CN206580444U - A kind of urban construction building prefabricated components hanging apparatus - Google Patents
A kind of urban construction building prefabricated components hanging apparatus Download PDFInfo
- Publication number
- CN206580444U CN206580444U CN201720286863.9U CN201720286863U CN206580444U CN 206580444 U CN206580444 U CN 206580444U CN 201720286863 U CN201720286863 U CN 201720286863U CN 206580444 U CN206580444 U CN 206580444U
- Authority
- CN
- China
- Prior art keywords
- rotating
- rotating beam
- prefabricated components
- curved
- hoisting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses a kind of urban construction building prefabricated components hanging apparatus, including the first rotating beam, lifting cross beam, Curved beam, ribs and the second rotating beam, the upper and lower ends of the lifting cross beam are installed with multigroup hoist cable button and suspension ring, the first rotating beam and the second rotating beam be located at the both sides of hoisting beam main body respectively, the Curved beam is fixedly mounted on the both sides of hoisting beam main body, and sliding groove is provided with the middle of the side of Curved beam, the bottom of first rotating beam and the second rotating beam has been fixedly connected with multigroup suspension ring, the ribs is embedded between lifting cross beam and Curved beam respectively, the adjustment hole is arranged on Curved beam, the front end of first rotating beam and the second rotating beam is equipped with fixed via.The urban construction building prefabricated components hanging apparatus is adjusted to prefabricated part hanging posture by the anglec of rotation of the first rotating beam of regulation or the second rotating beam, is connected with Curved beam, be easy to the rotation of the first rotating beam and the second rotating beam.
Description
Technical field
The utility model is related to technical field of building construction, specially a kind of urban construction building prefabricated components hanging apparatus.
Background technology
In fabricated shear wall structure construction procedure, it is often necessary to which prefabricated components are lifted, usually using tower
The suspension hook hung catches on the steel wire rope on prefabricated components, and prefabricated components are sling, and is then placed within predetermined installation site.Due to
The component feature dimension such as PCF plates and PC plate, stair, balcony, Prefabricated stacking floor is larger, and section is smaller, various component suspension centres
Position, spacing it is different, in order to ensure component level, vertical lifting in lifting, the vertical stress of suspension centre, but directly lift by crane often
Requirement can not be met.
In traditional urban construction building prefabricated components hanging apparatus, when deviation occurs in pre-buried hanger position, sling prefabricated
Component occurs that posture during with installing fixed is different, so that the installation and fixing band to component come difficult, influence engineering
Construction quality, is not easy to the lifting posture to prefabricated components and is adjusted, and influences the construction speed of people.
Utility model content
The purpose of this utility model is to provide a kind of urban construction building prefabricated components hanging apparatus, to solve above-mentioned background skill
The lifting posture being not easy to prefabricated components proposed in art is adjusted, the problem of influenceing the construction speed of people.
To achieve the above object, the utility model provides following technical scheme:A kind of urban construction building prefabricated components lifting dress
Put, including hoisting beam main body, hoist cable button, suspension ring, main rope, component steel wire rope, prefabricated components, the first rotating beam, lifting horizontal stroke
Beam, Curved beam, ribs, the second rotating beam, adjustment hole, fixing bolt, sliding groove, rotating pin hole and fixed via, it is described to hang
The two ends of dress beam main body have been fixedly connected with lifting cross beam, and the upper and lower ends of lifting cross beam are installed with multigroup hoist cable button
With suspension ring, the main rope is connected to hoist cable and buckled, and the component steel wire rope is connected to the bottom of suspension ring, and component steel wire rope
Lower end be connected with prefabricated components, first rotating beam and the second rotating beam are both connected in hoisting beam main body, and first rotation
Turn the both sides that beam and the second rotating beam are located at hoisting beam main body respectively, the Curved beam is fixedly mounted on the two of hoisting beam main body
Sliding groove is provided with the middle of side, and the side of Curved beam, the front end of first rotating beam and the second rotating beam is respectively provided at two groups
The inner side of sliding groove, and the bottom of the first rotating beam and the second rotating beam has been fixedly connected with multigroup suspension ring, the ribs point
It is not embedded between lifting cross beam and Curved beam, the adjustment hole is arranged on Curved beam, and Curved beam and the first rotating beam,
It is connected between two rotating beams by fixing bolt, the front end of first rotating beam and the second rotating beam is equipped with fixed lead to
Hole, and the other end of the first rotating beam and the second rotating beam is respectively equipped with rotating pin hole.
It is preferred that, the hoisting beam main body is overall using the center line of hoisting beam main body as the symmetrical structure of axle.
It is preferred that, the front end of first rotating beam and the second rotating beam is convex shape, and the thickness of the convex shape
Degree is respectively less than the height of sliding groove.
It is preferred that, one end of the ribs is arcuate structure, and the radian of the arcuate structure is consistent with Curved beam.
It is preferred that, the rear end of first rotating beam is convex shape, and the rear end of second rotating beam is matrix knot
Structure, and the concave structure is mutually chimeric with the convex shape of the first rotating beam rear end.
It is preferred that, the rotating range of the first rotating beam and the second rotating beam is 0-120 °.
Compared with prior art, the beneficial effects of the utility model are:The urban construction building prefabricated components hanging apparatus is provided with
Rotating range is 0-120 ° of the first rotating beam and the second rotating beam, is differed when prefabricated components lift by crane posture with installing fixed pose
During cause, by adjusting the anglec of rotation of the first rotating beam or the second rotating beam, the lifting posture to prefabricated components is adjusted,
Regulation more facilitates, and is inlaid with ribs, the overall intensity of increase hoisting beam, is connected with Curved beam, be easy to the first rotating beam with
The rotation of second rotating beam, while strengthening the intensity of the first rotating beam and the second rotating beam, provided with multigroup adjustment hole, is easy to rotation
The first rotating beam after turning is fixed with the second rotating beam.
Brief description of the drawings
Fig. 1 is the utility model structural representation;
Fig. 2 is the utility model hoisting beam main body overlooking the structure diagram;
Fig. 3 is the utility model hoisting beam body side structural representation;
Fig. 4 is the utility model Curved beam positive structure schematic;
Fig. 5 is the utility model the first rotating beam structural representation;
Fig. 6 is the utility model the second rotating beam structural representation.
In figure:1st, hoisting beam main body, 2, hoist cable button, 3, suspension ring, 4, main rope, 5, component steel wire rope, 6, prefabricated components,
7th, the first rotating beam, 8, lifting cross beam, 9, Curved beam, 10, ribs, the 11, second rotating beam, 12, adjustment hole, 13, fixed spiral shell
Bolt, 14, sliding groove, 15, rotating pin hole, 16, fixed via.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out
Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is made
The every other embodiment obtained, belongs to the scope of the utility model protection.
Fig. 1-6 are referred to, the utility model provides a kind of technical scheme:A kind of urban construction building prefabricated components hanging apparatus,
Including hoisting beam main body 1, hoist cable button 2, suspension ring 3, main rope 4, component steel wire rope 5, prefabricated components 6, the first rotating beam 7, hang
Fill crossbeam 8, Curved beam 9, ribs 10, the second rotating beam 11, adjustment hole 12, fixing bolt 13, sliding groove 14, rotating pin hole 15
With fixed via 16, the two ends of hoisting beam main body 1 have been fixedly connected with lifting cross beam 8, and the upper and lower ends of lifting cross beam 8 are solid
Dingan County is connected on hoist cable button 2 equipped with multigroup hoist cable button 2 and suspension ring 3, main rope 4, and component steel wire rope 5 is connected to suspension ring 3
Bottom, and the lower end of component steel wire rope 5 is connected with prefabricated components 6, the first rotating beam 7 and the second rotating beam 11 are both connected to lifting
In beam main body 1, and the first rotating beam 7 and the second rotating beam 11 are located at the both sides of hoisting beam main body 1 respectively, and Curved beam 9 fixes peace
Sliding groove 14, the first rotating beam 7 and the second rotating beam are provided with the middle of the both sides of hoisting beam main body 1, and the side of Curved beam 9
11 front end is respectively provided at the inner side of two groups of sliding grooves 14, and the fixed company in bottom of the first rotating beam 7 and the second rotating beam 11
Multigroup suspension ring 3 are connected to, ribs 10 is embedded between lifting cross beam 8 and Curved beam 9 respectively, and adjustment hole 12 is arranged on Curved beam 9
On, and be connected between Curved beam 9 and the first rotating beam 7, the second rotating beam 11 by fixing bolt 13, the first rotating beam 7 with
The front end of second rotating beam 11 is equipped with fixed via 16, and the other end of the first rotating beam 7 and the second rotating beam 11 is set respectively
There is rotating pin hole 15.
In above-described embodiment, specifically, hoisting beam main body 1 is overall right in left and right by axle of the center line of hoisting beam main body 1
Claim structure, four groups of hangers of prefabricated components 6 can be attached with the second rotating beam 11 by two group of first rotating beam 7, it is to avoid
Prefabricated components 6 are rocked during lifting.
In above-described embodiment, specifically, the front end of the first rotating beam 7 and the second rotating beam 11 is convex shape, and should
The thickness of convex shape is respectively less than the height of sliding groove 14, can be placed on the front end of the first rotating beam 7 and the second rotating beam 11
The inner side of sliding groove 14 inside Curved beam 9, so that the first rotating beam 7 and the second rotating beam 11 are rotated in sliding groove 14.
In above-described embodiment, specifically, one end of ribs 10 is arcuate structure, and the radian and arc of the arcuate structure
Beam 9 is consistent, can increase the intensity of hoisting beam main body 1 and Curved beam 9.
In above-described embodiment, specifically, the rear end of the first rotating beam 7 is convex shape, the rear end of the second rotating beam 11 is equal
For concave structure, and the concave structure is mutually chimeric with the convex shape of the rear end of the first rotating beam 7, can be by after the first rotating beam 7
End is inside the rear end of the second rotating beam 11.
In above-described embodiment, specifically, the rotating range of the first rotating beam 7 and the second rotating beam 11 is 0-120 °, when
Prefabricated components 6 are in the posture during lifting and inconsistent installation fixed pose, the rotation of the first rotating beam of regulation 7 or second
The anglec of rotation of beam 11, so that the lifting posture to prefabricated components 6 is adjusted.
Operation principle:Main rope 4 is connected on the hoist cable button 2 at two groups of two ends of lifting cross beam 8 first, afterwards to prefabricated
The pre-buried hanger position of component 6 is checked, and the posture after lifting is judged, then according to the result of judgement selection the
One rotating beam 7 and the suspension ring 3 of the bottom of the second rotating beam 11, and component steel wire rope 5 is connected to the first rotating beam 7 and the second rotation
On the suspension ring 3 of the bottom of beam 11, and steel wire rope is penetrated in four above prefabricated components 6 pre-buried hangers, confirmed after connection fastening,
Prefabricated components 6 are slowly lifted by crane, crane slowly slings prefabricated components 6, treats that the base of prefabricated components 6 is risen to away from ground
Slightly paused during 500mm, check again for hanging it is whether firm, while check prefabricated components 6 lifting posture with install fixed pose
It is whether consistent, if inconsistent, prefabricated components 6 are put down, fixing bolt 13, the rotation of the first rotating beam of regulation 7 or second is pulled down
The anglec of rotation of beam 11, so that the lifting posture to prefabricated components 6 is adjusted, by fixing bolt 13 through the after the completion of adjustment
The corresponding rotating beam 7 of adjustment hole 12 and first in the top of one rotating beam 7 and the second rotating beam 11 and the front end of the second rotating beam 11
Prefabricated components 6, so that the first rotating beam 7 be fixed with the second rotating beam 11, are then risen by fixed via 16 again
Hang, slightly paused when the base of prefabricated components 6 is risen to away from ground 500mm, check again for whether hanging is firm, confirmation is errorless
Afterwards, continue to lift up and be allowed to slowly close to installation exercise face.
In summary, general principle of the present utility model, principal character and advantage has been shown and described above.The industry
Technical staff it should be appreciated that the utility model is not restricted to the described embodiments, described in above-described embodiment and specification only
It is to illustrate principle of the present utility model, on the premise of the utility model spirit and scope are not departed from, the utility model also has
Various changes and modifications, these changes and improvements are both fallen within the range of claimed the utility model.The utility model requirement
Protection domain is defined by appended claims and its effect thing.
Claims (6)
1. a kind of urban construction building prefabricated components hanging apparatus, including hoisting beam main body (1), hoist cable button (2), suspension ring (3), king wire
Rope (4), component steel wire rope (5), prefabricated components (6), the first rotating beam (7), lifting cross beam (8), Curved beam (9), ribs
(10), the second rotating beam (11), adjustment hole (12), fixing bolt (13), sliding groove (14), rotating pin hole (15) and fixed via
(16), it is characterised in that:The two ends of the hoisting beam main body (1) have been fixedly connected with lifting cross beam (8), and lifting cross beam (8)
Upper and lower ends be installed with multigroup hoist cable button (2) and suspension ring (3), the main rope (4) is connected to hoist cable button (2)
On, the component steel wire rope (5) is connected to the bottom of suspension ring (3), and the lower end of component steel wire rope (5) is connected with prefabricated components
(6), first rotating beam (7) is both connected in hoisting beam main body (1) with the second rotating beam (11), and the first rotating beam (7)
It is located at the both sides of hoisting beam main body (1) respectively with the second rotating beam (11), the Curved beam (9) is fixedly mounted on hoisting beam main body
(1) sliding groove (14), first rotating beam (7) and the second rotating beam are provided with the middle of both sides, and the side of Curved beam (9)
(11) front end is respectively provided at the inner side of two groups of sliding grooves (14), and the bottom of the first rotating beam (7) and the second rotating beam (11)
Multigroup suspension ring (3) are fixedly connected with, the ribs (10) is embedded between lifting cross beam (8) and Curved beam (9) respectively, institute
State adjustment hole (12) to be arranged on Curved beam (9), and lead between Curved beam (9) and the first rotating beam (7), the second rotating beam (11)
Cross fixing bolt (13) to be connected, first rotating beam (7) and the front end of the second rotating beam (11) are equipped with fixed via
, and the other end of the first rotating beam (7) and the second rotating beam (11) is respectively equipped with rotating pin hole (15) (16).
2. a kind of urban construction building prefabricated components hanging apparatus according to claim 1, it is characterised in that:The hoisting beam master
Body (1) is overall using the center line of hoisting beam main body (1) as the symmetrical structure of axle.
3. a kind of urban construction building prefabricated components hanging apparatus according to claim 1, it is characterised in that:First rotation
The front end of beam (7) and the second rotating beam (11) is convex shape, and the thickness of the convex shape is respectively less than sliding groove (14)
Highly.
4. a kind of urban construction building prefabricated components hanging apparatus according to claim 1, it is characterised in that:The ribs
(10) one end is arcuate structure, and the radian of the arcuate structure is consistent with Curved beam (9).
5. a kind of urban construction building prefabricated components hanging apparatus according to claim 1, it is characterised in that:First rotation
The rear end of beam (7) is convex shape, and the rear end of second rotating beam (11) is concave structure, and the concave structure and first
The convex shape of rotating beam (7) rear end is mutually fitted together to.
6. a kind of urban construction building prefabricated components hanging apparatus according to claim 1, it is characterised in that:First rotation
The rotating range of beam (7) and the second rotating beam (11) is 0-120 °.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720286863.9U CN206580444U (en) | 2017-03-23 | 2017-03-23 | A kind of urban construction building prefabricated components hanging apparatus |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720286863.9U CN206580444U (en) | 2017-03-23 | 2017-03-23 | A kind of urban construction building prefabricated components hanging apparatus |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206580444U true CN206580444U (en) | 2017-10-24 |
Family
ID=60114860
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720286863.9U Expired - Fee Related CN206580444U (en) | 2017-03-23 | 2017-03-23 | A kind of urban construction building prefabricated components hanging apparatus |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206580444U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111634797A (en) * | 2020-06-15 | 2020-09-08 | 广东一桥建设工程有限公司 | Steel bar lifting appliance for building construction |
-
2017
- 2017-03-23 CN CN201720286863.9U patent/CN206580444U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111634797A (en) * | 2020-06-15 | 2020-09-08 | 广东一桥建设工程有限公司 | Steel bar lifting appliance for building construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206521197U (en) | A kind of adjustable balance hoisting beam | |
CN106586811B (en) | Lifting equipment for supporting patient with burn and lifting turn-over method for concrete tower | |
CN212772802U (en) | Suspension structure system with weak correlation of each layer | |
CN205576744U (en) | Special jack -up hoist is erect to cable -stay bridge cordless district large -tonnage steel case girder segment section | |
CN206580444U (en) | A kind of urban construction building prefabricated components hanging apparatus | |
CN207090788U (en) | A kind of special tie-beam for being used for two cranes and synchronously lifting | |
CN103663144A (en) | Special turnover device used for steel members | |
CN205953378U (en) | Tower crane counter weight is put from dismouting | |
CN106698188B (en) | It is a kind of new to avoid sliding tower crane hook structure | |
CN206244301U (en) | A kind of architectural engineering tower crane anti-sway control device | |
CN105947910B (en) | The hoisting of FPSO crane superstructures | |
CN202441045U (en) | Rail-type electric attached lifting scaffold | |
CN202030434U (en) | Large-span whole-section hoisting sling for steel box girder | |
CN207511723U (en) | A kind of flat arm tower crane supporting beam transporting device of new construction inner climbing type | |
CN109626249B (en) | Simple three-dimensional positioning installation and load bearing device and using method | |
CN208776230U (en) | A kind of large-tonnage mast hoist | |
CN202988556U (en) | Special lifting appliance for angle-steel type frame body | |
CN210393401U (en) | Hoisting and positioning device for stand column | |
CN205840190U (en) | A kind of pin key connects the mounting structure of prefabricated bench | |
CN204778268U (en) | A special lifting device for hoist and mount of large -tonnage precast box girder | |
CN205367457U (en) | Cast member installs special hoist | |
CN114671329A (en) | Hoisting mechanism for assembly type building construction | |
CN209957212U (en) | Lifting appliance and lifting system for mounting component under beam | |
CN210369846U (en) | Operating platform capable of being clamped on elevator shaft shear wall surface and lifted layer by layer | |
CN206705563U (en) | A kind of novel pile formula crane |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171024 Termination date: 20180323 |
|
CF01 | Termination of patent right due to non-payment of annual fee |