CN207566717U - A kind of I-shaped floor steel beam lifting structure - Google Patents

A kind of I-shaped floor steel beam lifting structure Download PDF

Info

Publication number
CN207566717U
CN207566717U CN201721481651.2U CN201721481651U CN207566717U CN 207566717 U CN207566717 U CN 207566717U CN 201721481651 U CN201721481651 U CN 201721481651U CN 207566717 U CN207566717 U CN 207566717U
Authority
CN
China
Prior art keywords
shaped floor
positioning pin
supporting plate
girder steel
plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721481651.2U
Other languages
Chinese (zh)
Inventor
魏成权
莫永红
徐刃
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG INDUSTRIAL EQUIPMENT INSTALLATION Co Ltd
Original Assignee
GUANGDONG INDUSTRIAL EQUIPMENT INSTALLATION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG INDUSTRIAL EQUIPMENT INSTALLATION Co Ltd filed Critical GUANGDONG INDUSTRIAL EQUIPMENT INSTALLATION Co Ltd
Priority to CN201721481651.2U priority Critical patent/CN207566717U/en
Application granted granted Critical
Publication of CN207566717U publication Critical patent/CN207566717U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a kind of I-shaped floor steel beam lifting structures, including I-shaped floor girder steel and special hanger, the technique hole for hoist in a center of symmetry about top flange central point there are two being set at a quarter span of I-shaped floor girder steel top flange, special hanger includes supporting plate and the shackle plate at the upper side of supporting plate, one piece of reinforcing plate is equipped between supporting plate and shackle plate, opposite side above supporting plate is equipped with the positioning pin being connect with technique hole for hoist, and the upper end of positioning pin is equipped with trapezoidal thread and screwed retaining ring.The installation and removal time of Current Collector Sleave can be significantly reduced in hoisting process using this I-shaped floor steel beam lifting structure, and it can guarantee that girder steel is always maintained at level in hoisting process, it is in place convenient for girder steel, greatly speed up lifting progress, in addition, trapezoidal thread on positioning pin and screwed retaining ring are come off from technique hole for hoist with the use of can effectively prevent positioning pin in hoisting process, have achieved the effect that effectively improve lifting efficiency, safe and simple.

Description

A kind of I-shaped floor steel beam lifting structure
Technical field
The utility model is related to structural steelwork installation Technology field, more particularly to a kind of I-shaped floor girder steel is hung Assembling structure.
Background technology
Steel construction has many advantages, such as that light-weight, anti-seismic performance is good, repeatable utilization, shared by recent year construction steel structure Ratio significantly rises.In various configurations, floor beam is largely using I-shaped floor girder steel, and girder steel quantity is more, hoisting steel beam Occupy longer construction period and more large-scale tower crane machine-team.
There are two types of traditional hoisting steel beam methods.
The first hanging method:Using two steel cord ends joining shackles, steel wire rope is bundled in girder steel with shackle At a quarter span, the quadrangle setting flexible material that steel wire rope is contacted with girder steel protects girder steel and steel wire rope;It is adjusted before lifting Whole shackle and the position of steel wire rope binding point, so that horizontality is presented after steel beam lifting;Shackle is removed after in place and flexibility is protected Protect substance.There are following defects for this method:If binding is loosely, steel wire rope is likely to situation about having skidded, and causes lifting accident; If the guarded by location that steel wire rope is contacted with girder steel is bad, the paint and steel wire rope of girder steel will be damaged, cause quality accidents; When steel wire rope is removed after in place, flexible protective substance freely descends slowly and lightly, and is difficult to collect in upper air installing.The hanging method, which exists, to be hung Heavy workload is filled, security-hidden trouble is more, and the occupancy loop wheel machine time is longer, and installation progress is slow.
Second of hanging method:Lifting lug is symmetrically welded in girder steel both ends top flange.Although the hanging method is safe and reliable, Progress is fast, but the transport space of bigger that girder steel occupies after top flange welding lifting lug, conevying efficiency decline;It needs to cut after the completion of lifting Lifting lug is cut, not only wastes steel, also increase additional human weld and cuts off lifting lug work, and destroy girder steel antifouling paint.
The quantity of girder steel is more in general structural steelwork, and the lifting speed of girder steel directly determines entire structural steelwork Construction speed, therefore the security-hidden trouble improved in the lifting speed of girder steel, reduction hoisting process is that current urgent need solves Problem.
Utility model content
Lifting efficiency, safe and reliable I-shaped are effectively improved the technical problem to be solved by the utility model is to provide a kind of Type floor steel beam lifting structure.
Used technical solution to solve above-mentioned technical problem:A kind of I-shaped floor steel beam lifting structure, including work Font floor girder steel and special hanger, it is characterised in that:It is set at a quarter span of the I-shaped floor girder steel top flange There are two the technique hole for hoist in a center of symmetry about top flange central point, the special hanger includes supporting plate and in supporting plate The shackle plate of upper side is equipped with one piece of reinforcing plate between the supporting plate and shackle plate, the opposite side above the supporting plate Equipped with the positioning pin being connect with the technique hole for hoist, the upper end of the positioning pin is equipped with a nut.
Further, the supporting plate and the shackle plate are orthogonal.
Further, the reinforcing plate is arranged on side of the shackle plate far from the positioning pin.
Further, the upper end of the positioning pin is processed to trapezoidal thread and nut cooperation.
Further, the nut is screwed retaining ring.
Advantageous effect:It is convenient and efficient using this I-shaped floor steel beam lifting structure, only it need to will connect shackle Positioning pin on special hanger installs screwed retaining ring after passing through the technique hole for hoist on I-shaped floor girder steel, is lifting The installation and removal time of Current Collector Sleave is considerably reduced in journey, and can guarantee that girder steel is always maintained at level in hoisting process, just It is in place in girder steel, lifting progress is greatly accelerated, in addition, the trapezoidal thread on positioning pin and screwed retaining ring are with the use of can be effective It prevents positioning pin from coming off in hoisting process from technique hole for hoist, has reached and effectively improved lifting efficiency, safe and simple effect Fruit.
Description of the drawings
The utility model is described further with reference to the accompanying drawings and examples:
Fig. 1 is the positive elevational schematic view of the utility model embodiment;
Fig. 2 is the side elevation schematic diagram of the utility model embodiment;
Fig. 3 is the side elevation schematic diagram of I-shaped floor steel beam lifting in the utility model embodiment;
Fig. 4 is the plane signal that I-shaped floor girder steel top flange sets technique hole for hoist in the utility model embodiment Figure;
Fig. 5 is the positive elevational schematic view of I-shaped floor steel beam lifting in the utility model embodiment.
Specific embodiment
Referring to figs. 1 to Fig. 4, a kind of I-shaped floor steel beam lifting structure of the utility model, including special hanger 10 and work Font floor girder steel 20, special hanger 10 include supporting plate 11 and the shackle plate 12 of side, supporting plate 11 are put on supporting plate 11 The opposite side of top is equipped with the positioning pin 13 being connect with I-shaped floor girder steel 20, in the side of 12 remotely located pin 13 of shackle plate Equipped with one piece of reinforcing plate 15 to strengthen the connection between supporting plate 11 and shackle plate 12, the upper part of positioning pin 13 is processed to Trapezoidal thread coordinates with screwed retaining ring 14.Set at a quarter span of I-shaped 20 top flange of floor girder steel there are two about Top flange central point technique hole for hoist 21 in a center of symmetry.
Preferably, special hanger 10 is by supporting plate 11, shackle plate 12, positioning pin 13 and strengthens for one kind as the utility model Plate 15 is welded to form, and material is Q345B.The thickness of supporting plate 11 and shackle plate 12 is set as 20mm, the diameter of positioning pin 13 It is set as 20mm.
One kind as the utility model is preferred, in steel construction Deepen Design, in I-shaped 20 top flange of floor girder steel A quarter span at design two technique holes for hoist 21 in a center of symmetry about top flange central point, technique hole for hoist 21 Diameter be set as 22mm, hole center to the outer peripheral distance of steel beam flange is 50mm.According to Deepen Design drawing, processed in workshop Manufacture craft hole for hoist 21 together during I-shaped floor girder steel 20.
With reference to Fig. 3 and Fig. 5, the end of the lifting steel wire rope 40 of two equal lengths is connect respectively with two shackles 30, Shackle 30 passes through the hole on shackle plate 12 to be connect with special hanger 10.The positioning pin 13 of special hanger 10 is from I-shaped floor girder steel Technique hole for hoist 21 is penetrated below 20 top flange, screwed retaining ring 14 is installed, in trapezoidal thread and screwed retaining ring 14 with cooperation Under, the connection between special hanger 10 and I-shaped floor girder steel 20 is very secured.After completing above-mentioned steps, crane can rise It hangs, due to the equal length of two lifting steel wire ropes 40 and two technique holes for hoist 21 are in a center of symmetry about top flange center, Therefore two 40 uniform forces of steel wire rope and ensure that I-shaped floor girder steel 20 can be always maintained at level in hoisting process.By work Font floor girder steel 20 is hung to installation site, treats that its fixation first can remove screwed retaining ring 14, under the suspension hook of crane rearward Drop, at the same time, special hanger 10 is detached with I-shaped floor girder steel 20, completes lifting operation.
The embodiment of the utility model is explained in detail above in conjunction with attached drawing, but the utility model is not limited to Embodiment is stated, in the knowledge having in the technical field those of ordinary skill, this practicality can also not departed from Various changes can be made under the premise of novel objective.

Claims (5)

1. a kind of I-shaped floor steel beam lifting structure, including I-shaped floor girder steel and special hanger, it is characterised in that:It is described It is in a center of symmetry about top flange central point there are two being set at a quarter span of I-shaped floor girder steel (20) top flange Technique hole for hoist (21), the special hanger include supporting plate (11) and the shackle plate (12) at the upper side of supporting plate (11), One piece of reinforcing plate (15) is equipped between the supporting plate (11) and shackle plate (12), the opposite side above the supporting plate (11) is set There is the positioning pin (13) being connect with the technique hole for hoist (21), the upper end of the positioning pin (13) is provided with a nut (14).
2. I-shaped floor steel beam lifting structure according to claim 1, it is characterised in that:The supporting plate (11) and institute It is orthogonal to state shackle plate (12).
3. I-shaped floor steel beam lifting structure according to claim 1, it is characterised in that:Reinforcing plate (15) setting In side of the shackle plate (12) far from the positioning pin (13).
4. I-shaped floor steel beam lifting structure according to claim 1, it is characterised in that:The positioning pin (13) it is upper End is processed to trapezoidal thread and coordinates with the nut (14).
5. I-shaped floor steel beam lifting structure according to claim 4, it is characterised in that:The nut (14) is anticreep Nut.
CN201721481651.2U 2017-11-08 2017-11-08 A kind of I-shaped floor steel beam lifting structure Active CN207566717U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721481651.2U CN207566717U (en) 2017-11-08 2017-11-08 A kind of I-shaped floor steel beam lifting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721481651.2U CN207566717U (en) 2017-11-08 2017-11-08 A kind of I-shaped floor steel beam lifting structure

Publications (1)

Publication Number Publication Date
CN207566717U true CN207566717U (en) 2018-07-03

Family

ID=62694113

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721481651.2U Active CN207566717U (en) 2017-11-08 2017-11-08 A kind of I-shaped floor steel beam lifting structure

Country Status (1)

Country Link
CN (1) CN207566717U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978867A (en) * 2018-08-24 2018-12-11 浙江远大钢构实业有限公司 A kind of steel beam lifting structure
CN110552504A (en) * 2019-06-28 2019-12-10 中冶(上海)钢结构科技有限公司 rapid installation device and construction method for welding-free lifting lug of H-shaped steel beam
CN112252736A (en) * 2020-09-25 2021-01-22 中建新疆建工集团第五建筑工程有限公司 Assembled steel beam hoisting device

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108978867A (en) * 2018-08-24 2018-12-11 浙江远大钢构实业有限公司 A kind of steel beam lifting structure
CN110552504A (en) * 2019-06-28 2019-12-10 中冶(上海)钢结构科技有限公司 rapid installation device and construction method for welding-free lifting lug of H-shaped steel beam
CN112252736A (en) * 2020-09-25 2021-01-22 中建新疆建工集团第五建筑工程有限公司 Assembled steel beam hoisting device
CN112252736B (en) * 2020-09-25 2022-04-01 中建新疆建工集团第五建筑工程有限公司 Assembled steel beam hoisting device

Similar Documents

Publication Publication Date Title
CN207566717U (en) A kind of I-shaped floor steel beam lifting structure
CN202346637U (en) Holding rod of double-flat-arm spinning self-lifting seat
CN101966965A (en) Special hanger with guide cover wheel hub and turning and hanging method
CN201419967Y (en) Sling for large-scale components
CN102900021A (en) Split mounting type bridge wet joint construction method
CN204342257U (en) A kind of large-scale component turning device
CN201703776U (en) Inverted lifting device of storage tank
CN106049896A (en) Dismantling method for resisting impact load in high-altitude overhanging steel-structure-platform dismantling process
CN205603986U (en) Railway hangs pillow ware fast
CN205034985U (en) Tower crane lifting hook anti -falling device
CN209923970U (en) Bailey beam fixing device for suspension pipeline
CN203546619U (en) Horizontal type simple cable unreeling disc for bridge construction
CN203497919U (en) Integral lifting device of helicopter platform
CN203667822U (en) Pipe truss for hoisting
CN203582268U (en) Clamp for unloading front-section column of steel structure on site
CN202704797U (en) Hoisting device of guide wheel
CN108163713B (en) Simple box-shaped component turning-over device and method
CN202185847U (en) Overturning fixture for box type beams
CN201857225U (en) Hoisting device for bridge crane frame
CN201619944U (en) Sling instrument
CN212687323U (en) Hoisting system for hoisting converter vaporization cooling system equipment
CN101734549A (en) Lifting sling
CN206693730U (en) Composite construction formula power transmission tower
CN202561404U (en) Hoisting device
CN213245216U (en) Steel pipe hoisting accessory

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant