in mined-out area
CN207512770U (en) A kind of metope planting type soil block
CN203730023U (en) Frame shed beam device
CN204140104U (en) Soft medium-thickness seam big cross section open-off cut
CN202926348U (en) U-shaped shed fixing device
CN208793009U (en) A kind of roadway support device for goaf
CN207920616U (en) A kind of suspension device for taking out tunnel speedy drivage the bottom of for
CN203669899U (en) Strip steel mesh for isolating roadway behind working face from gob
CN208749379U (en) A kind of back anchor cable protective device
CN207144941U (en) A kind of high-dipping fully-mechanized mining working open-off cut tunnels safely auxiliary facility
CN204716264U (en) A kind of forestope temporary lining
CN204877467U (en) Telescopic work arm of scaling jumbo
CN204060745U (en) High inclination-angle half-edge coal seam protects lane structure without coal pillar entry retaining coal-face

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant