CN207092041U - A kind of water conservancy construction retains part flow arrangement with current - Google Patents

A kind of water conservancy construction retains part flow arrangement with current Download PDF

Info

Publication number
CN207092041U
CN207092041U CN201720746225.0U CN201720746225U CN207092041U CN 207092041 U CN207092041 U CN 207092041U CN 201720746225 U CN201720746225 U CN 201720746225U CN 207092041 U CN207092041 U CN 207092041U
Authority
CN
China
Prior art keywords
current
plate
water conservancy
installing plate
conservancy construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720746225.0U
Other languages
Chinese (zh)
Inventor
付玉伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201720746225.0U priority Critical patent/CN207092041U/en
Application granted granted Critical
Publication of CN207092041U publication Critical patent/CN207092041U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of water conservancy construction part flow arrangement is retained with current, including installing plate, the first opening is provided with the installing plate, two columns are installed under the installing plate, mounting base under the column, the first slideway and the second slideway are fixed on the column, the first intercepter plate is inserted in first slideway.The utility model, which can substitute, manually to be discharged water, while can control the size of flow, so as to the loss of rice shoot at anti-waterstop port, and can be illuminated at night, observes current.

Description

A kind of water conservancy construction retains part flow arrangement with current
Technical field
Field of flow control is the utility model is related to, particularly a kind of water conservancy construction retains part flow arrangement with current.
Background technology
Field irrigation often utilizes the water of rivers, by being opened on ground its " ditch ", introduce farmland.Water channel is manually dug Water channel, there are trunk canal, point of branch canal.Trunk canal is typically built up with branch canal with barnacle or cement.
In field irrigation, unfolding mode typically uses soil-burial mode between branch canal and farmland, and so needs Manually excavated, under current scour, breach can be made to become big, trunk canal stabilization can be influenceed for a long time, in consideration of it, to above mentioned problem Furtherd investigate, obtain this case then.
Utility model content
The purpose of this utility model is to solve the above problems, and devises a kind of water conservancy construction current retention shunting dress Put.
To achieve the above object, the utility model provides following technical scheme:A kind of water conservancy construction is retained with current and shunted Device, including installing plate, the first opening is provided with the installing plate, two columns are installed under the installing plate, under the column Mounting base, fixes the first slideway and the second slideway on the column, the first intercepter plate of inserting in first slideway, and described the The second intercepter plate is inserted in two slideways, first support is installed on the installing plate, the first bogie is installed in the first support, Installation first hydraulic cylinder in first bogie, second support is installed on the installing plate, the is installed in the second support Two bogies, second bogie is interior to install second hydraulic cylinder, fixes support column on the installing plate, pacifies on the support column Baffle plate is filled, mounted LED lamp under the baffle plate.
Preferably, the first pushing block is fixed on first intercepter plate, the first hydraulic cylinder drive end connects the first pushing block.
Preferably, the second pushing block is fixed on second intercepter plate, the second hydraulic cylinder drive end connects the second pushing block.
Preferably, a pair of mounting holes are provided with the installing plate, hoisting ring is installed in the mounting hole.
Preferably, the LED is covered with protective cover, and explosion-proof net is fixed outside the protective cover.
Preferably, built-in fitting is fixed under the bottom plate.
Part flow arrangement is retained with current using a kind of water conservancy construction that the technical solution of the utility model makes, the present apparatus can Manually discharged water with substituting, while the size of flow can be controlled, so as to the loss of rice shoot at anti-waterstop port, and black It can be illuminated during night, observe current.
Brief description of the drawings
Fig. 1 is a kind of structural representation of water conservancy construction current retention part flow arrangement described in the utility model;
Fig. 2 is a kind of top view of water conservancy construction current retention part flow arrangement described in the utility model;
Fig. 3 is a kind of side view of water conservancy construction current retention part flow arrangement described in the utility model;
Fig. 4 is a kind of explosion-proof net relevant view of water conservancy construction current retention part flow arrangement described in the utility model;
In figure, 1- installing plates;2- columns;3- bottom plates;The slideways of 4- first;The slideways of 5- second;The intercepter plates of 6- first;7- second Intercepter plate;8- first supports;The bogies of 9- first;10- first hydraulic cylinders;11- second supports;12- second hydraulic cylinders;13- branch Dagger;14- baffle plates;15-LED lamps;The pushing blocks of 16- first;The bogies of 17- second;The pushing blocks of 18- second;19- hoisting rings;20- is protected Cover;21- explosion-proof nets;22- built-in fittings.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the embodiment of the utility model is carried out Clearly and completely describing, it is clear that described embodiment is only the utility model part of the embodiment, rather than whole Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made The every other embodiment obtained, belong to the scope of the utility model protection.
