CN207260142U - A kind of prestress anchorage cable is from anchor device - Google Patents

A kind of prestress anchorage cable is from anchor device Download PDF

Info

Publication number
CN207260142U
CN207260142U CN201721144889.6U CN201721144889U CN207260142U CN 207260142 U CN207260142 U CN 207260142U CN 201721144889 U CN201721144889 U CN 201721144889U CN 207260142 U CN207260142 U CN 207260142U
Authority
CN
China
Prior art keywords
shape
billet
anchorage
steel plate
saddle
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721144889.6U
Other languages
Chinese (zh)
Inventor
张恩祥
龙照
张森安
何腊平
曹程明
李小伟
孙志虎
刘志刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Gansu Zhongjian Municipal Engineering Survey Design And Research Institute
Gansu CSCEC Municipal Engineering Investigation and Design Institute Co Ltd
Original Assignee
Gansu Zhongjian Municipal Engineering Survey Design And Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Gansu Zhongjian Municipal Engineering Survey Design And Research Institute filed Critical Gansu Zhongjian Municipal Engineering Survey Design And Research Institute
Priority to CN201721144889.6U priority Critical patent/CN207260142U/en
Application granted granted Critical
Publication of CN207260142U publication Critical patent/CN207260142U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

A kind of prestress anchorage cable be the utility model is related to from anchor device, including two blocks of shape of a saddle steel plates placed with a determining deviation Parallel Symmetric, the second circular aperture is respectively equipped with four angles of shape of a saddle steel plate, steel connecting rod is equipped with second circular aperture, the both ends of steel connecting rod are connected with two blocks of shape of a saddle steel plates respectively, shape of a saddle steel plate is respectively equipped with billet against the two sides of bottom surface, the lower surface of billet and the side of shape of a saddle steel plate are connected, the upper surface of billet is equipped with anchorage, anchorage center is aligned with the first circular aperture center of circle on billet, the upper surface of anchorage is affixed with billet outer surface;The anchor cable of two diagonal cross is equipped with space between shape of a saddle steel plate, one end of anchor cable is connected after the first circular aperture on billet is pierced by with anchorage, and the other end is anchored among the soil body.The utility model size is small, makes simply, and installation is quick, detachably and reuses, can realize standardization, streamlined operation, highly practical, is worthy to be popularized.

Description

A kind of prestress anchorage cable is from anchor device
Technical field
The utility model belongs to foundation pit or slope excavating impermanency support engineering field, and in particular to a kind of prestressed anchor Rope is from anchor device.
Background technology
In foundation pit or the construction of slope excavating impermanency support engineering, stake-anchor support system is widely used.In general, stake When spacing is smaller, the same height between adjacent two support pile stakes sets an anchor cable to provide enough pulling force;Stake spacing compared with When big, with height two anchor cables need to be set to provide enough pulling force in the both sides of every support pile.The company of anchor cable and support pile Connection device is generally made of waist rail and anchorage, specifically using rest of the waist rail as anchorage for being arranged at support pile side, is opened After drawing anchor cable, anchorage cable anchoring power is passed to adjacent two support piles by anchorage through waist rail, with soil pressure suffered by this balance supporting stake. Because waist rail Path of Force Transfer is clear, it has been widely used at present, common waist rail has cast-in-situ steel reinforced concrete waist rail and steel welding Assembled two kinds of waist rail is connect, wherein cast-in-situ steel reinforced concrete waist rail rigidity is big, and small, prestressd anchor cable is deformed under anchor cable pulling force effect Lose small, support pile displacement at pile top is controlled, the shortcomings that it is maximum is that formwork takes and needs certain concrete curing time Anchorage cable stretching can be carried out, is had a great influence to foundation pit or side slope entirety excavation construction speed;The assembled waist rail installation of shaped steel welding is applied Work speed is relatively fast, but the drawback is that rigidity is relatively small, torsional deformation is also easy to produce under anchor cable pulling force effect, and anchor cable in advance should Power loss is larger, is also unfavorable for the control of support pile displacement at pile top.In addition, generally masterpiece is concentrated by multiple span centres when waist rail designs Multispan simply supported beam under is calculated, when support pile stake spacing (girder span) is larger, waist rail institute bending moment is larger, deformation compared with Greatly, meet that the required waist rail sectional dimension of safety is also corresponding larger, and then cause the increasing of waist rail operation side, installation difficulty to carry High, project cost increase.
Utility model content
In view of this, the utility model provides a kind of prestress anchorage cable from anchor device, of the prior art to solve Deficiency.
The technical solution of the utility model is:A kind of prestress anchorage cable is from anchor device, including two pieces parallel with a determining deviation Symmetrically placed shape of a saddle steel plate, is respectively arranged with the second circular aperture on four angles of the shape of a saddle steel plate, and described Steel connecting rod is provided with two circular apertures, the both ends of the steel connecting rod are connected with two blocks of shape of a saddle steel plates respectively, the shape of a saddle Steel plate is respectively arranged with billet against the two sides of bottom surface, and the lower surface and the side of shape of a saddle steel plate of the billet are consolidated Even, the upper surface of the billet is provided with anchorage, and the anchorage center is aligned with the first circular aperture center of circle on billet, The upper surface of anchorage is affixed with billet outer surface;Two diagonal cross are provided with space between the shape of a saddle steel plate Anchor cable, one end of the anchor cable are connected after the first circular aperture on billet is pierced by with anchorage, and the other end is anchored in the soil body Among.
Compared with prior art, a kind of prestress anchorage cable provided by the utility model is from the beneficial effect of anchor device:
1st, a kind of prestress anchorage cable provided by the utility model makes full use of the big spy of support pile pile body stiffness from anchor device Point, anchorage force of pre-stressed anchor cable is directly acted on supporting stake body, make support pile stake spacing it is larger, need every supporting When the both sides of stake set two anchor cables with height, without setting waist rail, Path of Force Transfer is definitely, intuitively.
2nd, the whole of the utility model is connected reliably from anchor device with support pile, avoid because waist rail deformation and caused by anchor Rope loss of prestress, rigidity is big, can more effectively control support pile displacement at pile top.
3rd, the utility model is all process using steel, and size is smaller, is made simply, and installation is quick, and construction is completed After can be dismantled and reused, can realize standardization, streamlined operation.
Brief description of the drawings
Fig. 1 is the overlooking the structure diagram of the utility model;
Fig. 2 is the positive structure diagram of the utility model;
Fig. 3 is shape of a saddle steel plate schematic diagram;
Fig. 4 is billet schematic diagram;
The overlooking structure figure for stake-anchor support system that Fig. 5 is applicable in by the utility model;
The main structure figure for stake-anchor support system that Fig. 6 is applicable in by the utility model.
Description of reference numerals:
1st, the first shape of a saddle steel plate;2nd, the second shape of a saddle steel plate;3rd, the first steel connecting rod;4th, the second steel connecting rod;5th, the 3rd steel Connecting rod;6th, the 4th steel connecting rod;7th, support pile;8th, the first anchor cable;9th, the second anchor cable;10th, the first billet;11st, the second billet; 12nd, the first anchorage;13rd, the second anchorage;14th, prestress anchorage cable is from anchor device;15th, stake top Guan Liang;16th, the first circular aperture;17、 Second circular aperture.
Embodiment
The utility model provides a kind of prestress anchorage cable from anchor device, with reference to the structure diagram of Fig. 1~Fig. 6, The utility model is illustrated.
A kind of prestress anchorage cable provided by the utility model is placed from anchor device, including two pieces with a determining deviation Parallel Symmetric Shape of a saddle steel plate, be respectively arranged with the second circular aperture, second round hole on four angles of the shape of a saddle steel plate Intraocular is provided with steel connecting rod, and the both ends of the steel connecting rod are connected with two blocks of shape of a saddle steel plates respectively, and the shape of a saddle steel plate abuts The two sides of bottom surface are respectively arranged with billet, and the lower surface and the side of shape of a saddle steel plate of the billet are connected, the steel The upper surface of backing plate is provided with anchorage, and the anchorage center is aligned with the first circular aperture center of circle on billet, anchorage it is upper Surface is affixed with billet outer surface;The anchor cable of two diagonal cross, institute are provided with space between the shape of a saddle steel plate The one end for stating anchor cable is connected after the first circular aperture on billet is pierced by with anchorage, and the other end is anchored among the soil body.
As shown in Figure 1, Figure 2 and Figure 3, the utility model includes the first shape of a saddle steel plate 1 and the second shape of a saddle steel plate 2, the One shape of a saddle steel plate 1 is identical with the shape of the second shape of a saddle steel plate 2, and the four of the first shape of a saddle steel plate 1 and the second shape of a saddle steel plate 2 The second circular aperture 17 is offered on a angle respectively, is disposed with the first steel connecting rod 3 in second circular aperture 17, second Steel connecting rod 4, the 3rd steel connecting rod 5 and the 4th steel connecting rod 6, the first steel connecting rod 3, the second steel connecting rod 4, the 3rd steel connecting rod 5 and The both ends of four steel connecting rods 6 are connected with the first shape of a saddle steel plate 1 and the second shape of a saddle steel plate 2 respectively in a welding manner, and described One shape of a saddle steel plate 1 and the second shape of a saddle steel plate 2 are respectively welded the first billet 10 and second on the two sides of bottom surface Billet 11, is provided with the first anchorage 12 on the first billet 10, is provided with the second anchorage 13 on the second billet 11, and described The center of one anchorage 12 and the second anchorage 13 respectively with the first circular aperture 16 on the first billet 10 and the second billet 11 Center of circle alignment, the upper surface of the first anchorage 12 and the second anchorage 13 is outer with the first billet 10 and the second billet 11 respectively Surface is affixed;The first anchor cable 8 and the second anchor cable 9 of diagonal cross are provided with space between two blocks of shape of a saddle steel plates, it is described The first circular aperture 16 on one end the first billet 10 and the second billet 11 of first anchor cable 8 and the second anchor cable 9 is pierced by It is connected respectively with the first anchorage 12 and the second anchorage 13 afterwards, the other end is anchored among the soil body respectively.
The utility model includes two blocks of shape of a saddle steel plates, four steel connecting rods and two pieces of billets, two blocks of shape of a saddle steel Parallel Symmetric is set plate at a certain distance, and four steel connecting rods are divided into symmetrical four Angle Positions of two blocks of shape of a saddle steel plates, two pieces Billet respectively symmetrically, is vertically close to the both sides of two blocks of shape of a saddle steel plates, and four steel connecting rods and two pieces of billets are respectively with two Block shape of a saddle steel plate firm welding, forms a single unit system, and described two blocks of shape of a saddle steel plates, four angle opposite positions are set Aperture second circular aperture 17 bigger compared with steel connecting rod diameter;Four steel connecting rods are respectively also cross two pieces of parallel shapes of a saddle Second circular aperture 17 of steel plate symmetric position, then by every steel connecting rod two end and two blocks of shape of a saddle steel plates in the first round hole Firm welding at eye 16;As shown in figure 4, two pieces of billet centres set the first circular aperture of circle of certain size 16, while two pieces of billets respectively symmetrically, are vertically close to the both sides of two blocks of shape of a saddle steel plates, and firm welding.
The utility model is vertically close to 7 pile body of support pile when mounted, by the recess side of the shape of a saddle steel plate, together When by two adjacent anchor cables of 7 both sides of support pile from the inner space of two blocks of shape of a saddle steel plates and four steel connecting rod institute constituent apparatus And intersect in circular first circular aperture 16 set by two pieces of billet centres and be pierced by, anchor cable circle first among billet Circular aperture 16 is pierced by and then through anchorage;After jack tension anchor cable to desired stretching force, by anchorage self-locking Determine method locking anchor cable;At this time, pulling force suffered by anchor cable is transmitted to billet by anchorage, and billet is transmitted to two pieces of saddle shaped steel again Plate, steel plate are finally transmitted to support pile 7, and two anchor cables being pierced by are same with two anchorages being respectively arranged on the outside of two pieces of billets When tensioning fixation.
As shown in Figure 5 and Figure 6, when carrying out engineering construction, first construction supporting stake 7, then construction stake apical cap beam 15, waits to prop up After fender pile 7 and stake top Guan Liang 15 reach design requirement intensity, earth excavation is to anchor cable absolute altitude certain depth below, anchor of then constructing Rope, after two anchor cables of 7 adjacent both sides of same root support pile reach design requirement intensity, you can using prestress anchorage cable certainly Anchor device 14 is by two anchorage cable anchorings on the pile body of same root support pile 7.
The utility model provide it is a kind of support pile stake spacing it is larger, need to be in same root supporting stake body with highly setting When putting two anchor cables, can preferably control support pile displacement at pile top and time saving material-saving, it is safe and reliable, standardization can be achieved The prestress anchorage cable of construction is highly practical from anchor device, is worthy to be popularized.
Disclosed above is only the preferable specific embodiment of the utility model, and still, the utility model embodiment is not This is confined to, what any those skilled in the art can think change should all fall into the scope of protection of the utility model.

Claims (1)

1. a kind of prestress anchorage cable is from anchor device, it is characterised in that including two pieces of saddles placed with a determining deviation Parallel Symmetric Shape steel plate, is respectively arranged with the second circular aperture on four angles of the shape of a saddle steel plate, is set in second circular aperture Steel connecting rod is equipped with, the both ends of the steel connecting rod are connected with two blocks of shape of a saddle steel plates respectively, and the shape of a saddle steel plate is against bottom surface Two sides are respectively arranged with billet, and the lower surface and the side of shape of a saddle steel plate of the billet are connected, the billet Upper surface is provided with anchorage, and the anchorage center is aligned with the first circular aperture center of circle on billet, the upper surface of anchorage with Billet outer surface is affixed;The anchor cable of two diagonal cross, the anchor cable are provided with space between the shape of a saddle steel plate One end be connected after the first circular aperture on billet is pierced by with anchorage, the other end is anchored among the soil body.
CN201721144889.6U 2017-09-07 2017-09-07 A kind of prestress anchorage cable is from anchor device Expired - Fee Related CN207260142U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721144889.6U CN207260142U (en) 2017-09-07 2017-09-07 A kind of prestress anchorage cable is from anchor device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721144889.6U CN207260142U (en) 2017-09-07 2017-09-07 A kind of prestress anchorage cable is from anchor device

Publications (1)

Publication Number Publication Date
CN207260142U true CN207260142U (en) 2018-04-20

Family

ID=61920320

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721144889.6U Expired - Fee Related CN207260142U (en) 2017-09-07 2017-09-07 A kind of prestress anchorage cable is from anchor device

Country Status (1)

Country Link
CN (1) CN207260142U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109252517A (en) * 2018-10-31 2019-01-22 五冶集团上海有限公司 A kind of anchorage pile anchorage and its application method
CN110984176A (en) * 2019-12-14 2020-04-10 长安大学 Method for safely cutting piles of foundation pit by using support piles to support foundation pit
CN115012426A (en) * 2022-06-13 2022-09-06 山东建材勘察测绘研究院有限公司 Steel pipe pile support and construction method for existing telegraph pole during four-cycle full excavation

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109252517A (en) * 2018-10-31 2019-01-22 五冶集团上海有限公司 A kind of anchorage pile anchorage and its application method
CN110984176A (en) * 2019-12-14 2020-04-10 长安大学 Method for safely cutting piles of foundation pit by using support piles to support foundation pit
CN115012426A (en) * 2022-06-13 2022-09-06 山东建材勘察测绘研究院有限公司 Steel pipe pile support and construction method for existing telegraph pole during four-cycle full excavation
CN115012426B (en) * 2022-06-13 2024-02-13 山东建材勘察测绘研究院有限公司 Steel pipe pile support and construction method for existing telegraph pole during four-week full excavation

Similar Documents

Publication Publication Date Title
CN207260142U (en) A kind of prestress anchorage cable is from anchor device
CN110284535B (en) Vertical load loading device for civil engineering field test
CN203923924U (en) No. 0 section bracket prepressing device
CN101255697A (en) Method for integrally applying prestress to truss-type inner support of deep foundation pit
CN208701729U (en) A kind of offshore wind farm High-Rise Pile Cap Foundation using prefabricated cushion cap
CN102505636A (en) Construction method of No.0 block of continuous rigid frame bridge of double-thin-wall pier
CN107338864A (en) Prefabricated reinforced concrete frame structure node
CN211922337U (en) Bridge jacking underpins device
CN206784392U (en) The horizontal inner supporting body system of deep basal pit assembled combination steel construction
CN203284735U (en) Anti-blocking grouting device for cast-in-place continuous beam vertical prestressing rib metal corrugated pipe
CN109914434A (en) Foundation pit supporting pile top crown beam construction structure
CN109826202A (en) A kind of prefabricated concrete structure for pattern foundation pit supporting structure
CN107023020A (en) Deep basal pit assembled combines the horizontal inner supporting body system of steel construction and its construction method
CN203113226U (en) Formwork support system with towering asymmetric concrete cantilever structure
CN201343705Y (en) Auxiliary device for anchoring rear supporting legs of lower guide beam of bridge-erecting machine
CN212533734U (en) Cable buckle integrated tower
CN114525791A (en) Foundation pit steel support and steel trestle combined system
CN110284534B (en) Horizontal load loading device for civil engineering field test
CN210439163U (en) Diagonal joist supporting structure applicable to assembly and disassembly of continuous beam
CN208023838U (en) A kind of novel Self-resetting energy consumption steel column foot connection structure
CN102444131B (en) Foundation pit support method
CN111576439A (en) Concrete support dismantling prestressed support and construction method thereof
CN111335350A (en) Oppositely clamped prestressed cable-stayed foundation
CN211079895U (en) High pier bent cap does not have cast-in-place structure of support
CN112854542B (en) Steel plate shear wall structure with semi-wrapped concrete combined column and anchoring structure thereof

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180420