CN206570703U - A kind of working job platform of pier stud reinforcing bar - Google Patents
A kind of working job platform of pier stud reinforcing bar Download PDFInfo
- Publication number
- CN206570703U CN206570703U CN201720151565.9U CN201720151565U CN206570703U CN 206570703 U CN206570703 U CN 206570703U CN 201720151565 U CN201720151565 U CN 201720151565U CN 206570703 U CN206570703 U CN 206570703U
- Authority
- CN
- China
- Prior art keywords
- pier stud
- reinforcing bar
- job platform
- support body
- stud reinforcing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000003014 reinforcing effect Effects 0.000 title claims abstract description 20
- 241000282326 Felis catus Species 0.000 claims abstract description 7
- 238000010276 construction Methods 0.000 abstract description 9
- 229910000831 Steel Inorganic materials 0.000 description 3
- 239000010959 steel Substances 0.000 description 3
- 238000004519 manufacturing process Methods 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 230000003247 decreasing effect Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000002787 reinforcement Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 230000007306 turnover Effects 0.000 description 1
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a kind of working job platform of pier stud reinforcing bar, it is desirable to provide a kind of working job platform of pier stud reinforcing bar for effectively improving efficiency of construction.It includes support body, and multilayer equi-spaced apart is arranged at the operating desk on the outside of support body, is arranged at the guard rail on the outside of operating desk, and be arranged at the cat ladder of support body side;The support body includes many vertical rods, and multigroup cross bar group for being fixedly connected with each vertical rod.This practicality is newly remarkably improved the efficiency of reinforcing bar colligation on pier stud.
Description
Technical field
The utility model is related to bridge auxiliary construction equipment technical field, working more particularly, to a kind of pier stud reinforcing bar
Job platform.
Background technology
Pier stud construction generally uses over-form construction, and the colligation of pier stud reinforcing bar is generally set up scaffold and constructed, scaffold
Dismounting is cumbersome, and construction efficiency is low.
Utility model content
The utility model overcomes shortcoming of the prior art there is provided one kind is easy to use, can effectively improve construction effect
The working job platform of pier stud reinforcing bar of rate.
In order to solve the above-mentioned technical problem, the utility model is achieved through the following technical solutions:
A kind of working job platform of pier stud reinforcing bar, including support body, multilayer equi-spaced apart are arranged at the behaviour on the outside of support body
Make platform, be arranged at the guard rail on the outside of operating desk, and be arranged at the cat ladder of support body side;The support body includes many and stood
Bar, and multigroup cross bar group for being fixedly connected with each vertical rod.
The lower end of the operating desk sets the hound being connected with vertical rod.
Protection network is provided with the guard rail.
The cross bar group is with support body by being welded to connect.
The cross bar group is bolted with support body.
The cross bar group is three groups.
Compared with prior art, the utility model has the following advantages that:
The utility model overall processing, bulk handling is convenient to mount and dismount, and reinforcing bar colligation operation work efficiency is greatly increased.
Brief description of the drawings
, below will be to embodiment in order to illustrate more clearly of the utility model embodiment or technical scheme of the prior art
Or the accompanying drawing used required in description of the prior art is briefly described, it should be apparent that, drawings in the following description are only
It is some embodiments of the present utility model, for those of ordinary skill in the art, is not paying the premise of creative work
Under, other accompanying drawings can also be obtained according to these accompanying drawings.
Fig. 1 is structural representation of the present utility model.
Fig. 2 is Fig. 1 left view.
Embodiment
Below in conjunction with the accompanying drawing in the utility model embodiment, the technical scheme in the utility model embodiment is carried out
Clearly and completely describe, it is clear that described embodiment is only a part of embodiment of the utility model, rather than whole
Embodiment.Based on the embodiment in the utility model, those of ordinary skill in the art are not under the premise of creative work is paid
The every other embodiment obtained, belongs to the scope of the utility model protection.
The working job platform of pier stud reinforcing bar shown in Fig. 1-2, including support body 1, three layers of equi-spaced apart are arranged at outside support body 1
The operating desk 2 of side, is arranged at the guard rail 3 in the outside of operating desk 2, and is arranged at the cat ladder 4 of the side of support body 1;The support body 1
Including many vertical rods 5, and three groups of cross bar groups 6 for being fixedly connected with each vertical rod 5.
The lower end of the operating desk 2 sets the hound 7 being connected with vertical rod 5.
Protection network is provided with the guard rail 3(Not shown in figure).
The cross bar group 6 is with support body 11 preferably by being welded to connect, it is clear that can also be bolted.
Obviously, the quantity of the cross bar group 6 also can reasonably be increased and decreased according to the height of pier stud.
In use, job platform is arranged on the outside of pier stud surrounding, the rod member of vertical rod 5 and cross bar group 6 uses 10 × 10
× 1cm angle steel welding productions, the level interval 3m of vertical rod 5, the height spacing 2m of cross bar group 6, the side of platform of being constructed at every layer using 5 ×
5 × 0.5cm angle steel sets hound with vertical rod 5 in the welding of 45° angle degree, is supported as the reinforcement of operating desk, then in operating desk
Outside guard rail 3 is welded using 5 × 5 × 0.5cm angle steel, the outside of guard rail 3 is hung to be used on protection network, operating platform
The spiral spacing 10cm of Φ 16 are welded scaffold board.Simultaneously for convenience of workman's down operation, Φ 22 is used in operating platform side
Spiral is welded the cat ladder 4 above and below workman, the vertical width of cat ladder 4 60cm, and cat ladder 4 tramples distance between tie rods 20cm, and job platform exists
Smooth ground is made, and is allocated and transported when pier stud is constructed using crane or tower crane to pier stud construction location.
The utility model overall processing, bulk handling is convenient to mount and dismount, low manufacture cost, construction safety, and repeatable turnover makes
With reinforcing bar operation work efficiency is greatly increased.Powerful guarantee is provided to accelerate bridge pier column construction speed.
Preferred embodiment of the present utility model is the foregoing is only, it is all at this not to limit the utility model
Within the spirit and principle of utility model, any modification, equivalent substitution and improvements made etc. should be included in the utility model
Protection domain within.
Claims (8)
1. a kind of working job platform of pier stud reinforcing bar, it is characterised in that:Including support body, multilayer equi-spaced apart is arranged at support body
The operating desk in outside, is arranged at the guard rail on the outside of operating desk, and be arranged at the cat ladder of support body side;The support body includes
Many vertical rods, and multigroup cross bar group for being fixedly connected with each vertical rod.
2. the working job platform of pier stud reinforcing bar according to claim 1, it is characterised in that:The lower end of the operating desk is set
Put the hound being connected with vertical rod.
3. the working job platform of pier stud reinforcing bar according to claim 1 or claim 2, it is characterised in that:On the guard rail
It is provided with protection network.
4. the working job platform of pier stud reinforcing bar according to claim 1 or claim 2, it is characterised in that:The cross bar group and frame
Body is by being welded to connect.
5. the working job platform of pier stud reinforcing bar according to claim 3, it is characterised in that:The cross bar group is led to support body
Cross and be welded to connect.
6. the working job platform of pier stud reinforcing bar according to claim 1 or claim 2, it is characterised in that:The cross bar group and frame
Body is bolted.
7. the working job platform of pier stud reinforcing bar according to claim 3, it is characterised in that:The cross bar group is led to support body
Cross bolt connection.
8. the working job platform of pier stud reinforcing bar according to claim 1 or claim 2, it is characterised in that:The cross bar group is three
Group.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720151565.9U CN206570703U (en) | 2017-02-20 | 2017-02-20 | A kind of working job platform of pier stud reinforcing bar |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720151565.9U CN206570703U (en) | 2017-02-20 | 2017-02-20 | A kind of working job platform of pier stud reinforcing bar |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206570703U true CN206570703U (en) | 2017-10-20 |
Family
ID=60059136
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720151565.9U Expired - Fee Related CN206570703U (en) | 2017-02-20 | 2017-02-20 | A kind of working job platform of pier stud reinforcing bar |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206570703U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108385526A (en) * | 2018-01-31 | 2018-08-10 | 中国建筑第六工程局有限公司 | A kind of pier stud reinforcing bar security protection integration sizing moulding bed |
-
2017
- 2017-02-20 CN CN201720151565.9U patent/CN206570703U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108385526A (en) * | 2018-01-31 | 2018-08-10 | 中国建筑第六工程局有限公司 | A kind of pier stud reinforcing bar security protection integration sizing moulding bed |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206233102U (en) | A kind of packaged type faces side operation work platform | |
CN205224622U (en) | Equipment operation platform with adjustable | |
CN206570703U (en) | A kind of working job platform of pier stud reinforcing bar | |
CN206873495U (en) | A kind of Portable piping lane side wall formwork jumbo | |
CN203877780U (en) | High-leg and low-leg handle gantry crane for road | |
CN203097250U (en) | Telescopic safety protection device of discharging platform | |
CN205295965U (en) | Large -span continuous beam bridge strides existing station rotation construction and wraps protective structure entirely with hanging basket | |
CN207063484U (en) | Movable operation platform for corridor construction | |
CN206887644U (en) | A kind of medium-and low-speed maglev single line beam job platform and edge protection device | |
CN207361652U (en) | The mobile device of large-scale steel pipe | |
CN206503068U (en) | A kind of bridge construction anti-drop device | |
CN206205414U (en) | A kind of elevator multilayer operating platform | |
CN204917745U (en) | Portable portal crane | |
CN214656435U (en) | Movable truss type bridge construction operation platform | |
CN205472340U (en) | People's passageway on instrument formula tower crane | |
CN108104124A (en) | Three frame leading truck of Large-diameter Steel casing and auxiliary positioning stage apparatus | |
CN208023970U (en) | Construction discharging platform | |
CN206318219U (en) | A kind of prefabricated tee girder deposits the support meanss of beam overturn-preventing | |
CN207910259U (en) | Crane combination frame shell for electric cabinet | |
CN204847843U (en) | Hoist traveling carriage bearing structure | |
CN208280636U (en) | A kind of elevator well safety device | |
CN206983978U (en) | A kind of small rail car for improving sloping area roll guard conevying efficiency | |
CN206956739U (en) | A kind of portable edge protection device | |
CN112010172A (en) | Sound barrier unit plate mounting trolley for railway construction | |
CN206476686U (en) | A kind of gate-type hoisting bracket |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171020 |
|
CF01 | Termination of patent right due to non-payment of annual fee |