In description of the present utility model, it is to be understood that term " " center ", " longitudinal direction ", " transverse direction ", " on ", " under ", The orientation or position relationship of the instruction such as "front", "rear", "left", "right", " vertical ", " level ", " top ", " bottom ", " interior ", " outer " are Based on orientation shown in the drawings or position relationship, merely to make sub- description the utility model and simplify to describe, rather than instruction Or imply that signified device or element must have specific orientation, with specific azimuth configuration and operation, therefore be not understood that For to limitation of the present utility model.In addition, term " first ", " second " are only used for describing purpose, and it is not intended that instruction or Imply relative importance or the implicit quantity for indicating indicated technical characteristic.Thus, define " first ", " second " is only used In description purpose, and it is not intended that indicating or implying relative importance or implicitly include one or more spy Sign.In description of the present utility model, unless otherwise indicated, " multiple " are meant that two or more.
The utility model provides a kind of water conservancy construction current retention part flow arrangement as Figure 1-4, including installation Plate 1, is provided with the first opening on the installing plate 1, described 1 time two column 2 of installation of installing plate, mounting base 3 under the column, The first slideway 4 and the second slideway 5 are fixed on the column 2, the first intercepter plate 6 is inserted in first slideway 4, described second slides The second intercepter plate 7 is inserted in road 5, first support 8 is installed on the installing plate 1, first bogie is installed in the first support 8 9, first bogie 9 is interior to install first hydraulic cylinder 10, and second support 11, the second support are installed on the installing plate 1 Second bogie 17 is installed on 11, second hydraulic cylinder 12 is installed in second bogie 17, support is fixed on the installing plate 1 Post 13, baffle plate 14, described 14 times mounted LED lamps of baffle plate 15 are installed on the support column 13;Is fixed on first intercepter plate 6 One pushing block 16, the drive end of first hydraulic cylinder 10 connect the first pushing block 16;The second pushing block is fixed on second intercepter plate 7 18, the drive end of second hydraulic cylinder 12 connects the second pushing block 18;A pair of mounting holes, the installation are provided with the installing plate 1 Hoisting ring 19 is installed in hole;The LED 15 is covered with protective cover 20, and explosion-proof net 21 is fixed outside the protective cover 20;The bottom 3 times fixed built-in fittings 22 of plate
When specifically used:The present apparatus, which can substitute, manually to be discharged water, while can control the size of flow, to prevent The loss of rice shoot at the mouth of a river, and can be illuminated at night, observe current.
Embodiment:Programmable Series Controller and 2 relays are installed first at the present apparatus free time, with MAM- Exemplified by 200 controller, by the output end of the model controller by wire respectively with 2 relays and the input of LED Connection, while the magnetic valve that 2 relays are carried with first hydraulic cylinder and second hydraulic cylinder respectively by wire is connected.Ability After domain personnel are by controller programming, the job order of each electrical part of fully controllable system, concrete operating principle is as follows:First will The present apparatus is attached to T-shaped branch canal infall or installation farmland dewatering outlet, to the present apparatus and is fixed, prevented by built-in fitting 22 Only wash away for a long time and cause to tilt, while make bottom plate 3 go to water channel bottom surface horizontal, in use, first in the first bogie 9 of control Hydraulic cylinder 10, the drive end of first hydraulic cylinder 10 are controlled the rise or decline of the first intercepter plate 6 by the first pushing block 16, come Branch canal current are controlled, while start the second hydraulic cylinder 12 in the second bogie 17, the drive end of second hydraulic cylinder 12 passes through second Pushing block 18 is controlled the rise or decline of the second intercepter plate 17, to control current, at night, opens LED 15 and carries out Illumination, allows night intuitively to be controlled, while prevents rainwater from causing to corrode by the protection part of baffle plate 14, specific work Finished as principle demonstration.
Finally it should be noted that:Preferred embodiment of the present utility model is the foregoing is only, is not limited to this Utility model, although the utility model is described in detail with reference to the foregoing embodiments, for those skilled in the art For, it can still modify to the technical scheme described in foregoing embodiments, or to which part technical characteristic Progress equivalent substitution, all within the spirit and principles of the utility model, any modification, equivalent substitution and improvements made etc., It should be included within the scope of protection of the utility model.

Claims (6)

1. a kind of water conservancy construction retains part flow arrangement, including installing plate (1) with current, it is characterised in that on the installing plate (1) The first opening is provided with, two columns (2) are installed under the installing plate (1), mounting base (3) under the column, the column (2) On fix the first slideway (4) and the second slideway (5), the first intercepter plate of inserting (6) in first slideway (4), described second slides The second intercepter plate (7) is inserted in road (5), first support (8) is installed on the installing plate (1), installed on the first support (8) First bogie (9), first bogie (9) is interior to install first hydraulic cylinder (10), and second is installed on the installing plate (1) Frame (11), installs the second bogie (17) on the second support (11), the second hydraulic pressure of installation in second bogie (17) Cylinder (12), support column (13) is fixed on the installing plate (1), baffle plate (14), the baffle plate are installed on the support column (13) (14) mounted LED lamp (15) under.
2. a kind of water conservancy construction according to claim 1 retains part flow arrangement with current, it is characterised in that described first section The first pushing block (16) is fixed in flowing plate (6), first hydraulic cylinder (10) drive end connects the first pushing block (16).
3. a kind of water conservancy construction according to claim 1 retains part flow arrangement with current, it is characterised in that described second section The second pushing block (18) is fixed in flowing plate (7), second hydraulic cylinder (12) drive end connects the second pushing block (18).
4. a kind of water conservancy construction according to claim 1 retains part flow arrangement with current, it is characterised in that the installing plate (1) a pair of mounting holes are provided with, hoisting ring (19) is installed in the mounting hole.
5. a kind of water conservancy construction according to claim 1 retains part flow arrangement with current, it is characterised in that the LED (15) protective cover (20) is covered with, the protective cover (20) fixes explosion-proof net (21) outside.
6. a kind of water conservancy construction according to claim 1 retains part flow arrangement with current, it is characterised in that the bottom plate (3) built-in fitting (22) is fixed under.
CN201720746225.0U 2017-06-23 2017-06-23 A kind of water conservancy construction retains part flow arrangement with current Expired - Fee Related CN207092041U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720746225.0U CN207092041U (en) 2017-06-23 2017-06-23 A kind of water conservancy construction retains part flow arrangement with current

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720746225.0U CN207092041U (en) 2017-06-23 2017-06-23 A kind of water conservancy construction retains part flow arrangement with current

Publications (1)

Publication Number Publication Date
CN207092041U true CN207092041U (en) 2018-03-13

Family

ID=61554252

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720746225.0U Expired - Fee Related CN207092041U (en) 2017-06-23 2017-06-23 A kind of water conservancy construction retains part flow arrangement with current

Country Status (1)

Country Link
CN (1) CN207092041U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112900387A (en) * 2021-01-12 2021-06-04 夏正一 Anticreep formula water conservancy interception device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112900387A (en) * 2021-01-12 2021-06-04 夏正一 Anticreep formula water conservancy interception device

Similar Documents

Publication Publication Date Title
CN208219587U (en) It is a kind of for intercept in hydraulic facility hang floating material clear fishing device
CN207092041U (en) A kind of water conservancy construction retains part flow arrangement with current
CN109898465A (en) A kind of construction of hydro project baffle device for water
CN107226559A (en) A kind of artificial Lake Water Body bascule and its construction method
CN109056879A (en) A kind of riverway sludge cleaning plant and construction method
CN206052744U (en) A kind of highway bridge construction cofferdam device
CN204919607U (en) City is prefab for underpass
CN207074836U (en) A kind of building chase
CN103055555A (en) Air distribution system of filter
CN107187369A (en) A kind of flood control and drainage car of speedily carrying out rescue work with automatic control function
CN110984300A (en) Anti-seepage anti-extrusion integrated pump station device
CN110273434A (en) A kind of building site, which is faced, builds underground pipe gallery and construction method
CN207125130U (en) Livestock field drinking water automatically supplying apparatus
CN109339193A (en) Inside is equipped with the shunting well and control system of cut-off equipment
CN211816399U (en) Prefabricated assembled city utility tunnel
CN208311025U (en) It is a kind of waterborne from mud scum stock pump
CN107034925A (en) The well cover for sewer of light-operated osculum automatic plugging opening and closing
CN214884205U (en) Sewage blocking device in canal
CN206491093U (en) A kind of pumping plant irrigated for irrigation and water conservancy
CN212026513U (en) Municipal works drainage open channel construction fixing device
CN219033359U (en) Underwater excavator
CN211621890U (en) Water blocking device for road construction
CN210529838U (en) Backwashing water tank
CN214245350U (en) High-temperature-resistant water drain pipe for bridge
CN110004864A (en) A kind of foundation pit dust pelletizing system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180313

Termination date: 20180623

CF01 Termination of patent right due to non-payment of annual fee