CN207048353U - A kind of prefabricated post installed height mark control device - Google Patents

A kind of prefabricated post installed height mark control device Download PDF

Info

Publication number
CN207048353U
CN207048353U CN201721021400.6U CN201721021400U CN207048353U CN 207048353 U CN207048353 U CN 207048353U CN 201721021400 U CN201721021400 U CN 201721021400U CN 207048353 U CN207048353 U CN 207048353U
Authority
CN
China
Prior art keywords
prefabricated post
post
leveling bolt
plate face
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721021400.6U
Other languages
Chinese (zh)
Inventor
袁术友
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Bureau Third Construction Co Ltd
Original Assignee
China Construction Fifth Bureau Third Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fifth Bureau Third Construction Co Ltd filed Critical China Construction Fifth Bureau Third Construction Co Ltd
Priority to CN201721021400.6U priority Critical patent/CN207048353U/en
Application granted granted Critical
Publication of CN207048353U publication Critical patent/CN207048353U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

A kind of prefabricated post installed height mark control device, straight screw sleeve including leveling bolt and with sleeve pedestal, the bottom of multiple straight screw sleeves is cast in floor structure plate face, leveling bolt is installed with the straight screw sleeve, the nut of the leveling bolt exposes floor structure plate face, prefabricated post to be installed projects in the floor structure plate face and forms prefabricated post position to be installed, the straight screw sleeve is arranged on the point midway on prefabricated post four sides in position to be installed, so that the midpoint on prefabricated post four sides in position to be installed is at least provided with a leveling bolt, and leveling bolt 3cm~5cm apart from the post sideline of prefabricated post position to be installed.Before the lifting of the utility model prefabricated post, prefabricated post post bottom absolute altitude is pre-adjusted by swivel bolt, so as to ensure the accuracy of its absolute altitude after the completion of prefabricated post lifting, and present apparatus material is simple, easy to operate, it is not easily susceptible to disturb, can effectively controls the installed height mark of prefabricated post.

Description

A kind of prefabricated post installed height mark control device
Technical field
Assembled architecture construction field is the utility model is related to, particularly a kind of prefabricated post installed height mark control device.
Background technology
As country vigorously advocates to green building and green construction, assembled architecture already turns into building trade and developed Inexorable trend.In assembled architecture, absolute altitude control of the vertical member such as prefabricated post and shear wall in installation process is dress One of key with formula construction.Control prefabricated post installation mark in the form of post heelpiece sets steel plate washer mostly at this stage Height, but steel plate washer is vulnerable to disturbance, and, it is necessary to the thickness type of steel plate washer is more when being adjusted to specific absolute altitude, operation inconvenience.
Utility model content
One kind is provided and simple and effective can be controlled in order to overcome the shortcomings of prefabricated post installed height mark control method at this stage Prefabricated post installed height mark processed, improve the prefabricated post installed height mark control device of the qualification rate of prefabricated post installation.
Technical scheme is used by the utility model:A kind of prefabricated post installed height mark control device, including leveling bolt With the straight screw sleeve with sleeve pedestal, the bottom of multiple straight screw sleeves is cast in floor structure plate face, described straight Leveling bolt is installed with screw shell, the nut of the leveling bolt exposes floor structure plate face, and prefabricated post to be installed is in institute State projection in floor structure plate face and form prefabricated post position to be installed, the straight screw sleeve is arranged on prefabricated post position to be installed four The point midway on side so that the midpoint on prefabricated post four sides in position to be installed is at least provided with a leveling bolt, and leveling bolt 3cm~5cm apart from the post sideline of prefabricated post position to be installed.Using said structure, after pouring the present apparatus in floor structure plate face, Before the lifting of prefabricated post, measured by spirit level and adjust the absolute altitude of four leveling bolts, comply with design and prefabricated post The requirement of post bottom absolute altitude, the bullet for then carrying out all kinds of control lines are set and the correction of reserved steel bar position, then pass through leveling bolt , it is necessary to steel plate washer when controlling prefabricated post absolute altitude, be vulnerable to disturbance so as to solve existing steel plate washer, and being adjusted to specific absolute altitude Thickness type is more, operates the defects of inconvenient, has and uses material simple, easy to operate, is not easily susceptible to disturb, can effectively control The advantages of installed height mark of prefabricated post processed.
Preferably, the nut upper surface of the leveling bolt is no more than 2cm apart from plate face.
Further, the leveling bolt is using the specification hex bolts of M24 × 60.Straight screw sleeve carries 60 × 60 × 4mm Thick sleeve pedestal, sleeve pedestal are fixed with straight screw sleeve using welding manner.
In summary, before the lifting of the utility model prefabricated post, prefabricated post post bottom absolute altitude is pre-adjusted by swivel bolt, So as to ensure the accuracy of its absolute altitude after the completion of prefabricated post lifting, and present apparatus material is simple, easy to operate, is not easily susceptible to disturb It is dynamic, it can effectively control the installed height mark of prefabricated post.
Brief description of the drawings
Fig. 1 is the structural representation that the present apparatus is arranged in floor structure plate face.
Fig. 2 is present apparatus leveling bolt and straight screw sleeve combination diagram.
In accompanying drawing:1st, leveling bolt;2nd, floor structure plate face;3rd, post sideline;4th, the reserved steel bar of post;5th, straight thread set Cylinder;6th, sleeve pedestal.
Embodiment
Specific embodiment of the present utility model is illustrated below in conjunction with the accompanying drawings so that feature of the present utility model and Its advantage can be easier to be understood by those skilled in the art.
As described in Fig. 1,2, before the casting concrete of floor structure plate face 2, leveling bolt 1 is inserted in straight screw sleeve in advance In 5, straight screw sleeve 5 carries sleeve pedestal 6, by its integral built-in near the midpoint on four sides of prefabricated post, distance post side The about 3cm to 5cm of line 3, nut upper surface are no more than 2cm apart from plate face, fixed using welding manner.After the completion of concreting, To prefabricated post bottom dabbing and leveling bolt 1 is found out, is measured by spirit level and adjusts the absolute altitude of four leveling bolts 1, make its symbol Close design and the requirement of prefabricated post post bottom absolute altitude.After the completion of Pass line adjustment, the bullet for carrying out all kinds of control lines is set and reserved steel bar 4 The correction put, finally complete the lifting of prefabricated post.

Claims (3)

  1. A kind of 1. prefabricated post installed height mark control device, it is characterised in that the straight thread including leveling bolt and with sleeve pedestal Sleeve, the bottom of multiple straight screw sleeves are cast in floor structure plate face, and leveling is installed with the straight screw sleeve Bolt, the nut of the leveling bolt expose floor structure plate face, and prefabricated post to be installed projects in the floor structure plate face Prefabricated post position to be installed is formed, the straight screw sleeve is arranged on the point midway on prefabricated post four sides in position to be installed so that pre- The midpoint on post four sides in position to be installed processed is at least provided with a leveling bolt, and leveling bolt is apart from prefabricated post position to be installed Post sideline 3cm~5cm.
  2. 2. according to the prefabricated post installed height mark control device described in claim 1, it is characterised in that the spiral shell of the leveling bolt Cap upper surface is no more than 2cm apart from plate face.
  3. 3. according to the prefabricated post installed height mark control device described in claim 2, it is characterised in that the leveling bolt is six Corner bolt.
CN201721021400.6U 2017-08-15 2017-08-15 A kind of prefabricated post installed height mark control device Expired - Fee Related CN207048353U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721021400.6U CN207048353U (en) 2017-08-15 2017-08-15 A kind of prefabricated post installed height mark control device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721021400.6U CN207048353U (en) 2017-08-15 2017-08-15 A kind of prefabricated post installed height mark control device

Publications (1)

Publication Number Publication Date
CN207048353U true CN207048353U (en) 2018-02-27

Family

ID=61503224

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721021400.6U Expired - Fee Related CN207048353U (en) 2017-08-15 2017-08-15 A kind of prefabricated post installed height mark control device

Country Status (1)

Country Link
CN (1) CN207048353U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108317045A (en) * 2018-03-22 2018-07-24 许占欣 A kind of magnetic suspending wind turbine generator with air gap regulatory function
CN109518980A (en) * 2018-11-26 2019-03-26 福建工程学院 Prefabricated concrete structure column lifts absolute altitude and perpendicularity regulating device and its construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108317045A (en) * 2018-03-22 2018-07-24 许占欣 A kind of magnetic suspending wind turbine generator with air gap regulatory function
CN109518980A (en) * 2018-11-26 2019-03-26 福建工程学院 Prefabricated concrete structure column lifts absolute altitude and perpendicularity regulating device and its construction method
CN109518980B (en) * 2018-11-26 2021-04-27 福建工程学院 Device for adjusting hoisting elevation and verticality of fabricated concrete structure column and construction method thereof

Similar Documents

Publication Publication Date Title
CN103628680B (en) Large steel space truss hanging layer construction method
CN103334496B (en) Pre-embedded steel slab leveling bolt and application method under shock isolating pedestal
CN106639336A (en) Prefabricated concrete wall panel installation and emplacement orientation adjustment device and construction method thereof
CN108118900A (en) The construction method of prefabricated panel
CN203097307U (en) Horizontal adjuster for adjusting outer wallboard in installation of assembling type outer wallboard
CN207048353U (en) A kind of prefabricated post installed height mark control device
CN106865414A (en) A kind of combined hanging installation method of Con casting ladle panoramic table
CN104032969A (en) Precise positioning and process regulation and control device for vibration isolation support embedded plate
CN106808578A (en) A kind of prefabricated piping lane of two-piece unit formula and method for prefabricating
CN203878965U (en) Device for construction of elevator shaft
CN206873945U (en) A kind of constructing device for lifting concrete floorslab thickness qualities
CN205224561U (en) Rail mounted removes scaffold
CN107587770A (en) Disjunctor storehouse synchronization slding form operation method
CN206902768U (en) A kind of post-cast strip adjustable supporting
CN206986918U (en) A kind of asymmetric template for blower fan crab-bolt foundation grouting
CN203080931U (en) Shear wall outer wall formwork bearing device
CN205955225U (en) Thick controlling means of cast in situ concrete floor board
CN208219724U (en) A kind of bracing means for preventing diaphram wall from settling
CN205296213U (en) Utility tunnel lining cutting platform truck
CN203924411U (en) Prefabricated assembled fire wall
CN204782194U (en) Simple and easy emergency communication tower
CN107724419A (en) A kind of equipment prefabricated foundation locator and its application method
CN207749817U (en) A kind of builder's jack installation system
CN207525964U (en) A kind of prefabricated composite wallboard pitched roof system
CN207144174U (en) A kind of large scale equipment essence Heibei provincial opera regulating device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180227

CF01 Termination of patent right due to non-payment of annual fee