CN106639336A - Prefabricated concrete wall panel installation and emplacement orientation adjustment device and construction method thereof - Google Patents

Prefabricated concrete wall panel installation and emplacement orientation adjustment device and construction method thereof Download PDF

Info

Publication number
CN106639336A
CN106639336A CN201611076842.0A CN201611076842A CN106639336A CN 106639336 A CN106639336 A CN 106639336A CN 201611076842 A CN201611076842 A CN 201611076842A CN 106639336 A CN106639336 A CN 106639336A
Authority
CN
China
Prior art keywords
wall panel
concrete wall
precast concrete
place
adjusting apparatus
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201611076842.0A
Other languages
Chinese (zh)
Inventor
武大伟
黄玉林
杨佳林
董建曦
杜晓燕
金玺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI CONSTRUCTION REAL ESTATE CO Ltd
Shanghai Construction Group Co Ltd
Original Assignee
SHANGHAI CONSTRUCTION REAL ESTATE CO Ltd
Shanghai Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI CONSTRUCTION REAL ESTATE CO Ltd, Shanghai Construction Group Co Ltd filed Critical SHANGHAI CONSTRUCTION REAL ESTATE CO Ltd
Priority to CN201611076842.0A priority Critical patent/CN106639336A/en
Publication of CN106639336A publication Critical patent/CN106639336A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/167Tools or apparatus specially adapted for working-up plates, panels or slab shaped building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/26Strutting means for wall parts; Supports or the like, e.g. for holding in position prefabricated walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention provides a prefabricated concrete wall panel installation and emplacement orientation adjustment device and a construction method thereof, and belongs to the technical field of prefabrication and assembly, in order to solve the problems that the existing prefabricated concrete wall panel construction and installation efficiency is low, the process is complicated, and the installation quality can not be ensured. The adjustment device includes a funnel-shaped structure formed by vertical plates and a base, each vertical plate includes an upper bent portion and a lower vertical portion, the bottom end of each vertical plate is vertically and fixedly connected with the base, the base is fixedly connected with a floorboard through embedded bolts, and the two vertical plates located at the same side of a prefabricated concrete wall panel are fixed through a connection rod to form a cavity which can contain the prefabricated concrete wall panel. The invention further provides the construction method of the prefabricated concrete wall panel installation and emplacement orientation adjustment device, the problem that the prefabricated concrete wall panel is difficult to rapidly and accurately emplace and adjust is solved, and the prefabricated wall panel installation efficiency is improved.

Description

Precast concrete wall panel installs guiding adjusting apparatus in place and its construction method
Technical field
The present invention relates to prefabrication and assembly construction technical field, more particularly to a kind of precast concrete wall panel installation is in place to be oriented to adjustment Device and its construction method.
Background technology
Precast concrete wall panel brings much as in a kind of widely used preformed material of building field to building industry Facility.But precast concrete wall panel quality is larger, lower end swings and is difficult to control to during hanging, and causes its lower end to be difficult to soon Speed is accurately positioned.Precast concrete wall panel construction and installation need to the perforate in level and wallboard, connected by bracing reinforcement bar and hole Fixation is connect, construction and installation efficiency is low, and technique is loaded down with trivial details, can destroy the overall structure of prefabricated panel, it is impossible to ensure pre-cast concrete walling The construction and installation quality of plate.
For foregoing problems, a kind of simple structure, easy to operate, safe and reliable precast concrete wall panel peace how are provided Guiding adjusting apparatus in place and its construction method are filled, precast concrete wall panel is solved and is difficult to quick accurately in place and adjustment asking Topic, improves the installation effectiveness of prefabricated panel, is the technical problem of those skilled in the art's urgent need to resolve.
The content of the invention
For existing precast concrete wall panel construction and installation need to the perforate on horizontal floorboard and wallboard, by bracing reinforcement Bar is connected with hole, and construction and installation efficiency is low, and technique is loaded down with trivial details, can destroy the overall structure of precast concrete wall panel, it is impossible to Ensure the problem of the construction and installation quality of precast concrete wall panel, the present invention provides a kind of precast concrete wall panel and installs in place leading To adjusting apparatus and its installation method, solve the problems, such as that precast concrete wall panel is difficult to quick accurate in place and adjustment, improve pre- The installation effectiveness of wallboard processed.
The technical solution adopted for the present invention to solve the technical problems is:
Precast concrete wall panel installs guiding adjusting apparatus in place, including " funnel type " structure that riser and base are formed, The riser includes top bending part and lower vertical part, and the bottom of the riser is vertically fixed on the base, institute State base to be fixed on floorboard by pre-embedded bolt, by connection between two pieces of risers of precast concrete wall panel homonymy Bar is fixed, and is formed one and can be accommodated the cavity of the precast concrete wall panel.
Further, bracing reinforcement bar is additionally provided between the riser and the base.
Further, the top and bottom of the lower vertical part are respectively equipped with upward adjustment screw and lower adjustment screw rod.
Further, described bracing reinforcement bar one end is welded to connect with the lower vertical part of the riser, the support The other end of reinforcing bar is connected with the tube chamber welds with base.
Further, the upward adjustment screw and the lower adjustment screw rod are threaded rod.
Further, bolt hole is offered on the base, the base is by pre-buried in bolt and horizontal floorboard Bolt collar connects.
Present invention also offers a kind of precast concrete wall panel installs the construction method for being oriented to adjusting apparatus in place, including such as Lower step:
Step one:There is provided some aforesaid precast concrete wall panels installations guiding adjusting apparatus in place standby;
Step 2:Line setting is carried out to the installation site of precast concrete wall panel on floorboard, is pacified by unwrapping wire position Fill the precast concrete wall panel in place and guiding adjusting apparatus in place are installed, and be fixed on floorboard;
Step 3:Precast concrete wall panel is hung to by position top to be installed using tower crane, it is prefabricated mixed by human assistance Solidifying cob wall plate is accurate to up to position to be installed along the top bending part of riser, and by upper and lower adjustment screw rod concrete is adjusted The perpendicularity of cob wall plate is simultaneously fixed.
Further, the base inward flange preset distance installs sideline and reserves 3mm-5mm laterally.
The precast concrete wall panel of the present invention installs guiding adjusting apparatus in place and its construction method and existing concrete Cob wall plate construction installation method is compared, and has following points advantage:
One is that the precast concrete wall panel of the present invention installs guiding adjusting apparatus in place, and by riser and base " leakage is formed Bucket type " structure, such that it is able to the precast concrete wall panel of lifting is accurately guided to position to be installed, and by upward adjustment screw Complete to be fixed installation again after perpendicularity adjustment with lower adjustment screw rod, so as to without the need for the perforate on precast concrete wall panel, have Effect prevents the structural integrity of precast concrete wall panel, so as to ensure that the installation quality of precast concrete wall panel.
Two is that the precast concrete wall panel of the present invention installs guiding adjusting apparatus in place, by by the upper design of riser into The top bending part for bending laterally, and with the use of the upward adjustment screw and lower adjustment spiral shell of the setting of riser lower vertical part Bar, also assures that the perpendicularity of precast concrete wall panel, so as to solve concrete while accurately lifting positioning is met Cob wall plate is difficult to quick accurate in place and adjustment problem, improves the installation effectiveness of prefabricated panel.
Three is that the precast concrete wall panel of the present invention installs guiding adjusting apparatus in place, rational in infrastructure, simple to operation, peace Total stability is good, and it is repeatable be used in turn, save cost.And the precast concrete wall panel installs in place guiding and adjusts dress The construction method put, it is easy to operate, with preferable promotional value.
Description of the drawings
Fig. 1 installs the structural representation for being oriented to adjusting apparatus in place for the precast concrete wall panel of one embodiment of the invention;
Fig. 2 installs the stereogram for being oriented to adjusting apparatus in place for the precast concrete wall panel of one embodiment of the invention;
Fig. 3 installs the front view for being oriented to adjusting apparatus in place for the precast concrete wall panel of one embodiment of the invention;
Fig. 4 installs the scheme of installation for being oriented to adjusting apparatus in place for the precast concrete wall panel of one embodiment of the invention.
In figure:
1- risers, 101- tops bending part;2- upward adjustment screws;Screw rod is adjusted under 3-;4- connecting rods;5- bracing reinforcements Bar;6- bases;7- bolts;8- precast concrete wall panels.
Specific embodiment
Guiding in place is installed to a kind of precast concrete wall panel proposed by the present invention below in conjunction with the drawings and specific embodiments Adjusting apparatus and its construction method are described in further detail.According to description below, advantages and features of the invention will be more clear Chu.Hereinafter accompanying drawing will be combined by cited embodiment, describe the technology contents and feature of the present invention in detail.Need to illustrate in addition It is that accompanying drawing in the form of simplifying very much and uses non-accurately ratio, only conveniently, lucidly to aid in illustrating this The purpose of bright embodiment.For sake of convenience, it is described below " on ", the upper and lower direction of D score and accompanying drawing it is consistent, but this is not The restriction of technical solution of the present invention can be become.
Embodiment one
Fig. 1 to Fig. 4 is referred to, the precast concrete wall panel for describing the present invention in detail installs the knot for being oriented to adjusting apparatus in place Structure is constituted.
As shown in Figures 1 to 4, a kind of precast concrete wall panel installs guiding adjusting apparatus in place, including riser 1 and base 6 " funnel type " structures for being formed, riser 1 includes top bending part 101 and lower vertical part (not shown), the bottom of riser 1 End is vertically fixed on base 6, and base 6 is fixed on floorboard (not shown), positioned at pre-cast concrete walling by pre-embedded bolt Being fixed by connecting rod 4 between two pieces of risers of the homonymy of plate 8, and form one can accommodate the cavity of precast concrete wall panel 8.
Specifically, will be prefabricated mixed by setting in precast concrete wall panel of the invention installation guiding adjusting apparatus in place Being fixed by connecting rod 4 between two pieces of risers of the solidifying homonymy of cob wall plate 8, and form one can accommodate precast concrete wall panel 8 Cavity, so as to the installation for facilitating precast concrete wall panel 8 is fixed.The connecting rod 4 can select channel-section steel, by bolt or buckle Form connects.And, in order to improve the lifting efficiency of precast concrete wall panel 8, the precast concrete wall panel installs guiding in place The top bending laterally of the riser 1 of adjusting apparatus forms top bending part 101, is similar to the shape of funnel, plays guiding Effect, so as to prevent producing skew during the lifting of precast concrete wall panel 8, to ensure once to lift in place, when saving installation positioning Between.Precast concrete wall panel 8 is hung to by position top to be installed by tower crane, and adjusts perpendicularity, adjusting will after perpendicularity Its fixation completes the installation of precast concrete wall panel 8.The precast concrete wall panel of the present invention installs guiding adjusting apparatus in place Rational in infrastructure, simple to operation, security and stability is good, can realize the positioning and guiding and quick adjustment work(of precast concrete wall panel Can, improve the installation effectiveness of precast concrete wall panel.
It is preferred that toppling to prevent riser 1 from producing, bracing reinforcement bar 5 is additionally provided between riser 1 and base 6.Support and add Gu the one end of bar 5 is welded to connect with the lower vertical part of riser 1, the other end and the base 6 of bracing reinforcement bar 5 are welded to connect.
It is preferred that the upper end of the lower vertical part of riser 1 is provided with upward adjustment screw 2, the lower vertical part of riser 1 Lower end is provided with lower adjustment screw rod 3, and by upward adjustment screw 2 and lower adjustment screw rod 3 the vertical of precast concrete wall panel 8 is adjusted Degree, so as to improve installation effectiveness.Certainly, it is easy to adjust in order to cost-effective, upward adjustment screw 2 and it is lower adjustment screw rod 3 be spiral shell Rasp bar.
It is preferred that offer bolt hole on base 6, base 6 is by the built-in bolt sleeve in bolt and horizontal floorboard Connection, is fixedly installed in horizontal floorboard, it is ensured that pre- so as to the precast concrete wall panel is installed into guiding adjusting apparatus in place Concrete panel processed is accurately positioned installation.Certainly, because the precast concrete wall panel installs guiding adjusting apparatus in place and water With bolts between flat floorboard, so as to easy accessibility, the precast concrete wall panel installs guiding adjusting apparatus in place can It is cost-effective to be used in turn.
Embodiment two
Please continue to refer to Fig. 1 to Fig. 4, embodiments provide precast concrete wall panel and guiding adjustment dress in place is installed The construction method put, the construction method comprises the steps:
Step one:There is provided some precast concrete wall panels installations guiding adjusting apparatus in place standby;
Step 2:Line setting is carried out to the installation site of precast concrete wall panel on floorboard, is pacified by unwrapping wire position Fill precast concrete wall panel in place and guiding adjusting apparatus in place are installed, and be fixed on floorboard;
Step 3:Precast concrete wall panel 8 is hung to by position top to be installed using tower crane, it is prefabricated by human assistance Concrete panel 8 is accurate to up to position to be installed along the top bending part of riser 1, by it is upper and lower adjustment screw rod (2,3) adjust The perpendicularity of precast concrete wall panel 8 is simultaneously fixed, so as to complete the installation of one block of precast concrete wall panel 8, such circulating repetition, Until completing the installation of all precast concrete wall panels.
It is preferred that the inward flange preset distance of base 6 installs sideline reserves laterally 3mm-5mm, to ensure that component can be in place, And be fixed on the floorboard for being embedded with bolt collar, and be fixed by bolt 7.
In sum, precast concrete wall panel of the invention install guiding adjusting apparatus in place and its construction method with it is existing Precast concrete wall panel construction installation method is compared, and has following points advantage:
One is that the precast concrete wall panel of the present invention installs guiding adjusting apparatus in place, and by riser and base " leakage is formed Bucket type " structure, such that it is able to the precast concrete wall panel of lifting is accurately guided to position to be installed, and by upward adjustment screw Complete to be fixed installation again after perpendicularity adjustment with lower adjustment screw rod, so as to without the need for the perforate on precast concrete wall panel, have Effect prevents the structural integrity of precast concrete wall panel, so as to ensure that the installation quality of precast concrete wall panel.
Two is that the precast concrete wall panel of the present invention installs guiding adjusting apparatus in place, by by the upper design of riser into The top bending part for bending laterally, and with the use of the upward adjustment screw and lower adjustment spiral shell of the setting of riser lower vertical part Bar, also assures that the perpendicularity of precast concrete wall panel, so as to solve concrete while accurately lifting positioning is met Cob wall plate is difficult to quick accurate in place and adjustment problem, improves the installation effectiveness of prefabricated panel.
Three is that the precast concrete wall panel of the present invention installs guiding adjusting apparatus in place, rational in infrastructure, simple to operation, peace Total stability is good, and it is repeatable be used in turn, save cost.And the precast concrete wall panel installs in place guiding and adjusts dress The construction method put, it is easy to operate, with preferable promotional value.
Foregoing description is only the description to present pre-ferred embodiments, not to any restriction of the scope of the invention, this Any change, modification that the those of ordinary skill in bright field does according to the disclosure above content, belong to the protection of claims Scope.

Claims (8)

1. precast concrete wall panel installs guiding adjusting apparatus in place, it is characterised in that including " the funnel that riser and base are formed Type " structure, the riser includes top bending part and lower vertical part, and the bottom of the riser is vertically fixed in the bottom On seat, the base is fixed on floorboard by pre-embedded bolt, between two pieces of risers of precast concrete wall panel homonymy Being fixed by connecting rod, and form one can accommodate the cavity of the precast concrete wall panel.
2. precast concrete wall panel according to claim 1 installs guiding adjusting apparatus in place, it is characterised in that described perpendicular Bracing reinforcement bar is additionally provided between plate and the base.
3. precast concrete wall panel according to claim 1 installs guiding adjusting apparatus in place, it is characterised in that under described The top and bottom of portion's vertical portion are respectively equipped with upward adjustment screw and lower adjustment screw rod.
4. precast concrete wall panel according to claim 2 installs guiding adjusting apparatus in place, it is characterised in that described Support reinforcing bar one end is welded to connect with the lower vertical part of the riser, the other end and the base of the bracing reinforcement bar It is welded to connect.
5. precast concrete wall panel according to claim 3 installs guiding adjusting apparatus in place, it is characterised in that on described Adjustment screw rod and the lower adjustment screw rod are threaded rod.
6. precast concrete wall panel according to claim 1 installs guiding adjusting apparatus in place, it is characterised in that the bottom Bolt hole is offered on seat, the base is connected by bolt with the built-in bolt sleeve in horizontal floorboard.
7. precast concrete wall panel installs the construction method for being oriented to adjusting apparatus in place, it is characterised in that comprise the steps:
Step one:Some precast concrete wall panels as described in any one of claim 1 to 6 are provided guiding adjustment dress in place is installed Purchase use;
Step 2:Line setting is carried out to the installation site of precast concrete wall panel on floorboard, is installed just by unwrapping wire position The position precast concrete wall panel installs guiding adjusting apparatus in place, and is fixed on floorboard;
Step 3:Precast concrete wall panel is hung to by position top to be installed using tower crane, by human assistance, precast concrete Wallboard is accurate to up to position to be installed along the top bending part of riser, and by upper and lower adjustment screw rod pre-cast concrete walling is adjusted The perpendicularity of plate is simultaneously fixed.
8. construction method as claimed in claim 7, it is characterised in that it is outside that the base inward flange preset distance installs sideline Reserve 3mm-5mm in side.
CN201611076842.0A 2016-11-30 2016-11-30 Prefabricated concrete wall panel installation and emplacement orientation adjustment device and construction method thereof Pending CN106639336A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611076842.0A CN106639336A (en) 2016-11-30 2016-11-30 Prefabricated concrete wall panel installation and emplacement orientation adjustment device and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611076842.0A CN106639336A (en) 2016-11-30 2016-11-30 Prefabricated concrete wall panel installation and emplacement orientation adjustment device and construction method thereof

Publications (1)

Publication Number Publication Date
CN106639336A true CN106639336A (en) 2017-05-10

Family

ID=58813198

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611076842.0A Pending CN106639336A (en) 2016-11-30 2016-11-30 Prefabricated concrete wall panel installation and emplacement orientation adjustment device and construction method thereof

Country Status (1)

Country Link
CN (1) CN106639336A (en)

Cited By (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107939052A (en) * 2017-12-07 2018-04-20 贵州微粉纳米技术应用研究院有限责任公司 A kind of installation method of concrete panel
CN108756259A (en) * 2018-07-25 2018-11-06 河南二建集团钢结构有限公司 A kind of the auxiliary mounting assembly and installation method of large-scale steel structure component
CN108952185A (en) * 2018-07-30 2018-12-07 青岛理工大学 Wallboard installation guider in prefabrication
CN109356389A (en) * 2018-11-21 2019-02-19 郴州远大住宅工业有限公司 A kind of prefabricated panel installation limiting device and its construction method
CN110409771A (en) * 2019-07-23 2019-11-05 天元建设集团有限公司 A kind of prefabricated outer wall panel installation auxiliary device and its application method
CN110700602A (en) * 2019-10-18 2020-01-17 甘肃建投科技研发有限公司 Assembled interior wall location jacking device
CN110778137A (en) * 2019-11-08 2020-02-11 九江职业技术学院 Assembled counterfort fixing device
CN111519916A (en) * 2020-05-14 2020-08-11 上海建工五建集团有限公司 Component mounting and positioning guide frame and method
CN111535597A (en) * 2020-05-19 2020-08-14 蒋昌俊 On-site assembling, installing and constructing method for energy-saving reinforced concrete prefabricated wall
CN111608402A (en) * 2020-05-23 2020-09-01 成都市天柱建筑工程有限公司 Connecting device for prefabricated house and connecting method thereof
CN111945918A (en) * 2020-08-10 2020-11-17 徐州易尚饰家装饰工程有限责任公司 Prefabricated template installation shock attenuation stabilising arrangement of assembled
CN112282381A (en) * 2020-10-28 2021-01-29 浙江工业职业技术学院 Mounting and positioning device for assembly type building wall and working method thereof
CN112620353A (en) * 2020-12-12 2021-04-09 中冶天工集团有限公司 Vertical rolling mill stand foundation embedded part mounting device and mounting adjustment method
CN112962985A (en) * 2021-02-23 2021-06-15 上海中森建筑与工程设计顾问有限公司 Guide positioning device for assembly type building component and construction method
CN113047666A (en) * 2021-04-09 2021-06-29 西安建筑科技大学 Limiting device is supported in installation of assembled PC wall
CN113502944A (en) * 2021-07-26 2021-10-15 广东省构建工程建设有限公司 PC exterior wall cladding structure and construction process thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202007017708U1 (en) * 2007-08-10 2008-03-06 Rachinger, Reinhold tipping
CN104912344A (en) * 2015-07-01 2015-09-16 中国建材检验认证集团西安有限公司 Guide structure and installation method used for installation of light wall boards
CN105587127A (en) * 2015-06-17 2016-05-18 深圳建业工程集团股份有限公司 Method for locating outer wall prefabricated hanging plate based on laser line marking instrument
CN205713169U (en) * 2016-06-20 2016-11-23 三能集成房屋股份有限公司 A kind of support means connecting wallboard

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE202007017708U1 (en) * 2007-08-10 2008-03-06 Rachinger, Reinhold tipping
CN105587127A (en) * 2015-06-17 2016-05-18 深圳建业工程集团股份有限公司 Method for locating outer wall prefabricated hanging plate based on laser line marking instrument
CN104912344A (en) * 2015-07-01 2015-09-16 中国建材检验认证集团西安有限公司 Guide structure and installation method used for installation of light wall boards
CN205713169U (en) * 2016-06-20 2016-11-23 三能集成房屋股份有限公司 A kind of support means connecting wallboard

Cited By (21)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107939052A (en) * 2017-12-07 2018-04-20 贵州微粉纳米技术应用研究院有限责任公司 A kind of installation method of concrete panel
CN108756259A (en) * 2018-07-25 2018-11-06 河南二建集团钢结构有限公司 A kind of the auxiliary mounting assembly and installation method of large-scale steel structure component
CN108952185A (en) * 2018-07-30 2018-12-07 青岛理工大学 Wallboard installation guider in prefabrication
CN108952185B (en) * 2018-07-30 2020-06-26 青岛理工大学 Wallboard installation guider in prefabrication
CN109356389A (en) * 2018-11-21 2019-02-19 郴州远大住宅工业有限公司 A kind of prefabricated panel installation limiting device and its construction method
CN109356389B (en) * 2018-11-21 2024-07-09 郴州远大住宅工业有限公司 Prefabricated wallboard installation limiting device and construction method thereof
CN110409771B (en) * 2019-07-23 2024-05-03 天元建设集团有限公司 Prefabricated external wall panel installation auxiliary device and application method thereof
CN110409771A (en) * 2019-07-23 2019-11-05 天元建设集团有限公司 A kind of prefabricated outer wall panel installation auxiliary device and its application method
CN110700602A (en) * 2019-10-18 2020-01-17 甘肃建投科技研发有限公司 Assembled interior wall location jacking device
CN110778137A (en) * 2019-11-08 2020-02-11 九江职业技术学院 Assembled counterfort fixing device
CN110778137B (en) * 2019-11-08 2020-05-12 九江职业技术学院 Assembled counterfort fixing device
CN111519916A (en) * 2020-05-14 2020-08-11 上海建工五建集团有限公司 Component mounting and positioning guide frame and method
CN111535597A (en) * 2020-05-19 2020-08-14 蒋昌俊 On-site assembling, installing and constructing method for energy-saving reinforced concrete prefabricated wall
CN111608402A (en) * 2020-05-23 2020-09-01 成都市天柱建筑工程有限公司 Connecting device for prefabricated house and connecting method thereof
CN111945918A (en) * 2020-08-10 2020-11-17 徐州易尚饰家装饰工程有限责任公司 Prefabricated template installation shock attenuation stabilising arrangement of assembled
CN112282381A (en) * 2020-10-28 2021-01-29 浙江工业职业技术学院 Mounting and positioning device for assembly type building wall and working method thereof
CN112620353A (en) * 2020-12-12 2021-04-09 中冶天工集团有限公司 Vertical rolling mill stand foundation embedded part mounting device and mounting adjustment method
CN112962985A (en) * 2021-02-23 2021-06-15 上海中森建筑与工程设计顾问有限公司 Guide positioning device for assembly type building component and construction method
CN112962985B (en) * 2021-02-23 2022-06-21 上海中森建筑与工程设计顾问有限公司 Guide positioning device for assembly type building component and construction method
CN113047666A (en) * 2021-04-09 2021-06-29 西安建筑科技大学 Limiting device is supported in installation of assembled PC wall
CN113502944A (en) * 2021-07-26 2021-10-15 广东省构建工程建设有限公司 PC exterior wall cladding structure and construction process thereof

Similar Documents

Publication Publication Date Title
CN106639336A (en) Prefabricated concrete wall panel installation and emplacement orientation adjustment device and construction method thereof
CN103510702B (en) Steel core concrete column pin type concrete pouring construction method
CN102953546B (en) Construction method for mounting deformation joint template at double walls
CN108118900A (en) The construction method of prefabricated panel
CN208023710U (en) A kind of connection structure of assembly concrete shear wall
CN107859058A (en) A kind of cast-in-place concrete retaining wall anti-incline anti-floating large steel moulding plate device and installation method
CN206693611U (en) A kind of cylindrical pit shaft formwork for placing
CN105133754A (en) Prefabricated concrete shear wallboard counterbore guide type mounting device and method
CN205712590U (en) A kind of fabricated shear wall and the attachment structure of Prefabricated concrete-filled steel tube post
CN110761411A (en) Large-span suspended spherical dome concrete pouring method
CN109457814B (en) Construction method for top cover of high-rise and large-diameter building based on Bailey truss structure
CN105347142B (en) A kind of building hoist is mounted on the threading installation method on basement roof
CN207700669U (en) A kind of bracing means of builder's jack and laminated floor slab
CN104831832B (en) Assembly of shear wall structure and its installation method
CN206408951U (en) A kind of architectural industrialization project conversion layer position level ladder muscle
CN207063497U (en) A kind of aerial work basket suspension arrangement available for architectural engineering privileged sites
CN106567538B (en) A kind of positioning mold of toilet concrete flanging
CN205936608U (en) Vertical shaft concrete and quick slip form construction device of rock mass grout
CN102444275A (en) Silo flexible slip form torsion resistance construction device
CN110005215B (en) Reliable installation construction process for shear wall structure system
CN103938755A (en) Shock insulation structure for under-shaft hanging type transfer girders, and construction method of shock insulation structure
CN209585576U (en) Overhanging scaffold
CN207685855U (en) A kind of anti-anti-floating large steel moulding plate device that inclines of cast-in-place concrete retaining wall
CN207376661U (en) A kind of plugging structure of poured band of outer wall of basement
CN106499180B (en) A kind of novel exterior sheathing is reinforced and external scaffolding drawknot device and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510

RJ01 Rejection of invention patent application after publication