CN206670622U CN201720416985.5U CN201720416985U CN206670622U CN 206670622 U CN206670622 U CN 206670622U CN 201720416985 U CN201720416985 U CN 201720416985U CN 206670622 U CN206670622 U CN 206670622U
Authority
CN
China
Prior art keywords
tunnel
water pipe
shallow
depth
bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720416985.5U
Other languages
Chinese (zh)
Inventor
赵航
赵淑浩
贺伟
樊国燕
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ganges River Jiangsu Construction Engineering Co Ltd
Original Assignee
Ganges River Jiangsu Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ganges River Jiangsu Construction Engineering Co Ltd filed Critical Ganges River Jiangsu Construction Engineering Co Ltd
Priority to CN201720416985.5U priority Critical patent/CN206670622U/en
Application granted granted Critical
Publication of CN206670622U publication Critical patent/CN206670622U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

It the utility model is related to a kind of shallow-depth-excavation tunnel settlement monitoring structure, including tunnel body, horizontal rod support is provided with tunnel body, horizontal rod support restocking is provided with the water pipe of the built-in liquid through tunnel body length, uniformly upwardly extend to form the first extension on water pipe, the first through hole with being connected inside water pipe is provided with first extension, fly rod is equipped with first through hole, fly rod is connected with hollow ball towards one end inside water pipe, observation bar is arranged with fly rod, the other end for observing bar is connected to tunnel bodies top;Fly rod is connected with hollow ball, and hollow ball is swum on liquid level, and observation rod set is located on fly rod;Because observation bar is connected to tunnel bodies top, when tunnel vault declines, observation bar moves down, and changes with the relative position of fly rod.Change of the Observation personnel by observing relative position between observation bar and fly rod learns whether tunnel vault settles.

Description

A kind of shallow-depth-excavation tunnel settlement monitoring structure
Technical field
Monitoring field is the utility model is related to, more particularly to a kind of shallow-depth-excavation tunnel settlement monitoring structure.
Background technology
With burying, shallow, formation lithology is poor, underground water be present, surrounding environment for the underground setting that shallow burial hidden digging construction forms The features such as complicated.Due to low cost, remove less, flexible and changeable, do not disturb without too many special equipment and traffic above-ground and surrounding The features such as environment, shallow burial hidden digging are used widely in the similar stratum in the whole nation and various underground engineerings.
And the sinking of vault may trigger the significant security risk or accident of tunnel and surrounding building structure in tunnel, so The sedimentation for monitoring tunnel is a particularly important thing;As disclosed in publication No. for the Chinese patent of " CN105136113A " The level monitoring system of a kind of tunnel subsidence, although this is a kind of more effective monitoring system;But whole system is more multiple It is miscellaneous, it is complex when mounted;We provide a kind of relatively simple monitoring of structures herein.
Utility model content
The purpose of this utility model is to provide a kind of shallow-depth-excavation tunnel settlement monitoring structure, for monitoring multistage segment type Tunnel subsidence.
Above-mentioned technical purpose of the present utility model technical scheme is that:A kind of shallow-depth-excavation tunnel Settlement monitoring structure, including tunnel body, horizontal rod support is provided with the tunnel body, and the horizontal rod support restocking is provided with and passed through The water pipe of the built-in liquid of tunneling road body length, uniformly upwardly extend to form the first extension on the water pipe, described first The first through hole with being connected inside water pipe is provided with extension, fly rod, the fly rod direction are equipped with the first through hole One end inside water pipe is connected with hollow ball, and observation bar is arranged with the fly rod, and the other end of the observation bar is connected to tunnel Road bodies top.
By using above-mentioned technical proposal, fly rod is connected with hollow ball, and hollow ball is swum on liquid level, and observation rod set is located at On fly rod;Because observation bar is connected to tunnel bodies top, when tunnel vault declines, observation bar moves down, with floating The relative position of bar changes.Change of the Observation personnel by observing relative position between observation bar and fly rod learns that tunnel vault is It is no to settle.Because being connection inside water pipe, the position of each fly rod is all identical, and observation bar is also connected At the sustained height of tunnel body, Observation personnel need to only write down one of which observation bar and floating lever between position relationship i.e. Can.
Preferably, the horizontal rod support includes being arranged on the support column at tunnel body both ends and is arranged between support column Transverse arc bar, protection pawl is set on the transverse arc bar.
By using above-mentioned technical proposal, the support column for being arranged on tunnel both sides plays a part of support, transverse arc bar pair Water pipe plays a part of bracketing, protects pawl further protection water pipe not come off from transverse arc bar.
Preferably, the support column includes pre- buried column and the support column body being set on pre- buried column, the support column Contiguous block is threaded with body, the support column body is connected on contiguous block.
By using above-mentioned technical proposal, support column is provided in tunnel both ends, over time, may be because Soil shrinkage is caused so as to cause support column to sink for a variety of causes so that water pipe is not parallel with ground.Adjustment contiguous block is propping up Position on dagger, so as to adjust the position of support column body, water pipe is adjusted to level.
Preferably, the water pipe is provided at both ends with scale.
By using above-mentioned technical proposal, scale is observed at the both ends of water pipe at regular intervals, if the liquid level in water pipe At identical graduation, it is horizontal positioned to illustrate water pipe;If the liquid level both ends in water pipe are not at identical graduation, adjustment connects Position of the block on pre- buried column is connect so as to reach the horizontal effect of water pipe.
Preferably, set on the water pipe with the check valve injected for liquid.
By using above-mentioned technical proposal, because being provided with multiple first extensions on water pipe, and disposed over Water pipe is connected by one through hole with the external world, and the liquid in water pipe outwards after volatilization, is inwardly supplemented by check valve.
Preferably, it is vertically arranged with scale on the fly rod.
By using above-mentioned technical proposal, fly rod is mutually arranged with observation bar, records observation bar on fly rod It is observed behind scale position and periodically;When observing bar in the scale change on fly rod, under tunnel vault may occur It is heavy, it is further to arrange monitoring personnel to carry out further careful observation.
Preferably, being provided with elastic protective layer outside the water pipe, the elastic protective layer is dried after being coated by SEBS Form.
By using above-mentioned technical proposal, most tunnel is for vehicle by order to avoid vehicle is because travelling not It is careful that water pipe is broken or artificially damaged water pipe, in one layer of SEBS elastic protective layer of water pipe outer wrapping, the elasticity of this material Well and there is good inoxidizability, alleviate caused active force when vehicle collides with water pipe.
Preferably, the tunnel bodies top is provided with hook, the observation bar is hung on hook.
By using above-mentioned technical proposal, observation bar can by be hung on that hook reaches observation bar and tunnel bodies top Dismantling connection;If observation bar is damaged and can changed in time.
Preferably, the observation bar top is embedded in tunnel bodies top.
By using above-mentioned technical proposal, observation bar is directly embedded in tunnel bodies top, this connection side during construction Formula is more firm.
In summary, the utility model has the advantages that:Fly rod is connected with hollow ball, and hollow ball swims in liquid level On, observation rod set is located on fly rod;Because observation bar is connected to tunnel bodies top, when tunnel vault declines, Observation bar moves down, and changes with the relative position of fly rod.Observation personnel is changed by observing relative position between observation bar and fly rod Change learns whether tunnel vault settles.Because being connection inside water pipe, the position of each fly rod is all identical , observation bar is also connected at the sustained height of tunnel body, Observation personnel need to only write down one of which observation bar with floating Position relationship between bar.This detection mode is built simply, and observation is direct.
Brief description of the drawings
Fig. 1 is overall structure diagram in embodiment 1, is closed for embodying the position between horizontal rod support and tunnel body System;
Fig. 2 is part-structure schematic diagram in embodiment 1, and the intrinsic horizontal rod support in tunnel and water are arranged on for embodying Pipe;
Fig. 3 is supporting bar structure sectional view in embodiment 1, for embodying the position between three parts for forming support bar Relation;
Fig. 4 is water pipe structure sectional view in embodiment 1, for embodying the position relationship between fly rod, observation bar;
Fig. 5 is part-structure schematic diagram in embodiment 1, for embodying check valve;
Fig. 6 is part-structure schematic diagram in embodiment 2, for embodying detachably connecting between observation bar and tunnel body Connect.
In figure, 1, tunnel body;2nd, horizontal rod support;21st, water pipe;211st, check valve;22nd, the first extension;23rd, first is logical Hole;24th, fly rod;241st, hollow ball;25th, bar is observed;26th, support column;261st, transverse arc bar;262nd, pre- buried column;263rd, support column Body;264th, contiguous block;265th, pawl is protected;3rd, elastic protective layer;4th, link up with.
Embodiment
The utility model is described in further detail below in conjunction with accompanying drawing.
This specific embodiment is only that it is not to limitation of the present utility model, ability to explanation of the present utility model Field technique personnel can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but As long as all protected in right of the present utility model by Patent Law.
Embodiment 1:As shown in figure 1, a kind of shallow-depth-excavation tunnel settlement monitoring structure, horizontal rod support 2 is provided in tunnel In body 1, in order to ensure the accuracy of observation, horizontal rod support 2, the present embodiment table can be both provided with the both sides of tunnel body 1 Existing is the situation that only side is provided with horizontal rod support 2.
As depicted in figs. 1 and 2, horizontal rod support 2 includes being arranged on the support column 26 at the both ends of tunnel body 1 and is erected at branch Transverse arc bar 261 between dagger 26, the upper surface of transverse arc bar 261 is arc, can agree with the shape of the lower surface of water pipe 21. Multigroup protection pawl 265 is arranged at intervals with transverse arc bar 261, protection pawl 265 mutually agrees with the shape of water pipe 21, water pipe 21 half is wrapped Wrap.
As shown in figure 3, support column 26 includes pre- buried column 262, support column body 263 and contiguous block 264 altogether.Pre- buried column Below ground is embedded at lower 1/3rd of 262, is provided with screw thread on outer wall, contiguous block 264 be threaded in it is pre- On the outer wall of buried column 262, support column body 263 is set on pre- buried column 262 and is connected on contiguous block 264.Transverse arc bar 261 are connected on support column body 263.
As shown in figure 4, water pipe 21 is towards raising up to form the first extension 22 on the face of the vault of tunnel body 1, first First through hole 23 is offered on extension 22, first through hole 23 connects through the first extension 22 with the inside of water pipe 21;First prolongs Extending portion 22 is uniformly provided with multiple on water pipe 21.
As shown in Figure 2 and Figure 4, the liquid that viscosity is low, mobility is strong and volatility is weaker is filled with water pipe 21, it is contemplated that Cost can inside filling clear water.Fly rod 24 is plugged in each first through hole 23, and the bottom of fly rod 24 is provided with hollow ball 241, fly rod 24 and hollow ball 241 are made using PVC, and bonding is integral.Fly rod 24 exposes the side wall of first through hole 23 On be provided with scale, observation bar 25 is set on fly rod 24, and the other end is embedded in the top of tunnel body 1.
As shown in figure 4, being coated with one layer of elastic protective layer 3 on the outer wall of water pipe 21, elastic protective layer 3 is by SEBS(It is poly- Styrene-polyethylene-polybutene-polystyrene)Drying forms after coating, and thickness is about one centimetre to two cm thicks.
As shown in figure 5, being both provided with longitudinal scale on two end walls of water pipe 21, and also set up in the wherein one end of water pipe 21 Have check valve 211, by check valve 211 can into water pipe 21 liquid make-up.
Application method:Before coming into operation, clear water is poured into water pipe 21 from check valve 211, in the buoyancy of clear water Under, hollow ball 241 floats.The liquid level at the both ends of water pipe 21 is observed whether at identical graduation, if be not at identical graduation, The position on pre- buried column 262 of contiguous block 264 is adjusted, so as to adjust the position of support column body 263, makes water pipe 21 horizontal.Record Scale of the lower everywhere observation bar 25 on fly rod 24, observes once, observes between bar 25 and fly rod 24 at regular intervals Whether whether relative position changes, sink if changing and can further be surveyed and drawn the vault of tunnel body 1 on the spot Phenomena such as collapsing and the safeguard measure for carrying out next step.
Embodiment 2:Structure in embodiment 2 and the structure in embodiment 1 are essentially identical, as shown in fig. 6, a kind of shallow embedding is dark Hole settlement monitoring structure, observation bar 25 is connected with the top side detachable of tunnel body 1;In tunnel, the top of body 1 is embedded hangs Hook 4, the top of observation bar 25 are provided with the hook that can be engaged with hook 4, are engaged by both by the activity of observation bar 25 even It is connected on the top of tunnel body 1.
Application method:The application method of embodiment 2 and the application method and embodiment 1 of embodiment 1 is essentially identical, but herein In embodiment, observation bar 25 is connected with the top side detachable of tunnel body 1, so when observation bar 25 is damaged, can Changed in time.

Claims (9)

1. a kind of shallow-depth-excavation tunnel settlement monitoring structure, including tunnel body(1), it is characterised in that:The tunnel body(1) In be provided with horizontal rod support(2), the horizontal rod support(2)Restocking, which is provided with, runs through tunnel body(1)The water of the built-in liquid of length Pipe(21), the water pipe(21)On uniformly upwardly extend to form the first extension(22), first extension(22)Upper setting Have and water pipe(21)The first through hole of inside connection(23), the first through hole(23)In be equipped with fly rod(24), the fly rod (24)Towards water pipe(21)Internal one end is connected with hollow ball(241), the fly rod(24)On be arranged with observation bar(25), institute State observation bar(25)The other end be connected to tunnel body(1)Top.
A kind of 2. shallow-depth-excavation tunnel settlement monitoring structure according to claim 1, it is characterised in that:The horizontal rod support (2)Including being arranged on tunnel body(1)The support column at both ends(26)Be arranged on support column(26)Between transverse arc bar (261), the transverse arc bar(261)It is upper that protection pawl is set(265).
A kind of 3. shallow-depth-excavation tunnel settlement monitoring structure according to claim 2, it is characterised in that:The support column (26)Including pre- buried column(262)Be set in pre- buried column(262)On support column body(263), the support column body(263) On be threaded with contiguous block(264), the support column body(263)It is connected to contiguous block(264)On.
A kind of 4. shallow-depth-excavation tunnel settlement monitoring structure according to claim 3, it is characterised in that:The water pipe(21) It is provided at both ends with scale.
A kind of 5. shallow-depth-excavation tunnel settlement monitoring structure according to claim 4, it is characterised in that:The water pipe(21) It is upper to set with the check valve injected for liquid(211).
A kind of 6. shallow-depth-excavation tunnel settlement monitoring structure according to claim 5, it is characterised in that:The fly rod(24) On be vertically arranged with scale.
A kind of 7. shallow-depth-excavation tunnel settlement monitoring structure according to claim 6, it is characterised in that:The water pipe(21) It is provided with elastic protective layer outside(3), the elastic protective layer(3)It is that drying forms after being coated by SEBS.
A kind of 8. shallow-depth-excavation tunnel settlement monitoring structure according to claim 7, it is characterised in that:The tunnel body (1)Top is provided with hook(4), the observation bar(25)It is hung on hook(4)On.
A kind of 9. shallow-depth-excavation tunnel settlement monitoring structure according to claim 7, it is characterised in that:The observation bar (25)Top is embedded in tunnel body(1)Top.
CN201720416985.5U 2017-04-20 2017-04-20 A kind of shallow-depth-excavation tunnel settlement monitoring structure Expired - Fee Related CN206670622U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720416985.5U CN206670622U (en) 2017-04-20 2017-04-20 A kind of shallow-depth-excavation tunnel settlement monitoring structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720416985.5U CN206670622U (en) 2017-04-20 2017-04-20 A kind of shallow-depth-excavation tunnel settlement monitoring structure

Publications (1)

Publication Number Publication Date
CN206670622U true CN206670622U (en) 2017-11-24

Family

ID=60372405

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720416985.5U Expired - Fee Related CN206670622U (en) 2017-04-20 2017-04-20 A kind of shallow-depth-excavation tunnel settlement monitoring structure

Country Status (1)

Country Link
CN (1) CN206670622U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107816970A (en) * 2017-12-04 2018-03-20 三洋电梯(珠海)有限公司 The built-in fitting divergence component and method of a kind of exterior wall elevator

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107816970A (en) * 2017-12-04 2018-03-20 三洋电梯(珠海)有限公司 The built-in fitting divergence component and method of a kind of exterior wall elevator

Similar Documents

Publication Publication Date Title
CN107916683A (en) A kind of device and method for monitoring the underground space and line track lateral soil movement and sedimentation
CN105806418A (en) Reservoir landslide multi-field information field monitoring system and construction method thereof
CN103556602B (en) Structural body for preventing starting of gully debris flows and design method of structural body
CN206756813U (en) Rainfall infiltration experiment simulator
CN205387720U (en) Tertiary light -duty retaining structure of double circular pile pile foundation of superelevation embankment
CN110485433A (en) Sand gravel geology Among Piles In Deep Foundation Pit formula diaphragm wall steel anchor method for protecting support
CN108979659A (en) The ruggedized construction and method of structures are worn under weak soil rich water large cross-section tunnel group
CN206173990U (en) Asymmetric clump of piles cushion cap formula anchorage structure suitable for suspension bridge
CN206670622U (en) A kind of shallow-depth-excavation tunnel settlement monitoring structure
CN106884431B (en) A kind of building pit foundation construction safety supporting construction
CN205077499U (en) Double row pile supporting construction with transverse connection component
CN104499502A (en) Riverway arch retaining wall structure and construction method thereof
CN110904983B (en) Highway side slope reinforcing apparatus
CN104612105A (en) Steel concrete structure type flood control wall
CN207934046U (en) A kind of combination unit based on deep basal pit protection
CN205175392U (en) Tunnel earth's surface settlement monitoring device based on distributed optical fiber sensing
CN206467646U (en) A kind of foundation pit slope protection horizontal displacement monitoring device
CN207331625U (en) A kind of erosion control water conservancy dam configuration
CN207063007U (en) A kind of walling crib ruggedized construction
CN206887939U (en) It is applied to the flexible shroud of steel reinforcement cage under coral reef geology
CN213204179U (en) Foundation pit peripheral water level stabilizing device utilizing high gravity recharge
CN205857161U (en) It is applicable to the steel-pipe pile of coral reef geology
CN212801551U (en) Rectangular shape deep basal pit supporting device
JPH06983B2 (en) Protective method of underground structure in sand ground that is easily liquefied
CN103422487A (en) Method for measuring settlement deformation by utilizing inclinometer and angle-adjustable converter

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20171124