CN206427941U - Construction tower crane builds attachment temporarily - Google Patents

Construction tower crane builds attachment temporarily Download PDF

Info

Publication number
CN206427941U
CN206427941U CN201720020167.3U CN201720020167U CN206427941U CN 206427941 U CN206427941 U CN 206427941U CN 201720020167 U CN201720020167 U CN 201720020167U CN 206427941 U CN206427941 U CN 206427941U
Authority
CN
China
Prior art keywords
anchoring ring
tower body
pedestal
tower crane
attachment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201720020167.3U
Other languages
Chinese (zh)
Inventor
崔凯
高峰
陈玉禄
张希海
赵发
赵志毅
宋莹莹
王钰
李磊
赵文君
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG HUABANG CONSTRUCTION GROUP CO Ltd
Original Assignee
SHANDONG HUABANG CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG HUABANG CONSTRUCTION GROUP CO Ltd filed Critical SHANDONG HUABANG CONSTRUCTION GROUP CO Ltd
Priority to CN201720020167.3U priority Critical patent/CN206427941U/en
Application granted granted Critical
Publication of CN206427941U publication Critical patent/CN206427941U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to a kind of construction tower crane and builds attachment temporarily, including tower crane tower body, also include at least two attachment pedestals for being located at tower crane tower body homonymy, pedestal anchoring ring is fixed with described attachment pedestal, tower body anchoring ring I is fixed with the position being generally aligned in the same plane on described tower crane tower body with described pedestal anchoring ring, described tower crane tower body is further fixed on tower body anchoring ring II above or below tower body anchoring ring I, two horizontal Anchored Bars are at least hinged between wherein tower body anchoring ring I and each pedestal anchoring ring, fix bar is fixed between horizontal Anchored Bar in adjacent pedestal anchoring ring, oblique Anchored Bar is hinged between described fix bar and described tower body anchoring ring II.The utility model is set up firmly, can be set up for deep basal pit and foundation ditch periphery narrow and small place, be efficiently solved the problem of tower crane is reinforced.

Description

Construction tower crane builds attachment temporarily
Technical field
The utility model is related to construction engineering technical field, and in particular to a kind of construction safety device, particularly one kind is applied Work tower crane builds attachment temporarily.
Background technology
In Building Construction, the use of tower crane is indispensable, and with the construction of architectural engineering, the height of tower crane is not Disconnected increase, risk is also increased therewith, and this is accomplished by setting up rock-steady structure, referred to as tower crane attachment in tower crane relevant position.When need How tower crane attachment is set to add tower crane when deep basal pit is installed and has non-demolition of buildings around tower crane and closing foundation ditch Admittedly being a great problem, adhere to for deep-excavation tower crane, a kind of construction tower crane of design builds attachment temporarily, can well solve The reinforcing problem of tower crane in deep basal pit.
Utility model content
The utility model builds attachment, this attachment temporarily there is provided one kind construction tower crane in view of the shortcomings of the prior art Put and set up firmly, can be set up for deep basal pit and foundation ditch periphery narrow and small place, efficiently solve the problem of tower crane is reinforced.
The utility model is achieved by the following technical solution:
A kind of construction tower crane is provided and builds attachment, including tower crane tower body temporarily, in addition at least two are located at tower crane tower body It is fixed with the attachment pedestal of homonymy, described attachment pedestal on pedestal anchoring ring, described tower crane tower body and described pedestal Tower body anchoring ring I is fixed with the position that anchoring ring is generally aligned in the same plane, described tower crane tower body is in tower body anchoring ring I top Or lower section is further fixed on tower body anchoring ring II, and two are at least hinged between wherein tower body anchoring ring I and each pedestal anchoring ring Be fixed with fix bar between horizontal Anchored Bar in horizontal Anchored Bar, adjacent pedestal anchoring ring, described fix bar with it is described Tower body anchoring ring II between be hinged with oblique Anchored Bar.
Adhere to and connected between the stand anchoring ring of pedestal and the tower body anchoring ring I of tower crane tower body by horizontal Anchored Bar, filled Divide the stability using triangle, strengthen the stability of tower crane attachment, be hinged between horizontal Anchored Bar in fixed fix bar The other end of one oblique Anchored Bar and oblique Anchored Bar is hinged with the tower body anchoring ring II on tower crane tower body, constitutes vertical plane triangle Structure, further increases the stability of tower crane attachment.
Preferably, described pedestal anchoring ring, tower body anchoring ring I and tower body anchoring ring II are logical by two adhesion frames Connecting bolt is crossed to be spliced.
Pedestal anchoring ring, tower body anchoring ring I and tower body anchoring ring II are set to the splicing of two adhesion frames, convenient dismounting with Install, and may be reused.
Preferably, be hinged between described tower body anchoring ring I and each pedestal anchoring ring two horizontal Anchored Bars and Strengthening support is fixed between horizontal Anchored Bar.
Preferably, being fixed with girt between described attachment pedestal.
Girt is fixed pedestal is adhered to, and further enhances the triangular structure stability of pedestal and tower crane tower body.
Preferably, described attachment pedestal is provided with two and symmetrical centered on tower crane tower body.
Two attachment pedestals are set to meet the requirement of firm tower crane tower body, it is symmetrical so that structure is attractive in appearance, more Aesthetic feeling.
Preferably, described horizontal Anchored Bar and oblique Anchored Bar be respectively adjustable length horizontal Anchored Bar and can The oblique Anchored Bar of adjustment length.
Set adjustable length horizontal Anchored Bar and adjustable length oblique Anchored Bar, can according to attachment pedestal with The distance of tower crane tower body adjusts appropriate length, may apply to more job sites, with good general applicability.
Preferably, described horizontal Anchored Bar two ends pass through bearing pin between attachment pedestal and tower body anchoring ring I respectively It is hinged.
Preferably, described oblique Anchored Bar two ends are cut with scissors between fix bar and tower body anchoring ring II by bearing pin respectively Connect.
The two ends of horizontal Anchored Bar are respectively equipped with pin shaft hole, match somebody with somebody with the pin shaft hole in pedestal anchoring ring and tower body anchoring ring I Close, and be hinged by inserting bearing pin realization;The two ends of oblique Anchored Bar are respectively equipped with pin shaft hole, with being anchored in fix bar with tower body Pin shaft hole on ring II coordinates, and is hinged by inserting bearing pin realization, convenient dismounting.
The beneficial effects of the utility model:
First, by being hinged horizontal Anchored Bar and oblique attachment in tower body anchoring ring I, tower body anchoring ring II and pedestal anchoring ring Bar, makes full use of the stability of triangle, substantially increases the security and stability of tower crane;
2nd, the adjustable in length of horizontal Anchored Bar and oblique Anchored Bar, disclosure satisfy that the use of different condition, applicability Extensively;
3rd, set up firmly, can be set up for deep basal pit and foundation ditch periphery narrow and small place, and it is reusable, effectively solve The problem of tower crane of having determined is reinforced.
Brief description of the drawings
Fig. 1 is top view of the present utility model;
Fig. 2 is front view of the present utility model;
Shown in figure:
1st, adhere to pedestal, 2, pedestal anchoring ring, 3, connecting bolt, 4, horizontal Anchored Bar and pedestal anchor interannular bearing pin, 5, Horizontal Anchored Bar, 6, strengthening support, 7, fix bar, 8, oblique Anchored Bar, bearing pin between 9, tower body anchoring ring II and oblique Anchored Bar, 10th, tower crane tower body, 11, tower body anchoring ring II, 12, girt, 13, tower body anchoring ring I.
Embodiment
For the technical characterstic for illustrating this programme can be understood, below by embodiment, this programme is illustrated.
A kind of construction tower crane is provided and builds attachment, including tower crane tower body 10 temporarily, in addition at least two are located at tower crane tower Girt 12 is fixed between the attachment pedestal 1 of the homonymy of body 10, attachment pedestal 1, attachment pedestal 1 can set two, three It is even more many, as a kind of embodiment of the present utility model, as shown in figure 1, provided with two attachment pedestals 1 and with tower crane tower body It is symmetrical centered on 10;
It is fixed with pedestal anchoring ring 2, described tower crane tower body 10 and is anchored with described pedestal on described attachment pedestal 1 Tower body anchoring ring I13 is fixed with the position that ring 2 is generally aligned in the same plane, described tower crane tower body 10 is tower body anchoring ring I13's Above or below be further fixed on tower body anchoring ring II11, as a kind of embodiment of the present utility model, as shown in Fig. 2 tower body Anchoring ring II11 is located at tower body anchoring ring I13 top, described pedestal anchoring ring 1, tower body anchoring ring I13 and tower body anchoring ring II11 is spliced by two adhesion frames by connecting bolt 3, and tower crane tower body 10 and attachment pedestal 1 are square structure, It is also square that pedestal anchoring ring 2, tower body anchoring ring I13 and tower body anchoring ring II11 match therewith, so adhesion frame is en Shape structure and by connecting bolt 3 fixed bit, one square structure, certain pedestal anchoring ring 2 can also be other shapes, such as The shapes such as cylinder, triangular prism, adhesion frame matches with the shape of pedestal anchoring ring 2;
Two horizontal Anchored Bars 5 are at least hinged between wherein tower body anchoring ring I13 and each pedestal anchoring ring 2, it is adjacent Pedestal anchoring ring 2 on horizontal Anchored Bar 5 between be fixed with fix bar 7, described fix bar 7 and described tower body anchoring ring Oblique Anchored Bar 8 is hinged between II11.
Two horizontal Anchored Bars 5 are hinged between described tower body anchoring ring I13 and each pedestal anchoring ring 2 and level is attached And be fixed with strengthening support 6 between bar 5.
Described horizontal Anchored Bar 5 and oblique Anchored Bar 8 are respectively the horizontal Anchored Bar and adjustable length of adjustable length The oblique Anchored Bar of degree.
Cut with scissors respectively between pedestal anchoring ring 2 and tower body anchoring ring I13 by bearing pin 4 at the described two ends of horizontal Anchored Bar 5 Connect.
The described two ends of oblique Anchored Bar 8 are hinged between fix bar 7 and tower body anchoring ring II11 by bearing pin 9 respectively.
The utility model can manufacture adhering member according to design drawing, and structure manufacture, which is finished, to be started to install, installation procedure It is as follows:
The position that attached wall frame is filled on tower crane tower body 10 adds provisional mounting platform, performs installation and prepares.Tower crane is installed During tower body anchoring ring I13 and tower body anchoring ring II11, first the adhesion frame of the side of tower body 10 is hung at the attachment point of tower body(Should Sling adhesion frame level), it is fixed on tower crane tower body 10, then slings second half adhesion frame just with iron wire Position, it is determined that the tower body anchoring ring I13 or tower body anchoring ring II11 that two adhesion frames are spliced into be horizontal after enter again Row is fixed;It is fixed after should appropriately adjusting if being not in horizontal level, two lateral frames are linked together with connecting bolt 2 It is spliced into tower body anchoring ring I13 or tower body anchoring ring II11.It is when horizontal Anchored Bar 5 and oblique Anchored Bar 8 are lifted, level is attached Bar 5 and oblique Anchored Bar 8 be assembled on the ground needed for be hung at attachment point after length, the bearing pin in alignment adhesion frame Hole, squeezes into connection bearing pin 4 and bearing pin 9, then adjusts again to attachment point adhesion frame, completes to install.
Certainly, described above is also not limited to the example above, and technical characteristic of the utility model without description can lead to Cross or realized using prior art, be will not be repeated here;Above example and accompanying drawing are merely to illustrate technology of the present utility model Scheme is not to limitation of the present utility model, with reference to preferred embodiment the utility model is described in detail, originally Field it is to be appreciated by one skilled in the art that those skilled in the art institute in essential scope of the present utility model The variations, modifications, additions or substitutions made are without departure from objective of the present utility model, and should also belong to right of the present utility model will Seek protection domain.

Claims (8)

1. one kind construction tower crane builds attachment, including tower crane tower body temporarily, it is characterised in that:Also include at least two and be located at tower crane Be fixed with the attachment pedestal of tower body homonymy, described attachment pedestal on pedestal anchoring ring, described tower crane tower body with it is described Tower body anchoring ring I is fixed with the position that pedestal anchoring ring is generally aligned in the same plane, described tower crane tower body is tower body anchoring ring I's Above or below be further fixed on tower body anchoring ring II, be at least hinged between wherein tower body anchoring ring I and each pedestal anchoring ring Be fixed with fix bar between horizontal Anchored Bar in two horizontal Anchored Bars, adjacent pedestal anchoring ring, described fix bar with Oblique Anchored Bar is hinged between described tower body anchoring ring II.
2. construction tower crane according to claim 1 builds attachment temporarily, it is characterised in that:Described pedestal anchoring ring, tower Body anchoring ring I and tower body anchoring ring II is spliced by two adhesion frames by connecting bolt.
3. construction tower crane according to claim 1 builds attachment temporarily, it is characterised in that:Described tower body anchoring ring I with It is hinged between each pedestal anchoring ring between two horizontal Anchored Bars and horizontal Anchored Bar and is fixed with strengthening support.
4. construction tower crane according to claim 1 builds attachment temporarily, it is characterised in that:It is solid between described attachment pedestal Surely there is girt.
5. construction tower crane according to claim 1 builds attachment temporarily, it is characterised in that:Described attachment pedestal is provided with two It is individual and symmetrical centered on tower crane tower body.
6. construction tower crane according to claim 1 builds attachment temporarily, it is characterised in that:Described horizontal Anchored Bar and tiltedly It is respectively the horizontal Anchored Bar of adjustable length and the oblique Anchored Bar of adjustable length to Anchored Bar.
7. the construction tower crane according to claim 1 or 6 builds attachment temporarily, it is characterised in that:Described horizontal Anchored Bar Two ends pass through hinge between pedestal anchoring ring and tower body anchoring ring I respectively.
8. the construction tower crane according to claim 1 or 6 builds attachment temporarily, it is characterised in that:Described oblique Anchored Bar Two ends pass through hinge between fix bar and tower body anchoring ring II respectively.
CN201720020167.3U 2017-01-09 2017-01-09 Construction tower crane builds attachment temporarily Expired - Fee Related CN206427941U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201720020167.3U CN206427941U (en) 2017-01-09 2017-01-09 Construction tower crane builds attachment temporarily

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201720020167.3U CN206427941U (en) 2017-01-09 2017-01-09 Construction tower crane builds attachment temporarily

Publications (1)

Publication Number Publication Date
CN206427941U true CN206427941U (en) 2017-08-22

Family

ID=59584724

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201720020167.3U Expired - Fee Related CN206427941U (en) 2017-01-09 2017-01-09 Construction tower crane builds attachment temporarily

Country Status (1)

Country Link
CN (1) CN206427941U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106495026A (en) * 2017-01-09 2017-03-15 山东华邦建设集团有限公司 Attachment built temporarily by construction tower crane
CN107522112A (en) * 2017-09-04 2017-12-29 储昭汉 A kind of multifunctional safe tower crane

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106495026A (en) * 2017-01-09 2017-03-15 山东华邦建设集团有限公司 Attachment built temporarily by construction tower crane
CN107522112A (en) * 2017-09-04 2017-12-29 储昭汉 A kind of multifunctional safe tower crane

Similar Documents

Publication Publication Date Title
CN206769354U (en) A kind of steel structure hoisting platform
CN104895335B (en) Method for mounting hanging pillar
CN105908761A (en) Construction technology of hanging basket moving platform for high slope
CN206427941U (en) Construction tower crane builds attachment temporarily
CN205777600U (en) Batter post installs auxiliary support apparatus
CN211689943U (en) Assembled pier stud template upset buffer
CN105464456A (en) Method and lifting sling for assembling extra-high voltage transmission iron tower through helicopter
CN109826082B (en) Construction method for installing decorative structure in multi-tower combined space of cable-stayed bridge
CN106495026B (en) Construction tower crane temporarily builds attachment
CN205953378U (en) Tower crane counter weight is put from dismouting
CN104563515B (en) The formwork erection structure of superelevation shear wall and construction method
CN204252083U (en) Arch dam bracket hangs plate device by the feet entirely
CN206607903U (en) A kind of pre-assembled elevator hard protection pipe support
CN107143198B (en) A method of UHV transmission steel tower is found suitable for mountain area sternness location group
CN205875168U (en) A prevent structure of falling for foundation ditch steel shotcrete
CN211920714U (en) Support system of pull-up and pull-down type external hanging self-climbing tower crane
CN209011132U (en) A kind of fixed foundation pit berm structure of assembled two point
CN210947661U (en) Installation device of socket type overhanging scaffold
CN108518119B (en) Portable power transmission pole maintenance tool and construction method
CN203101704U (en) Transmission line protection device
CN106245530A (en) A kind of universal rod body CABLEWAY ERECTION SYSTEM removes engineering method
CN208309937U (en) The support construction of artistic stone curtain wall is installed
CN111764623A (en) Lower hanging construction platform module of high-altitude large-cantilever steel roof truss and construction method
CN206580444U (en) A kind of urban construction building prefabricated components hanging apparatus
CN205476507U (en) Inside pump line fixing device of jacking platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant