CN206693465U - Assembling type steel structure builds out-hung panel - Google Patents
Assembling type steel structure builds out-hung panel Download PDFInfo
- Publication number
- CN206693465U CN206693465U CN201621417460.5U CN201621417460U CN206693465U CN 206693465 U CN206693465 U CN 206693465U CN 201621417460 U CN201621417460 U CN 201621417460U CN 206693465 U CN206693465 U CN 206693465U
- Authority
- CN
- China
- Prior art keywords
- contiguous block
- plate
- short slab
- assembling type
- steel structure
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Finishing Walls (AREA)
Abstract
The utility model discloses a kind of assembling type steel structure to build out-hung panel, including steel construction and the plate being fixed on steel construction, plate includes long plate body and short slab body, junction is provided with clinch between long plate body and short slab body and between short slab body and short slab body, plate both ends, which are respectively arranged with to erect across the contiguous block I between upper long plate body, short slab body and lower body and contiguous block II, long plate body and short slab body end portion, is respectively arranged with contiguous block I or contiguous block II groove;The utility model is fluted by the end set in plate body, using being provided with contiguous block in groove, when being assembled into plate under the contiguous block is online, the fit tolerance between overlap joint recess and corresponding overlap joint convex portion can be adjusted, it is bolted in plate on steel construction, it can avoid moving between plate up and down, and can make that contiguous block is coordinated at perps between plate and plate, improve its poor waterproof properties and the low intensity of Side fascia.
Description
Technical field
The utility model belongs to the technical field being made up of barrier material and concrete, building stones or stone class material, is specifically
It is related to a kind of assembling type steel structure building out-hung panel and installation method.
Background technology
The upper surface of assembling type steel structure building out-hung panel is formed with overlap joint recess on existing market;Corresponding assembling
Formula steel building out-hung panel forms overlap joint convex portion close to opposite side lower surface, and adjacent two pieces of assembling type steel structures are built during installation
Build out-hung panel and be connected by overlapping recess with corresponding overlap joint convex portion, then two pieces of assembling type outer walls are bolted
On steel construction, the lower overall assembling and be in level during mounting hanger online of this assembling type steel structure building out-hung panel
Place, suspender is removed after the completion of lifting, assembling type steel structure building out-hung panel prevents it except bolt is fixedly connected
Outside toppling over and coming off, upper assembling type steel structure building out-hung panel in the assembling type steel structure building out-hung panel being vertically connected with
Most of Gravity support is built on overlap joint recess or overlap joint convex portion due to being fixed on bolt on steel construction with assembling type steel structure
Build between the gap between out-hung panel mounting hole and overlap joint recess and corresponding overlap joint convex portion and fit tolerance be present, easily go out
Now shifted up and down between assembling type steel structure building out-hung panel, assembling type steel structure builds the surfacing of out-hung panel
Degree is inadequate, prevents between assembling type steel structure building out-hung panel and assembling type steel structure building out-hung panel at perps from realizing
It is fully sealed, its poor waterproof properties, the low intensity of wall,
The content of the invention
In view of this, the purpose of this utility model is to provide assembling type steel structure building out-hung panel, the assembled steel
Structural construction out-hung panel is fluted by the end set in plate body, using being provided with contiguous block in groove, the contiguous block
When being assembled into plate under online, the fit tolerance between overlap joint recess and corresponding overlap joint convex portion can be adjusted, is passed through in plate
It is bolted on steel construction, can avoids moving between plate up and down, and perps between plate and plate can be made
Place's contiguous block is coordinated, and improves its poor waterproof properties and the low intensity of Side fascia.
In order to achieve the above object, a kind of assembling type steel structure of the utility model building out-hung panel, including by steel column, on
Girder steel connects the steel construction to be formed with lower girder steel and no less than 1 row and the plate that is bolted in steel construction side wall, institute
Stating plate includes about a pair horizontally disposed long plate bodys and is arranged between long plate body and no less than the short slab body of 2 rows, described
Junction is provided with clinch, the plate both ends difference between long plate body and short slab body and between short slab body and short slab body
It is provided with perpendicular across the contiguous block I between upper long plate body, short slab body and lower body and contiguous block II, the long plate body and short slab body
End is respectively arranged with contiguous block I or contiguous block II groove.
Further, window frame is provided with the plate, is connected around the window frame with short slab body.
Further, the width of the contiguous block I and contiguous block II are arranged to the 1/2~2/3 of plate width, the contiguous block
The height that groove is extended in I and contiguous block II upper surfaces is 5~10mm.
Further, contact surface is respectively set to concave and convex surface between the contiguous block I and contiguous block II.
Further, serrate slot is correspondingly arranged on the surface contacted between the contiguous block I and contiguous block II.
Further, cavity is arranged at intervals with the contiguous block I and contiguous block II, foaming agent is provided with the cavity,
Be provided with contiguous block I and contiguous block the II side walls connected with cavity go out agent hole, contiguous block I and contiguous block the II surface
On covered with one layer of plastic sheet or film for closing out agent hole.
Further, the foaming agent is arranged to mixed foaming agent, and foaming agent is arranged to Lauxite in contiguous block I, described
Foaming agent is arranged to furfural alcohol modified urea formaldehyde resin in contiguous block II.
The beneficial effects of the utility model are:
1st, the utility model assembling type steel structure building out-hung panel it is fluted by the end set in plate body, using
Contiguous block is provided with groove, when being assembled into plate under the contiguous block is online, can adjust overlap joint recess with it is corresponding overlap it is convex
Fit tolerance between portion, is bolted on steel construction in plate, can avoid moving between plate up and down, and
And can make that contiguous block is coordinated at perps between plate and plate, improve its poor waterproof properties and the intensity of Side fascia
It is low;
2nd, the utility model assembling type steel structure building out-hung panel passes through the two neighboring contiguous block in plate stitching portion
Between be provided with and be correspondingly arranged on concave panel and convex, conveniently carry out lifting positioning, can avoid occurring between plate up and down
It is mobile, improve working efficiency;
3rd, the utility model assembling type steel structure building out-hung panel passes through the two neighboring contiguous block in plate stitching portion
Expanded material is inside arranged at intervals with, after plate lifting in place, the expanded material in contiguous block is carried out mixed foaming, makes plate
Expanded material in block stitching portion foams from the inside to the outside, and avoiding stitching portion, either space or gap occurs in edge joint position, avoids ant
Ant or termite discrepancy edge joint position, improve its water resistance.
Brief description of the drawings
In order that the purpose of this utility model, technical scheme and beneficial effect are clearer, the utility model provides as follows
Accompanying drawing illustrates:
Fig. 1 is the structural representation that the utility model assembling type steel structure builds out-hung panel;
Fig. 2 is the plate body lifting structure graph that the utility model assembling type steel structure builds out-hung panel;
Fig. 3 is that the utility model assembling type steel structure builds plate body side view in out-hung panel;
Fig. 4 is that the utility model assembling type steel structure builds stitching portion sectional view in out-hung panel.
Brief description of the drawings:1- steel constructions;2- plates;The long plate bodys of 3-;4- short slab bodies;5- HOOK BOLTSs;6- contiguous blocks I;7- connects
Meet block II;8- window frames;9- suspenders;10- grooves;11- clinch;12- perps;13- foaming agents.
Embodiment
Below in conjunction with accompanying drawing, preferred embodiment of the present utility model is described in detail.
The structural representation of out-hung panel is built for the utility model assembling type steel structure as shown in Figure 1;It is illustrated in figure 2
The plate body lifting structure graph of the utility model assembling type steel structure building out-hung panel;It is illustrated in figure 3 the utility model
Plate body side view in assembling type steel structure building out-hung panel;It is outer to be illustrated in figure 4 the utility model assembling type steel structure building
Stitching portion sectional view in wallboard;A kind of assembling type steel structure building out-hung panel of the utility model, including by steel column, upper girder steel
The steel construction 1 to be formed is connected with lower girder steel and no less than 1 row and the plate 2 that is bolted in steel construction side wall, it is described
Plate 2 includes about a pair horizontally disposed long plate bodys 3 and is arranged between long plate body 3 and no less than the short slab body 4 of 2 rows, institute
State between long plate body 3 and short slab body 4 and junction is provided with clinch 11, the plate between short slab body 4 and short slab body 4
2 both ends are respectively arranged with perpendicular across the contiguous block I6 between upper long plate body, short slab body and lower body and contiguous block II7, the length
Plate body 3 and the end of short slab body 4 are respectively arranged with contiguous block I6 or contiguous block II7 groove 10.
The present embodiment is fluted by the end set in plate body, using being provided with contiguous block in groove, the contiguous block
When being assembled into plate under online, the fit tolerance between overlap joint recess and corresponding overlap joint convex portion can be adjusted, is passed through in plate
It is bolted on steel construction, can avoids moving between plate up and down, and perps between plate and plate can be made
Place's contiguous block is coordinated, and improves its poor waterproof properties and the low intensity of Side fascia.
Further, window frame 8 is provided with the preferable plate 2, is connected around the window frame 8 with short slab body 4.
Further, preferable the contiguous block I6 and contiguous block II7 width are arranged to the 1/2~2/3 of plate width, institute
State contiguous block I6 and to extend the height of groove 10 be 5~10mm for contiguous block II7 upper surfaces.
Further, preferable contact surface between the contiguous block I6 and contiguous block II7 is respectively set to concave and convex surface, this
Embodiment is correspondingly arranged on concave panel and convex by being provided between the two neighboring contiguous block of plate stitching portion, convenient
Lifting positioning is carried out, can avoid moving between plate up and down, improve working efficiency, the present embodiment can also use another
Structure is planted, serrate slot is correspondingly arranged on the preferable surface contacted between the contiguous block I6 and contiguous block II7.
Further, cavity is arranged at intervals with preferable the contiguous block I6 and contiguous block II7, is provided with the cavity
Foaming agent 13, be provided with contiguous block I6 and contiguous block the II7 side walls connected with cavity go out agent hole, the contiguous block I and
Pass through on contiguous block II surfaces covered with one layer of plastic sheet or film for closing out agent hole, the present embodiment in plate stitching portion
Expanded material is arranged at intervals with two neighboring contiguous block, after plate lifting in place, enters the expanded material in contiguous block
Row mixed foaming, the expanded material in plate stitching portion is foamed from the inside to the outside, avoid stitching portion or edge joint position from space occur
Or gap, ant or termite discrepancy edge joint position are avoided, improves its water resistance.
Further, the preferable foaming agent is arranged to mixed foaming agent, and foaming agent is arranged to ureaformaldehyde tree in contiguous block I
Fat, foaming agent is arranged to furfural alcohol modified urea formaldehyde resin in the contiguous block II.
The invention also discloses a kind of installation method of assembling type steel structure building out-hung panel, its step are as follows:
1) prepared by long plate body, short slab body and contiguous block:ALC wallboards are made according to standard specification in long plate body and short slab body, and two
Groove is left in side, and contiguous block is used made of iron sheet or plastic skin,
2) the position wallboard that will be determined, sorts by erection sequence, and numbering is transported to scene, and steel construction is entered by drawing technical requirements
Row installation;
3) plate group pair:By 1 pair of long plate body and much lifted successively to platform for lining with 2 pairs of short slab bodies and scrabble up plate,
Closely connected between long plate body and short slab body and between short slab body and short slab body, termination will flush, by contiguous block I and contiguous block
II is connected in the groove at plate both ends;
4) suspender is installed:Suspender is in place using crane lifting, it is in place after bottom fixed with platform for lining with bearing pin, suspender and
Per block length plate body or short slab body is connected using screw rod;Screw hole uses the impact drilling, and screw rod is penetrated, twisted with nut from lower to upper
Enter fixation;
5) HOOK BOLTS mounting hole is bored:First positioned before drilling, position line is ejected using print cartridge line, after ejecting position line
Start to drill;
6) wallboard lifts:Suspender 9 is provided with two hangers, during lifting by two isometric hoist cables by snap ring respectively with hanging
Ear connects;Then wallboard is slowly sling, after wallboard is vertical directly, removes suspender bottom bearing pin, then rotary suspension arm, wallboard is hung
To installation site;
7) HOOK BOLTS 5 is installed:After wallboard is hung to installation site, wallboard and steel construction relative position, Ran Houkai are adjusted
Begin to carry out HOOK BOLTS installation;
8) suspender is removed:Treat that all HOOK BOLTSs are fixed to finish, suspender and wallboard connecting screw are removed one by one, then will
Suspender is hung to next plate assembling position, continues next piece of plate lifting;
9) wallboard jointing:Horizontal joint is docked than shallower, first opposite joint carries out surface cleaning before jointing, removes surface floating dust, so
Special seal gum is irrigated along transverse joint direction afterwards, fluid sealant perfusion is uniform, smooth, and the position deeper to gap can be first to use
PE rods are filled up, then Reperfu- sion fluid sealant, and docking perps 12 is deep, and depth is equal to thickness of slab, and width is usually 10mm~20mm,
It is slightly different with docking transverse joint to the processing scheme of this seam, first crammed with extruded sheet to transverse joint depth, then use PE rods again
Cram, finally use special seal gum capping again.
Further, be provided with foaming agent in the contiguous block I and contiguous block II, before jointing, tear initiation contiguous block I and
The one layer of plastic sheet or film covered on contiguous block II surfaces, after waiting foaming agent foam 1~2 hour, then proceeds by jointing
Processing.
Finally illustrate, preferred embodiment above is only unrestricted to illustrate the technical solution of the utility model, to the greatest extent
The utility model has been described in detail by above preferred embodiment for pipe, but those skilled in the art should manage
Solution, can make various changes, without departing from the utility model claims book institute to it in the form and details
The scope of restriction.
Claims (7)
1. a kind of assembling type steel structure builds out-hung panel, it is characterised in that:Including connecting shape with lower girder steel by steel column, upper girder steel
Into steel construction and include about a pair no less than 1 row and the plate that is bolted in steel construction side wall, the plate
Horizontally disposed long plate body and it is arranged between long plate body and no less than the short slab body of 2 rows, between the long plate body and short slab body
And junction is provided with clinch between short slab body and short slab body, the plate both ends are respectively arranged with perpendicular across upper long slab
Contiguous block I and contiguous block II between body, short slab body and lower body, the long plate body and short slab body end portion are respectively arranged with connection
Block I or contiguous block II groove.
2. assembling type steel structure according to claim 1 builds out-hung panel, it is characterised in that:It is provided with the plate
Window frame, it is connected with short slab body around the window frame.
3. assembling type steel structure according to claim 1 builds out-hung panel, it is characterised in that:The contiguous block I and company
The width for meeting block II is arranged to the 1/2~2/3 of plate width, and groove is extended in contiguous block I and contiguous block the II upper surface
Highly it is 5~10mm.
4. assembling type steel structure according to claim 1 builds out-hung panel, it is characterised in that:The contiguous block I and company
Contact surface is respectively set to concave and convex surface between meeting block II.
5. assembling type steel structure according to claim 1 builds out-hung panel, it is characterised in that:The contiguous block I and company
Connect and be correspondingly arranged serrate slot on the surface contacted between block II.
6. assembling type steel structure according to claim 1 builds out-hung panel, it is characterised in that:The contiguous block I and company
Connect and cavity is arranged at intervals with block II, foaming agent is provided with the cavity, is set in contiguous block I and contiguous block the II side walls
There is what is connected with cavity to go out agent hole, covered with one layer of plastic sheet for closing out agent hole on contiguous block I and contiguous block the II surface
Or film.
7. assembling type steel structure according to claim 6 builds out-hung panel, it is characterised in that:The foaming agent is arranged to
Mixed foaming agent, foaming agent is arranged to Lauxite in contiguous block I, and foaming agent is arranged to furfuryl alcohol modified urea in the contiguous block II
Urea formaldehyde.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621417460.5U CN206693465U (en) | 2016-12-22 | 2016-12-22 | Assembling type steel structure builds out-hung panel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201621417460.5U CN206693465U (en) | 2016-12-22 | 2016-12-22 | Assembling type steel structure builds out-hung panel |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206693465U true CN206693465U (en) | 2017-12-01 |
Family
ID=60439703
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201621417460.5U Active CN206693465U (en) | 2016-12-22 | 2016-12-22 | Assembling type steel structure builds out-hung panel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206693465U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108222337A (en) * | 2016-12-22 | 2018-06-29 | 徐州中煤汉泰建筑工业化有限公司 | Assembling type steel structure builds out-hung panel and its modularization installation method |
-
2016
- 2016-12-22 CN CN201621417460.5U patent/CN206693465U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108222337A (en) * | 2016-12-22 | 2018-06-29 | 徐州中煤汉泰建筑工业化有限公司 | Assembling type steel structure builds out-hung panel and its modularization installation method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207161110U (en) | One kind construction open cut horseshoe shaped section tunnel roof self-travel type is mobile trolley used | |
CN206737417U (en) | A kind of PC prefabricated outer wall panels grouting typified form | |
CN104120877B (en) | A kind of hydraulic climbing die block system and climbing form method | |
CN204225277U (en) | The prefabricated floor connector of steel building | |
CN206693465U (en) | Assembling type steel structure builds out-hung panel | |
CN105484403A (en) | Assembly type concrete bidirectional ribbed floor and construction method therefor | |
CN101818564A (en) | Adjustable hanger system | |
CN112727075A (en) | Integrated pouring structure of inclined roof and flat roof and construction method | |
CN206888506U (en) | The cast-in-place system of formwork structure and shear wall of shear wall angle node | |
CN109281487A (en) | A kind of tradition earth kiln local-style dwelling houses overall structure reinforcement system and its construction technology | |
CN205976215U (en) | Compound box roof beam of assembled concrete | |
CN105697019B (en) | Shaft wall cast-in-situ concrete joint and its erecting device and construction method | |
CN102268858A (en) | Cradle for suspension pouring of arch-type bridge | |
CN108222337A (en) | Assembling type steel structure builds out-hung panel and its modularization installation method | |
CN205805572U (en) | A kind of buttress type subway station section of track well | |
CN209384643U (en) | A kind of slip-form lifting device of thin-walled hollow pier stud | |
CN207760803U (en) | A kind of prefabricated amphistyly armour steel form | |
CN208803487U (en) | Piping lane new type formwork trolley | |
CN101818496B (en) | Inversely-constructed underground continuous wall with siamesed reinforcing cage | |
CN109056702A (en) | The construction method of coercion underground continuous wall | |
CN115807561A (en) | Connection reinforcing structure of ultra-high shale clear water brick hollowed decorative wall and construction method thereof | |
CN206581482U (en) | A kind of assembled architecture of concrete prefabricated wallboard and its composition | |
CN202164551U (en) | Hanging basket for suspension pouring arch-type bridge | |
CN109386070A (en) | A kind of assembled steel frame external wall system and its construction method | |
CN107191201A (en) | Constructing middle partition wall in tunnel template and its constructing device |