CN207331389U - A kind of composite road bed structure of corrugated steel pipe and rubble - Google Patents

A kind of composite road bed structure of corrugated steel pipe and rubble Download PDF

Info

Publication number
CN207331389U
CN207331389U CN201621462776.6U CN201621462776U CN207331389U CN 207331389 U CN207331389 U CN 207331389U CN 201621462776 U CN201621462776 U CN 201621462776U CN 207331389 U CN207331389 U CN 207331389U
Authority
CN
China
Prior art keywords
ventilation duct
metalling
rubble
steel pipe
utility
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621462776.6U
Other languages
Chinese (zh)
Inventor
刘戈
汪双杰
张会建
董元宏
李金平
符进
穆柯
彭惠
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Highway Consultants Co Ltd
Original Assignee
CCCC First Highway Consultants Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Highway Consultants Co Ltd filed Critical CCCC First Highway Consultants Co Ltd
Priority to CN201621462776.6U priority Critical patent/CN207331389U/en
Application granted granted Critical
Publication of CN207331389U publication Critical patent/CN207331389U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

It the utility model is related to a kind of composite road bed structure of corrugated steel pipe and rubble.Currently used ventilation duct is reinforced concrete structure, and cost is high, from great, long construction period, causes do not have extensive use in Permafrost Area.The utility model includes roadbed and pavement structure from bottom to top;Roadbed is metalling, sets horizontal ripple ventilation duct in metalling along line direction, and ripple ventilation tube end stretches out metalling from both sides;Ripple ventilation duct is made of more piece tube coupling, is fixed by flange and bolt splicing.The utility model makes up the low deficiency of ventilation duct heat transfer efficiency using Gravel road base, available for complicated geological environments such as high temperature, hight-ice-content permafrosts, can significantly reduce the temperature for the ever-frozen ground that underlies, show that its actively protects the strong convection effect of ever-frozen ground.

Description

A kind of composite road bed structure of corrugated steel pipe and rubble
Technical field
It the utility model is related to a kind of new-type embankment structure, and in particular to a kind of composite road base junction of corrugated steel pipe and rubble Structure.
Background technology
Ventilation pipe foundation is regulation measure more commonly used in the highway engineering of Permafrost Area, ventilation pipe foundation can directly by Cool ambient air is imported in roadbed body, compared to the temperature that common roadbed can further reduce the ever-frozen ground that underlies.But due to current Used ventilation duct is reinforced concrete structure, and cost is high, from great, long construction period, causes not having in Permafrost Area Extensive use, therefore, is tested by live entity project, ventilation duct can be used metal bellows structure.
Among the construction of Permafrost Area highway integral subgrade, since ventilation duct is to utilize air convection current in pipe Heat transfer occurs with tube wall, so as to influence the temperature field of tube wall and surrounding soil, cause its actual heat transfer efficiency be not it is too high, It is difficult to effectively solve the problems, such as the highly endothermic of wide cut bituminous paving, during exclusive use, cool down in high temperature hight-ice-content permafrost section and imitate Fruit is not fairly obvious.
The current spacing of ventilation pipe foundation is 2m, can only be tamped among construction using small-sized hydraulic, complex process and It is less efficient, it is unfavorable in a wide range of interior popularization and application.
The content of the invention
The purpose of this utility model is to provide a kind of composite road bed structure of corrugated steel pipe and rubble, by metal bellows and Gravel road base use for composite, actively protects the strong convection effect of ever-frozen ground.
Technical solution is used by the utility model:
A kind of composite road bed structure of corrugated steel pipe and rubble, it is characterised in that:
Include roadbed and pavement structure from bottom to top;
Roadbed is metalling, sets horizontal ripple ventilation duct in metalling along line direction, ripple divulge information tube end from Metalling is stretched out in both sides;
Ripple ventilation duct is made of more piece tube coupling, is fixed by flange and bolt splicing.
Ripple ventilation duct the latter half is transmural structure, has uniform through hole.
Pavement structure includes side trip, runway, hardened verge and earth shoulder from inside to outside, and pavement structure both sides are provided with shield Column.
The utility model has the following advantages:
The utility model makes up the low deficiency of ventilation duct heat transfer efficiency using Gravel road base, available for high temperature, Gao Hanbing The complicated geological environments such as frozen soil are measured, the temperature for the ever-frozen ground that underlies can be significantly reduced, show that its actively protects the strong of ever-frozen ground Convection effects.Simultaneously because ventilation duct is compound with rubble, filled between ventilation duct using rubble, Subgrade Compaction will be protected Barrier.
Brief description of the drawings
Fig. 1 is the utility model cross-sectional view.
In figure, 1- median strips, 2- guardrails, 3- metallings, 4- ripple ventilation ducts.
Embodiment
The utility model is described in detail with reference to embodiment.
The composite road bed structure of a kind of corrugated steel pipe and rubble that the utility model is related to, from bottom to top including roadbed and road Face structure.Pavement structure includes side trip, runway, hardened verge and earth shoulder from inside to outside, and the gradient is 2% and 3% from inside to outside. Pavement structure both sides are provided with guardrail 2.
Roadbed is metalling 3, and horizontal ripple ventilation duct 4,4 end of ripple ventilation duct are set along line direction in metalling 3 Metalling 3 stretches out from both sides in portion.Ripple ventilation duct 4 is made of more piece tube coupling, is fixed by flange and bolt splicing.Ripple is divulged information 4 the latter half of pipe is transmural structure, has uniform through hole.
Crushing technique requirement:Ballast grain sizes are 10~15cm, and floor height is determined according to ice content, and general ice-rich permafrost area uses 1.2 m, full ice permafrost region use 1.5m;
Ventilation duct technical requirements:Ventilation duct uses metal bellows, is laid in metalling, away from earth's surface 20cm, caliber 40cm, to strengthen the convection intensity of Gravel road base, the circular hole of 4 row aperture 5cm, Kong Jian are laid in the latter half of ventilation duct tube coupling Away from 5~10cm, different lines dislocation cloth hole.In frozen soil complicated condition section, bellows can use continuous laying mode.
The Compound Measure of the utility model has the advantages that ventilation pipe foundation strong convection and Gravel road base coverage are wide, and And it is easy to construction and late maintaining, it can meet the construction requirements of Permafrost Area highway wide cut roadbed.
The content of the utility model is not limited to cited by embodiment, and those of ordinary skill in the art are new by reading this practicality Type specification and any equivalent conversion taken technical solutions of the utility model, are the claim institute of the utility model Cover.

Claims (3)

  1. A kind of 1. composite road bed structure of corrugated steel pipe and rubble, it is characterised in that:
    Include roadbed and pavement structure from bottom to top;
    Roadbed is metalling(3), metalling(3)It is interior that horizontal ripple ventilation duct is set along line direction(4), ripple ventilation duct (4)Metalling is stretched out in end from both sides(3);
    Ripple ventilation duct(4)It is made of more piece tube coupling, is fixed by flange and bolt splicing.
  2. 2. the composite road bed structure of a kind of corrugated steel pipe according to claim 1 and rubble, it is characterised in that:
    Ripple ventilation duct(4)The latter half is transmural structure, has uniform through hole.
  3. 3. the composite road bed structure of a kind of corrugated steel pipe according to claim 1 and rubble, it is characterised in that:
    Pavement structure includes side trip, runway, hardened verge and earth shoulder from inside to outside, and pavement structure both sides are provided with guardrail (2).
CN201621462776.6U 2016-12-29 2016-12-29 A kind of composite road bed structure of corrugated steel pipe and rubble Active CN207331389U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621462776.6U CN207331389U (en) 2016-12-29 2016-12-29 A kind of composite road bed structure of corrugated steel pipe and rubble

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621462776.6U CN207331389U (en) 2016-12-29 2016-12-29 A kind of composite road bed structure of corrugated steel pipe and rubble

Publications (1)

Publication Number Publication Date
CN207331389U true CN207331389U (en) 2018-05-08

Family

ID=62374558

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621462776.6U Active CN207331389U (en) 2016-12-29 2016-12-29 A kind of composite road bed structure of corrugated steel pipe and rubble

Country Status (1)

Country Link
CN (1) CN207331389U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111733650A (en) * 2020-04-22 2020-10-02 青海路拓工程设施制造集团有限公司 Cooling construction method for corrugated steel pipe of frozen soil roadbed
CN112376344A (en) * 2020-10-29 2021-02-19 东南大学 Double-layer continuous reinforced concrete hollow slab concrete pavement composite structure for permafrost region and construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111733650A (en) * 2020-04-22 2020-10-02 青海路拓工程设施制造集团有限公司 Cooling construction method for corrugated steel pipe of frozen soil roadbed
CN112376344A (en) * 2020-10-29 2021-02-19 东南大学 Double-layer continuous reinforced concrete hollow slab concrete pavement composite structure for permafrost region and construction method

Similar Documents

Publication Publication Date Title
CN106801417B (en) Tunnel Passing structures steel pipe isolation pile stratum consolidation system and its construction method
CN104153269B (en) Ever-frozen ground guard method under a kind of wide cut road structure leading resistance combination
Chen Research on combined construction technology for cross-subway tunnels in underground spaces
CN103696376A (en) Concrete foundation-free highway culvert for permafrost region
CN104313967B (en) Row's water-seepage type is mated formation combining structure
CN207331389U (en) A kind of composite road bed structure of corrugated steel pipe and rubble
CN108193575A (en) The anti-freeze expansion structure and its paving method of seasonal frozen soil region roadbed
Qian et al. Analysis on the convection cooling process of crushed-rock embankment of high-grade highway in permafrost regions
CN108755284A (en) Reduce the railway bed structure of subgrade settlement deformation to lacing wire material U-type groove
CN107938480A (en) A kind of microorganism cures the desert highway embankment and its construction method of joint TGXG
CN204608547U (en) A kind of Permafrost Area is for spreading the ventilation curb of flexible pavement heat
Qian et al. Analysis of asymmetric temperature fields for the duct-ventilated embankment of highway in permafrost regions
CN206034218U (en) Hot pin compound road bed of block stone layer cooling
CN207176700U (en) A kind of solid matter perfusion inner support of pile foundation ditch permanent support structure under complex environment
CN107034756A (en) A kind of frozen earth roadbed structure of natural convection ventilation pipe
CN205557219U (en) Full wall ventilation formula frozen soil ventilation embankment structure
CN205557218U (en) Full wall ventilation formula frozen soil ventilation embankment structure of convection current regulation and control
CN106676988A (en) Construction method for permeable wall type ventiduct roadbed
CN109487793A (en) Inner support of pile foundation pit permanent support structure is perfused in a kind of solid matter under complex environment
CN207003157U (en) A kind of roadbed material of energy saving and environment friendly highway
CN207376648U (en) One kind is used for novel energy underground pipe gallery structure
CN207828722U (en) A kind of protection structure for crossing over karez suitable for Xinjiang region roadbed
CN205529732U (en) Sand seal layer is in bags woven to desert road bed
CN206298896U (en) A kind of Tunnel Passing structures steel pipe isolation pile stratum consolidation system
CN105525551B (en) Transformation method for temporary construction road of wind power field and grass planting pavement structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant