CN206721694U - A kind of cradle structure in reinforced concrete arch bridge building course - Google Patents

A kind of cradle structure in reinforced concrete arch bridge building course Download PDF

Info

Publication number
CN206721694U
CN206721694U CN201720488193.9U CN201720488193U CN206721694U CN 206721694 U CN206721694 U CN 206721694U CN 201720488193 U CN201720488193 U CN 201720488193U CN 206721694 U CN206721694 U CN 206721694U
Authority
CN
China
Prior art keywords
main truss
roller
running gear
load bearing
basket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720488193.9U
Other languages
Chinese (zh)
Inventor
龚兴生
孔余江
郑国�
孙全武
鲍灵高
陈竹
刘海奇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd
Original Assignee
GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd filed Critical GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd
Priority to CN201720488193.9U priority Critical patent/CN206721694U/en
Application granted granted Critical
Publication of CN206721694U publication Critical patent/CN206721694U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses the cradle structure in a kind of reinforced concrete arch bridge building course, include main truss load bearing system, the left and right sides is each provided with 1 secondary C-shaped hook in the middle part of main truss load bearing system, C-shaped hook top is connected with running gear, running gear bottom is located on the walking track poured at the top of the arch box of section, connecting plate is provided with C-shaped hook, connecting plate is each side connected by more oblique pull suspender belts with the pulling seat positioned at the preceding basket of main truss load bearing system and rear basket side, anti- roller devices are provided with rear basket, lifting load-bearing screw rod is provided with main truss load bearing system.The cradle structure using when can avoid sinking in concreting process larger, and Hanging Basket angle-regulation structure is fairly simple, and use is more convenient, and stopping mechanism will not be formed on bridge structure and influenceed.

Description

A kind of cradle structure in reinforced concrete arch bridge building course
Technical field
It the utility model is related to a kind of cradle structure, the Hanging Basket in particularly a kind of reinforced concrete arch bridge building course Structure.
Background technology
Since cast-in-place cantilever method is used in Arch Bridge Construction, successively there is positive triangle rod member in suspended casting suspended basket structure type Formula Hanging Basket, inverted triangle rod member formula Hanging Basket, both Hanging Baskets achieve success on type of service, but with cantilever pouring length And corresponding drawback also occur in the increasing of weight, both the above Hanging Basket, such as rod member stress is bigger than normal, the excessive feelings of cantilever end downwarp Condition so that existing Types of Cradles can not meet the requirement of cantilever pouring.
Hanging Basket, which pours, to be completed because arch ring Hanging Basket is inclined, conducting oneself with dignity, it is necessary to Hanging Basket is moved forward behind a section Under power effect, there is the trend slid backward, to move after avoiding Hanging Basket, generally open up aperture in the arch box bottom poured, insertion Shaped steel, form stopping mechanism.But this mode has a problem that that is, port size is larger, reserve when cage bar avoid aperture, Situations such as rear benefit concrete of orifice position can not completely be combined with original structure, cause arch ring force structure can not be kissed with original design Close, bridge performance is impacted.
Furthermore due to not effective anti-offset structure in existing cradle structure movement forward, before causing Hanging Basket Hanging Basket axis and arch ring axis not parallel situation occur during shifting so that horizontal drift condition occurs in Hanging Basket, and bridge needs To be constructed according to design drawing, it is time-consuming and take so that need to carry out its horizontal skew error correction after hanging basket advancing Power.
The content of the invention
The purpose of this utility model is, there is provided the Hanging Basket knot in a kind of bridge reinforcement concrete arch-type bridge building course Structure.The shortcomings that cradle structure is improved so that the span of rod member formula Hanging Basket is small, deformation is larger, cantilever pouring length extend to Unprecedented 8.0m length, and stopping mechanism is simple, convenient, and reliable, to arch ring structure not damaged, Hanging Basket angle of inclination leads to The counter-force roller devices adjustment of Hanging Basket afterbody is crossed, structure is simple and direct, accurate, and stress is clear and definite.
The technical solution of the utility model:A kind of cradle structure in reinforced concrete arch bridge building course, includes Main truss load bearing system, the main truss load bearing system middle part left and right sides are each provided with 1 secondary C-shaped hook, and C-shaped hook top is connected with walking Device, running gear bottom are located on the walking track poured at the top of the arch box of section, are provided with connecting plate on C-shaped hook, even Fishplate bar is each side connected by more oblique pull suspender belts with the pulling seat positioned at the preceding basket of main truss load bearing system and rear basket side, rear Anti- roller devices are provided with basket, lifting load-bearing screw rod is provided with main truss load bearing system;The anti-roller devices include Anti- roller supporting seat, the anti-bearing pin of roller first is provided with anti-roller supporting seat, the bottom of the anti-roller supporting arm of more than 2 is worn Enter in the anti-bearing pin of roller first, anti-roller supporting arm top is attached by the anti-bearing pin of roller second, the anti-bearing pin of roller second In penetrated anti-roller, 1 adjusting bolt has been also fed through on anti-roller supporting seat, adjusting bolt head end is connected with positioned at anti-roller Anti- roller sliding block on support base, anti-roller sliding block prop up the side of anti-roller supporting arm.
Cradle structure in foregoing reinforced concrete arch bridge building course, also include horizontal stopping device, it is horizontal Stopping device includes the counter-force support element for being embedded in the arch box bottom for having poured section, also includes and is arranged on main truss load-bearing system Counter-force support on system, counter-force screw rod is fixed with by counter-force nut on counter-force support.
Cradle structure in foregoing reinforced concrete arch bridge building course, the running gear include running gear Bottom plate, running gear bottom base plate are provided with running gear slide plate, and running gear bottom plate is through running gear strengthening web and walking Device top plate is connected, and running gear top plate is fixed together with C-shaped hook head end, and running gear strengthening web front and rear sides are set There is shrouding;The walking track includes the U-shaped reinforcing bar that section has been poured in embedment, and section surface has been poured in U-shaped reinforcing bar top with being located at Walking installing seat for rail connection, walking installing seat for rail include 2 blocks of side plates, form walking passageway between side plate;Walking dress Put in walking passageway, the running gear counter-force seat being fixed on side plate is additionally provided with walking passageway, running gear is anti- Hydraulic jack is provided with power seat.
Cradle structure in foregoing reinforced concrete arch bridge building course, the running gear strengthening web and side plate On be provided with bearing pin and penetrate hole.
Cradle structure in foregoing reinforced concrete arch bridge building course, two secondary C-shaped hook top and bottom are respectively Connection cross bar is linked up with by C-shaped to connect.
Cradle structure in foregoing reinforced concrete arch bridge building course, the main truss load bearing system are divided into the knot that winds up Structure and lower beam string structure, body structure is attached into by vertical rod and brace between upper and lower beam string structure, upper and lower beam string structure includes There is multi-disc longitudinal direction main truss piece, be attached between longitudinal main truss piece by multi-disc transverse direction main truss piece, main truss load bearing system is hung with C-shaped Hook is that node is divided into preceding basket and rear basket, wherein the horizontal main truss piece of preceding basket is more than rear basket, longitudinal main truss in preceding blue upper beam string structure The multi-disc distribution purlin piece parallel with horizontal main truss piece is also associated between piece, is also associated between longitudinal main truss piece of rear basket oblique Connection purlin piece.
Cradle structure in foregoing reinforced concrete arch bridge building course, basket both sides are each after the main truss load bearing system 1 anti-offset roller devices is provided with, anti-offset roller devices include the anti-offset roller being arranged on main truss load bearing system Mounting bracket, 2 pieces of horizontal mounting plates are provided with anti-offset roller mounting bracket, are connected between 2 pieces of horizontal mounting plates anti-bias Rolling wheel installing shaft is moved, is provided with anti-offset roller on anti-offset rolling wheel installing shaft, anti-offset roller props up the side for having poured section.
The beneficial effects of the utility model:Compared with prior art, cradle structure of the present utility model is by lifting load-bearing Main truss load bearing system, template system, concrete load are transferred to and have poured section by screw rod, meanwhile, caused by after forward and backward basket stand under load Horizontal pull realizes partial equilibrium and counteracting by C-shaped hook, tiltedly climbs sliding force caused by Hanging Basket, caused by concrete load Sliding force realizes balance by stopping mechanism, and main truss cradle intensity, rigidity are larger.During hanging basket advancing, load-bearing screw rod is lifted Decentralization, C-shaped is linked up with into upper end pressure-bearing on vertical shift walking track, the anti-roller in anti-roller devices reacts on arch box bottom surface, Lifting load-bearing screw rod is taken out, the hydraulic jack of top surface rear end is linked up with by C-shaped, moved forward Hanging Basket, and Hanging Basket is moved to and newly pours section Fragment position, and the adjustment at Hanging Basket angle of inclination can be carried out by the raising and lowering of the anti-roller devices in rear end, meanwhile, to avoid hanging The plan-position skew that basket is likely to occur during reach, anti-offset roller devices are laterally set in the side of main truss rear end, Anti-offset roller clamps arch ring side, is always ensured that Hanging Basket axis and arch ring diameter parallel, and the apparatus structure is simple, but can be effective Play a part of preventing Hanging Basket from producing lateral shift.During hanging basket advancing, hydraulic jack one end is supported on rail top face position Geostationary running gear counter-force seat is put, the other end is supported on C-shaped hook top surface rear end, and starting hydraulic jack can drive Hanging Basket forward, move up, iterative cycles hydraulic jack stroke, so as to realize the walking of whole Hanging Basket;Horizontal stopping device It is made up of counter-force support element and counter-force support, counter-force support element, which is embedded in, has poured section arch box bottom, counter-force support element Upper to reserve 12 bolts hole, upper surface of steel plate puts on nut, and nut top surface is closed using thick 3mm steel plate, avoids concrete from pouring During building, concrete immerses bolt hole.Hanging basket advancing in place after, counter-force support passes through 12 counter-force screw rods and counter-force branch framework Part is bolted together, and forms horizontal stopping device, need not be to arch in counter-force support element setting up procedure due to being bolt connection The reinforcing bar and concrete in bottom portion are caused to damage, and counter-force support is removed after the completion of use, and arch ring outward appearance can be recovered by giving modification, Bridge structure is not interfered with.Span that cradle structure of the present utility model improves former rod member formula Hanging Basket is small, deformation is larger Shortcoming, cantilever pouring length extend to unprecedented 8.0m length by original 6.5m, and main truss is held in casting process Weight system sinking is smaller, no more than 20mm;And stopping mechanism is simple, convenient, and reliable, to arch ring structure not damaged, Hanging Basket tilts Angle is adjusted by the counter-force roller devices of Hanging Basket afterbody, and structure is simple and direct, accurate, and stress is clear and definite.
Brief description of the drawings
Accompanying drawing 1 is structural representation of the present utility model;
Accompanying drawing 2 is the overlooking the structure diagram of accompanying drawing 1;
Accompanying drawing 3 is the side structure schematic diagram of accompanying drawing 1;
Accompanying drawing 4 is the structural representation of anti-roller devices;
Accompanying drawing 5 is the side structure schematic diagram of accompanying drawing 4;
Accompanying drawing 6 is the overlooking the structure diagram of accompanying drawing 4;
Accompanying drawing 7 is the close-up schematic view of accompanying drawing 2;
Accompanying drawing 8 is the structural representation of C-shaped hook;
Accompanying drawing 9 is the close-up schematic view of accompanying drawing 8;
Accompanying drawing 10 is the assembling schematic diagram of running gear and track of walking;
Accompanying drawing 11 is the structural representation of anti-offset roller devices;
Reference:1- main truss load bearing systems, 2-C shapes hook, 3- running gears, 4- arch boxes, 5- walking tracks, 6- connections Plate, 7- oblique pull suspender belts, 8- pulling seats, the anti-roller devices of 9-, the anti-roller supporting seats of 10-, the anti-bearing pins of roller first of 11-, the anti-rollers of 12- Support arm, the anti-bearing pins of roller second of 13-, the anti-rollers of 14-, 15- adjusting bolts, the anti-roller sliding blocks of 16-, 17- lifting load-bearing screw rods, 18- counter-force support elements, 19- counter-force supports, 20- counter-force nuts, 21- counter-force screw rods, 22- running gear bottom plates, 23- walking dresses Put slide plate, 24- running gear strengthening webs, 25- running gear top plates, 26-U shape reinforcing bars, 27- walking installing seat for rail, 28- sides Plate, 29- walking passageways, 30- running gear counter-force seats, 31- hydraulic jacks, 32- bearing pins penetrate hole, and the hook connection of 33-C shapes is horizontal Bar, 34- longitudinal directions main truss piece, 35- transverse direction main truss pieces, 36- braces, 37- are coupled purlin piece, and 38- distributes purlin piece, 39- shroudings, and 40- is stood Bar, the anti-offset roller devices of 41-, the anti-offset roller mounting brackets of 42-, 43- horizontal mounting plates, the anti-offset rolling wheel installing shafts of 44-, The anti-offset rollers of 45-.
Embodiment
The utility model is further described with reference to the accompanying drawings and examples, but is not intended as to the utility model The foundation of limitation.
Embodiment of the present utility model:Cradle structure in a kind of reinforced concrete arch bridge building course, such as accompanying drawing 1- Shown in 11, include main truss load bearing system 1, the middle part of main truss load bearing system 1 left and right sides is each provided with 1 secondary C-shaped hook 2, and C-shaped is hung The top of hook 2 is connected with running gear 3, and the bottom of running gear 3 is located on the walking track 5 at the top of arch box 4 for having poured section, C-shaped Connecting plate 6 is provided with hook 2, connecting plate 6 is each side by more oblique pull suspender belts 7 and before main truss load bearing system 1 Basket and the pulling seat 8 of rear basket side are connected, and 2 anti-roller devices 9 are provided with rear basket, are provided with main truss load bearing system 1 Lift load-bearing screw rod 17.After lifting load-bearing screw rod 17 passes through the reserved lifting load-bearing screw hole poured on section during use, it is pushed up Portion is connected with hydraulic feed-through jack, using hydraulic feed-through jack by lifting load-bearing screw rod 17 by main truss load bearing system After 1 lifting in place and anchor.Then the front end of main truss load bearing system 1 is that bed die and other mould bases are installed on the preceding basket of Hanging Basket again Structure, lifting load-bearing screw hole is reserved in die carrier structure installation process, then casting concrete.C-shaped hook 2 in whole process Top-hung is at the top for having poured section.Pour section it is up to standard after, release the lifting load-bearing screw rod 17 of Hanging Basket so that with C-shaped hook 2 The running gear 3 of connection falls in track 5 of walking, and C-shaped hook 2 and the master being attached thereto can be driven by running gear 3 Purlin load bearing system 1 is walked.The anti-roller devices 9 include the anti-roller supporting seat 10 being fixed on main truss load bearing system 1, instead The bottom that the anti-roller supporting arm 12 of anti-the first bearing pin of roller more than 11,2 is provided with roller supporting seat 10 penetrates anti-roller In first bearing pin 11, the anti-top of roller supporting arm 12 is attached by anti-the second bearing pin of roller 13, anti-the second bearing pin of roller 13 In penetrated anti-roller 14,1 adjusting bolt 15 has been also fed through on anti-roller supporting seat 10, the head end of adjusting bolt 15 is connected with position In the anti-roller sliding block 16 on anti-roller supporting seat 10, anti-roller sliding block 16 props up the side of anti-roller supporting arm 12.It is whole to hang In basket moving process, roller 14 is pressed on the bottom surface for having poured section, is formed 1 strong point, is facilitated the movement of Hanging Basket.Bridge pours During, it is necessary to adjust the angle of bed die by the angle of main truss load bearing system 1 and horizontal plane, method of adjustment is:Rotation is adjusted Whole screw rod 15, because the other end of adjusting bolt 15 contacts with anti-roller sliding block 16, after rotating adjusting bolt 15 inwards, adjustment Screw rod 15 can promote anti-roller sliding block 16 to move inwards, because anti-roller supporting arm 12 contacts with anti-roller sliding block 16 again, anti-rolling Wheel sliding block 16 in moving process, can drive anti-roller supporting arm 12 to be rotated around anti-the first bearing pin of roller 11 so that anti-roller inwards Angle increase between the main truss load bearing system 1 of support arm more than 12, the preceding basket of main truss load bearing system 1 can make it that during angle increase Sink, rear basket upwarps the angle adjustment for realizing main truss load bearing system 1, when adjusting bolt 15 screws out backward, can cause anti-roller Angle between the main truss load bearing system 1 of support arm more than 12 diminishes, and angle can cause the preceding basket of main truss load bearing system 1 during diminishing Upwarp, after sink in the key.
Also include horizontal stopping device, horizontal stopping device, which includes, is embedded in the anti-of the bottom of arch box 4 for having poured section Power support element 18, also include the counter-force support 19 being arranged on main truss load bearing system 1, pass through counter-force spiral shell on counter-force support 19 Mother 20 is fixed with counter-force screw rod 21.When Hanging Basket, which is moved to, needs position, Hanging Basket is lifted up by lifting load-bearing screw rod 17, So that the rear end of counter-force screw rod 21 props up counter-force support element 18, Hanging Basket is avoided to be moved after occurring under gravity.Due to counter-force branch Frame member 18 is just embedded in mould bases before casting concrete, therefore sets counter-force support again after need not having poured concrete the later stage Component 18, avoid damaging the concrete that has poured in setting up procedure.
The running gear 3 includes running gear bottom plate 22, and the bottom of running gear bottom plate 22 is provided with running gear cunning Plate 23, running gear bottom plate 22 are connected through running gear strengthening web 24 with running gear top plate 25, running gear top plate 25 and C Shape is linked up with 2 head ends and is welded and fixed together, and the front and rear sides of running gear strengthening web 24 are provided with shrouding 39;The walking track 5 include the U-shaped reinforcing bar 26 that section has been poured in embedment, and U-shaped reinforcing bar 26 is first embedded in die carrier structure when setting mould bases, Ran Houzai Casting concrete, and cause the head end of U-shaped reinforcing bar 26 is exposed to stop outside concrete, then again by the top of U-shaped reinforcing bar 26 with being located at The walking installing seat for rail 27 for having poured section surface connects, and walking installing seat for rail 27 includes 2 blocks of side plates 28, between side plate 28 Form walking passageway 29;Running gear 3 is put into walking passageway 29, is additionally provided with and is fixed on side plate 28 in walking passageway 29 Running gear counter-force seat 30, be provided with hydraulic jack 31 on running gear counter-force seat 30.When Hanging Basket moves, hydraulic jack 31 afterbodys prop up running gear counter-force seat 30, and hydraulic jack 31 contacts after releasing with shrouding 39, so as to promote running gear 3 to exist Moved in the walking passageway 29 of walking track 5, running gear 3 drives C-shaped hook 2 and main truss load bearing system 1 to move together, works as shifting When moving to the range of hydraulic jack 31, first running gear 3 is fixed, then dismantled running gear counter-force seat 30, It is arranged on side plate 28, then unclamps securing running gear 3, hydraulic jack 31 is released again, you can again further along It is secondary to promote running gear 3 forward, and so on until Hanging Basket is moved to and needs position.
Bearing pin is provided with the running gear strengthening web 24 and side plate 28 and penetrates hole 32, when needing to running gear 3 when being fixed, and the bearing pin on fixed bearing pin insertion running gear strengthening web 24 and side plate 28 is penetrated into hole 32, you can Realize the fixation work of running gear 3.
Connection cross bar 33 is linked up with by C-shaped respectively and connected in the two secondary top and bottom of C-shaped hook 2.So that C-shaped hook 2 is formed One entirety, it is easy to bear the gravity of main truss load bearing system 1.
The main truss load bearing system 1 divides for upper beam string structure and lower beam string structure, by vertical rod 40 and tiltedly between upper and lower beam string structure Bar 36 is attached into body structure, and upper and lower beam string structure includes multi-disc longitudinal direction main truss piece 34, passed through between longitudinal main truss piece 34 Multi-disc transverse direction main truss piece 35 is attached, and main truss load bearing system 1 is divided into preceding basket and rear basket by node of C-shaped hook, wherein preceding basket Horizontal main truss piece 35 be more than rear basket, be also associated with multi-disc and horizontal main truss between longitudinal main truss piece 34 in preceding blue upper beam string structure The parallel distribution purlin piece 38 of piece 35, oblique connection purlin piece 37 is also associated between longitudinal main truss piece 34 of rear basket.It is easy to pour The gravity afforded is distributed when concrete.
Basket both sides are each provided with 1 anti-offset roller devices 41, anti-offset roller devices 41 after the main truss load bearing system 1 Include the anti-offset roller mounting bracket 42 being arranged on main truss load bearing system 1, set in anti-offset roller mounting bracket 42 Have and anti-offset rolling wheel installing shaft 44 is connected between 2 pieces of horizontal mounting plates, 43,2 pieces of horizontal mounting plates 43, anti-offset roller installation Anti-offset roller 45 is provided with axle 44, anti-offset roller 45 props up the side for having poured section.It is anti-offset during hanging basket advancing Roller 45 props up the side for having poured section all the time, is always ensured that Hanging Basket axis and arch ring diameter parallel, and the apparatus structure is simple, but The effect for preventing Hanging Basket from producing lateral shift can be effectively played.

Claims (7)

  1. A kind of 1. cradle structure in reinforced concrete arch bridge building course, it is characterised in that:Include main truss load bearing system (1), main truss load bearing system(1)Middle part arranged on left and right sides is each provided with 1 secondary C-shaped hook(2), C-shaped hook(2)Top is connected with row Walking apparatus(3), running gear(3)Bottom is located at the arch box for having poured section(4)The walking track at top(5)On, C-shaped hook(2) On be provided with connecting plate(6), connecting plate(6)Arranged on left and right sides respectively passes through more oblique pull suspender belts(7)With positioned at main truss load bearing system (1)Preceding basket and the pulling seat of rear basket side(8)Connection, is provided with anti-roller devices on rear basket(9), in main truss load bearing system(1) On be provided with lifting load-bearing screw rod(17);The anti-roller devices(9)Include anti-roller supporting seat(10), anti-roller supporting seat (10)On be provided with the anti-bearing pin of roller first(11), the anti-roller supporting arm of more than 2(12)Bottom penetrate anti-roller first Bearing pin(11)In, anti-roller supporting arm(12)Top passes through the anti-bearing pin of roller second(13)It is attached, the anti-bearing pin of roller second (13)In penetrated anti-roller(14), anti-roller supporting seat(10)On be also fed through 1 adjusting bolt(15), adjusting bolt(15) Head end is connected with positioned at anti-roller supporting seat(10)On anti-roller sliding block(16), anti-roller sliding block(16)Prop up anti-roller supporting Arm(12)Side.
  2. 2. the cradle structure in reinforced concrete arch bridge building course according to claim 1, it is characterised in that:Also wrap Horizontal stopping device is included, horizontal stopping device, which includes, is embedded in the arch box for having poured section(4)The counter-force support element of bottom (18), also include and be arranged on main truss load bearing system(1)On counter-force support(19), counter-force support(19)It is upper to pass through counter-force nut (20)It is fixed with counter-force screw rod(21).
  3. 3. the cradle structure in reinforced concrete arch bridge building course according to claim 1, it is characterised in that:It is described Running gear(3)Include running gear bottom plate(22), running gear bottom plate(22)Bottom is provided with running gear slide plate(23), Running gear bottom plate(22)Through running gear strengthening web(24)With running gear top plate(25)Connection, running gear top plate(25) Linked up with C-shaped(2)Head end is fixed together, running gear strengthening web(24)Front and rear sides are provided with shrouding(39);The row Walk track(5)Include the U-shaped reinforcing bar that section has been poured in embedment(26), U-shaped reinforcing bar(26)Section surface has been poured with being located in top Walking installing seat for rail(27)Connection, installing seat for rail of walking(27)Include 2 blocks of side plates(28), side plate(28)Between formed row Walk passage(29);Running gear(3)It is put into walking passageway(29)In, in walking passageway(29)In be additionally provided with and be fixed on side plate (28)On running gear counter-force seat(30), running gear counter-force seat(30)On be provided with hydraulic jack(31).
  4. 4. the cradle structure in reinforced concrete arch bridge building course according to claim 3, it is characterised in that:It is described Running gear strengthening web(24)And side plate(28)On be provided with bearing pin and penetrate hole(32).
  5. 5. the cradle structure in reinforced concrete arch bridge building course according to claim 1, it is characterised in that:Two is secondary C-shaped is linked up with(2)Connection cross bar is linked up with by C-shaped respectively in top and bottom(33)Connection.
  6. 6. the cradle structure in reinforced concrete arch bridge building course according to claim 1, it is characterised in that:It is described Main truss load bearing system(1)It is divided into beam string structure and lower beam string structure, passes through vertical rod between upper and lower beam string structure(40)And brace(36)Enter Row connects into body structure, and upper and lower beam string structure includes multi-disc longitudinal direction main truss piece(34), longitudinal main truss piece(34)Between by more Piece transverse direction main truss piece(35)It is attached, main truss load bearing system(1)It is divided into preceding basket and rear basket by node of C-shaped hook, wherein before The horizontal main truss piece of basket(35)More than rear basket, longitudinal main truss piece in preceding blue upper beam string structure(34)Between be also associated with multi-disc with it is horizontal To main truss piece(35)Parallel distribution purlin piece(38), longitudinal main truss piece of rear basket(34)Between be also associated with oblique connection purlin piece (37).
  7. 7. the cradle structure in reinforced concrete arch bridge building course according to claim 1, it is characterised in that:It is described Main truss load bearing system(1)Basket both sides are each provided with 1 anti-offset roller devices afterwards(41), anti-offset roller devices(41)Include It is arranged on main truss load bearing system(1)On anti-offset roller mounting bracket(42), anti-offset roller mounting bracket(42)Upper setting There are 2 pieces of horizontal mounting plates(43), 2 pieces of horizontal mounting plates(43)Between be connected with anti-offset rolling wheel installing shaft(44), anti-offset rolling Take turns installation axle(44)On be provided with anti-offset roller(45), anti-offset roller(45)Prop up the side for having poured section.
CN201720488193.9U 2017-05-04 2017-05-04 A kind of cradle structure in reinforced concrete arch bridge building course Active CN206721694U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720488193.9U CN206721694U (en) 2017-05-04 2017-05-04 A kind of cradle structure in reinforced concrete arch bridge building course

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720488193.9U CN206721694U (en) 2017-05-04 2017-05-04 A kind of cradle structure in reinforced concrete arch bridge building course

Publications (1)

Publication Number Publication Date
CN206721694U true CN206721694U (en) 2017-12-08

Family

ID=60508686

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720488193.9U Active CN206721694U (en) 2017-05-04 2017-05-04 A kind of cradle structure in reinforced concrete arch bridge building course

Country Status (1)

Country Link
CN (1) CN206721694U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988230A (en) * 2017-05-04 2017-07-28 贵州桥梁建设集团有限责任公司 A kind of cradle structure in reinforced concrete arch bridge building course
CN115162211A (en) * 2022-09-07 2022-10-11 中铁十七局集团第五工程有限公司 Cantilever pouring construction method for main arch ring of reinforced concrete arch bridge

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106988230A (en) * 2017-05-04 2017-07-28 贵州桥梁建设集团有限责任公司 A kind of cradle structure in reinforced concrete arch bridge building course
CN115162211A (en) * 2022-09-07 2022-10-11 中铁十七局集团第五工程有限公司 Cantilever pouring construction method for main arch ring of reinforced concrete arch bridge
CN115162211B (en) * 2022-09-07 2022-12-30 中铁十七局集团第五工程有限公司 Cantilever pouring construction method for main arch ring of reinforced concrete arch bridge

Similar Documents

Publication Publication Date Title
CN208815424U (en) A kind of bridge descending hanging basket
CN106988230A (en) A kind of cradle structure in reinforced concrete arch bridge building course
CN104631343B (en) From traveling rhombus keying cradle in truss type structure and suspended basket and construction method
CN109868755B (en) Hanging basket construction method for diamond truss hanging basket and cantilever beam
CN203904851U (en) Continuous beam side span straight section hanger support system
CN105951610A (en) Support structure assisting in cantilever beam construction and construction method
WO2020052291A1 (en) Construction elevator wall-attaching frame mounting platform attached to steel platform formwork and method therefor
CN106120568A (en) Cross a river Main Bridge bridge pier secondary locking temporary consolidation structure and construction method
CN105568870B (en) For the triangle hanging basket method cantilever device and its construction method of cross-line bridge construction
CN107905124B (en) A kind of symmetrical expression rigid frame-continuous girder construction technology
CN107905111B (en) A kind of rigid frame-continuous girder end bay construction technology
CN206721694U (en) A kind of cradle structure in reinforced concrete arch bridge building course
CN206680962U (en) Hydraulic self-lifting truss-like cantilever heavy type arch dam template system
CN113882279A (en) Self-walking and self-adjusting concrete continuous beam cantilever pouring construction equipment and process
CN101858055A (en) Setting steel pipe bracket support system of cover beam and construction method thereof
CN111622781A (en) Construction equipment and method for suspension bridge tunnel anchor chamber vault secondary lining
CN203878979U (en) Bolt opposite-pulling type track sliding formwork
CN211472207U (en) Suspension beam system for hoisting prefabricated section box girder
CN109356618A (en) A kind of simple integral movable type square type tunnel frame and its construction method
CN105386414B (en) Lower-guide type main-truss-free hanging basket
CN111827648A (en) Construction device and method for down-supporting type overhanging scaffold
WO2023159853A1 (en) Suspension stepping type shed erecting machine
CN108797380B (en) Suspension construction device and construction method for suspension irrigation continuous beam bracket
CN205975377U (en) Structure is concretied in locking of cross a river bridge owner pier secondary temporarily
CN108867411A (en) System bridge jacking system and its construction method are underpined based on detachable prestressing force

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant