CN207609155U - Hydraulic pressure is from climbing construction operation platform - Google Patents
Hydraulic pressure is from climbing construction operation platform Download PDFInfo
- Publication number
- CN207609155U CN207609155U CN201721688481.5U CN201721688481U CN207609155U CN 207609155 U CN207609155 U CN 207609155U CN 201721688481 U CN201721688481 U CN 201721688481U CN 207609155 U CN207609155 U CN 207609155U
- Authority
- CN
- China
- Prior art keywords
- upright bar
- supporting leg
- hydraulic pressure
- frame body
- operation platform
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model discloses a kind of hydraulic pressure from climbing construction operation platform, including single Pin framves, the list Pin framves include left side upper supporting leg, right side upper supporting leg, left side upper beam, right side upper beam, bearing diagonal on left side, bearing diagonal on right side, Lifting Equipment, supporting leg under left side, supporting leg under right side, left side upright bar and right side upright bar, the left side upper beam, climb triangle frame body for bearing diagonal and left side upright bar composition left side on left side, the right side upper beam, climb triangle frame body for bearing diagonal and right side upright bar composition right side on right side, Lifting Equipment is set between triangle frame body is climbed in the left side and the right side is climbed triangle frame body.The present apparatus effectively realizes the automatic climbing and angular adjustment of frame body, reduces the use of live lifting means, artificial input amount is small, is effectively reduced security risk.
Description
Technical field
The utility model is related to civil construction technical fields, and in particular to one kind being suitable for power station, dam, massif protection
Hydraulic pressure from climbing construction operation platform.
Background technology
It needs to carry out anchor bolt drawknot protection to original rock mass in the work progress of power station, dam and massif protection, but
It is the scrambling of the height and rock mass face in construction work due to rock mass, is not easy effectively with traditional construction auxiliary equipment
Completion, and need construction personnel to carry some equipments and a small amount of material during protecting, deposited in work progress
In very big difficulty, hydraulic pressure of the invention is from construction operation platform effective solution this difficult point of climbing.
Utility model content
The technical issues of the utility model is in order to overcome background technology part to mention provides a kind of hydraulic pressure from the construction behaviour that climbs
Make platform.
In view of the above problem of the prior art, according to one side disclosed by the utility model, the utility model uses
Following technical scheme:
From climb construction operation platform, including single Pin framves, the list Pin framves include left side upper supporting leg, on right side for a kind of hydraulic pressure
Supporting leg, left side upper beam, right side upper beam, bearing diagonal on left side, supporting leg, right side under bearing diagonal, Lifting Equipment, left side on right side
Lower supporting leg, left side upright bar and right side upright bar, bearing diagonal and left side upright bar composition left side climb three on the left side upper beam, left side
Corner bracket body, climb triangle frame body for bearing diagonal and right side upright bar composition right side on the right side upper beam, right side, and the left side is climbed
Triangle frame body and the right side are climbed, and Lifting Equipment is arranged between triangle frame body, and it is vertical that the left side upper supporting leg is set to the left side
Bar upper end, supporting leg is set to left side upright bar lower end under the left side, and the right side upper supporting leg is set to the right side upright bar
Upper end, supporting leg is set to right side upright bar lower end under the right side.
In order to which the utility model is better achieved, further technical solution is:
An embodiment according to the present utility model, the left side upper beam lower section also set up middle cross beam and bottom end rail,
The left side upper beam, middle cross beam and the respective one end of bottom end rail are connected by the second upright bar, and wherein the middle cross beam is also vertical with left side
Bar connects, and is also connected by hanging beam between wherein the middle cross beam and bottom end rail.
Another embodiment according to the present utility model, is also tiltedly propped up by third between wherein the middle cross beam and the hanging beam
Support connection.
Another embodiment according to the present utility model, on wherein the middle cross beam or bottom end rail setting go along with sb. to guard him upright bar.
Another embodiment according to the present utility model, on the left side upper beam setting go along with sb. to guard him upright bar.
Another embodiment according to the present utility model, the left side upper supporting leg and right side upper supporting leg include respectively
Outer stay tube and can it is described it is outer support inner telescoping tube interior stay tube.
Hanging ring is arranged on the outer stay tube in another embodiment according to the present utility model.
Another embodiment according to the present utility model, the interior stay tube are connect with support base, the outer stay tube and tune
Save leading screw connection.
The utility model can also be:
Another embodiment according to the present utility model, at least two list Pin framves are assembled into construction by bolt and axis pin
Operating platform.
Compared with prior art, one of the beneficial effects of the utility model are:
In to power station, dam, massif construction of prevention work, even if the height of rock mass and outer profile is irregular, pass through this
A kind of hydraulic pressure of utility model also easily can carry out anchor bolt drawknot protection, and this reality from the construction operation platform that climbs to rock mass
It is simple with new structure, it is easy to operate.
Description of the drawings
Illustrate present specification embodiment or technical solution in the prior art in order to clearer, it below will be to embodiment
Or attached drawing needed in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only
It is the reference to some embodiments in present specification, for those skilled in the art, what is do not made the creative labor
In the case of, other attached drawings can also be obtained according to these attached drawings.
Fig. 1 is the structural schematic diagram according to single Pin framves of the utility model one embodiment.
Fig. 2 is the structural schematic diagram according to the upper supporting leg of the utility model one embodiment.
Fig. 3 is the stereoscopic schematic diagram of Fig. 2.
Fig. 4 and Fig. 5 is the construction frame body schematic diagram according to the utility model one embodiment.
Wherein, entitled corresponding to the reference numeral in attached drawing:
Upper supporting leg on the left of 1a-, the right sides 1b- upper supporting leg, the left sides 2a- upper beam, the right sides 2b- upper beam, the left sides 3a-
Upper bearing diagonal, bearing diagonal on the right sides 3b-, 4- Lifting Equipments, lower supporting leg on the left of 5a-, lower supporting leg on the right side of 5b-, on the left of 6a-
Upright bar, 6b- right side upright bars, 7- middle cross beams, 8- bottom end rails, the second upright bars of 9-, 10- hanging beams, 11- third bearing diagonals,
12- goes along with sb. to guard him upright bar.
Specific implementation mode
The utility model is described in further detail with reference to embodiment, but the embodiment of the utility model is not
It is limited to this.
As shown in Figure 1, Fig. 1 shows single Pin framves structure according to the utility model one embodiment, a kind of hydraulic pressure is from climbing
Construction operation platform is risen, including single Pin framves, the list Pin framves include left side upper supporting leg 1a, right side upper supporting leg 1b, left side upper beam
2a, right side upper beam 2b, it bearing diagonal 3a on left side, is propped up under supporting leg 5a, right side under bearing diagonal 3b, Lifting Equipment 4, left side on right side
Bearing diagonal 3a and left side upright bar 6a compositions are left on leg 5b, left side upright bar 6a and right side upright bar 6b, the left side upper beam 2a, left side
Climb triangle frame body for side, and climb tripod for bearing diagonal 3b and right side upright bar 6b compositions right side on the right side upper beam 2b, right side
Lifting Equipment 4, the left side upper supporting leg is arranged between triangle frame body is climbed in the left side and the right side is climbed triangle frame body in body
1a is set to the upper ends left side upright bar 6a, and supporting leg 5a is set to the lower ends left side upright bar 6a, the right side under the left side
Upper supporting leg 1b is set to the upper ends right side upright bar 6b, and supporting leg 5b is set to the lower ends right side upright bar 6b under the right side.
Triangle frame body is climbed in above left side and right side is climbed, and triangle frame body is alternately climbed by Lifting Equipment 4, to reach
To the purpose climbed certainly, Lifting Equipment 4 is hydraulic test.Its specific connection relation and principle of climbing can be:Hydraulic pressure is climbed certainly
It rises climbing for brill filling platform and promotes the stretching and contracting of oil cylinder lever by adjusting the pressure size of hydraulic oil in hydraulic jacking equipment
It returns, to realize that hydraulic pressure fills climbing mutually for the frame body peace rack body that climbs in platform from climbing to bore.One hydraulic pressure is from the brill that climbs
Fill in platform includes the two sets of frame body that climbs (i.e. two sets of hydraulic jacking equipments:Climb on tripod mounted on two sets), in order to ensure
During climbing, two sets of frame bodies that climb are synchronized and are climbed, and two sets of hydraulic jacking equipments are controlled with individual pumping plant respectively, and uses
The same electric cabinet control, realizes synchronization of frame body during climbing.
Middle cross beam 7 and bottom end rail 8, the left side upper beam 2a, middle cross beam 7 and lower cross are also set up below the upper beam 2a of left side
8 respective one end of beam is connected by the second upright bar 9, and wherein the middle cross beam 7 is also connect with left side upright bar 6a, and wherein the middle cross beam 7 is under
It is also connected by hanging beam 10 between crossbeam 8.
It is also connected by third bearing diagonal 11 between middle cross beam 7 and the hanging beam 10.Left side upper beam 2a, middle cross beam 7 or
Upright bar 12 is gone along with sb. to guard him in setting on bottom end rail 8.
As shown in Fig. 2, Fig. 2 shows the structure according to the upper supporting leg of the utility model one embodiment, left side upper supporting leg
1a and right side upper supporting leg 1b is respectively including outer stay tube 1-4 and the interior stay tube 1-5 that can be stretched in the outer stay tube 1-4.Outside
Hanging ring 1-3 is set on stay tube 1-4.Interior stay tube 1-5 is connect with support base 1-1, and the outer stay tube 1-4 is connect with adjusting screw 1-2.
With this configuration, it can be achieved that angular adjustment.
In conjunction with the structure that above example provides, its Construction Principle is made further describing below:
The assembly of frame body is carried out according to design in the place of setting, at least two list Pin framves are assembled, between each component of frame body
Connection is connected with axis pin with bolt, and axis pin connection is the angle of inclination in order to effectively adjust frame body and ensures operating platform
Smooth, the close connection being bolted between can ensureing particular elements.
The frame body that assembly is completed is lifted on corresponding structural plane with the lifting means at scene, utilizes the anchor pole on rock mass
Frame body is fixed on rock mass structure, every group of frame body there are four Pin to climb tripod, and four Pin climb tripod under Construction State
All it is fixed together with rock mass.
The adjusting of frame body is carried out by the upper supporting leg of frame body upper end, ensures that frame body is effectively attached on rock mass structure, and
And ensure the smooth of platform, so that platform is can be used normally, adjusting the lead screw of upper supporting leg makes interior stay tube extend and retract adjusting bracket
The angle of inclination of body does not influence the flatness of platform because being connect with axis pin between platform.
After completing current construction section, climbing for frame body is completed by the cooperation of two sets of tripods that climb, because frame body is included
Power Lifting Equipment can be completed and climb without the auxiliary of other lifting means, when climbing first by two Pin climb tripod with
Structure, which releases, fixes, and is promoted next construction location using included hydraulic jacking equipment, and carry out the anchor with rock mass
Gu then promoting other two Pin in the same way climbs tripod to complete the automatic climbing of operation platform.
The operating procedure of the utility model:
(1) using the given bolthole of design as the hanging point of erection of frames, the work of individually embedded embedded part is saved;
(2) angle of inclination that frame body is adjusted by the supporting leg that frame body upper end is arranged, because being to pass through axis pin between shelf component
Connection, does not influence the flatness of platform when adjusting frame body gradient;
(3) after completing to construct, frame body is carried out using the hydraulic climbing power-equipment that fits through of two sets of frame bodies that climb
It climbs.
In conclusion the utility model has:1) scaffold phosphor bodies provide effective operating platform for construction, can be with
Stack a small amount of material;2) hydraulic climbing power-equipment effectively realizes the automatic climbing and angular adjustment of frame body, makes frame body
It effectively seeks connections on rock mass surface, reduces the use of live lifting means, artificial input amount is small, is effectively reduced safety
Hidden danger;3) operating platform can automatically adjust, and the flatness of operating platform will not be influenced because of the variation at frame body angle of inclination.
" one embodiment " for being spoken of in the present specification, " another embodiment ", " embodiment ", etc., refer to tying
Specific features, structure or the feature for closing embodiment description are included at least one embodiment of the application generality description
In.It is not centainly to refer to the same embodiment that statement of the same race, which occur, in multiple places in the description.Appoint furthermore, it is understood that combining
When one embodiment describes a specific features, structure or feature, to be advocated be realized in conjunction with other embodiment it is this
Feature, structure or feature are also fallen in the scope of the utility model.
Although reference be made herein to the utility model is described in multiple explanatory embodiments of the utility model, still,
It should be understood that those skilled in the art can be designed that a lot of other modification and implementations, these modifications and implementations
It will fall within scope and spirit disclosed in the present application.More specifically, it is disclosed and the scope of the claims in the application
It is interior, a variety of variations and modifications can be carried out to the building block and/or layout of theme combination layout.In addition to building block and/
Or outside the variations and modifications of layout progress, to those skilled in the art, other purposes also will be apparent.
Claims (9)
- The construction operation platform 1. a kind of hydraulic pressure climbs certainly, it is characterised in that including single Pin framves, the list Pin framves include being propped up on left side It is leg (1a), right side upper supporting leg (1b), left side upper beam (2a), right side upper beam (2b), bearing diagonal (3a) on left side, oblique on right side Support supporting leg (5b), left side upright bar (6a) and right side upright bar under supporting leg (5a), right side under (3b), Lifting Equipment (4), left side (6b), climb triangle frame body for bearing diagonal (3a) and left side upright bar (6a) composition left side on the left side upper beam (2a), left side, institute State right side upper beam (2b), climb on right side triangle frame body on the right side of bearing diagonal (3b) and right side upright bar (6b) composition, the left side It climbs triangle frame body and the right side is climbed setting Lifting Equipment (4) between triangle frame body, left side upper supporting leg (1a) setting In left side upright bar (6a) upper end, supporting leg (5a) is set to left side upright bar (6a) lower end, the right side under the left side Upper supporting leg (1b) is set to right side upright bar (6b) upper end, and supporting leg (5b) is set to the right side upright bar (6b) under the right side Lower end.
- The construction operation platform 2. hydraulic pressure according to claim 1 climbs certainly, it is characterised in that the left side upper beam (2a) Lower section also sets up middle cross beam (7) and bottom end rail (8), and the left side upper beam (2a), middle cross beam (7) and bottom end rail (8) are respective One end is connected by the second upright bar (9), and wherein the middle cross beam (7) is also connect with left side upright bar (6a), wherein the middle cross beam (7) and lower cross It is also connected by hanging beam (10) between beam (8).
- 3. hydraulic pressure according to claim 2 is from climbing construction operation platform, it is characterised in that wherein the middle cross beam (7) with it is described It is also connected by third bearing diagonal (11) between hanging beam (10).
- The construction operation platform 4. hydraulic pressure according to claim 2 climbs certainly, it is characterised in that wherein the middle cross beam (7) or lower cross Upright bar (12) is gone along with sb. to guard him in setting on beam (8).
- The construction operation platform 5. hydraulic pressure according to claim 1 climbs certainly, it is characterised in that the left side upper beam (2a) Upright bar (12) is gone along with sb. to guard him in upper setting.
- The construction operation platform 6. hydraulic pressure according to claim 1 climbs certainly, it is characterised in that the left side upper supporting leg (1a) Interior stay tube (the 1- that includes respectively outer stay tube (1-4) with right side upper supporting leg (1b) and can stretch in the outer stay tube (1-4) 5)。
- The construction operation platform 7. hydraulic pressure according to claim 6 climbs certainly, it is characterised in that set on the outer stay tube (1-4) Set hanging ring (1-3).
- The construction operation platform 8. hydraulic pressure according to claim 6 climbs certainly, it is characterised in that the interior stay tube (1-5) and branch It supports seat (1-1) to connect, the outer stay tube (1-4) connect with adjusting screw (1-2).
- The construction operation platform 9. hydraulic pressure according to claim 6 climbs certainly, it is characterised in that at least two list Pin framves pass through spiral shell Bolt and axis pin are assembled into construction operation platform.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721688481.5U CN207609155U (en) | 2017-12-07 | 2017-12-07 | Hydraulic pressure is from climbing construction operation platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201721688481.5U CN207609155U (en) | 2017-12-07 | 2017-12-07 | Hydraulic pressure is from climbing construction operation platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207609155U true CN207609155U (en) | 2018-07-13 |
Family
ID=62797860
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201721688481.5U Active CN207609155U (en) | 2017-12-07 | 2017-12-07 | Hydraulic pressure is from climbing construction operation platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207609155U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111021701A (en) * | 2019-12-18 | 2020-04-17 | 青岛康太源建设集团有限公司 | Lifting system for building |
-
2017
- 2017-12-07 CN CN201721688481.5U patent/CN207609155U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111021701A (en) * | 2019-12-18 | 2020-04-17 | 青岛康太源建设集团有限公司 | Lifting system for building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100707549B1 (en) | Rail mounted climbing system | |
CN105220769B (en) | Large area bolt-ball net frame integral top lifting construction method | |
KR102038877B1 (en) | Pile frame and its installation method | |
CN105836639B (en) | For integrated tower crane and the support meanss and its application method of integrated platform | |
CN104420641A (en) | Extensible lifting construction platform | |
CN104234200B (en) | A kind of suspen-shell structure rope leverage is by ring lifting installation method | |
CN109457951B (en) | Formwork system for collecting and dividing shear wall and construction method thereof | |
CN207609155U (en) | Hydraulic pressure is from climbing construction operation platform | |
KR102059552B1 (en) | Modular work platform of a long span bridge main tower rebar and construction method using the same | |
CN105386604A (en) | High altitude grid structure mounting method | |
CN105442853A (en) | Long-span deformed steel truss and floor steel structure installation and construction method | |
CN206289964U (en) | For the climbing form system of sloping core construction | |
CN106150525A (en) | A kind of rock anchorage beam construction trolley and construction method thereof | |
CN206289963U (en) | For the climbing form system of section Core tube construction | |
JP2015203223A (en) | Height adjustment column for framework scaffold | |
CN206375527U (en) | Attached wall structure for building hoist | |
CN104847108A (en) | Hydraulic climbing formwork structure and construction method of hydraulic climbing formwork structure | |
CN207905333U (en) | Saddle combines Construction of Supporting hoistable platform | |
CN210164205U (en) | Civil engineering safety construction scaffold frame | |
CN205046572U (en) | Bulky concrete removes over -and -under type construction platform | |
CN206616845U (en) | A kind of elevating scaffold corner device for erecting pole | |
CN105064396B (en) | A kind of mass concrete movable up-down operation platform | |
RU123048U1 (en) | FORMWORK | |
CN207392229U (en) | One kind ± 800kV current conversion station DC fields high voltage installation mounting structures | |
CN109469308A (en) | The structure of major diameter group storehouse support platform |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |