CN207046635U - A kind of elevator hoistways structure - Google Patents
A kind of elevator hoistways structure Download PDFInfo
- Publication number
- CN207046635U CN207046635U CN201720949937.2U CN201720949937U CN207046635U CN 207046635 U CN207046635 U CN 207046635U CN 201720949937 U CN201720949937 U CN 201720949937U CN 207046635 U CN207046635 U CN 207046635U
- Authority
- CN
- China
- Prior art keywords
- hoistway
- unit
- pedestal
- slide rail
- sections
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Types And Forms Of Lifts (AREA)
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
Abstract
The utility model discloses the hoistway structure of a kind of elevator hoistways structure, including N section hoistway units to be arranged on pedestal, and pedestal is provided with vertically and horizontally slide rail;First paragraph hoistway unit N1On pedestal, its side is additionally provided with from hoisting mechanism;It is arranged on first paragraph hoistway unit N1Side N section hoistway units NnIt is lifted up with matching to merge along vertical slide rail from hoisting mechanism;N section hoistway units NnWhen being promoted to preset height and the translation mechanism with being arranged on horizontal slide rail is engaged, and is translated to 1 section of hoistway unit N of Nn‑1Top.Compared with prior art, the utility model, which has, can be achieved outdoor installation elevator, and safe and efficient, construct the advantages that factor is few, and the engineering time is short that disturb residents.
Description
Technical field
The utility model belongs to elevator technology field, and in particular to a kind of elevator hoistways structure.
Background technology
Aging blocks install elevator major part additional and construct the hoistway needed for elevator using steel construction at present, such as publication number CN
105329751 A Chinese invention patent discloses elevator hoistways structure, and it includes four parallel columns set up and multiple horizontal strokes
Beam, connects four columns by crossbeam between two neighboring column and encloses and connect the passage to form rectangle.Electricity is installed in hoistway
Ladder, in-site installation hoistway with steel structure, which generally requires, builds that scaffold, the job content that disturbs residents are a lot, and the duration is very long, has made steel construction
Elevator is marched into the arena installation again after hoistway, and the whole duration needs one month or so.
In addition, also having some producers by the elevator components scene crane hanging component in the hoistway in advance, have integral hoisting or
Segmental hoisting, but in whole hoisting process, many safety precautions because being influenceed to realize by specific environment, have compared with
Big potential safety hazard, the live goliath for running into narrow space cannot be introduced into, constructional difficulties.
Utility model content
The shortcomings that for above-mentioned prior art or deficiency, the technical problems to be solved in the utility model is to provide one kind can be real
Existing outdoor installation elevator, safe and efficient, the construction factor that disturbs residents is few, engineering time short elevator hoistways structure.
In order to solve the above technical problems, the utility model has following form:
A kind of elevator hoistways structure, the hoistway structure include N section hoistway units, and it is arranged on pedestal, the pedestal
Provided with vertical slide rail and horizontal slide rail, first paragraph hoistway unit N1On the pedestal, the first paragraph hoistway unit N1's
Side is also configured with from hoisting mechanism, N section hoistway units NnIt is arranged on the first paragraph hoistway unit N1Side, the N
Duan Jingdao units NnWith it is described match from hoisting mechanism merge along the vertical slide rail and be lifted up;The N sections hoistway unit Nn
When being promoted to preset height, the N sections hoistway unit NnIt is engaged with the translation mechanism being arranged on horizontal slide rail, and it is described
N section hoistway units NnIt is translated to N-1 section hoistway units Nn-1Top.
Also include the lifting assembly installed in Chuck top, one end of the lifting assembly and the N sections hoistway unit
NnIt is flexibly connected, the other end is arranged on the horizontal slide rail.
The lifting assembly is hoist engine, and the lifting end of the hoist engine is linked up with the N sections hoistway unit NnOn,
The other end is arranged on the horizontal slide rail.
The lifting assembly is pulley assembly, and the pulley end of the pulley assembly is arranged on the horizontal slide rail, surrounded
The lifting end that pulley in the pulley assembly is set is linked up with the N sections hoistway unit NnOn.
Described from hoisting mechanism is hydraulic mandril, and the hydraulic mandril is arranged on the first paragraph hoistway by push rod support
Unit N side.
Described from hoisting mechanism is rack and pinion assembly, and the gear in the rack and pinion assembly is respectively and fixedly installed to institute
First paragraph hoistway unit N side and the Chuck top are stated, the outside of the gear is around setting rack.
The translation mechanism is rack and pinion assembly or timing belt or back-shaped steel wire rope.
The frame structure that the pedestal is assembled by H profile steel is formed, and being additionally provided with sliding block in the H profile steel leads boots.
The also horizontally disposed limited location bar of the pedestal, the gag lever post are provided with for being arranged on the N sections hoistway unit
NnThe mobile pulley N that top is set01The chute of slip.
Also include connecting plate, the connecting plate is by N-1 section hoistway units N setting up and downn-1With the N section hoistways
Unit NnPositioning and locking.
Compared with prior art, the utility model has the following technical effect that:
1) the utility model is gone forward side by side pedestrian in place using electronic lifting assembly and translation mechanism to realize elevator hoistways structure
Work positions, and safe operation process is controllable;
2) the utility model can realize outdoor installation elevator, reduce construction and disturb residents factor, shorten the engineering time, can bigger model
Exclosure realizes target;
3) the utility model can realize that elevator components prefabrication, in-site installation elevator speed are fast;Semi-automatic segmentation peace
The steel structure lift shaft scheme of dress can not need crane hanging component, whole installation process simple operation, safely controllable.
Brief description of the drawings
By reading the detailed description made to non-limiting example made with reference to the following drawings, the application's is other
Feature, objects and advantages will become more apparent upon:
Fig. 1:The utility model elevator hoistways structural base structural representation;
Fig. 2:The utility model elevator hoistways structure installs structural representation during the second hoistway unit;
Fig. 3:The utility model elevator hoistways structure lifts structural representation during the second hoistway unit;
Fig. 4:The utility model elevator hoistways structure translates structural representation during the second hoistway unit;
Fig. 5:The utility model elevator hoistways structure installs structural representation during the 3rd hoistway unit.
Embodiment
Design, concrete structure and caused technique effect of the present utility model are made furtherly below with reference to accompanying drawing
It is bright, to be fully understood from the purpose of this utility model, feature and effect.
As shown in Figures 1 to 5, the utility model elevator hoistways structure, the hoistway structure is arranged on pedestal 10, described
Pedestal 10 is provided with vertical slide rail and horizontal slide rail, and the hoistway structure includes multistage hoistway unit, and the present embodiment is preferably provided with
Three sections of hoistway units.The utility model can realize the outdoor installation elevator of simplicity, reduce construction and disturb residents factor, when shortening construction
Between, it can more broadly realize target.A is residential building in Fig. 1, and B is balcony or residential quarter.
The frame structure that the pedestal 10 is assembled by H profile steel is formed, and sliding block is additionally provided with the H profile steel and leads boots 11.It is described
Pedestal 10 is not limited to be made up of H profile steel, and there is slide rail can also be used with the other structures for leading boots.
The hoistway structure also includes the lifting assembly 40 installed in the top of pedestal 10, and the lifting assembly 40 is used to be lifted
N section hoistway units Nn, one end of the lifting assembly 40 and the N sections hoistway unit NnIt is flexibly connected, the other end is arranged on
On the horizontal slide rail.
Preferably, the lifting assembly 40 is hoist engine, and the hook 42 at the end of lifting rope 41 of the hoist engine hooks up described
N section hoistway units Nn, the other end is on the horizontal slide rail.
Preferably, the lifting assembly 40 is pulley assembly, and the pulley end of the pulley assembly is arranged on the level and slided
On rail, the hook 42 at the end of lifting rope 41 that the pulley in the pulley assembly is set hooks up the N sections hoistway unit Nn。
Be additionally provided with the portal frame 20 from hoisting mechanism, it is described from hoisting mechanism be hydraulic mandril 21, the hydraulic top
Bar 21 is arranged on the first paragraph hoistway unit N by push rod support 221Side.The portal frame 20 is provided with from elevator
Structure, set up, dismounting leans on the operating mechanism of setting itself can complete independently.
Preferably, described from hoisting mechanism is rack and pinion assembly, and the gear in the rack and pinion assembly is fixed respectively
Installed in the first paragraph hoistway unit N1Side and the top of the pedestal 10, the outside of the gear is around setting tooth
Bar.
The translation mechanism 30 is rack and pinion assembly or timing belt or back-shaped steel wire rope.Translation mechanism 30 can be a variety of
Structure, can suitably it be selected as needed in actual application, flexibility is stronger.
The also horizontally disposed limited location bar 50 of the pedestal 10, the gag lever post 50 is provided with for being arranged on the N section wells
Road unit NnThe mobile pulley N that top is set01The chute of slip.The gag lever post 50 is used for the N sections hoistway unit Nn
Raised position be defined.
As shown in Figures 2 to 4, first paragraph hoistway unit N1On the pedestal 10, the first paragraph hoistway unit N1
Side be also equipped with being configured with the portal frame 20 from hoisting mechanism, second segment hoistway unit N2It is arranged on the first paragraph hoistway
Unit N1Side, be lifted up in the vertical slide rail described in the driving effect lower edge from hoisting mechanism on pedestal 10;Institute
State second segment hoistway unit N2When being promoted to preset height, translation mechanism 30 on horizontal slide rail is arranged on by the second segment well
Road unit N2Move to first paragraph hoistway unit N1Top.The utility model is utilized from hoisting mechanism, described below electronic carried
Component and translation mechanism are risen to realize that elevator hoistways structure is in place and is positioned manually, safe operation process is controllable.
As above-mentioned second segment hoistway unit N2Lifted and move to the first paragraph hoistway unit N1Top when, using even
Fishplate bar is by second segment hoistway unit N setting up and down2With the first paragraph hoistway unit N1Positioning and locking;Then the 3rd section is carried out
Hoistway unit N3Operation.
As shown in figure 3, the 3rd section of hoistway unit N3It is arranged on the first paragraph hoistway unit N1Side, in the self-carry
The vertical slide rail described in the driving effect lower edge of mechanism on pedestal 10 is risen to be lifted up;The 3rd section of hoistway unit N3It is promoted to
During preset height, translation mechanism 30 on horizontal slide rail is arranged on by the 3rd section of hoistway unit N3Move to second segment hoistway
Unit N2Top;As above-mentioned 3rd section of hoistway unit N3Lifted and move to the second segment hoistway unit N2Top when, adopt
With connecting plate by second segment hoistway unit N setting up and down2With the 3rd section of hoistway unit N3Positioning and locking;The like it is straight
To completion N section hoistway units Nn, specific method for improving is:
N section hoistway units NnIt is arranged on the first paragraph hoistway unit N1Side, in the driving from hoisting mechanism
Vertical slide rail described in effect lower edge on pedestal 10 is lifted up;The N sections hoistway unit NnWhen being promoted to preset height, if
Translation mechanism 30 on horizontal slide rail is put by the N sections hoistway unit NnMove to N-1 section hoistway units Nn-1It is upper
Side, as above-mentioned N sections hoistway unit NnLifted and move to the N-1 sections hoistway unit Nn-1Top when, using connecting plate
By N section hoistway units N setting up and downnWith N-1 section hoistway units Nn-1Positioning and locking.After above-mentioned installation terminates, institute is unloaded
State lifting assembly 40.
The utility model realizes that elevator hoistways structure is in place and it is artificial to carry out using electronic lifting assembly and translation mechanism
Positioning, safe operation process are controllable;The utility model can realize the outdoor installation elevator of simplicity, reduce construction and disturb residents factor, contracting
The short engineering time, it can more broadly realize target;The utility model can realize elevator components prefabrication, in-site installation electricity
Terraced speed is fast;The steel structure lift shaft scheme of semi-automatic segmentation installation can not need crane hanging component, whole installation process
It is simple operation, safely controllable.Therefore, the utility model has good market application foreground.
Above example is only to illustrate the technical solution of the utility model and non-limiting, reference only to preferred embodiment pair
The utility model is described in detail.It will be understood by those within the art that can be to technology of the present utility model
Scheme is modified or equivalent substitution, without departing from the spirit and scope of technical solutions of the utility model, all should cover in this reality
With in new right.
Claims (10)
1. a kind of elevator hoistways structure, the hoistway structure includes N section hoistway units, and it is arranged on pedestal (10), its feature
It is,
The pedestal (10) is provided with vertical slide rail and horizontal slide rail,
First paragraph hoistway unit N1On the pedestal (10), the first paragraph hoistway unit N1Side be also configured with from
Hoisting mechanism,
N section hoistway units NnIt is arranged on the first paragraph hoistway unit N1Side, the N sections hoistway unit NnWith it is described
Match to merge along the vertical slide rail from hoisting mechanism and be lifted up;
The N sections hoistway unit NnWhen being promoted to preset height, the N sections hoistway unit NnWith being arranged on horizontal slide rail
Translation mechanism (30) be engaged, and the N sections hoistway unit NnIt is translated to N-1 section hoistway units Nn-1Top.
2. elevator hoistways structure according to claim 1, it is characterised in that also include carrying installed in pedestal (10) top
Rise component (40), one end of the lifting assembly (40) and the N sections hoistway unit NnIt is flexibly connected, the other end is arranged on institute
State on horizontal slide rail.
3. elevator hoistways structure according to claim 2, it is characterised in that the lifting assembly (40) is hoist engine, institute
Lifting rope (41) the end hook of hoist engine is stated in the N sections hoistway unit NnOn, the other end is arranged on the horizontal slide rail.
4. elevator hoistways structure according to claim 2, it is characterised in that the lifting assembly (40) is pulley assembly,
The pulley end of the pulley assembly is arranged on the horizontal slide rail, the lifting rope that the pulley in the pulley assembly is set
(41) end hook is in the N sections hoistway unit NnOn.
5. elevator hoistways structure according to claim 1, it is characterised in that it is described from hoisting mechanism be hydraulic mandril
(21), the hydraulic mandril (21) is arranged on the first paragraph hoistway unit N by push rod support (22)1Side.
6. elevator hoistways structure according to claim 1 or 5, it is characterised in that it is described from hoisting mechanism be rack-and-pinion
Component, the gear in the rack and pinion assembly are respectively and fixedly installed to the first paragraph hoistway unit N1Side and described
Pedestal (10) top, the outside of the gear is around setting rack.
7. elevator hoistways structure according to claim 1, it is characterised in that the translation mechanism (30) is rack-and-pinion group
Part or timing belt or back-shaped steel wire rope.
8. elevator hoistways structure according to claim 1, it is characterised in that the frame that the pedestal (10) is assembled by H profile steel
Frame structure is formed, and being additionally provided with sliding block in the H profile steel leads boots (11).
9. the elevator hoistways structure according to claim 1 or 8, it is characterised in that the pedestal (10) is also horizontally disposed to be had
Gag lever post (50), the gag lever post (50) are provided with for being arranged on the N sections hoistway unit NnThe mobile pulley that top is set
N01The chute of slip.
10. elevator hoistways structure according to claim 1, it is characterised in that will also be upper including connecting plate, the connecting plate
The N-1 section hoistway units N of lower settingn-1With the N sections hoistway unit NnPositioning and locking.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720949937.2U CN207046635U (en) | 2017-08-01 | 2017-08-01 | A kind of elevator hoistways structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720949937.2U CN207046635U (en) | 2017-08-01 | 2017-08-01 | A kind of elevator hoistways structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN207046635U true CN207046635U (en) | 2018-02-27 |
Family
ID=61498712
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720949937.2U Active CN207046635U (en) | 2017-08-01 | 2017-08-01 | A kind of elevator hoistways structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN207046635U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107215749A (en) * | 2017-08-01 | 2017-09-29 | 周晓锋 | A kind of elevator hoistways structure and method for improving |
CN112744664A (en) * | 2021-01-08 | 2021-05-04 | 华城(天津)建筑科技有限公司 | Self-lifting hoisting equipment, construction method and sliding locking assembly |
-
2017
- 2017-08-01 CN CN201720949937.2U patent/CN207046635U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107215749A (en) * | 2017-08-01 | 2017-09-29 | 周晓锋 | A kind of elevator hoistways structure and method for improving |
CN112744664A (en) * | 2021-01-08 | 2021-05-04 | 华城(天津)建筑科技有限公司 | Self-lifting hoisting equipment, construction method and sliding locking assembly |
CN112744664B (en) * | 2021-01-08 | 2024-04-26 | 华城(天津)建筑科技有限公司 | Self-lifting hoisting equipment, construction method and sliding locking assembly |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109399432B (en) | A kind of hoistway job platform that climbs certainly | |
CN206408952U (en) | A kind of construction adhesion type lifts discharging platform | |
CN207046635U (en) | A kind of elevator hoistways structure | |
CN102448866A (en) | Method for installing the hoisting roping of an elevator | |
WO2000007923A1 (en) | A device and method for installing elevator equipment | |
CN102493666A (en) | High-altitude translation installation and construction method for super-large super-heavy member | |
CN104989111A (en) | Construction method for steel structure high-rise hoisting | |
CN107215749A (en) | A kind of elevator hoistways structure and method for improving | |
CN105715028A (en) | Successive lifting device and lifting scaffold with same | |
US4205826A (en) | Lifting and supporting apparatus for a tower crane | |
CN109516409A (en) | Flooring construction tower crane turns device for hoisting | |
CN203229334U (en) | Lifting framework for lifting and translating single steel member | |
CN209179426U (en) | A kind of elevator shaft steel construction section construction device | |
CN206328067U (en) | Movable draining platform | |
CN109372242B (en) | Elevator shaft construction safety lifting platform device and using method | |
CN208648493U (en) | A kind of no scaffold installation elevator operation platform device | |
CN207226943U (en) | A kind of double crossbeam synchronous hoisting devices | |
CN201826523U (en) | Integral shaft lifting steel form | |
CN206384699U (en) | A kind of tower bright shaft hoisting system of non-stop production reformation | |
CN105060124A (en) | Intra-frame portal crane system and hoisting use method thereof | |
CN105671245B (en) | A kind of method of utilization hoist engine flip-over type installing converter | |
CN218912242U (en) | Tripod extension jacking formwork platform for elevator shaft construction | |
JPH08218620A (en) | Scaffold device for constructing towerlike structure | |
CN211341822U (en) | Building curtain wall mounting bracket | |
CN203008347U (en) | Steel platform for elevator shaft construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20200305 Address after: 334000 No.11, Chaoyang 5th Road, Chaoyang Industrial Park, Xinzhou District, Shangrao City, Jiangxi Province Patentee after: Shangrao fengke Elevator Co., Ltd Address before: 201600, room 25, No. 30, Lane 602, Rong Yue Middle Road, Shanghai, Songjiang District Patentee before: Zhou Xiaofeng |
|
TR01 | Transfer of patent right |