Prior art keywords
built
fitting
eaves board
concrete floor
buried structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201720102563.0U
Other languages
Chinese (zh)
Inventor
冯永惠
冯浪
曹艳
付学会
杨应余
饶剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Ming Chuan Environmental Engineering Co Ltd
Original Assignee
Yunnan Ming Chuan Environmental Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Ming Chuan Environmental Engineering Co Ltd filed Critical Yunnan Ming Chuan Environmental Engineering Co Ltd
Priority to CN201720102563.0U priority Critical patent/CN206607873U/en
Application granted granted Critical
Publication of CN206607873U publication Critical patent/CN206607873U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Floor Finish (AREA)

Abstract

The utility model overcomes the deficiency of prior art presence there is provided a kind of pre-buried structure of anti-dropout, and the pre-buried structure will not only come off out of concrete floor, and can play and prevent the leakage problems between concrete floor and built-in fitting;In order to solve the above-mentioned technical problem, the technical solution adopted in the utility model is:A kind of pre-buried structure of anti-dropout, including concrete floor and built-in fitting, the built-in fitting is in cylindrical cylinder, the upper end of the built-in fitting is provided with a circular eaves board, the eaves board is sleeved on the upper end of built-in fitting, and the upper surface of the eaves board is flushed with the upper surface of built-in fitting, the built-in fitting and eaves board are embedded into concrete floor together, and upper surface and the upper planes align of concrete floor of eaves board;The utility model can be widely applied to floor built-in fitting field.

Description

A kind of pre-buried structure of anti-dropout
Technical field
A kind of pre-buried structure of anti-dropout of the utility model, belongs to floor built-in fitting technical field.
Background technology
In floor construction work progress, the seepage at sewer pipeline of toilet is relatively common common quality defect, at present Structure construction at this, is not all subject to the construction method and related measure of detailed system in scheme or on drawing either, applies Work workman and related management personnel are constructed with the construction experience of oneself more, and construction method is simple and crude, while wasting time and energy, and oozes Leakage problem is also the failure to substantial elimination.
Traditional construction passes through the mode reserving hole frequently with artificial molding, after band is installed, recycle artificial molding and The mode that iron wire hangs mould blocks reserving hole.Or first not reserving hole, treat to carry out building using machinery after the completion of concreting The mode of plate perforation sets hole, after concreting after sewer pipe is installed at hole, is dug, noted again Slurry, filling chink, consume substantial amounts of manpower and materials.Above two method, the problem of there is seepage, and concrete are dry During dry, because its own has shrinkage character, built-in fitting is caused to be come off from concrete floor so that built-in fitting loses it Function.
Utility model content
The utility model overcomes the deficiency of prior art presence there is provided a kind of pre-buried structure of anti-dropout, and this is pre-buried Structure will not only come off out of concrete floor, and can play prevents the seepage between concrete floor and built-in fitting from asking Topic.
In order to solve the above-mentioned technical problem, the technical solution adopted in the utility model is:A kind of pre-buried structure of anti-dropout, Including concrete floor and built-in fitting, the built-in fitting is in the cylinder of cylinder, and the upper end of the built-in fitting is provided with a circle The eaves board of ring-type, the eaves board is sleeved on the upper end of built-in fitting, and the upper surface of the eaves board is flushed with the upper surface of built-in fitting, The built-in fitting and eaves board are embedded into concrete floor together, and the upper surface of eaves board and the upper plane of concrete floor are neat It is flat.
The eaves board is welded on built-in fitting, or is integrally formed with built-in fitting.
Sealing ring is provided with the downside of the eaves board.
Adhesive linkage is provided with the downside of the sealing ring.
The lateral surface of the eaves board and sealing ring is provided with adhesive linkage.
The utility model has an advantageous effect in that compared with prior art:The utility model sets eaves in built-in fitting upper end Plate, and built-in fitting and eaves board are integrally embedded into concrete floor, concrete floor is prevented in the drying process, due to shrinking And built-in fitting leaks down, and because the eaves board of built-in fitting upper end so that water will not be directly from built-in fitting and concrete floor Between gap in seepage, it is to avoid seepage between built-in fitting and concrete floor, then sealing ring is set on the downside of eaves board, And be bonded by adhesive linkage, further enhance antiseep effect.
Brief description of the drawings
The utility model is described further below in conjunction with the accompanying drawings.
Fig. 1 is structural representation of the present utility model.
In figure:1 it is concrete floor, 2 be built-in fitting, 3 be eaves board, 4 be sealing ring, 5 is adhesive linkage.
Embodiment
As shown in figure 1, a kind of pre-buried structure of anti-dropout of the utility model, including concrete floor 1 and built-in fitting 2, institute Cylinder of the built-in fitting 2 in cylinder is stated, the upper end of the built-in fitting 2 is provided with a circular eaves board 3,3 sets of the eaves board Upper surface mounted in the upper end of built-in fitting 2, and the eaves board 3 is flushed with the upper surface of built-in fitting 2, the built-in fitting 2 and eaves board 3 It is embedded into together in concrete floor 1, and upper surface and the upper planes align of concrete floor 1 of eaves board 3.
The eaves board 3 is welded on built-in fitting 2, or is integrally formed with built-in fitting 2.
The downside of the eaves board 3 is provided with sealing ring 4.
The downside of the sealing ring 4 is provided with adhesive linkage 5.
The lateral surface of the eaves board 3 and sealing ring 4 is provided with adhesive linkage 5.
The utility model sets eaves board 3 in the upper end of built-in fitting 2, and built-in fitting 2 and eaves board 3 are integrally embedded into concrete building In layer 1, place concrete floor 1 in the drying process, built-in fitting 2 is leaked down due to contraction, and because on built-in fitting 2 The eaves board 3 at end so that water will not seepage in the gap directly between built-in fitting 2 and concrete floor 1, it is to avoid built-in fitting 2 With the seepage between concrete floor 1, sealing ring 4 then is set in the downside of eaves board 3, and is bonded by adhesive linkage 5, enters one Step strengthens antiseep effect.
Embodiment of the present utility model is explained in detail above in conjunction with accompanying drawing, but the utility model is not limited to Embodiment is stated, in the knowledge that those of ordinary skill in the art possess, the utility model objective can also not departed from On the premise of various changes can be made.

Claims (5)

1. a kind of pre-buried structure of anti-dropout, it is characterised in that including concrete floor(1)And built-in fitting(2), the built-in fitting (2)For in the cylinder of cylinder, the built-in fitting(2)Upper end be provided with a circular eaves board(3), the eaves board(3) It is sleeved on built-in fitting(2)Upper end, and the eaves board(3)Upper surface and built-in fitting(2)Upper surface flush, the built-in fitting (2)And eaves board(3)Concrete floor is embedded into together(1)It is interior, and eaves board(3)Upper surface and concrete floor(1)It is upper flat Face is flushed.
2. a kind of pre-buried structure of anti-dropout according to claim 1, it is characterised in that the eaves board(3)It is welded on pre- Embedded part(2)On, or and built-in fitting(2)It is integrally formed.
3. a kind of pre-buried structure of anti-dropout according to claim 1 or 2, it is characterised in that the eaves board(3)Downside It is provided with sealing ring(4).
4. a kind of pre-buried structure of anti-dropout according to claim 3, it is characterised in that the sealing ring(4)Downside It is provided with adhesive linkage(5).
5. a kind of pre-buried structure of anti-dropout according to claim 4, it is characterised in that the eaves board(3)And sealing ring (4)Lateral surface be provided with adhesive linkage(5).
CN201720102563.0U 2017-02-01 2017-02-01 A kind of pre-buried structure of anti-dropout Active CN206607873U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720102563.0U CN206607873U (en) 2017-02-01 2017-02-01 A kind of pre-buried structure of anti-dropout

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720102563.0U CN206607873U (en) 2017-02-01 2017-02-01 A kind of pre-buried structure of anti-dropout

Publications (1)

Publication Number Publication Date
CN206607873U true CN206607873U (en) 2017-11-03

Family

ID=60167861

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720102563.0U Active CN206607873U (en) 2017-02-01 2017-02-01 A kind of pre-buried structure of anti-dropout

Country Status (1)

Country Link
CN (1) CN206607873U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847392A (en) * 2019-11-26 2020-02-28 上海品宅装饰科技有限公司 Construction method for splicing waterproof chassis
CN113530151A (en) * 2021-06-29 2021-10-22 大荣建设集团有限公司 Construction method for vertical pipeline of segmented and assembled high-rise building pipe well

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110847392A (en) * 2019-11-26 2020-02-28 上海品宅装饰科技有限公司 Construction method for splicing waterproof chassis
CN113530151A (en) * 2021-06-29 2021-10-22 大荣建设集团有限公司 Construction method for vertical pipeline of segmented and assembled high-rise building pipe well

Similar Documents

Publication Publication Date Title
CN104088254B (en) Pressure-bearing reinforced concrete structure leakage repair device and construction method thereof
CN207231732U (en) A kind of assembled piping lane joint waterproofing test device
CN203222815U (en) Composite basement-structure exterior wall construction formed by utilizing underground diaphragm wall
CN105862873A (en) Construction method of underground water prevention and exterior wall structures of narrow space of deep foundation pit
CN108166517B (en) Well sealing method and well sealing device for super high-rise high-water pressure deep well dewatering well
CN105220713A (en) The waterproof construction of outer wall of basement settlement joint
CN206607873U (en) A kind of pre-buried structure of anti-dropout
CN106013471A (en) Anti-seepage construction method for expansion joint
CN104047423B (en) A kind of mould and construction method of wearing the accurate reserved opening of flooring plate
CN206409246U (en) A kind of Water slop injector
CN203977368U (en) Pressure-bearing reinforced concrete structure leakage repair device
CN107514150A (en) A kind of construction technology of utilization space displacement method reconstruction Durable Water Repellant
CN111473165A (en) Waterproof structure of superimposed sheet and PVC water piping connection department
CN203549141U (en) Novel floor slab sleeve
CN215635443U (en) Water-proof structure for hanging hole of drain pipe and floor slab
CN207003602U (en) Urban discharging pipeline anti-leakage structure
CN206539353U (en) A kind of tunnel-liner infiltration punishment is reserved to check aperture apparatus
WO2022198848A1 (en) Construction method of pre-laid waterproof roll lap joint edge of bottom plate and bottom plate side formwork supporting structure
CN203403445U (en) Steel sleeve used for plugging basement tube well
CN104631477B (en) A kind of method that dewatering device is installed and blocked in processing foundation ditch
CN111535173A (en) Bridge wet joint connecting structure and connecting method
CN206943599U (en) Floor drainage pipeline service sleeve
CN216447563U (en) Steamed bun package structure for plugging floor penetrating pipeline
CN211524065U (en) Slurry leakage protection aluminum template at joint of prefabricated laminated slab and cast-in-place floor slab
CN218719380U (en) Roof penetrating waterproof sleeve based on main structure embedding

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 650000 301 rooms, Beijing Road Garden, No. 517, Baiyun Road, Panlong District, Kunming, Yunnan

Patentee after: Haina Ming Chuan Construction Engineering Co., Ltd.

Address before: No. 203, No. 203, Beijing Road Garden, No. 517, Baiyun Road, Kunming, Kunming, Yunnan

Patentee before: Yunnan Ming Chuan Environmental Engineering Co., Ltd.