CN207020522U - One kind is based on BIM sewage disposal remote monitoring systems - Google Patents

One kind is based on BIM sewage disposal remote monitoring systems Download PDF

Info

Publication number
CN207020522U
CN207020522U CN201720922879.4U CN201720922879U CN207020522U CN 207020522 U CN207020522 U CN 207020522U CN 201720922879 U CN201720922879 U CN 201720922879U CN 207020522 U CN207020522 U CN 207020522U
Authority
CN
China
Prior art keywords
bim
electrically connected
monitoring systems
sewage disposal
database server
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720922879.4U
Other languages
Chinese (zh)
Inventor
黄申斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Jiading City Development Group Co Ltd
Original Assignee
Shanghai Jiading City Development Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Jiading City Development Group Co Ltd filed Critical Shanghai Jiading City Development Group Co Ltd
Priority to CN201720922879.4U priority Critical patent/CN207020522U/en
Application granted granted Critical
Publication of CN207020522U publication Critical patent/CN207020522U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Testing And Monitoring For Control Systems (AREA)
  • Sewage (AREA)

Abstract

The utility model discloses one kind to be based on BIM sewage disposal remote monitoring systems, including multiple front end pumping station monitoring systems, collection host computer, database server, BIM servers and at least one BIM terminating machines;Multiple front end pumping station monitoring systems carry out data monitoring and information monitoring to multiple pumping plants respectively;The collection host computer is acquired, filters and handled to the data message of multiple front end pumping station monitoring systems;The collection host computer is electrically connected with the database server, and the database server is electrically connected with the BIM servers, and at least one BIM terminating machines receive the data message of database server and the BIM servers, and carry out real-time display;The disposition of sewage can be monitored in real time, and form model and be monitored, sewage situation is made and timely and effectively tackled, and sewage situation data can be managed collectively, for the follow-up validity and accuracy for providing reference data, improving processing.

Description

One kind is based on BIM sewage disposal remote monitoring systems
Technical field
Sewage management system is the utility model is related to, more particularly to one kind is based on BIM sewage disposal remote monitoring systems.
Background technology
Often there is the problem of urban waterlogging in existing environment, the upgrading, flood control to urban drainage pipe network are met an urgent need Speedily carry out rescue work, routine servicing maintenance management proposes more urgent information-based requirement;Existing urban pipe network system does not have information Change management, be all much manually operated, scene is not equipped with robot control system(RCS), is unfavorable for Sewage Disposal to equipment of pumping station state and instrument The real-time detections of table data, can not system sewage network is controlled, effectively solve problem, also data do not entered The effective unified management of row, causes many contingency questions not to be resolved.
Utility model content
The utility model purpose is to provide one kind and is based on BIM sewage disposal remote monitoring systems, solves in the prior art not The problem of sewage situation can be monitored in real time, solution fully rely on manually-operated present situation in the prior art, solve in the prior art Data can not be accomplished with effectively automatic record, cause many contingency questions can not reflect the problem of being conveniently resolved in time.
The utility model solves technical problem and adopted the following technical scheme that:One kind is based on BIM sewage disposal remote monitorings system System, including multiple front end pumping station monitoring systems, collection host computer, database server, BIM servers and at least one BIM are whole Terminal;Multiple front end pumping station monitoring systems carry out data monitoring and information monitoring to multiple pumping plants respectively;It is multiple it is described before End pumping station monitoring system is electrically connected by VPN and the collection host computer, and the collection host computer is to multiple front end pumps The data message for monitoring system of standing is acquired, filters and handled;The collection host computer is electrically connected with the database server, The database server is electrically connected with the BIM servers, at least one BIM terminating machines respectively with the database service Device and BIM servers are electrically connected;At least one BIM terminating machines receive the data of database server and the BIM servers Information, and carry out real-time display.
Preferably, the front end pumping station monitoring system includes PLC, digital video recorder, at least one shooting Machine, vpn routers, at least one immersible pump, at least one electrically operated valve, at least one grid, at least one flowmeter and extremely A few tank gage;The water inlet of the immersible pump is provided with grid, and the electrically operated valve enters to the Inlet and outlet water of the immersible pump Row control, uniformly the PLC is electrically connected for the immersible pump, electrically operated valve, flowmeter and tank gage;It is described at least one to take the photograph Camera is electrically connected with the digital video recorder, and at least one video camera carries out IMAQ, the VPN routes to pumping plant Device is electrically connected with the PLC and multiple video cameras;The vpn routers are electrically connected with the collection host computer.
Preferably, in addition to pipe network monitor system and sewage disposal monitoring system, the pipe network monitor system is to multiple pumps Pipeline between standing is monitored, and the sewage disposal monitoring system is monitored to sewage disposal;The pipe network monitor system, Multiple front end pumping station monitoring systems and sewage disposal monitoring system pass through VPN and the upper electromechanics of collection Even.
Preferably, the front end pumping station monitoring system also includes flowmeter well and steel sheet pile, and the steel sheet pile is in inside Empty structure, the flowmeter well are arranged in the steel sheet pile, flowmeter are provided with the pipeline of pumping plant, and the pipeline is worn The steel sheet pile and the flowmeter well are crossed, the flowmeter is located in the flowmeter well.
Preferably, in addition to WEB server, the WEB server connect with database server communication.
The utility model has the advantages that:The disposition of sewage can be monitored in real time, and form model and supervised Control, is made to sewage situation and timely and effectively tackling, and sewage situation data can be managed collectively, and reference is provided to be follow-up Data, improve the validity and accuracy of processing.
Brief description of the drawings
Fig. 1 is the line assumption diagram based on BIM sewage disposal remote monitoring systems;
Fig. 2 is the line assumption diagram of front end pumping station monitoring system;
Fig. 3 is flowmeter well and steel sheet pile setting structure schematic diagram.
Mark is illustrated as in figure:1- front ends pumping station monitoring system;2- gathers host computer;3- database servers;4-BIM takes Business device;5-BIM terminating machines;6-PLC controllers;7- digital video recorders;8- video cameras;9-VPN routers;10- immersible pumps; 11- electrically operated valves;12- grids;13- flowmeters;14- tank gages;15- pipe network monitor systems;16- sewage disposal monitoring systems; 17- flowmeter wells;18- steel sheet piles.
Embodiment
The technical solution of the utility model is further elaborated with reference to embodiment and accompanying drawing.
Embodiment 1
As shown in figure 1, the present embodiment, which provides one kind, is based on BIM sewage disposal remote monitoring systems, including multiple front end pumps Monitoring system of standing 1, collection host computer 2, database server 3, BIM servers 4 and at least one BIM terminating machines 5;It is multiple described Front end pumping station monitoring system 1 carries out data monitoring and information monitoring to multiple pumping plants respectively;Multiple front end pumps station systems System 1 is electrically connected by VPN and the collection host computer 2, and the collection host computer 2 is to multiple front end pumps station systems The data message of system 1 is acquired, filters and handled;The collection host computer 2 is electrically connected with the database server 3, described Database server 3 is electrically connected with the BIM servers 4, at least one BIM terminating machines 5 respectively with the database service Device 3 and BIM servers 4 are electrically connected;At least one BIM terminating machines 5 receive database server 3 and the BIM servers 4 Data message, and carry out real-time display.
The flow, water level and real-time image information of multiple pumping plants are acquired using front end pumping station monitoring system 1, passed through Collection host computer 2 is integrated, filtered and handled to resulting information, and database server 3 is combined with BIM servers 4, Display model and real data and the switching monitoring of image on BIM terminating machines 5.Database server 3 can be constantly to history number According to record processing is carried out, make operation management system every time no longer since initial data, but accumulated in a process data On platform, monitoring processing to sewage etc. is analyzed, checked and simulated comprehensively;And sewage situation data can be carried out with unified pipe Reason, for the follow-up validity and accuracy for providing reference data, improving processing.
As shown in Fig. 2 the front end pumping station monitoring system 1 includes PLC 6, digital video recorder 7, at least one Individual video camera 8, vpn routers 9, at least one immersible pump 10, at least one electrically operated valve 11, at least one grid 12, at least One flowmeter 13 and at least one tank gage 14;The water inlet of the immersible pump 10 is provided with grid 12, the electrically operated valve The Inlet and outlet water of 11 pairs of immersible pumps 10 is controlled, and the immersible pump 10, electrically operated valve 11, flowmeter 13 and tank gage 14 are equal The even PLC 6 is electrically connected;At least one video camera 8 is electrically connected with the digital video recorder 7, at least one institute State video camera 8 and IMAQ is carried out to pumping plant, the vpn routers 9 carry out electricity with the PLC 6 and multiple video cameras 8 Even;The vpn routers 9 are electrically connected with the collection host computer 2.The switch of immersible pump 10 is controlled by PLC 6, And by flowmeter 13 and the monitoring record water-carrying capacity of tank gage 14 and water level, transfer data to vpn routers 9;Digitally recorded video The image information imprinting that camera 7 gathers at least one video camera 8 sends vpn routers 9 to, by vpn routers 9 by information It is driven and gives collection host computer 2.
As shown in figure 1, pipe network monitor system 15 and dirt further may include based on BIM sewage disposal remote monitoring systems Water process monitoring system 16, the pipe network monitor system 15 are monitored to the pipeline between multiple pumping plants, the sewage disposal Monitoring system 16 is monitored to sewage disposal;The pipe network monitor system 15, multiple front end pumping station monitoring systems 1 and dirt Water process monitoring system 16 is electrically connected by VPN and the collection host computer 2.
As shown in figure 3, preferably front end pumping station monitoring system 1 described further also includes the He of flowmeter well 17 to the present embodiment Steel sheet pile 18, the steel sheet pile 18 are the structure of inner hollow, and the flowmeter well 17 is arranged in the steel sheet pile 18, pumping plant Pipeline on be provided with flowmeter 13, and the pipeline is through the steel sheet pile 18 and the flowmeter well 17, the flowmeter 13 in the flowmeter well 17.
In transformation process is carried out for original pipe network, there are very much pipe network or pumping plant to be fitted without flowmeter 13 in itself, for Pumping plant in online operation, the installation of flowmeter 13 need to cut off the water just implement, so, the construction time pair that flowmeter 13 is installed The operation of sewage our station has considerable influence, if the time is oversize, sewage can not be discharged normally, can cause shadow to the enterprise of service and resident Ring, flowmeter well 17 and steel sheet pile 18 are set, when mounted, can directly dig pit, steel sheet pile 18 and flowmeter well 17 are assembled in On pipeline, when cutting off the water supply the short time between replace need to set the former duct section of flowmeter 13, can water flowing immediately, road surface can be recovered.
The preferable further embodiment of the present embodiment, WEB service is also included based on BIM sewage disposals remote monitoring system Device, the WEB server connect with database server communication.B/S system architectures can be used, using WEB server, if The UNICOM for putting the smart machines such as mobile phone, palm PC uses, and sets related APP cell phone softwares information transmission platform.
The sequencing of above example only for ease of describing, does not represent the quality of embodiment.
Finally it should be noted that:Above example is only to illustrate the technical solution of the utility model, rather than its limitations; Although the utility model is described in detail with reference to the foregoing embodiments, it will be understood by those within the art that: It can still modify to the technical scheme described in foregoing embodiments, or which part technical characteristic is carried out etc. With replacement;And these modifications or replacement, the essence of appropriate technical solution is departed from various embodiments of the utility model technology The spirit and scope of scheme.

Claims (5)

1. one kind is based on BIM sewage disposal remote monitoring systems, it is characterised in that including multiple front end pumping station monitoring systems, adopts Collect host computer, database server, BIM servers and at least one BIM terminating machines;
Multiple front end pumping station monitoring systems carry out data monitoring and information monitoring to multiple pumping plants respectively;Multiple front ends Pumping station monitoring system is electrically connected by VPN and the collection host computer, and the collection host computer is to multiple front end pumping plants The data message of monitoring system is acquired, filters and handled;
The collection host computer is electrically connected with the database server, and the database server is electrically connected with the BIM servers, At least one BIM terminating machines are electrically connected with the database server and BIM servers respectively;At least one BIM is whole Terminal receives the data message of database server and the BIM servers, and carries out real-time display.
2. according to claim 1 be based on BIM sewage disposal remote monitoring systems, it is characterised in that the front end pumping plant Monitoring system include PLC, digital video recorder, at least one video camera, vpn routers, at least one immersible pump, At least one electrically operated valve, at least one grid, at least one flowmeter and at least one tank gage;
The water inlet of the immersible pump is provided with grid, and the electrically operated valve is controlled to the Inlet and outlet water of the immersible pump, institute Stating immersible pump, electrically operated valve, flowmeter and tank gage, uniformly the PLC is electrically connected;At least one video camera and institute Digital video recorder is stated to be electrically connected, at least one video camera to pumping plant carry out IMAQ, the vpn routers with it is described PLC and multiple video cameras are electrically connected;
The vpn routers are electrically connected with the collection host computer.
3. according to claim 2 be based on BIM sewage disposal remote monitoring systems, it is characterised in that is also supervised including pipe network Control system and sewage disposal monitoring system, the pipe network monitor system are monitored to the pipeline between multiple pumping plants, the dirt Water process monitoring system is monitored to sewage disposal;
The pipe network monitor system, multiple front end pumping station monitoring systems and sewage disposal monitoring system pass through Virtual Private Network Network is electrically connected with the collection host computer.
4. according to claim 3 be based on BIM sewage disposal remote monitoring systems, it is characterised in that the front end pumping plant Monitoring system also includes flowmeter well and steel sheet pile, and the steel sheet pile is the structure of inner hollow, and the flowmeter well is arranged on In the steel sheet pile, flowmeter is provided with the pipeline of pumping plant, and the pipeline passes through the steel sheet pile and the flowmeter well, The flowmeter is located in the flowmeter well.
5. according to claim 1-4 any one based on BIM sewage disposal remote monitoring systems, it is characterised in that also Including WEB server, the WEB server connects with database server communication.
CN201720922879.4U 2017-07-27 2017-07-27 One kind is based on BIM sewage disposal remote monitoring systems Expired - Fee Related CN207020522U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720922879.4U CN207020522U (en) 2017-07-27 2017-07-27 One kind is based on BIM sewage disposal remote monitoring systems

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720922879.4U CN207020522U (en) 2017-07-27 2017-07-27 One kind is based on BIM sewage disposal remote monitoring systems

Publications (1)

Publication Number Publication Date
CN207020522U true CN207020522U (en) 2018-02-16

Family

ID=61482388

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720922879.4U Expired - Fee Related CN207020522U (en) 2017-07-27 2017-07-27 One kind is based on BIM sewage disposal remote monitoring systems

Country Status (1)

Country Link
CN (1) CN207020522U (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109267612A (en) * 2018-11-13 2019-01-25 株洲珠华智慧水务科技有限公司 One kind being based on BIM water transfer pipe network Stress management systems
CN111115727A (en) * 2020-01-02 2020-05-08 中建一局华江建设有限公司 Rural sewage treatment system and method
CN111709656A (en) * 2020-06-22 2020-09-25 苏州柝创智慧建筑科技有限公司 Shield tunnel construction management system based on BIM
CN113608470A (en) * 2021-08-04 2021-11-05 苏州思萃融合基建技术研究所有限公司 Rainwater flood control pump station state monitoring method and device based on BIM information platform

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109267612A (en) * 2018-11-13 2019-01-25 株洲珠华智慧水务科技有限公司 One kind being based on BIM water transfer pipe network Stress management systems
CN109267612B (en) * 2018-11-13 2024-03-26 株洲珠华智慧水务科技有限公司 BIM-based water delivery pipe network pressure management system
CN111115727A (en) * 2020-01-02 2020-05-08 中建一局华江建设有限公司 Rural sewage treatment system and method
CN111709656A (en) * 2020-06-22 2020-09-25 苏州柝创智慧建筑科技有限公司 Shield tunnel construction management system based on BIM
CN113608470A (en) * 2021-08-04 2021-11-05 苏州思萃融合基建技术研究所有限公司 Rainwater flood control pump station state monitoring method and device based on BIM information platform

Similar Documents

Publication Publication Date Title
CN207020522U (en) One kind is based on BIM sewage disposal remote monitoring systems
CN104950855A (en) Town sewage plant and pump station operation monitoring management system and town sewage plant and pump station operation monitoring management method
CN110322027A (en) A kind of domestic sewage in rural areas Internet of Things management platform
CN110535845A (en) A kind of GROUP OF HYDROPOWER STATIONS remote date transmission method, system, terminal and storage medium based on Internet of Things
CN101622952A (en) Water management informatization structure system of irrigation district
CN104766173A (en) Digital water supply management system and method
CN112437116A (en) Sewage treatment wisdom operation system based on thing networking and cloud platform
CN206021060U (en) Urban Drainage Pumping Stations intelligent linkage control system
CN109905406A (en) A kind of drainage pipeline networks monitoring system based on big data
CN111665766A (en) Water affair intelligent monitoring system based on thing networking
CN106292596A (en) A kind of sewage treatment plant intelligent management expert diagnostic system
CN110223411A (en) A kind of public water dispenser cruising inspection system and method
CN205102881U (en) Distributing type water level measurement device
CN117072883A (en) Urban drainage pipe network remote monitoring maintenance system based on Internet of things technology
CN112330491A (en) Water supply and drainage system based on wisdom water utilities
CN206114005U (en) Irrigated area hydrological information remote supervising system
CN114640828A (en) Factory network river and lake integrated operation monitoring and early warning system based on pipe network GIS
CN204490681U (en) A kind of wireless monitor Sewage treatment systems
CN106647579B (en) A kind of sewage collecting pipe network information networked control systems and method
CN107606490A (en) A kind of drainage pipeline networks monitoring system based on big data
CN208314510U (en) A kind of dust-proof automatic monitoring processing system based on BIM technology
CN203746223U (en) Internet of things technology-based mechanical equipment expert system
CN207380516U (en) A kind of sewage disposal remote centralized monitoring system
CN205899337U (en) Remote monitoring and management system of sewage factory based on network and control technique combine together
CN107703894A (en) A kind of drainage pipeline networks remotely monitors SCADA system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180216

Termination date: 20180727